Fuel exchange method and fuel exchange device
The method optimizes fuel exchange in nuclear reactors by minimizing transfers to the spent fuel pool and enhancing in-reactor movements, thereby shortening the process and ensuring subcriticality.
Patent Information
- Application Number
- JP2023080662
- Authority / Receiving Office
- JP · JP
- Patent Type
- Patents
- Current Assignee / Owner
- Filing Date
- 2023-05-16
- Publication Date
- 2026-11-11
- Estimated Expiration
- 2043-05-16
AI Technical Summary
Conventional fuel exchange methods in nuclear reactors are time-consuming due to the need for transferring fuel between the reactor and the spent fuel pool, and the process heavily relies on individual expertise, lacking standardized automation.
A method and apparatus that involves temporarily placing spent fuel in the spent fuel pool and using a fuel exchange machine to rearrange fuel within the reactor core, minimizing transfers to the spent fuel pool and optimizing in-reactor movements to reduce overall process time.
This approach significantly shortens the fuel exchange period by reducing time spent transferring fuel between the reactor and spent fuel pool, allowing for parallel inspection and fuel movement, and ensures subcriticality through strategic fuel placement.
Smart Images

Figure 0007948888000001 
Figure 0007948888000002 
Figure 0007948888000003
Abstract
Description
Technical Field
[0001] The present invention relates to a fuel exchange method and a fuel exchange apparatus for a boiling water nuclear reactor.
Background Art
[0002] Patent Document 1 describes that after a plurality of fuels are simultaneously transferred from the reactor core to the SFP (Spent Fuel Pool), fuel shuffling considering the fuel arrangement of the reactor core and replacement with new fuel are performed in the SFP, and then a plurality of fuels are simultaneously transferred from the SFP to the reactor core and loaded.
[0003] Patent Document 2 describes that the target extracted fuel arrangement for each unit work period during execution of reactor core-related work is determined based on fuel arrangement information, work processes for each unit work period, constraint conditions, and the like, and the fuel movement work procedure for each unit work period is created based on the target extracted fuel arrangement, the upper limit value of the number of possible fuel movements in the unit work period, fuel arrangement information, constraint conditions, and the like.
Prior Art Documents
Patent Documents
[0004]
Patent Document 1
Patent Document 2
Summary of the Invention
Problems to be Solved by the Invention
[0005] In nuclear power plants, as part of nuclear fuel management in the nuclear reactor, fuel exchange (fuel shuffling) is performed periodically to achieve uniform burnup and effective utilization of nuclear fuel. Fuels are classified according to their in-core residence cycles, and in fuel exchange, fuels are moved to the positions where fuels of the next cycle number should be placed.
[0006] The fuel residing in the reactor undergoes five cycles, from one to five. The fuel in the fifth cycle, which has the longest stay, is removed from the reactor. The fuel from cycles one through four is then moved to the position corresponding to the next cycle (cycles two through five).
[0007] This transfer may involve either passing through another location, such as a spent fuel pool, before being loaded at the final loading location, or moving directly from the source to the destination.
[0008] Conventionally, the method employed involved moving all the fuel from the reactor to the spent fuel pool, performing inspections, and then moving the fuel from the spent fuel pool to the designated position in the reactor based on the fuel placement information after shuffling within the reactor. This process required time for the fuel to move between the spent fuel pool and the reactor, which contributed to the prolongation of the fuel transfer process and the overall periodic inspection process.
[0009] Furthermore, the fuel exchange procedure described above is created by the workers themselves, and it is necessary to accurately set the source and destination of each fuel, as well as to check the subcriticality of the reactor, which places a heavy burden on those who create the fuel exchange procedure.
[0010] In particular, there was a demand to shorten the periodic inspection process, so the plan had to be created while considering that the fuel transfer process and inspection work would be carried out in parallel. However, the created process tended to depend on the experience and skill of the person who created it.
[0011] As mentioned above, conventional methods for creating fuel change procedures are highly dependent on the individual who creates them. Therefore, it has been difficult to provide guidelines for creating fuel change procedures when automating the procedure creation process.
[0012] Patent Document 1 shows that fuel exchange time can be shortened by moving fuel from the reactor core to the SFP (Ship Free Space), performing fuel replacement within the SFP while considering the arrangement within the reactor core after fuel shuffling, and then simultaneously moving multiple fuel assemblies from the SFP to the reactor core and loading them into the reactor. This method is expected to reduce the number of fuel movements that are constrained within the reactor and to shorten the fuel movement process in a systematic way. However, since fuel movement between the SFP and the reactor core takes time, further measures to shorten the time are required.
[0013] Patent Document 2 demonstrates that an efficient fuel shuffling plan can be created using a fuel database containing data on the initial fuel arrangement in the reactor core, the final target fuel arrangement, and the target fuel; a work environment database containing data on the core structure and fuel pool structure of the target reactor; and a periodic inspection process database containing data on the target, duration, and proposed work process for core-related work requiring fuel transfer or control rod operation during periodic inspections of the reactor. However, fuel transfer between the SFP and the reactor core still occurs as before, and further measures to shorten the process are needed.
