Panel-type support, support structure and tunnel construction method
The panel type shoring system addresses the inefficiencies and safety concerns of manual steel shoring connection by providing pre-connected supporting members, enhancing tunnel construction efficiency and safety through automated assembly and integration with shotcrete.
Patent Information
- Application Number
- JP2022516936
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Priority Date
- 2020-04-20
- Filing Date
- 2021-04-06
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2041-04-06
AI Technical Summary
Existing tunnel construction methods using NATM require manual labor for connecting steel shoring and tie rods, which is time-consuming and unsafe due to the need for workers to work under exposed ground or primary shotcrete.
A panel type shoring system with pre-connected supporting members and connecting steel elements, allowing for efficient erection and integration with existing shoring structures, reducing the need for manual assembly and enhancing safety by ensuring proper positioning and integration with shotcrete.
Improves workability and safety by eliminating the need for manual connection of steel shoring and tie rods, ensuring secure and efficient construction of tunnel supports.
Smart Images

Figure 0007577264000001 
Figure 0007577264000002 
Figure 0007577264000003
Abstract
Description
[Technical field]
[0001] The present invention relates to a panel-type support, a support structure, and a tunnel construction method using the same. [Background technology]
[0002] In tunnel construction using NATM, the ground surface exposed by tunnel excavation is sealed off early with shoring. Tunnel shoring is generally composed of shotcrete sprayed onto the ground surface, steel shoring assembled along the ground surface, and rock bolts set up as necessary. The shoring is installed by assembling the steel shoring after or before spraying the primary shotcrete onto the ground exposed by excavation, and then spraying the shotcrete (secondary shotcrete).
[0003] When assembling steel shoring, it is common to use heavy machinery such as a drill jumbo to hold the steel shoring while manually tightening the bolts on both sides of the steel shoring near the top of the face. However, tightening bolts manually and attaching ties and tie rods to prevent tipping over is time-consuming work, and requires work to be done on the exposed ground before the shoring is completed, or directly under the first shotcrete.
[0004] For this reason, construction methods have been disclosed that aim to improve workability and safety during construction of shoring.For example, Patent Document 1 discloses a tunnel construction method in which one-touch joints are provided at joints formed at the ends of steel shoring, and an erector device having a pair of hands capable of holding the steel shoring is used to butt the joints of the left and right steel shoring together to connect the one-touch joints and erect the steel shoring assembled in an arch shape along the face. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] Patent No. 6374051 Summary of the Invention [Problem to be solved by the invention]
[0006] In the tunnel construction method described in Patent Document 1, although a robot is used to erect the steel supports, after erecting the steel supports, the new steel supports must be manually connected to the existing supports with tie rods or ties. Therefore, workers must work in the exposed natural ground due to excavation or directly below the primary shotcrete.
[0007] An object of the present invention is to propose a panel-type support and a tunnel construction method that make it possible to improve workability and safety during support construction. [Means for solving the problem]
[0008] The panel-type support of the present invention, which solves these problems, comprises a pair of support members arranged at the front and rear, and a tie steel material that connects the support members. The support members have a U-shaped cross section consisting of a pair of flanges and a web that connects the pair of flanges, and the pair of support members are arranged so that the tips of the flanges face each other. In the case where a bottom plate with a guide pin is fixed to the lower end of the support member provided on the face side, a bottom plate with a through hole is fixed to the lower end of the support member provided on the tunnel mouth side. Also, the support member provided on the face side may be provided with a receiving bracket protruding toward the face side.
[0009] The tunnel construction method of the present invention includes an excavation step of excavating the natural ground, and a shoring step of forming shoring along the natural ground surface exposed by excavating the natural ground, and the shoring step includes an erection work of erecting the panel-type shoring and a spraying work of spraying concrete toward the natural ground surface. In the erection work, the web of the support member on the tunnel mouth side of the newly installed panel-type shoring is juxtaposed to the web of the support member on the face side of the existing panel-type shoring.
[0010] According to the panel-type support and the tunnel construction method using the same, the tie steel members are fixed to the support members constituting the steel support in advance, so that a predetermined distance is secured between the support members in advance, and the labor required for positioning the steel support can be omitted or reduced. Also, the installation of tie rods and tie members near the tunnel face after the steel support is installed can be omitted.
[0011] It is desirable that the support members have a cross-sectional area of at least half that of the steel support set in the support pattern according to the ground grade, and a section modulus of at least half that of the steel support.By doing this, by combining the support members of the panel-type support with the support members of an existing panel-type support, a steel support is formed that has cross-sectional dimensions equal to or greater than those of the steel support set in the support pattern according to the ground grade. Furthermore, if a wire mesh is provided between the support members along the circumferential direction of the support members, the work of installing the wire mesh near the face after the steel support is installed can be omitted, thereby improving workability and safety.
[0012] In addition, if the web of at least one of the pair of support members is provided with a plurality of studs protruding on the opposite side of the other support member, the panel-type support can be installed at a specified interval on the face side of the existing panel-type support. In addition, the studs function as fixing members in the sprayed concrete, ensuring the integrity of the sprayed concrete and the support members. In addition, a bottom plate with a guide pin standing thereon is fixed to the lower end of the support member provided on the face side, and a bottom plate with a through hole formed therein is fixed to the lower end of the support member provided on the tunnel mouth side. In the case Positioning is completed by inserting the guide pin of the existing panel-type support into the through hole and then installing the new panel-type support, which significantly reduces the amount of construction work required.
