Arch installation method

By using the boom to grab and carry construction personnel in the arch frame installation method, the exposure time of construction personnel under the excavation surface is reduced, the safety risks and operation difficulty in the existing technology are solved, and the construction efficiency is improved And save costs.

WO2024235192A1PCT designated stage expired Publication Date: 2024-11-21SICHUAN LANHAI ENG EQUIP MFG CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
PCT/CN2024/092844
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-18
Filing Date
2024-05-13
Publication Date
2024-11-21

AI Technical Summary

Technical Problem

In the existing arch frame installation methods, construction workers have long exposure to the excavation surface, which poses great safety risks, and is difficult to operate, which affects construction efficiency.

Method used

Part of the boom frames grab the middle section arch frame and the edge section arch frames separately, and complete the installation and connection of the connection points in a short time, reducing the exposure time of construction workers under the excavation surface. Use a separate boom frame to carry construction workers Perform homework and simplify operations.

Benefits of technology

Reduce construction risks, improve construction efficiency, and save costs by reducing the use of hanging baskets.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2024092844_21112024_PF_FP_ABST
    Figure CN2024092844_21112024_PF_FP_ABST
Patent Text Reader

Abstract

An arch installation method, comprising: step S1, by means of a portion of booms, separately grabbing and moving a middle section arch and an edge section arch at one side of the middle section arch to designated positions; step S2, carrying construction personnel on a remaining boom to complete connection at a connecting point of the middle section arch and the edge section arch at one side of the middle section arch; step S3, releasing the boom grabbing the middle section arch; step S4, using the released boom to grab an edge section arch at the other side of the middle section arch, and move same to a designated position; step S5, using the boom in step S2 to then carry the construction personnel to complete connection at a connecting point of the middle section arch and the edge section arch at the other side of the middle section arch. Using the present method, construction personnel are on a separate boom, and time of exposure to an excavation surface is short, which reduces the construction risk. In addition, operation and control are flexible, and construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Arch installation method

[0001] CROSS-REFERENCE TO RELATED APPLICATIONS

[0002] This application claims priority to the Chinese patent application filed with the China Patent Office on May 18, 2023, with application number 202310563233.1 and invention name “A method for installing an arch frame”, the entire contents of which are incorporated by reference into this application. Technical Field

[0003] The present application relates to the field of tunnel engineering equipment, and in particular to an arch frame installation method. Background Art

[0004] The statements in this section merely provide background information related to the present disclosure and may not constitute prior art.

[0005] During tunnel excavation, the installation of arch frames is essential. Currently, due to the large cross-sectional area of ​​some tunnels, the corresponding arch frames are also longer. In the existing technology, in order to facilitate transportation, the arch frames are usually split into multiple arch frame sections for transportation, and then assembled and installed on site using a special arch frame trolley.

[0006] A Chinese patent with publication number CN106761855B discloses an arch frame trolley and, based on the arch frame trolley, proposes an arch frame installation method. During the process of grabbing and installing the arch frame, construction workers are always exposed under the excavation surface, which poses a great safety risk and is difficult to operate, affecting construction efficiency to a certain extent.

[0007] Summary of the Invention

[0008] The purpose of this application is to provide an arch frame installation method to address the problems existing in the prior art, change the construction method of arch frame installation, solve the safety problems of construction workers and improve construction efficiency.

[0009] The technical solution of this application is as follows:

[0010] An arch installation method, comprising:

[0011] Step S1: grabbing the middle arch frame and the edge arch frame on one side thereof by using part of the boom and moving them to the designated positions;

[0012] Step S2: The remaining booms carry construction workers to complete the connection between the middle arch and the edge arch on one side;

[0013] Step S3: releasing the arm that grabs the middle arch;

[0014] Step S4: using the released arm to grab the edge arch on the other side of the middle arch and move it to a designated position;

[0015] Step S5: Use the boom in step S2 to continue carrying construction workers to complete the connection between the middle arch section and the edge arch section on the other side.

[0016] Optionally, the three-arm arch trolley includes: a first arm, a second arm and a third arm;

[0017] The second boom and the third boom are used to grab the arch;

[0018] The first boom is used for carrying construction workers.

[0019] Optionally, a hanging basket for carrying construction workers is provided on the first boom.

[0020] Optionally, the arch frame includes: a first section arch frame, a second section arch frame, and a third section arch frame;

[0021] The first arch section is an intermediate arch section;

[0022] The second arch frame and the third arch frame are edge arch frames on both sides of the middle arch frame respectively.

[0023] Optionally, step S1 includes:

[0024] The second arch section and the first arch section are grabbed by the second boom and the third boom respectively, and moved to the designated positions.