[0014] This invention has been made in view of the circumstances described above, and aims to provide a fuel replacement method and a fuel replacement device that can shorten the fuel replacement work period during periodic inspections compared to conventional methods. [Means for solving the problem]
[0015] The present invention includes multiple means for solving the above problems, but one example is a method for replacing fuel in the core of a boiling water reactor, comprising the steps of moving spent fuel that has completed a predetermined in-reactor stay cycle to a spent fuel pool, Inspection Perform position The process includes the step of temporarily placing the fuel loaded in the vehicle into the empty space after the used fuel has been moved. [Effects of the Invention]
[0016] According to the present invention, it is possible to shorten the period of fuel exchange work in periodic inspections compared with the conventional case. Problems, configurations, and effects other than those described above will be clarified by the following description of the embodiments. [Brief Description of the Drawings]
[0017] [Figure 1] It is a plan view of a nuclear power plant provided with the fuel exchange apparatus and peripheral facilities according to the first embodiment. [Figure 2] It is a top view of the nuclear power plant provided with the fuel exchange apparatus and peripheral facilities according to the first embodiment. [Figure 3] It is a diagram for explaining movement constraints related to fuel movement. [Figure 4] It is a functional block diagram of the fuel exchange apparatus according to the first embodiment. [Figure 5] It is a functional block diagram of another configuration of the fuel exchange apparatus according to the first embodiment. [Figure 6] It is a conceptual diagram of fuel movement in the fuel exchange method according to the first embodiment. [Figure 7] It is a flow diagram showing an outline of the work flow in the fuel exchange method according to the first embodiment. [Figure 8] It is a diagram showing the effect of fuel movement by the fuel exchange apparatus and the fuel exchange method of the first embodiment. [Figure 9] It is a diagram showing reactor shutdown margin evaluation results for confirming the subcriticality of the reactor related to temporary fuel placement at the outermost periphery of the core in the fuel exchange method according to the second embodiment. [Figure 10] It is a diagram showing an outline of fuel movement in the fuel exchange method of the third embodiment. [Figure 11] It shows an output example of fuel movement information in the fuel exchange apparatus according to the fourth embodiment. [Mode for Carrying Out the Invention]
[0018] Embodiments of the fuel exchange method and fuel exchange apparatus of the present invention will be described below with reference to the drawings. In the drawings used herein, the same or corresponding components are denoted by the same or similar reference numerals, and repeated descriptions of these components may be omitted.
[0019] <First Embodiment> A first embodiment of the fuel exchange method and fuel exchange apparatus of the present invention will be described with reference to Figures 1 to 8.
[0020] First, the configuration of a nuclear power plant equipped with a fuel exchange device and peripheral equipment will be explained using Figures 1 to 3. Figure 1 is a plan view of a nuclear power plant equipped with a fuel exchange device and peripheral equipment according to the first embodiment, Figure 2 is a top view thereof, and Figure 3 is a diagram illustrating the movement constraints related to fuel movement.
[0021] Figures 1 and 2 show the nuclear power plant 1 during a periodic inspection. The nuclear power plant 1 includes a reactor 60, a spent fuel pool 70, a fuel exchange machine 80, a fuel arrangement management device 120, a display unit 110, an input device 112, and the like.
[0022] Of these, the fuel exchange system for the reactor core 63 of reactor 60 consists of a fuel exchange machine 80 and a fuel arrangement management system 120.
[0023] The reactor 60 comprises a reactor pressure vessel 61 and a reactor well 68 located on its upper part. The reactor pressure vessel 61 is surrounded by a reactor containment vessel (omitted for illustrative purposes) and is installed within a reactor building (omitted in the illustration). The reactor 60 is connected to a spent fuel pool 70 via a gate section 72. Multiple fuel assemblies 4 are arranged in the reactor core 63 of the reactor pressure vessel 61 and in the spent fuel pool 70, respectively. Furthermore, the reactor 60, the spent fuel pool 70, and the gate section 72 are filled with water W, indicated by dots.
[0024] The reactor core 63 of reactor 60 is composed of fuel assemblies 4, control rods 5, neutron instrumentation tubes (not shown), etc. Each fuel assembly 4 consists of bundles of fuel rods and water rods placed inside a channel box. The fuel rods are filled with fuel pellets. The channel box forms a flow path for the coolant and prevents the floating of steam that is heated and boiled by the fuel rods. Outside the channel box, that is, between the fuel assemblies, there is a region of non-boiling water which promotes neutron deceleration, and also serves as a space for inserting control rods and a location for installing neutron instrumentation tubes.
[0025] The reactor 60 is designed so that it can be shut down by the other control rods 5 even if the control rod 5 with the highest reactivity value is not inserted. The reactor shutdown margin is an indicator of the margin of the reactor 60's ability to shut down, and it shows how much margin the reactor 60 has from criticality when all the control rods 5 are inserted. If this reactor shutdown margin is above a predetermined value, it is determined that the reactor can maintain a subcritical state.