[0013] In addition, the support member provided on the face side is provided with a receiving metal fitting protruding toward the face side. If The placement of the panel-type support is completed by engaging the support components on the portal side of the new panel-type support with the receiving brackets of the existing panel-type support, significantly reducing the amount of construction work required. Furthermore, if a handle that can be grasped by an erector is fixed to the connecting steel, the panel-type support can be moved and positioned using the erector without requiring special tools for grasping the panel-type support with the erector.
[0014] In addition, in the erection work, it is desirable to form an arch-shaped support structure by connecting the pair of left and right panel-type supports at their upper ends. At this time, if a joiner with a joint pin at its tip is protruding from the joint plate at the upper end of the support member of one of the panel-type supports, and if a joint plate with an opening through which the joiner is inserted is provided at the upper end of the support member of the other panel-type support, and a stiffener capable of engaging with the joint pin is fixed, the panel-type supports can be connected to each other simply by engaging the joint pin with the stiffener. Effect of the Invention
[0015] According to the panel-type support of the present invention and the tunnel construction method using the same, it is possible to improve workability and safety during support construction. [Brief description of the drawings]
[0016] [Figure 1] FIG. 2 is a cross-sectional view showing an overview of a tunnel according to the first embodiment. [Diagram 2] This is a cross-sectional view showing an overview of the support structure. [Diagram 3] FIG. 2 is a cross-sectional view showing the primary spraying work of the tunnel construction method. [Figure 4] FIG. 2 is a cross-sectional view showing the construction work of the tunnel construction method. [Figure 5A] This is a front view of the panel-type support structure. [Figure 5B] This is a plan view of the panel-type support structure. [Figure 6A]FIG. 2 is a plan view showing a portion of the panel-type support structure. [Figure 6B] A cross-sectional view showing a portion of a panel-type support structure. [Figure 7] FIG. 2 is a perspective view showing the installation status of a panel-type support according to an embodiment of the present invention. [Figure 8A] FIG. 2 is a plan view showing a portion of the panel-type support structure. [Figure 8B] FIG. 2 is a front view showing a portion of the panel-type support structure. [Figure 9] FIG. 13 is an oblique view showing the installation status of the first panel-type support. [Figure 10] FIG. 4 is a plan view showing the installation status of the first panel-type support. [Figure 11] This is a plan view showing the installation status of the second panel-type support. [Figure 12] 4 is a cross-sectional view showing a joint between support members. FIG. [Figure 13] FIG. 4 is a plan view showing an outline of a joint between support members. [Figure 14] FIG. [Figure 15] A cross-sectional view showing an overview of a tunnel related to the second embodiment. [Figure 16] A cross-sectional view showing an overview of the support of the second embodiment. [Figure 17] FIG. 2 is a cross-sectional view showing the primary spraying work of the tunnel construction method. [Figure 18] FIG. 2 is a cross-sectional view showing the construction work of the tunnel construction method. [Figure 19A] This is a plan view of the panel-type support structure. [Figure 19B] This is a front view of the panel-type support structure. [Figure 20A] This is a longitudinal section of a panel-type support structure. [Figure 20B] FIG. 2 is a plan view showing a portion of the panel-type support structure. [Figure 21A] A side view showing the leg of the support member on the face side. [Figure 21B] This is a cross-sectional plan view showing the leg of the support member on the face side. [Figure 21C]A side view showing the leg of the support member on the wellhead side. [Figure 21D] A cross-sectional plan view showing the leg of the support member on the wellhead side. [Figure 21E] This is an enlarged cross-sectional view showing the installation status of the panel-type support structure. [Figure 22A] FIG. 4 is a front view showing a joint between support members. [Figure 22B] FIG. 4 is a front view showing the joining state of the support members. [Figure 22C] FIG. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0017] First Embodiment In this embodiment, a case where a tunnel is constructed by NATM will be described. As shown in Fig. 1, a tunnel T is stabilized by blocking the exposed natural ground surface Gs by excavating the natural ground G with supports 1 made of sprayed concrete 2, steel supports (panel supports 3), etc. Note that the supports 1 include rock bolts as necessary. Furthermore, during tunnel construction, auxiliary construction methods such as advanced poling, pipe rule method, and chemical injection may be used in combination as necessary.
[0018] In tunnel construction, first, the natural ground G is excavated to form a borehole (tunnel T) (excavation process). The excavation method for the tunnel T is not limited, and may be, for example, blasting excavation or mechanical excavation. The excavation length of the tunnel T per cycle is determined according to the natural ground conditions (natural ground grade, earth covering, etc.), but in this embodiment, it is 1.0 to 1.2 m.
[0019] After the tunnel T has been excavated to a predetermined length (1.0 to 1.2 m in this embodiment), the support 1 is formed along the ground surface Gs exposed by excavating the ground G (support process). As shown in Fig. 2, the support 1 in this embodiment includes shotcrete 2 consisting of primary shotcrete 21 and secondary shotcrete 22, and a panel-type support 3 consisting of a steel support (support member 4) and a wire mesh 5, and the support process includes primary spraying work, erection work, and secondary spraying work (spraying work).
[0020] In the primary spraying work, as shown in Fig. 3, primary shotcrete 21 is sprayed onto the natural ground surface Gs exposed by excavation of the natural ground G. The primary shotcrete 21 is sprayed onto the tunnel face K in addition to the wall surface (side surface) of the tunnel T. The spraying thickness of the primary shotcrete 21 may be appropriately determined, but is set to 5 cm in this embodiment.
