Method for planting reinforcing bars of long spiral drilled press-grouting pile, and method for handling not-in-place planting of reinforcing bars of long spiral drilled press-grouting pile

By using a combined design of rollers and force-transfer rods in long auger drilling and press-cast piles, the problems of large resistance and offset of the planting reinforcement are solved, and a higher success rate and construction quality are achieved, and a depth of 18 meters is exceeded. Restrictions have improved construction efficiency and quality.

WO2024244289A1PCT designated stage expired Publication Date: 2024-12-05CHINA HYDROELECTRIC ENGINEERING CONSULTING GROUP CHENGDU RESEARCH HYDROELECTRIC INVESTIGATION DESIGN AND INSTITUTE

Patent Information

Application Number
PCT/CN2023/128465
Authority / Receiving Office
WO · WO
Patent Type
Applications
Current Assignee / Owner
Priority Date
2023-05-29
Filing Date
2023-10-31
Publication Date
2024-12-05

AI Technical Summary

Technical Problem

The planting bars of long auger drilling press-cast piles have a large resistance, and the steel cage is prone to deviate, resulting in the problem of inadequate planting bars. Especially when the pile foundation design depth exceeds 18 meters, the problem is even more serious, and the existing technology has not effectively solved it.

Method used

A long spiral drilling and press-cast pile is designed, and a roller and a force transmission rod are installed on the outside of the steel cage. The roller and the inner wall of the pile hole are rolled to reduce the resistance to the planting ribs. The force transmission rod is transmitted to the bottom of the steel cage through vibrating load. Ensure its correct insertion position, and set the limiting ribs and positioning structure in the introduction device to ensure the stability and effective function of the introduction rod.

Benefits of technology

Effectively reduce the resistance of the reinforcement planting, avoid the deviation of the steel cage, improve the success rate and construction quality of the reinforcement planting, break through the 18-meter depth limit, save construction period and project costs, improve the construction quality of the pile foundation and the competitiveness of the enterprise .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN2023128465_05122024_PF_FP_ABST
    Figure CN2023128465_05122024_PF_FP_ABST
Patent Text Reader

Abstract

The present invention relates to the field of building construction. Disclosed are a method for planting reinforcing bars of a long spiral drilled press-grouting pile, and a method for handling not-in-place planting of reinforcing bars of a long spiral drilled press-grouting pile, aiming to improve the success rate of reinforcing bar planting and improve the construction quality. The technical solution used in the present invention involves a method for planting reinforcing bars of a long spiral drilled press-grouting pile. The method comprises: manufacturing a reinforcement cage of a long spiral drilled press-grouting pile; mounting rollers on the outer side of the reinforcement cage; fixedly mounting force-transmitting rod pieces at the bottom of the reinforcement cage or close to the bottom; assembling a guide-in device and the reinforcement cage; planting the guide-in device, together with the reinforcement cage, into concrete in a pile hole; and finally pulling out the guide-in device, and replenishing the pile hole with concrete. The method for handling not-in-place planting of reinforcing bars of a long spiral drilled press-grouting pile comprises: taking, as an allowable length for not-in-place planting of reinforcing bars, a certain length of a section of a pile foundation structure that is not subjected to a bending moment and shearing force action. The present invention reduces the risk of failed planting of reinforcing bars, improves the construction quality, and reduces the construction quality problems caused by not-in-place planting of reinforcing bars. The present invention is used for the construction of a long spiral drilled press-grouting pile.
Need to check novelty before this filing date? Find Prior Art

Description

Long spiral drilling pressure grouting pile planting method and treatment method for inadequate planting Technical Field

[0001] The present invention relates to the field of building construction, in particular to a long spiral bored pile and a reinforcement structure thereof, as well as a reinforcement method for the long spiral bored pile. Background Art

[0002] The construction process of long-auger bored piles involves first drilling to the designed depth using a long auger rig, then lifting the drill. Simultaneously, self-compacting concrete is poured into the pile hole. After pouring, rebar is planted and a vibrating device is used to insert the rebar cage into the concrete, ultimately forming a reinforced concrete cast-in-place pile. To facilitate the insertion of the rebar cage into the concrete, a guide is installed within the cage, topped with a vibrating motor. The guide applies a vibration load to the cage, which is then inserted into the concrete within the pile hole along with the guide. Once the guide and cage are inserted to the designed elevation, the guide is removed. The guide's force point on the cage is generally located at the top of the cage. Because the cage is a flexible structure, the load applied to the top of the cage may not be fully transferred to the bottom, making it susceptible to deformation and tilting, resulting in the cage centerline deviating significantly from the pile hole centerline. Planting rebar also presents significant resistance, often resulting in inadequate rebar placement and the cage being unable to be lowered to its designed position.

[0003] According to Clause 3.4.3 of the US industry standard (FHWA-HIF-07-03), the maximum construction depth of long auger bored piles should not exceed 18 meters. In actual construction, to meet the design requirements for pile foundation bearing capacity, the design depth of the pile foundation often exceeds 18 meters. The longer the long auger bored pile, the higher the probability of the above-mentioned problems. my country's Technical Standard for Long Auger Drilled Piles (JGJT 419-2018), regarding the technical requirements for long auger bored pile rebar, does not provide a solution to this problem.

[0004] Summary of the Invention

[0005] The present invention first provides a long spiral bored pile, which first solves the problems of large reinforcement resistance and easy deviation of the reinforcement cage in the long spiral bored pile.