[0026] Figure 3 is a conceptual diagram showing one section of the reactor core 63 of reactor 60. The reactor core 63 of reactor 60 is divided into multiple square sections in a plan view, and these divided sections are called "cells 62".
[0027] As shown in Figure 3(a), each cell 62 can accommodate four fuel assemblies 4. Each fuel assembly 4 has a rectangular ID on its top surface, which is engraved or printed with a unique ID (identification number).
[0028] Here, if we consider the state shown in Figure 3(a) and then further withdraw fuel assemblies 4b and 4c, and attempt to withdraw fuel assembly 4a, there is a risk that fuel assembly 4a and control rods 5 may tip over. Therefore, in order to satisfy the constraints on fuel movement, unless fuel assemblies are loaded or temporarily placed at the positions of fuel assemblies 4b and 4c, or unless a double-blade guide 6 equivalent to dummy fuel is inserted as shown in Figure 3(b), further withdrawal of fuel assembly 4a and loading of fuel assembly 4a at its position is not possible.
[0029] As shown in Figure 3, the control rods 5 are cross-shaped and are arranged at a ratio of one rod per four fuel assemblies 4, i.e., one rod per cell 62. In a boiling water reactor, the control rods 5 are inserted from the bottom of the reactor core. Neutron instrumentation tubes are installed at a ratio of one tube per sixteen fuel assemblies 4.
[0030] Returning to Figures 1 and 2, the fuel exchange machine 80 is a device for moving fuel assemblies 4 within the reactor core 63 and between the reactor core 63 and the spent fuel pool 70, and includes a fuel exchange trolley 81, an expansion joint 82, a cable 87, a fuel exchange control device 88, etc.
[0031] The fuel exchange trolley 81 is installed above the reactor 60 and the spent fuel pool 70 so as to be movable horizontally. The telescopic tube 82 is attached to the fuel exchange trolley 81 and moves the fuel assembly 4 vertically by gripping and extending the tube. This allows the fuel exchange machine 80 to move the fuel assembly 4 to the desired position in the reactor 60 and the spent fuel pool 70.
[0032] The fuel exchange trolley 81 and the telescopic pipe 82 are connected to the fuel exchange control device 88 via a cable 87. The fuel exchange control device 88 receives work signals from the fuel arrangement management device 120 that command the details of fuel exchange work, and moves the fuel assembly 4 based on these work signals. The fuel exchange control device 88 can also perform fuel exchange work through manual operation by an operator. The fuel exchange control device 88 also outputs information on the placement of the fuel assembly 4 after the fuel exchange work to the fuel arrangement management device 120.
[0033] In addition to the elements shown in Figure 2, the fuel exchange machine 80 includes a pair of rails 83, a pair of other rails 84, and a traverse carriage 86. The rails 83 extend above the reactor 60 and the spent fuel pool 70, along the left-right direction in the figure. The fuel exchange carriage 81 moves along the upper surface of the rails 83 in the left-right direction. The rails 84 are laid on the upper surface of the fuel exchange carriage 81 in a direction perpendicular to the rails 83 (referred to as the front-rear direction), and move along the rails 83 in the left-right direction together with the traverse carriage 86.
[0034] Furthermore, the traverse carriage 86 moves in the forward and backward direction along the rail 84. As a result, as described above, the fuel exchange carriage 81 can move freely on a plane above the reactor 60 and the spent fuel pool 70.
[0035] The fuel placement management device 120 is a device that generates fuel movement patterns and outputs work signals to the fuel exchange control device 88 to instruct it on the details of fuel exchange work, etc. In this embodiment, the fuel placement management device 120 moves spent fuel assemblies 4 that have completed a predetermined in-reactor stay cycle to the spent fuel pool 70, and then temporarily places fuel assemblies 4 loaded at coordinates where core-related work will be performed in the empty space left after the spent fuel assemblies 4 have been moved. The details will be described later.
[0036] Furthermore, it is desirable that the fuel arrangement management device 120 designates the spent fuel assemblies 4 as those loaded on the outermost periphery of the reactor core 63. Details of this will be described later.
[0037] This fuel distribution management device 120 is equipped with hardware typical of a computer, such as a CPU (Central Processing Unit), RAM (Random Access Memory), ROM (Read Only Memory), and SSD (Solid State Drive). The SSD stores the OS (Operating System), management programs, and various data. The OS and management programs are loaded into RAM and executed by the CPU.
[0038] The input device 112 is equipped with a mouse, keyboard, etc. (not shown) and is operated by the operator.
[0039] Figure 4 shows a functional block diagram of the fuel exchange device according to the first embodiment, and Figure 5 shows a variation.