[0021] In the erection work, as shown in FIG. 4, the panel-type shoring 3 is erected along the surface of the first shotcrete 21 (or the ground surface Gs) near the face K. Note that a gap (for example, a gap of about 5 cm) is provided between the outer surface of the panel-type shoring 3 (wire mesh 5) and the surface of the first shotcrete 21 due to over-excavation during excavation, which is necessary for adjustment and movement during erection of the panel-type shoring 3. As shown in FIG. 5A and FIG. 5B, the panel-type shoring 3 includes a pair of support members 4, 4 arranged at the front and rear, a wire mesh 5 arranged between the support members 4, and a plurality of connecting steel members 6 connecting the pair of support members 4, 4. The length of the panel-type shoring 3 (the distance from the end face of the support member 4 on the face K side to the end face of the support member 4 on the tunnel mouth side) is set to the interval between the steel supports set according to the ground grade (1.0 to 1.2 m in this embodiment).
[0022] A pair of support members 4, 4 are arranged at the tunnel face K side and the tunnel entrance side with a gap in the tunnel axial direction. As shown in FIG. 6B, the support member 4 is composed of a so-called channel steel having a U-shaped cross section with a pair of flanges 4a, 4a and a web 4b connecting the pair of flanges 4a, 4a. The cross-sectional dimensions of the support member 4 are set to a size that ensures dimensions having a cross-sectional area of at least half the cross-sectional area of the steel support set by the support pattern according to the ground grade, and a cross-sectional modulus of at least half the cross-sectional modulus of the steel support. For example, if a steel support with a support pattern according to the ground grade is H-125×125×6.5×9 (cross-sectional area: 30.0 cm 2 , section modulus: 134cm 3 In the case of ), the support member 4 is [-125×65×6×8 (cross-sectional area: 17.1 cm 2 , section modulus: 67.8cm 3 ) may be used. As shown in Fig. 5A, the support member 4 is bent into a shape corresponding to the cross-sectional shape of the tunnel T, and has an arc shape when viewed from the front. The pair of support members 4, 4 are arranged so that the tips of their flanges 4a face each other (so that the space surrounded by the pair of flanges 4a, 4a and the web 4b faces inside).
[0023] As shown in Fig. 5B, the wire mesh 5 is provided along the circumferential direction of the support member 4. The wire mesh 5 in this embodiment has a mesh size of 15 x 15 cm, but the dimensions of the wire mesh 5 are not limited. As shown in Figs. 6A and 6B, in this embodiment, the wire mesh 5 is welded to the outer surface of the flange 4a on the ground G side of the support member 4. The wire mesh 5 is horizontally installed between the flange 4a of one support member 4 and the flange 4a of the other support member 4. The wire mesh 5 is welded to the front and rear support members 4, 4, ensuring safety in the unlikely event of a skin slippage.
[0024] As shown in FIG. 6A, the tie steel 6 is interposed between the support members 4 arranged in front and behind. The material constituting the tie steel 6 is not limited, and for example, steel materials such as H-shaped steel, channel steel, and L-shaped steel, steel rods, or steel pipes may be used. One end of the tie steel 6 is welded to the web 4b of one support member 4, and the other end is welded to the web 4b of the other support member 4. The method of fixing the tie steel 6 to the support member 4 is not limited, and for example, bolting may be used. In addition, the fixing point of the tie steel 6 to the support member 4 is not limited, and for example, it may be welded to the inner flange 4a. The multiple tie steels 6, 6, ... are arranged at intervals along the tunnel wall surface. The number of tie steels 6 and the arrangement pitch are not limited, and may be determined appropriately.
[0025] In the erection work, as shown in Fig. 4, the new panel type support 3 is erected on the face K side of the existing panel type support 3a. When erecting the panel type support 3, the web 4b of the support member 4 on the tunnel mouth side of the new panel type support 3 is overlapped on the web 4b of the support member 4 on the face K side of the existing panel type support 3a, and the two webs 4b, 4b are connected.
[0026] In this embodiment, as shown in Fig. 7, a pair of left and right panel-type supports 3, 3 are arranged and the panel-type supports 3 are combined at their tops (upper ends) to form an arch-shaped support structure. When combining the left and right panel-type supports 3, 3, the support members 4 are connected at their tops.
[0027] A connecting plate 7 (see FIG. 6) is used to connect the support members 4 together. The connecting plate 7 straddles the left and right support members 4, 4 and is attached to the webs 4b of both support members 4, 4. As shown in FIG. 6B, in this embodiment, a channel steel having a U-shape in cross section is used for the connecting plate 7. The connecting plate 7 has a cross-sectional dimension smaller than that of the support member 4, and can be inserted into the space surrounded by the flanges 4a, 4a and the web 4b. The connecting plate 7 is attached to the web 4b on the hole mouth side of the support member 4 of the existing panel-type support 3a and the web 4b on the face K side of the support member 4 of the newly installed panel-type support 3. That is, the top of the support member 4 is clamped by the connecting plate 7 from the front and rear of the support member 4 (the face K side and the hole mouth side).
[0028] As shown in Fig. 6A, a plurality of pins 8 (four in this embodiment) are fixed to one of the connecting plates 7 that sandwich the support member 4, and as shown in Fig. 8B, the other connecting plate 7 has through holes formed at positions corresponding to the plurality of pins 8. The supporting members 4 are connected to each other by inserting the pins 8 through the connecting plates 7, 7 that sandwich the supporting member 4.