[0025] Optionally, the grabbing order of the second section arch and the first section arch can be exchanged.

[0026] Optionally, step S2 includes:

[0027] The hanging basket on the first boom carries the construction workers to complete the connection between the first arch section and the second arch section.

[0028] Optionally, step S3 includes:

[0029] Release the third boom.

[0030] Optionally, step S4 includes:

[0031] Grab the third arch section through the third arm and move it to the designated position.

[0032] Optionally, step S5 includes:

[0033] The hanging basket on the first boom carries the construction workers to complete the connection between the first arch section and the third arch section.

[0034] Compared with the existing technology, the beneficial effects of this application are:

[0035] A method for installing an arch frame comprises: step S1: using part of the boom to respectively grab a middle arch frame and an edge arch frame on one side thereof and move them to a designated position; step S2: using the remaining boom to carry construction personnel to complete the connection between the middle arch frame and the edge arch frame on one side at a connection point; step S3: releasing the boom that grabs the middle arch frame; step S4: using the released boom to grab the edge arch frame on the other side of the middle arch frame and move it to a designated position; step S5: using the boom in step S2 to continue carrying construction personnel to complete the connection between the middle arch frame and the edge arch frame on the other side; since the construction personnel are on a separate boom and are exposed to the excavation surface for a short time, the construction risk is reduced, the operation is flexible, and the construction efficiency is improved; at the same time, since some booms do not need to be provided with a hanging basket, costs can be saved. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] FIG1 is a flow chart of an arch installation method;

[0037] FIG2 is a schematic diagram of arch installation in the prior art.

[0038] Figure numbers: 1-first arch frame, 2-second arch frame, 3-third arch frame, 4-first arm frame, 5-second arm frame, 6-third arm frame. DETAILED DESCRIPTION

[0039] It should be noted that relational terms such as "first" and "second" are used only to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any actual relationship or order between these entities or operations. Moreover, the terms "comprises," "comprising," or any other variations thereof are intended to cover non-exclusive inclusion, such that a process, method, article, or apparatus comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or elements inherent to such process, method, article, or apparatus. In the absence of further limitations, an element defined by the phrase "comprising a ..." does not exclude the presence of additional identical elements in the process, method, article, or apparatus comprising the element.

[0040] The features and performance of the present application are further described in detail below with reference to the embodiments.

[0041] Example 1

[0042] Chinese patent publication number CN106761855B discloses an arch trolley and proposes an arch installation method based on the arch trolley. Specifically, please refer to Figure 2, where 1, 2, and 3 represent the first arch 1, the second arch 2, and the third arch 3, respectively; 4, 5, and 6 represent the first arm 4, the second arm 5, and the third arm 6 of the three-arm arch trolley, respectively; a and b represent the connection points of the first arch 1 and the second arch 2, and the second arch 2 and the third arch 3, respectively; the process sequence is as follows:

[0043] (1) The first arm 4 grabs the first arch 1 and moves it to the designated position;

[0044] (2) The second boom 5 grabs the second arch 2 and moves it to the designated position, and the construction workers on the second boom 5 complete the connection between the first arch 1 and the second arch 2;

[0045] (3) The third boom 6 grabs the third arch 3 and moves it to the designated position. The construction workers on the third boom 6 complete the connection between the second arch 2 and the third arch 3 at the connection point.

[0046] The above existing process has the following problems:

[0047] (1) The construction workers on the second boom 5 and the third boom 6 are always exposed to the excavation surface during the process of grabbing the arch frame and installing it, which poses a great safety risk.

[0048] (2) The second boom 5 and the third boom 6 ensure the positioning of the arch frame while ensuring that the construction workers can smoothly connect the bolts. This operation is difficult and affects the construction efficiency.

[0049] Therefore, based on the problems existing in the above-mentioned prior art, this embodiment proposes an arch frame installation method, please refer to Figure 1, which specifically includes the following steps:

[0050] Step S1: grabbing the middle arch frame and the edge arch frame on one side thereof by using part of the boom and moving them to the designated positions;

[0051] Step S2: The remaining booms carry construction workers to complete the connection between the middle arch and the edge arch on one side;

[0052] Step S3: releasing the arm that grabs the middle arch;

[0053] Step S4: using the released arm to grab the edge arch on the other side of the middle arch and move it to a designated position;

[0054] Step S5: Use the boom in step S2 to continue carrying construction workers to complete the connection between the middle arch section and the edge arch section on the other side.