[0040] In Figure 4, the internal structure of the fuel distribution management device 120 is shown as blocks representing functions implemented by a management program, etc. The fuel distribution management device 120 includes an input unit 122, a fuel transfer plan database 126, a fuel transfer pattern generation unit 124, a remote control unit 144, a fuel transfer performance database 127, a fuel transfer plan display unit 145, an output unit 142, and the like.
[0041] The input unit 122 receives operator operation information or pre-programmed control information from the input device 112, and the fuel transfer pattern generation unit 124 generates a fuel transfer process based on fuel transfer source and destination information from the fuel transfer plan database 126. Fuel transfer information is sent to the remote control unit 144 according to the generated fuel transfer process, and this information is stored in the fuel transfer performance database 127 to record the fuel transfer status. In addition, the fuel transfer plan display unit 145 outputs the fuel transfer plan sequentially, and the output result from the output unit 142 is presented to the operator by the display unit 110.
[0042] The fuel distribution management device 120A in Figure 5 is a functional block diagram in which a fuel loading status monitoring unit 134, which monitors whether fuel loading is being carried out correctly, is added to the fuel distribution management device 120 shown in Figure 4. The "fuel distribution management device 120" described above or below can be replaced with "fuel distribution management device 120A" as appropriate.
[0043] Regarding fuel status monitoring, there are systems that use camera images to automatically read fuel IDs and compare them with fuel transfer plan information to ensure that the fuel loading status is always correct. Methods for monitoring fuel loading status that do not rely on camera images are also included.
[0044] Figure 6 is a 1 / 4 scale simplified schematic plan view of the reactor core 63 of reactor 60 shown in Figure 2.
[0045] As shown in Figure 6, fuel assemblies 4 loaded into the reactor core 63 are arranged in cells 62. The numbers marked in the center of cell 62 represent the cycle number, which is divided according to the length of time the fuel assemblies 4 reside in the reactor. The cycle number for newly loaded fuel is set to "1", and the cycle number for fuel that has been loaded in the reactor for a certain period and is ready to be removed from the reactor core is set to "5", and the numbers are shown from "1" to "5". During fuel replacement, 1-cycle fuel is moved to the position where 2-cycle fuel was loaded, similarly 2-cycle fuel is moved to the 3-cycle fuel position, and 3-cycle fuel is moved to the 4-cycle fuel position.
[0046] In conventional fuel transfer methods, the fuel loaded at the inspection location (the area hatched with dots) is first removed to the spent fuel pool 70 (as shown in Figure 6, one fuel assemblies each for 1st, 2nd, 3rd, and 4th cycles are loaded). At this point, the fuel loading location at the inspection location is empty, allowing the inspection to begin.
[0047] After the inspection begins, the fuel that has completed a predetermined in-reactor stay cycle (in this embodiment, the fuel loaded on the outermost periphery) is removed to the spent fuel pool 70. All the fuel moved here is being moved to the spent fuel pool 70, and the travel time from the core 63 to the spent fuel pool 70 is longer than the travel time within the reactor, which is a factor that prolongs the process.
[0048] In fuel transfer, a fuel source and destination must be paired to enable fuel transfer. Therefore, if there is no available space at the destination, fuel can be moved to another location to create space, thereby enabling fuel transfer. Based on these findings, if there is another available space within the reactor, regardless of the outermost perimeter, the fuel loaded at a potential destination can be moved to that available space to secure the destination space, thereby reducing the distance of fuel transfer.
[0049] Furthermore, in order to create empty space in the reactor 60, spent fuel that has completed a predetermined number of reactor stay cycles (5-cycle fuel) is removed to the spent fuel pool 70. This allows for the creation of empty space at the destination without the need for unnecessary fuel transfer to the spent fuel pool 70.
[0050] In the first embodiment, first, the spent fuel from the 5th cycle, which has been loaded on the outermost periphery as fuel that has gone through a predetermined number of in-fuel stay cycles as shown in Figure 6, is moved to the spent fuel pool 70. Then, the fuel loaded at the inspection position (one fuel each from the 1st, 2nd, 3rd, and 4th cycles is loaded at the inspection position shown in Figure 6) is moved to the space that was removed and made available.
[0051] During this relocation, the outermost empty space is where the 4th and 5th cycle fuels should be loaded. Therefore, there is no space on the outermost edge for the 1st and 2nd cycle fuels that are currently loaded at the inspection position. For this reason, these fuels are temporarily placed on the outermost edge.
[0052] However, if temporary storage is necessary, it is highly desirable to confirm whether subcriticality can be ensured by loading fuel other than the cycle fuel that is originally intended to be loaded into that space.
[0053] The fuel transfer process described above will be explained using a flowchart with reference to Figure 7. Figure 7 is a flowchart showing an overview of the workflow in the fuel exchange method according to the first embodiment.
[0054] First, as shown in Figure 7, spent fuel assemblies 4 located on the outermost periphery and inside the reactor 60 that have completed a predetermined number of reactor stay cycles are moved to the spent fuel pool 70 (S11).
[0055] Subsequently, the fuel assembly 4, which is loaded in the position where inspection (core-related work) will be performed, is temporarily placed in the empty space created on the outermost periphery by the previous step S11 (S12).