[0029] The joints between the supporting members 4 will be described in detail below. As shown in Figs. 6A and 6B, a first connecting plate 71 is fixed to the upper end of the support member 4 (hereinafter referred to as the "first-wing side support member 41") on the face K side of one of the pair of left and right panel-type supports 3, 3 (hereinafter referred to as the "first panel-type support member 31"). The first connecting plate 71 in this embodiment has a length of 400 mm, and is fixed to the first-wing side support member 41 with 200 mm protruding from the end of the first-wing side support member 41. The first connecting plate 71 is made of channel steel, and four pins 8, 8, ... are fixed to the first connecting plate 71 at equal intervals. Note that the method of fixing the first connecting plate 71 to the first-wing side support member 41 is not limited, but in this embodiment, it is mainly welded to the flanges 4a, 4a. In addition, the number of pins 8 fixed to the first connecting plate 71 and the arrangement pitch of the pins 8 are not limited. Furthermore, the material constituting the first connecting plate 71 and the dimensions of the first connecting plate 71 are not limited. Two through holes are formed in the upper end of the first blade side support member 41 corresponding to the positions of the pins 8. The first connecting plate 81 is fixed to the first blade side support member 41 with the two pins 8 passing through the through holes of the first blade side support member 41. The shape of the through holes is such that the pins 8 can be inserted and locked, and in this embodiment, the inner diameter is approximately 1 mm larger than the diameter of the pins 8.
[0030] A transmission plate 9 is fixed to the upper end of the support member 4 on the mine entrance side of the first panel-type support structure 31 (hereinafter referred to as the "first mine entrance side support member 42"). The transmission plate 9 is made of a steel plate approximately 100 mm wide and 200 mm long, and is welded to each of the flanges 4a, 4a while being attached to the surface of the web 4b within the space surrounded by the flanges 4a, 4a and the web 4b. The upper end of the first mine entrance side support member 42 and the transmission plate 9 have two through holes each, through which the pins 8 can be inserted.
[0031] As shown in Fig. 8A, a transmission plate 9 is fixed to the upper end of the support member 4 (hereinafter referred to as the "second face-side support member 43") on the face K side of the other panel-type support 3 (hereinafter referred to as the "second panel-type support 32") of the pair of left and right panel-type supports 3, 3. The transmission plate 9 is made of a steel plate with a width of about 100 mm and a length of about 200 mm, and is welded to each of the flanges 4a, 4a in a state of being attached to the surface of the web 4b within the space surrounded by the flanges 4a, 4a and the web 4b. Two through holes through which the pins 8 can be inserted are formed in each of the upper end portion of the second face-side support member 43 and the transmission plate 9.
[0032] A second connecting plate 72 is fixed to the upper end of the support member 4 (hereinafter referred to as the "second support member 44") on the pithead side of the second panel-type support 32. The second connecting plate 72 has a length of 400 mm, of which a range of 200 mm protrudes from the end of the second support member 44, and the remaining range of 200 mm is fixed to the second support member 44. The method of fixing the second connecting plate 72 to the second support member 44 is not limited, but in this embodiment, it is mainly welded to the flanges 4a, 4a. The second connecting plate 72 has four through holes for inserting the pins 8. The through holes are formed at positions corresponding to the pins 8 of the first connecting plate 71.
[0033] When erecting the panel-type shoring 3, first, as shown in FIG. 9, the first panel-type shoring 31 is arranged on the face K side of the existing panel-type shoring 3a. The first panel-type shoring 31 is once arranged with a gap on the face K side of the existing panel-type shoring 3a, and then pulled back to the tunnel mouth side to abut against the face K side of the existing panel-type shoring 3a. At this time, as shown in FIG. 10, the pin 8 arranged at the top of the support member 4 of the existing panel-type shoring 3a is penetrated through the through hole formed in the first tunnel mouth side support member 42 of the first panel-type shoring 31 and the through hole formed in the transmission plate 9. The panel-type shoring 3 is arranged and finely adjusted at a predetermined position while being held by a heavy machine such as an erector, and is held in place.
[0034] Next, as shown in FIG. 7 and FIG. 11, the second panel type support 32 is disposed on the face K side of the existing panel type support 1a. The second panel type support 32 is once disposed on the face K side of the existing panel type support 3a with a gap therebetween, and then pulled back to the mouth side to abut against the face K side of the existing panel type support 3a. At this time, the pin 8 of the first connecting plate 71 fixed to the top of the first face side support member 41 is passed through the through hole formed at the top of the second face side support member 43 and the through hole of the transmission plate 9. Also, the pin 8 disposed at the top of the existing panel type support 3a is passed through the through hole formed in the second mouth side support member 44 and the through hole formed in the second connecting plate 72. In this way, the support members 4, 4 of the newly installed left and right panel-type supports 3, 3 are connected to the support members 4, 4 of the existing left and right panel-type supports 3a, 3a. The support members 4, 4 are stacked in an H shape and connected by being clamped from the front and back by connecting plates 7, 7 as shown in Figure 12.
[0035] As shown in Fig. 13, the tip face of the support member 4 of the first panel type support 31 (the end face on the top side of the tunnel T) is inclined with respect to the tunnel axial direction (the direction of movement of the second panel type support 32) so as to approach the second panel type support 32 as it approaches the tunnel entrance. On the other hand, the tip face of the support member 4 of the second panel type support 32 is inclined so as to approach the first panel type support 31 as it approaches the face K. In this way, the end faces of the support members 4 are brought into metal-to-metal contact, forming a bearing joint and enabling the transmission of axial force.