[0055] In this embodiment, specifically, the three-arm arch trolley includes: a first arm 4, a second arm 5 and a third arm 6;

[0056] The second arm 5 and the third arm 6 are used to grab the arch;

[0057] The first boom 4 is used to carry construction workers; optionally, a hanging basket for carrying construction workers is provided on the first boom 4; that is, since the second boom 5 and the third boom 6 only perform grabbing actions, there is no need to separately set a hanging basket on the second boom 5 and the third boom 6, which further reduces the installation cost.

[0058] In this embodiment, specifically, the arch frame includes: a first section arch frame 1, a second section arch frame 2, and a third section arch frame 3;

[0059] The first arch 1 is a middle arch;

[0060] The second arch frame 2 and the third arch frame 3 are edge arch frames on both sides of the middle arch frame.

[0061] In this embodiment, specifically, step S1 includes:

[0062] The second arch section 2 and the first arch section 1 are grabbed by the second boom 5 and the third boom 6 respectively, and moved to the designated positions.

[0063] In this embodiment, specifically, the grabbing order of the second-section arch 2 and the first-section arch 1 can be exchanged.

[0064] In this embodiment, specifically, step S2 includes:

[0065] The hanging basket on the first boom 4 carries the construction workers to complete the connection at the connection point between the first arch frame 1 and the second arch frame 2; that is, using a separate first boom 4 to carry the construction workers, the construction workers can work on a separate boom, shortening the time the construction workers are exposed to the excavation surface, thereby reducing construction risks.

[0066] In this embodiment, specifically, step S3 includes:

[0067] Release the third arm 6.

[0068] In this embodiment, specifically, step S4 includes:

[0069] The third arch section 3 is grasped by the third arm 6 and moved to a designated position.

[0070] In this embodiment, specifically, step S5 includes:

[0071] The hanging basket on the first boom 4 carries the construction workers to complete the connection between the first arch section 1 and the third arch section 3 at the connection point.

[0072] The above-described embodiments merely represent specific implementation methods of the present application. While the descriptions are relatively specific and detailed, they should not be construed as limiting the scope of protection of the present application. It should be noted that a person skilled in the art would be able to make numerous variations and improvements without departing from the technical concept of the present application, and all such variations and improvements fall within the scope of protection of the present application.

Claims

1. An arch installation method, characterized in that: include: Step S1: grabbing the middle arch frame and the edge arch frame on one side thereof by partial booms and moving them to designated positions; Step S2: The remaining boom carries construction workers to complete the connection between the middle arch and the edge arch on one side; Step S3: Release the arm that grabs the middle section arch; Step S4: using the released arm to grab the edge arch frame on the other side of the middle arch frame and move it to a designated position; Step S5: Use the boom in step S2 to continue carrying construction workers to complete the connection between the middle arch section and the edge arch section on the other side.

2. The arch installation method according to claim 1, characterized in that: The three-arm arch trolley comprises: a first arm (4), a second arm (5) and a third arm (6); The second arm (5) and the third arm (6) are used to grab the arch; The first boom (4) is used to carry construction personnel.

3. The arch installation method according to claim 2, characterized in that: The first boom (4) is provided with a hanging basket for carrying construction workers.

4. The arch installation method according to claim 3, characterized in that: The arch frame comprises: a first arch frame (1), a second arch frame (2), and a third arch frame (3); The first arch frame (1) is a middle arch frame; The second arch frame (2) and the third arch frame (3) are respectively edge arch frames on both sides of the middle arch frame.

5. The arch installation method according to claim 4, characterized in that: The step S1 comprises: The second section arch frame (2) and the first section arch frame (1) are respectively grabbed by the second arm frame (5) and the third arm frame (6), and moved to the designated positions.

6. The arch installation method according to claim 5, characterized in that: The grabbing order of the second section arch frame (2) and the first section arch frame (1) can be exchanged.

7. The arch installation method according to claim 5, characterized in that: The step S2 comprises: The hanging basket on the first boom (4) carries the construction workers to complete the first arch frame (1) and the second arch frame (2). Connections at connection points.

8. The arch installation method according to claim 7, characterized in that: The step S3 comprises: Release the third arm support (6).

9. The arch installation method according to claim 8, characterized in that: The step S4 comprises: The third section of the arch frame (3) is grabbed by the third arm frame (6) and moved to a designated position.

10. The arch installation method according to claim 9, characterized in that: The step S5 comprises: The hanging basket on the first boom (4) carries construction workers to complete the connection between the first arch frame (1) and the third arch frame (3) at the connection point.

Citation Information

Patent Citations

  • Multifunctional arching drill jambo

    CN106401476A

  • Multifunctional tunnel construction manipulator group and construction method thereof

    CN106437783A

  • Equipment for supporting construction of highway tunnels and railway tunnels and construction method thereof