[0056] Next, it is determined whether or not fuel assemblies 4 still exist at the inspection location (S13). If it is determined that they do exist, the process proceeds to step S14, where they are temporarily placed in the empty space in the reactor core 60 created in step S11 (S14), and all fuel assemblies 4 at the inspection location are temporarily placed in the empty space for temporary placement. If there is no empty space left in the reactor core 60, the minimum number of fuel assemblies 4 are moved to the spent fuel pool 70.
[0057] If it is determined in step S13 that the fuel is not present, or after the completion of step S14, the inspection work can be started when all the fuel in the inspection location has been drained, and the inspection work is performed (S15).
[0058] The inspection work includes tasks using the fuel exchange cart 81 used for moving fuel, but this is not always necessary, and if it is not needed, the fuel exchange cart 81 will be left waiting for work.
[0059] Here, by carrying out inspection work and moving fuel inside the furnace to locations other than the inspection location in parallel, the overall construction period can be shortened. Therefore, depending on the work status, fuel movement inside the furnace to locations other than the inspection location is carried out without waiting for the completion of step 15 (S16). Here, continuous fuel movement can be achieved in this S16 by performing the domino effect of fuel movement as shown in the third embodiment described later.
[0060] After the inspection work is completed, the fuel for the appropriate number of cycles is moved to the inspection position (S17), and new fuel is loaded into the position of the first cycle fuel (S18), completing the fuel transfer (shuffling).
[0061] Figure 8 shows the effect of fuel transfer by the fuel exchange device and fuel exchange method of the first embodiment, illustrating the inspection process in a boiling water reactor. In Figure 8, the number of fuel assemblies to be transferred is assumed to be 872.
[0062] As shown in Figure 8, in the conventional method, all fuel assemblies 4 are moved to the spent fuel pool 70, and after the inspection work is completed, the fuel is moved to the appropriate loading location. In contrast, the present invention uses in-fuel chamber movement as much as possible to move the fuel, thereby reducing the movement time between the spent fuel pool 70 and the inside of the reactor 60 by approximately two-thirds, and is expected to shorten the overall process by approximately one day. This effect will vary depending on the number of inspections and the number of fuel assemblies moved, and the effect can also be improved by parallelizing the fuel movement work and the inspection work.
[0063] Next, the effects of this embodiment will be described.
[0064] The fuel exchange device for the reactor core 63 of a reactor 60 according to the first embodiment of the present invention, comprising a fuel exchange machine 80 that moves fuel assemblies 4 within the reactor core 63 and between the reactor core 63 and the spent fuel pool 70, and a fuel placement management device 120 that generates a fuel movement pattern, wherein the fuel placement management device 120 moves spent fuel assemblies 4 that have elapsed a predetermined in-reactor stay cycle to the spent fuel pool 70, and then temporarily places fuel assemblies 4 loaded at coordinates where core-related work is to be performed in the empty space after the spent fuel assemblies 4 have been moved. Furthermore, the fuel exchange method for the reactor core 63 of a reactor 60 according to the first embodiment of the present invention comprises the steps of moving spent fuel assemblies 4 that have elapsed a predetermined in-reactor stay cycle to the spent fuel pool 70, and temporarily placing fuel assemblies 4 loaded at coordinates where core-related work is to be performed in the empty space after the spent fuel assemblies 4 have been moved.
[0065] This minimizes the transfer of fuel to the spent fuel pool 70, thereby shortening the fuel transfer time during fuel shuffling, and consequently shortening the process in periodic inspections compared to conventional methods.
[0066] Furthermore, by making the spent fuel assemblies 4 loaded on the outermost periphery of the reactor core 63, it becomes possible to temporarily place high-burnup fuel on the outermost periphery, making it easy to ensure subcriticality, and enabling the temporary placement of fuel assemblies 4 with various burnup levels while ensuring subcriticality.
[0067] <Second Embodiment> A fuel exchange method and fuel exchange apparatus according to a second embodiment of the present invention will be described with reference to Figure 9. Figure 9 is a diagram showing a reactor shutdown margin evaluation method for confirming the subcriticality of a reactor with respect to the temporary placement of fuel on the outermost periphery of the reactor core.
[0068] In the second embodiment, in addition to spent fuel assemblies 4 that have completed a predetermined number of in-reactor stay cycles, fuel assemblies 4 other than the spent fuel assemblies 4 located on the outermost periphery (fuel assemblies 4 with 5 cycles) (mainly fuel assemblies 4 with 4 cycles) are also removed to create a temporary storage area. This creates empty space for the fuel to be moved to without separately checking the subcriticality of the fuel during temporary storage.
[0069] In this embodiment shown in Figure 6, the areas hatched with dots within the grid indicate the areas from which fuel is removed from the reactor core.