[0036] After the panel-type supports 3 are connected to each other, the legs of the support members 4 of the second panel-type supports 32 are pushed out (spread out) to the side (towards the ground G) as shown in FIG. 14. The second panel-type supports 32 are designed so that the positions of the legs of the support members 4 pushed out to the side are aligned with the support members 4 of the existing panel-type supports 3a. At this time, the support members 4 are pushed out so that a bending force of about 10% (about 150 kN / cm) of the yield bending strength of the steel support is applied. In this way, a shear force acts on the pins 8 and the through holes (through holes formed in the connecting plates 7, webs 4b, etc.), and the pins 8 are less likely to come out of the through holes due to friction. This improves the joining of the support members 4 to each other. In order to retain this reaction force, it is advisable to provide a separate pin in the leg of the support member 4 of the existing panel-type support 3a and insert it into a hole previously drilled in the leg of the second panel-type support 32. The force used to push the leg of the support member 4 to the side is not limited. Also, the leg of the support member 4 does not necessarily have to be pushed to the side.
[0037] By installing the panel-type support 3, the surface of the primary shotcrete 21 is covered with the wire mesh 5. In this state, adjacent support members 4 in the front-rear direction or adjacent support members 4 in the cross-sectional direction may be bolted together near the face K.
[0038] Once the assembly of the panel-type shoring 3 is complete, secondary shotcrete 22 is sprayed toward the side of the tunnel T (secondary spraying work). The secondary shotcrete 22 is sprayed onto the legs of the shoring and between the supporting members 4 arranged at the front and rear (see FIG. 2), and in this embodiment, it is sprayed to a thickness (e.g., 10 cm to 25 cm) that exposes the inner side of the supporting member 4. The thickness of the secondary shotcrete 22 is not limited, and for example, it may be a thickness that exposes the inner side flange 2a of the supporting member 4, or a thickness that allows the supporting member 4 to be buried.
[0039] According to the panel-type support 3 of this embodiment and the tunnel construction method using it, the wire mesh 5 is fixed in advance to the support members 4 that constitute the steel support, so that the installation of the steel support and the installation of the wire mesh 5 can be performed simultaneously. Therefore, the work of installing the wire mesh 5 near the face K after the installation of the steel support can be omitted, and workability and safety can be improved.
[0040] Furthermore, since the support members 4 arranged at the front and rear are fixed at a predetermined distance from each other, the effort required for positioning the steel support can be omitted or reduced. The support members 4 are firmly connected to each other via connecting steel members 6, so that when assembling the panel-type support structure 3, the support member 4 on the face K side (or the support member 4 on the tunnel mouth side) can be grasped and moved by heavy machinery.
[0041] The support member 4 is combined with the support member 4 of the existing panel-type support structure 3a to ensure the necessary cross-sectional dimensions, thereby ensuring the strength of the support structure for the tunnel T. The connection of the support members 4 to each other can be completed simply by passing the pin 8 fixed to one connecting plate 7 through the through hole of the support member 4 and inserting it into the other connecting plate 7, making it easy to install.
[0042] At the joints between the support members 4 arranged on the left and right sides, force is transmitted via the connecting plate 7, so that the arch-shaped support structure can fully exhibit its capabilities. That is, stress is transmitted between the first wing side support member 41 and the second pit-side support member 44, which are fixed together, and the connecting plate 7. That is, stress acting on the flange 4a of the support member 4 (first wing side support member 41 or second pit-side support member 44) is transmitted to the web 4b and the connecting plate 7 welded to the flange 4a. On the other hand, the first pit-side support member 42 and the second face side support member 43 have the transmission plate 9 welded to the flange 4a, so that stress acting on the flange 4a of the support member 4 (first pit-side support member 42 or second face side support member 43) is transmitted to the web 4b and the transmission plate 9, and then transmitted to the connecting plate 7 via the pin 8.
[0043] Adjacent support members 4 on the left and right are connected by shear joints between the through holes of the support members 4 and multiple (four in this embodiment) pins 8. The bending stress acting on the upper end of the arch (the joint between the support members 4) is transmitted by the multiple pins 8, and the couple caused by the shear force of the multiple pins 8 ensures the necessary bending strength.
[0044] Second Embodiment In the second embodiment, a case where a tunnel is constructed by NATM will be described as in the first embodiment. As shown in Fig. 15, the tunnel T is stabilized by blocking the exposed natural ground surface Gs by excavating the natural ground G with supports 1 made of sprayed concrete 2, steel supports (panel supports 3), etc.
[0045] The shoring 1 is formed along the ground surface Gs exposed by excavating the ground G every time the tunnel T is excavated to a predetermined length (1.0 to 1.2 m in this embodiment). The shoring 1 in this embodiment includes shotcrete 2 consisting of primary shotcrete 21 and secondary shotcrete 22, and a panel-type shoring 3 consisting of a steel shoring (support member 4), a wire mesh 5, and tie steel members 6, as shown in Fig. 16.
[0046] As shown in Fig. 17, the primary shotcrete 21 is sprayed onto a natural ground surface Gs exposed by excavation of the natural ground G. The primary shotcrete 21 is sprayed onto the wall surface (side surface) of the tunnel T as well as onto the face K. The spraying thickness of the primary shotcrete 21 may be determined appropriately, but is set to 5 cm in this embodiment.