[0070] First, as the first step, the 4-cycle fuel is removed from the core 63 in addition to the 5-cycle fuel located on the outermost edge. In the second step, the 1-cycle and 2-cycle fuel at the inspection positions are temporarily placed on the outermost edge. In the third step, the 3-cycle fuel is moved to the 4-cycle fuel position on the outermost edge, and the 4-cycle fuel is moved to the 5-cycle fuel position on the outermost edge.
[0071] The above steps remove all fuel from the inspection location, allowing the inspection work to begin. Note that the order in which steps 3 and 4 are performed does not matter, as the subsequent state will be the same regardless of which step is performed first.
[0072] Figure 9 shows the results of evaluating subcriticality using the reactor shutdown margin when one control rod 5 falls, with the outermost periphery loaded with high-burnup first-cycle fuel. If the reactor shutdown margin is 1%dk or more, it can be evaluated that subcriticality can be ensured.
[0073] In Figure 9, when considering fuel assembly 4d as an inner unit with control rods 5 surrounding it, fuel assembly 4e as the outermost unit without control rods 5 surrounding it, and a highly reactive temporary fuel assembly 4f, as shown in Figure 9, it was confirmed that the reactor shutdown margin in the event of one control rod 5 falling is 4.7% in Case 1, 3.4% in Case 2, and 2.7% in Case 3, and that this value is maintained in all cases. In some areas, there are regions where control rods are not present around the fuel, but even in those cases, subcriticality is guaranteed. From the above, it is possible to move fuel within the reactor using the outermost empty space as a temporary storage space for fuel of any cycle number.
[0074] Furthermore, if there are many inspection points, the amount of fuel to be removed from each inspection point will also increase, and it may not be possible to load all the fuel using only the empty space created by removing the fuel from the outermost perimeter. In such cases, the fuel from the four-cycle reactors other than those at the inspection points that has completed a predetermined number of in-reactor stay cycles can be removed to the spent fuel pool 70 to create empty space other than the outermost perimeter, and the four-cycle fuel loaded at the inspection points can be temporarily placed there to allow for the removal of the fuel at the inspection points.
[0075] Other configurations and operations are substantially the same as those of the fuel exchange method and fuel exchange apparatus of the first embodiment described above, and details are omitted.
[0076] The fuel exchange method and fuel exchange apparatus of the second embodiment of the present invention also provide substantially the same effects as the fuel exchange method and fuel exchange apparatus of the first embodiment described above.
[0077] Furthermore, by adding the steps of temporarily moving the fuel assemblies 4 loaded on the outermost periphery of the reactor core 63 to the spent fuel pool 70, and temporarily placing the fuel assemblies 4 loaded at the coordinates for performing core-related work in the empty space created by the temporary movement, it is possible to achieve in-reactor movement while reliably ensuring subcriticality.
[0078] <Third Embodiment> A third embodiment of the present invention, a fuel exchange method and a fuel exchange apparatus, will be described with reference to Figure 10. Figure 10 is a schematic diagram of fuel transfer in the fuel exchange method of the third embodiment.
[0079] In the third embodiment, similar to the first embodiment, the fuel assembly 4 that is to be removed is removed to the spent fuel pool 70. However, the spent fuel assembly 4 that has completed a predetermined number of in-reactor stay cycles is N+2 cycle fuel, and the N+1 cycle fuel is moved to the position of the N+2 cycle fuel which has become available through movement, and the N cycle fuel is moved to the position of the N+1 cycle fuel which has become available through movement.
[0080] More specifically, instead of removing all the fuel that should be removed, the same number of fuel assemblies 4 as those loaded in the inspection cell 62 are removed. This creates a state where the fuel assemblies 4 are loaded in all cells 62 except the inspection cell 62, and the fuel assemblies 4 in the inspection cell 62 have been removed, allowing the inspection work to begin.
[0081] After the inspection work begins, fuel is moved to locations other than the inspection area. However, since the number of fuel exchange machines 80 used for fuel movement is limited, fuel movement can be carried out if there is enough space at the fuel loading site to accommodate the number of machines.
[0082] Therefore, the fuel placement management device 120 can move the fuel assemblies 4 to the position where they will be subsequently loaded in the reactor, thereby enabling fuel transfer by moving only the minimum necessary number of fuel assemblies 4 to the spent fuel pool 70.
[0083] Furthermore, it is desirable for the fuel placement management device 120 to move the fuel assembly 4 loaded in the target cell 62 to the position of a cell 62 loaded with a fuel assembly 4 that has had an equivalent or longer stay in the reactor, in order to create a destination for the movement of the fuel assembly 4.
[0084] More specifically, as shown in Figure 10, fuel transfer can be continuously performed by having the 3-cycle fuel move to the 4-cycle fuel position, the 2-cycle fuel move to the 3-cycle fuel position that became vacant as a result of the previous transfer, and the 1-cycle fuel move to the 2-cycle fuel position that became vacant as a result of the previous transfer (hereinafter referred to as domino effect transfer).