[0047] As shown in FIG. 18, the panel-type shoring 3 is erected near the face K along the surface of the primary shotcrete 21 (or the ground surface Gs). As shown in FIG. 19A and FIG. 19B, the panel-type shoring 3 includes a pair of support members 4, 4 arranged at the front and rear, a wire mesh 5 arranged between the support members 4, and a plurality of connecting steel members 6 connecting the pair of support members 4, 4. The length of the panel-type shoring 3 (the distance from the end face of the support member 4 on the face K side to the end face of the support member 4 on the tunnel mouth side) is set to the interval between the steel supports set according to the ground grade (0.96 to 1.16 m in this embodiment). The wire mesh 5 may be installed as necessary, and may be omitted depending on the ground grade, etc.
[0048] A pair of support members 4, 4 are arranged on the tunnel face K side and the tunnel mouth side with a gap in the tunnel axial direction. As shown in FIG. 20A, the support member 4 is composed of a so-called channel steel having a U-shaped cross section with a pair of flanges 4a, 4a and a web 4b connecting the pair of flanges 4a, 4a. The cross-sectional dimensions of the support member 4 are such that the cross-sectional area is at least half the cross-sectional area of the steel support set by the support pattern according to the ground grade, and the cross-sectional modulus is at least half the cross-sectional modulus of the steel support. As shown in FIG. 19B, the support member 4 is bent into a shape according to the cross-sectional shape of the tunnel T, and has an arc shape when viewed from the front. As shown in FIG. 20A, the pair of support members 4, 4 are arranged so that the tips of the flanges 4a face each other (so that the space surrounded by the pair of flanges 4a, 4a and the web 4b is on the inside).
[0049] As shown in Figures 20A and 20B, a plurality of stud materials 45 are erected (protruded) on the outer surface (the surface opposite to the other support member 4) of the web 4b of the support member 4. The heads of the stud materials 45 in this embodiment are enlarged in diameter. The stud materials 45 function as a ruler to ensure a gap of a predetermined size (about 40 mm in this embodiment) between the existing panel-type support 3 and the panel-type support 3 when installing the panel-type support 3, and also function as an anchoring member to ensure unity with the sprayed concrete.
[0050] In addition, the support member 4 provided on the face K side is provided with a receiving bracket 46 protruding toward the face K side. The receiving bracket 46 engages with the support member 4 on the pit mouth side of another panel-type support 3 provided on the face K side. In this way, adjacent support members 4 are connected to each other via the receiving bracket 46. The receiving bracket 46 of this embodiment has a main body plate 46a welded to the support member 4 and a protrusion 46b formed at the tip of the main body plate 46a. The protrusion 46b prevents the support member 4 of another panel-type support 3 from slipping out and falling when the support member 4 is placed on the receiving bracket 46. The protrusion 46b is formed at a position that ensures a distance from the end face of the support member 4 that is greater than the width of the flange 4a of the support member 4 plus the length of the stud material 45. Although the protrusions 46b in this embodiment are formed by fixing a separate member to the main body plate 46a, the protrusions 46b may also be formed by bending the ends of the plate material that constitutes the main body plate 46a.
[0051] As shown in FIG. 21A and FIG. 21B, a first bottom plate 47a is fixed to the lower end (leg) of the support member 4 provided on the face K side. The first bottom plate 47a has an outer shape larger than that of the support member 4 so as to protrude toward the face K side beyond the web 4b of the support member 4, and a guide pin 47c is erected on the protruding portion. In addition, as shown in FIG. 21C and FIG. 21D, a second bottom plate 47b is fixed to the lower end of the support member 4 on the tunnel mouth side. The second bottom plate 47b is formed with a through hole 47d that passes through a space surrounded by the flanges 4a, 4a and the web 4b of the support member 4. The through hole 47d can pass the guide pin 47c. As shown in FIG. 21E, when installing the panel-type support 3, the guide pin 47c of the existing panel-type support 3 is inserted into the through hole 47d.
[0052] As shown in Fig. 19A, the wire mesh 5 is provided along the circumferential direction of the support member 4. As shown in Figs. 20A and 20B, in this embodiment, the wire mesh 5 is welded to the outer surface of the flange 4a of the support member 4 on the ground G side. The wire mesh 5 is horizontally installed between the flange 4a of one support member 4 and the flange 4a of the other support member 4. Since the wire mesh 5 is welded to the front and rear support members 4, 4, safety is ensured in the unlikely event of skin slippage.
[0053] As shown in Fig. 20A, the tie steel 6 is interposed between the support members 4 arranged in front and behind. One end of the tie steel 6 is welded to the web 4b of one support member 4, and the other end is welded to the web 4b of the other support member 4. The multiple tie steel members 6, 6, ... are arranged at intervals along the tunnel wall surface.
[0054] As shown in Figures 19A and 19B, the panel-type support 3 of this embodiment is provided with a handle 61 that can be grasped by an erector. The handle 61 is made of steel and is horizontally supported by a pair of adjacent tie steel members 6, 6 at the shoulders. The handle 61 is fixed at the center of gravity of the panel-type support 3 or near the center of gravity so as to be perpendicular to the tie steel members 6. The fixing location and direction of the handle 61 are not limited, and it may be fixed to the support member 4, for example.
[0055] The newly constructed panel-type support 3 is erected on the face K side of the existing panel-type support 3a, as shown in Fig. 18. In this embodiment, as shown in Fig. 19B, a pair of left and right panel-type supports 3, 3 are arranged and the panel-type supports 3 are combined at their tops (upper ends) to form an arch-shaped support structure 30. When combining the left and right panel-type supports 3, 3, the support members 4 are connected at their tops.
[0056] As shown in FIG. 22A, a joint plate 48 is provided at the tip (upper end) of the support member 4, and when a pair of support members 4, 4 arranged on the left and right are connected, the joint plates 48 are butted against each other to connect them. At this time, one of the pair of support members 4, 4 is provided with a joiner 73 that penetrates the joint plate 48 and protrudes toward the other support member 4. As shown in FIG. 22B, the joiner 73 is a steel material welded to the support member 4, and has a shape in which the vertical width becomes narrower toward the tip. The base end of the joiner 73 is welded to the support member 4, and the middle part of the joiner 73 is welded to the joint plate 48. A joint pin 74 is provided at the tip of the joiner 73. The joint pin 74 is provided in a state of protruding from the tip of the joiner 73.
[0057] An opening for inserting the joiner 73 is formed in the joint plate 48 of the other support member 4 of the pair of left and right support members 4, 4. Also, as shown in Figures 22A and 22B, a stiffener 75 capable of engaging with a joint pin 74 is fixed to the other support member 4. The stiffener 75 is made of a plate material welded and fixed to the space surrounded by the flanges 4a, 4a and web 4b of the support member 4 as shown in Figure 22C, and has an engagement hole 76 formed therein capable of engaging with the joint pin 74.
[0058] The panel-type support 3 is carried to the face K with the handle 61 held by the clamp of an erector (not shown). The panel-type support 3 is erected by the erector just before the face K, and its position relative to the existing panel-type support 3a is adjusted.
[0059] When connecting a pair of left and right support members 4, 4, the bottom plate 47 (first bottom plate 47a, second bottom plate 47b) of the support member 4 is used as a fulcrum, and the upper end of the support member 4 is raised to create a gap between the joint plates 48 of the support member 4 (see FIG. 22B). Next, the upper ends of the left and right support members 4, 4 are lowered simultaneously to penetrate the joint plate 48 of the other support member 4 and insert the joint pin 74 into the engagement hole 76 of the stiffener 75 (see FIG. 22A). As a result, the pair of left and right support members 4 are joined, and the axial force direction between the support members 4 is a support joint by the joint plates 48, 48, and bending forces in the vertical direction (strong axis side) and horizontal direction (weak axis side) can be transmitted via the joiner 73. When a pair of left and right panel-type supports 3, 3 are connected, the support structure stands on its own with the front, rear, left and right legs (first bottom plate 47a, second bottom plate 47b) as support points.
[0060] When erecting the panel type support 3, as shown in Fig. 21E, the panel type support 3 is arranged with the guide pin 47c erected on the first bottom plate 47a of the existing panel type support 3a inserted into the through hole 47d formed in the second bottom plate 47b of the new panel type support 3. Then, the tip of the stud material 45 fixed to the web 4b of the support member 4 on the tunnel mouth side of the new panel type support 3 is abutted against the web 4b of the support member 4 on the face K side of the existing panel type support 3a, and the stud material 45 of the existing panel type support 3a is abutted against the web 4b of the support member 4 of the new panel type support 3, thereby creating a gap between the webs 4b (see Fig. 20A). Furthermore, the support member 4 on the entrance side of the newly constructed panel-type support 3 is engaged with the receiving bracket 46 of the existing panel-type support 3a (see FIG. 20A).
[0061] When the assembly of the panel-type shoring 3 is completed, the secondary shotcrete 22 is sprayed toward the side of the tunnel T (see FIG. 16). The secondary shotcrete 22 is sprayed onto the legs of the supporting members 4 and between the supporting members 4 arranged at the front and rear, and in this embodiment, it is sprayed to a thickness (for example, 10 cm to 25 cm) that exposes the inner side of the supporting members 4. The thickness of the secondary shotcrete 22 is not limited, and for example, the flange 2a on the inner side of the supporting members 4 may be exposed, or the supporting members 4 may be buried. In this embodiment, the secondary shotcrete 22 is also sprayed between the panel-type shoring 3 and the existing panel-type shoring 3a.
[0062] According to the panel-type shoring 3 of this embodiment and the tunnel construction method using it, the stud materials 45 provided on the supporting members 4 are embedded in the shotcrete sprayed between the panel-type shoring 3, thereby connecting the supporting members 4 of adjacent panel-type shoring 3 in the front and rear via the shotcrete. Therefore, the supporting members 4 of the newly installed panel-type shoring 3 and the supporting members 4 of the existing panel-type shoring 3a are combined to ensure the cross-sectional dimensions required for the steel shoring, and the necessary strength for the supporting structure 30 of the tunnel T can be ensured.
[0063] In addition, the support members 4 adjacent to each other on the left and right are joined at their tops via the joiner 73, so that the axial force between the support members 4 is pressure-bonded by the joint plate 48, and bending forces in the vertical direction (strong axis side) and horizontal direction (weak axis side) are transmitted by the joiner 73. The joiner 73 is tapered so that the cross-sectional shape is reduced toward the tip, making it easy to insert into the joint plate 48. In addition, by inserting the joiner 73 into the opening of the joint plate 48, the joiner 73 guides the joint pin 74 so that it is inserted into the engagement hole 76, so that the support members 4 can be easily joined together by simply operating the heavy equipment (erector). In addition, since the joint plate 48 and the stiffener 75 are formed at positions away from each other, the connection state between the support members 4 via the joiner 73 is stable.