[0085] In Figure 10, the circled numbers indicate the location of the fuel loading destination: (a) the 3-cycle fuel moves to the 4-cycle fuel position, (b) the 2-cycle fuel moves to the 3-cycle fuel position, (c) the 1-cycle fuel moves to the 2-cycle fuel position, and (d) the 1-cycle fuel position becomes an empty space.
[0086] The empty space at the 1-cycle fuel position created by the domino effect described above will eventually be used to load new fuel from outside the reactor. However, in this domino effect, the 4-cycle fuel is temporarily placed in the 1-cycle fuel position that was vacated by the previous movement, in order to enable the next domino effect. This allows the 3-cycle fuel to move to the 4-cycle fuel position, enabling the next domino effect.
[0087] Fuel temporarily placed at the 1-cycle position to continue the chain reaction movement will be moved to the spent fuel pool 70 or the final loading position in the reactor after the fuel movement is complete, and the new fuel will be loaded at the 1-cycle fuel position, completing the fuel movement.
[0088] In the third embodiment, during the chain reaction movement, there is no available space other than the inspection position and the fuel transfer destination space. Therefore, there are no constraints on fuel transfer, and there is flexibility in selecting the fuel transfer source.
[0089] Furthermore, while the fuel movement constraints shown in Figure 3 may necessitate the use of a double-blade guide 6, in the third embodiment, since only empty space exists at the destination and other cells are loaded with fuel, fuel can be removed and loaded without using the double-blade guide 6. Because the movement of the double-blade guide 6 is unnecessary, a further reduction in the fuel movement process can be expected.
[0090] Other configurations and operations are substantially the same as those of the fuel exchange method and fuel exchange apparatus of the first embodiment described above, and details are omitted.
[0091] In the fuel exchange method and fuel exchange apparatus of the third embodiment of the present invention, substantially the same effects as those of the fuel exchange method and fuel exchange apparatus of the first embodiment described above can be obtained.
[0092] Furthermore, when moving fuel within the reactor, spent fuel that has completed a predetermined number of in-reactor stay cycles is N+2 cycle fuel. By further including the step of moving N+1 cycle fuel to the position of the N+2 cycle fuel which has become available due to the movement, and moving N cycle fuel to the position of the N+1 cycle fuel which has become available due to the movement, it becomes possible to move fuel within the reactor other than the inspection work position during inspection work. This allows fuel movement work and inspection work to be carried out in parallel, and by making frequent use of fuel exchange by moving fuel within the reactor, it is possible to minimize movement between the reactor core 63 and the spent fuel pool 70, which is a factor that prolongs fuel movement, and further shorten the construction period. Moreover, since the next fuel assembly 4 is loaded into the space from which the fuel assembly 4 was withdrawn, it is not possible to withdraw adjacent fuel assemblies 4 within the same cell 62, and the fuel assemblies 4 that are withdrawn must always be in diagonal positions. This constraint condition in the extraction and loading of fuel within the reactor can be easily met, and further process shortening effects can be expected.
[0093] Furthermore, by adding a step of temporarily moving the fuel assembly 4 loaded at the target position to a position where a fuel assembly 4 with an equivalent or longer in-reactor residence time is loaded, it is possible to achieve in-reactor movement while ensuring subcriticality and shorten the process.
[0094] <Fourth Embodiment> A fuel exchange method and fuel exchange apparatus according to a fourth embodiment of the present invention will be described with reference to Figure 11. Figure 11 shows an example of fuel transfer information output in a fuel exchange apparatus according to the fourth embodiment.
[0095] In the fourth embodiment, the fuel transfer pattern and the next fuel transfer information are displayed on the display unit 110, making it possible to confirm that the planned fuel transfer is being carried out reliably. An example of the display screen 50 on the display unit 110 is shown in Figure 11.
[0096] In the display screen 50 in Figure 11, the inside of the reactor core 63 is displayed on the left side of the screen, and the internal conditions can be viewed in more detail using the Zoom button. The source and destination locations of the fuel to be moved in the next step are displayed in rectangular frames on the screen, making the movement plan easy to understand at a glance. The coordinates of the source and destination of the fuel and the ID of the fuel are displayed on the right side of the screen. By using this in conjunction with separately installed camera images (not shown), it is possible to check in real time whether the movement is being carried out correctly.
[0097] Other configurations and operations are substantially the same as those of the fuel exchange method and fuel exchange apparatus of the first embodiment described above, and details are omitted.
[0098] In the fuel exchange method and fuel exchange apparatus of the fourth embodiment of the present invention, substantially the same effects as those of the fuel exchange method and fuel exchange apparatus of the first embodiment described above can be obtained.
[0099] Furthermore, by including a step in which the movement pattern of the fuel assembly 4 and the fuel movement information for the next step are displayed on the display unit 110, the user can easily grasp the progress of the work and whether the movement work is proceeding correctly.
[0100] <Other> It should be noted that the present invention is not limited to the embodiments described above, and includes various modifications. The embodiments described above are explained in detail for the purpose of clearly illustrating the present invention, and are not necessarily limited to those having all the configurations described.