[0064] The embodiment of the present invention has been described above. However, the present invention is not limited to the above embodiment, and each of the above components can be appropriately modified without departing from the spirit of the present invention. For example, in each of the above embodiments, the supporting members 4 arranged at the front and rear (the new supporting member 4 and the existing supporting member 4) are connected to each other at the top of the supporting member 4, but the supporting members 4 adjacent to each other at the front and rear may be connected to each other at a part other than the top. For example, both supporting members 4 may be fixed by pins 8 in a state where they are sandwiched by connecting plates 7 from the front and rear at the legs of the supporting members 4.
[0065] In addition, in each of the above embodiments, the support members 4 are connected to each other using the pins 8 or the joint pins 74, but the support members 4 may be connected to each other with bolts. Furthermore, the left and right support members 4, 4 may be connected to each other by engaging the pin 8 provided on one support member 4 with an engagement hole formed in the joint plate 48 of the other support member 4. In addition, in each of the above-described embodiments, the primary shotcrete 21 is sprayed after excavation, but the primary shotcrete 21 may be applied according to the ground conditions. That is, in sections of relatively stable bedrock, the primary shotcrete 21 may be omitted.
[0066] Moreover, the transmission plate 9 may be provided as required. In addition, in the first embodiment, the pin 8 fixed to one connecting plate 7 is inserted into the other connecting plate 7, but the pin 8 may also be fixed (engaged, fastened, mechanically fixed, etc.) to the other connecting plate 7.
[0067] In each of the above embodiments, an arch shape is formed by combining left and right panel-type supports 3, 3, but the shape of the panel-type support 3 is not limited, and for example, one panel-type support 3 may be arch-shaped, or three or more panel-type supports 3 may be combined to form an arch shape. The panel-type support 3 may be manufactured in a factory and then transported into the tunnel, or it may be manufactured on-site. The wire mesh 5 may be installed as necessary, and may be omitted, for example, in sections with good quality natural ground. [Explanation of symbols]
[0068] 1 Shoring 2. Shotcrete 3. Panel-type support structure 30 Support structure 4 Supporting members 45 Stud material 46 Bracket 47 Bottom plate 47a First bottom plate 47b Second bottom plate 47c Guide pin 47d through hole 48 Joint plate 5. Wire Mesh 6. Steel joints 61 Handle 7 Connecting plate 73 Joiner 74 Joint pin 75 Stiffener 8-pin 9 Transmission Plate T-Tunnel
Claims
1. A pair of support members disposed at the front and rear; A panel-type support structure comprising a connecting steel material that connects the support members together, The support member has a U-shaped cross section formed by a pair of flanges and a web connecting the pair of flanges, The pair of support members are provided such that the tips of the flanges face each other, A bottom plate having a guide pin standing thereon is fixed to the lower end of the support member provided on the face side, A panel-type support structure, characterized in that a bottom plate having a through hole formed therein is fixed to the lower end of the support member provided on the tunnel entrance side.
2. A pair of support members disposed at the front and rear; A panel-type support structure comprising a connecting steel material that connects the support members together, The support member has a U-shaped cross section formed by a pair of flanges and a web connecting the pair of flanges, The pair of support members are provided such that the tips of the flanges face each other, A panel-type support structure, characterized in that the support member provided on the face side is provided with a receiving bracket protruding toward the face side.
3. A panel-type support as described in claim 1 or claim 2, characterized in that the support member has a cross-sectional area that is at least half the cross-sectional area of the steel support set by a support pattern corresponding to the ground grade, and a cross-sectional modulus that is at least half the cross-sectional modulus of the steel support.
4. The panel-type support structure according to any one of claims 1 to 3, further comprising a wire mesh provided between the support members along the circumferential direction of the support members.
5. A panel-type support structure as described in any one of claims 1 to 4, characterized in that the web of at least one of the pair of support members is provided with a plurality of stud materials protruding on the opposite side of the other support member.
6. A panel-type support structure as described in any one of claims 1 to 5, characterized in that a handle that can be held by an erector is fixed to the connecting steel material.
7. An arch-shaped support structure formed by connecting panel-type supports in the circumferential direction of a tunnel, The panel-type support structure includes a pair of support members arranged at the front and rear, and a connecting steel member connecting the support members to each other, The support member has a U-shaped cross section formed by a pair of flanges and a web connecting the pair of flanges, The pair of support members are provided such that the tips of the flanges face each other, A joiner having a joint pin at its tip is protruding from the joint plate at the upper end of the support member of one of the panel-type supports, A support structure characterized in that the upper end of the support member of the other panel-type support is provided with a joint plate having an opening through which the joiner is inserted, and a stiffener capable of engaging the joint pin is fixed thereto.
8. an excavation step of excavating natural ground; A tunnel construction method comprising: a supporting step of forming a support along a ground surface exposed by excavating the ground, The support process includes a construction work for erecting the panel-type support structure according to any one of claims 1 to 6, and a spraying operation of spraying sprayed concrete toward the ground surface. This tunnel construction method is characterized in that, in the installation work, the panel-type support is installed in a state in which the web of the support member on the tunnel entrance side of the newly installed panel-type support is juxtaposed to the web of the support member on the face side of the existing panel-type support.
9. A tunnel construction method as described in claim 8, characterized in that, during the installation work, a pair of left and right panel-type supports are connected to each other at their upper ends to form an arch shape.
Citation Information
Patent Citations
In the tunnel assembly support
JP1982038900U
Lamination of photopolymerizing film
JP1988074051A
Support method
JP1999159298A
Protective structure of existing tunnel lining
JP2003082991A
Connection structure of composite segment and composite segment provided with it
JP2008144505A