[0101] Furthermore, it is possible to replace parts of the configuration of one embodiment with parts of the configuration of another embodiment, and it is also possible to add parts of the configuration of another embodiment to the configuration of one embodiment. In addition, it is possible to add, delete, or replace parts of the configuration of each embodiment with parts of other configurations.
[0102] For example, the functions described above can be implemented in hardware or programmed and executed in software. [Explanation of symbols]
[0103] 1… Nuclear power plant 4,4a,4b,4c,4d,4e,4f…Fuel assembly 5... Control rods 6…Double Blade Guide 50…Display screen 60…Nuclear reactor 61… Reactor pressure vessel 62...Cell (partition) 63…Core 68… Reactor well 70…Spent Fuel Pool (SFP) 72...Gate section 80…Fuel exchange machine 81…Fuel exchange trolley 82...Extension pipe 83, 84… rails 86...Traversing bogie 87… Cable 88... Fuel exchange control device 110...Display section 112...Input device 120,120A…Fuel placement management device 122...Input section 124...Fuel transfer pattern generation unit 126…Fuel Transfer Plan Database 127…Fuel Transfer Record Database 134...Fuel Loading Status Monitoring Unit 142...Output section 144... Remote Control Unit 145...Fuel transfer plan display unit W…Water
Claims
1. A method for replacing the fuel in the core of a boiling water reactor, The steps include: moving spent fuel that has completed a predetermined in-reactor stay cycle to a spent fuel pool; The step includes temporarily placing the fuel loaded at the inspection location in the empty space after the used fuel has been moved. How to change fuel.
2. In the fuel exchange method described in claim 1, The spent fuel that has completed the predetermined in-reactor stay cycle is loaded onto the outermost periphery of the reactor core. How to change fuel.
3. In the fuel exchange method described in claim 1, Let N be a natural number. When moving the fuel within the reactor, if we define spent fuel that has completed a predetermined number of reactor stay cycles as N-cycle fuel, the process further includes the steps of moving N-1 cycle fuel to the position of the N-cycle fuel which has become available due to the movement, and moving N-2 cycle fuel to the position of the N-1 cycle fuel which has become available due to the movement. How to change fuel.
4. In the fuel exchange method described in claim 1, The spent fuel that has completed the predetermined in-reactor stay cycle is the fuel loaded on the outermost periphery of the reactor core, The process further includes the step of temporarily placing the fuel loaded at the inspection location into the empty space created by moving the aforementioned fuel. How to change fuel.
5. A fuel exchange method according to claim 1, When moving the fuel inside the reactor, the process further includes the step of temporarily placing the fuel in an empty space of cycle fuel whose residence time inside the reactor is equal to or longer than that of the fuel itself. How to change fuel.
6. In the fuel exchange method described in claim 1, The method further includes the step of displaying the fuel movement pattern and fuel movement information for the next step on a display device. How to change fuel.
7. A fuel exchange device for the core of a boiling water reactor, A fuel exchange machine for moving fuel within the reactor core and between the reactor core and the spent fuel pool, A fuel distribution management device that generates a fuel transfer pattern is provided, The fuel placement management device is Spent fuel that has completed a predetermined in-reactor stay cycle is moved to the spent fuel pool, and then fuel loaded in a position to be inspected is moved to the empty space left after the spent fuel has been moved. Fuel exchange device.
8. In the fuel exchange device according to claim 7, The fuel placement management device places spent fuel that has completed the predetermined in-reactor stay cycle at the outermost periphery of the reactor core. Fuel exchange device.
9. In the fuel exchange device according to claim 7, Let N be a natural number. When moving the fuel within the furnace, if we define the spent fuel that has completed a predetermined number of furnace stay cycles as N-cycle fuel, then we move the N-1 cycle fuel to the position of the N-cycle fuel that has become available due to the movement, and move the N-2 cycle fuel to the position of the N-1 cycle fuel that has become available due to the movement. Fuel exchange device.
10. In the fuel exchange device according to claim 7, The fuel placement management device moves spent fuel that has completed the predetermined in-fuel stay cycle to the spent fuel pool, and moves the fuel loaded at the inspection position to the newly created empty space. Fuel exchange device.
11. In the fuel exchange device according to claim 7, The fuel placement management device moves the fuel loaded in the target position to an empty space in the cycle fuel so that its in-fuel residence time is equal to or greater than that of the fuel itself. Fuel exchange device.
12. In the fuel exchange device according to claim 7, The system further comprises a display device that displays the fuel transfer pattern and the next fuel transfer information. Fuel exchange device.
Citation Information
Patent Citations
Method for loading reactor core of million-kilowatt pressurized water reactor nuclear power plant for 18 months
CN112259269A
Method for preparing fuel exchange procedure
JP1989312491A
Supporting device for planning of fuel transfer
JP1991248093A
Fuel loading method and core of nuclear reactor
JP1993080175A
Fuel replacing method
JP1995167977A