[0006] The technical solution adopted by the present invention is: a long spiral bored pile, including a cylindrical pile body, a steel cage inside the pile body, the steel cage including multiple main bars arranged vertically, and spiral bars wrapped around the outside of the main bars and arranged in a spiral structure, at least three rollers are also installed on the outside of the steel cage, the rollers are located in the pile body, the rotating surface of the rollers passes through the center line of the steel cage, the projections of each roller on the horizontal section are arranged around the circumference of the steel cage, and the center of the circle corresponding to the projection of the point farthest from the center line of the steel cage on the horizontal section coincides with the center of the steel cage.

[0007] In order to ensure that the center line of the pile body coincides with the center line of the steel cage, further: the diameter of the circle corresponding to the projection of the point of each roller farthest from the center line of the steel cage on the horizontal section is equal to the diameter of the pile body.

[0008] The roller can be directly inserted into the spiral reinforcement, and the section of the spiral reinforcement through which the roller is inserted also serves as the roller's rotating shaft; or, the roller can be inserted into the rotating shaft, and both ends of the rotating shaft are fixed to the steel cage, for example, both ends of the rotating shaft are respectively welded to the main reinforcement.

[0009] For seismic loads, the upper section of the long spiral bored pile is subjected to greater bending moment and shear force than the lower section. Therefore, the spacing of the spiral bars in the upper section of the steel cage is smaller than that in the lower section. Considering that the spacing of the spiral bars in the upper section of the steel cage is smaller, rollers cannot be installed in the gaps between the spiral bars, or rollers cannot be directly inserted into the spiral bars. In addition, considering that the main resistance to planting reinforcement comes from the lower section of the steel cage, further steps are as follows: rollers are installed in the lower section of the steel cage, and the rollers are inserted into the spiral bars, or the rollers are inserted into the rotating shaft, and the two ends of the rotating shaft are fixed to the steel cage; at least three pads are fixed on the outer side of the upper section of the steel cage, and the thickness of the pads is consistent with the distance between the steel cage and the side wall of the pile hole.

[0010] In order to apply vibration load to the bottom of the steel cage, further steps are: a force transmission rod is fixedly installed at the bottom of the steel cage or near the bottom, the force transmission rod is arranged inside the steel cage, and the plane corresponding to the force transmission rod is perpendicular to the center line of the steel cage.

[0011] In order to improve the ability of the steel cage to resist deformation and prevent the force transmission rod from falling off after being vibrated, further: reinforcing ring bars are arranged at intervals on the inner side of the steel cage, and reinforcing ring bars are provided on the inner side of the position where the force transmission rod is arranged. The force transmission rod, the reinforcing ring bars and the steel cage are fixedly connected, and the force transmission rod is fixed to the upper part of the reinforcing ring bars.

[0012] The force transmission rods play the role of transmitting vibration loads. For example, the force transmission rods are crisscrossed, or the force transmission rods are in the shape of a cross, or the force transmission rods include a main rod and auxiliary rods connected to both sides of the main rod, and the main rod is perpendicular to the center line of the steel cage.

[0013] The long spiral bored pile system of the present invention has the following advantages: rollers are arranged on the outside of the reinforcement cage. When the reinforcement cage is inserted into the concrete pile hole, rolling friction is generated between the rollers and the inner wall of the pile hole, which helps reduce the resistance to rebar planting. The rollers on the outside of the reinforcement cage also limit the distance between the reinforcement cage and the pile hole wall, preventing the reinforcement cage from deflecting and ensuring that the reinforcement cage is located at the centerline of the pile hole, thereby ensuring the quality of the pile.

[0014] The present invention also provides a long spiral bored pile reinforcement planting structure, which aims to improve the success rate of long spiral bored pile reinforcement planting. The technical solution adopted by the present invention is: a long spiral bored pile reinforcement structure, including an introduction device and the steel cage of the above-mentioned first subject long spiral bored pile, and a force transmission rod is fixedly installed at the bottom of the steel cage or near the bottom, the force transmission rod is arranged inside the steel cage, and the plane corresponding to the force transmission rod is perpendicular to the center line of the pile body; the introduction device includes a top cover plate, a casing and an introduction rod, the top surface of the top cover plate is the vibration motor installation surface, the casing is a cylinder, the diameter of the casing is adapted to the diameter of the steel cage, one end of the casing is fixedly connected to the bottom surface of the top cover plate, a lifting piece is arranged on the outside of the casing, the upper end of the introduction rod is fixedly connected to the bottom surface of the top cover plate, and the center line of the casing coincides with the center line of the introduction rod, the lower end of the introduction rod is closed and a clamping structure is provided; the upper section of the steel cage is inserted into the casing or the upper section of the steel cage is sleeved on the outside of the casing, the clamping structure at the lower end of the introduction rod is clamped in the center position of the force transmission rod, and the steel cage is connected to the lifting piece.

[0015] To ensure the stability of the lead-in rod within the cage, at least one retaining bar is further positioned within the cage to limit the horizontal movement of the lead-in rod. The ends of the retaining bar are tied or welded to the cage, and the middle of the retaining bar makes point contact with the lead-in rod. For example, the retaining bar has two obtuse, co-lateral bends. Three to four retaining bars are arranged evenly horizontally around the lead-in rod, with staggered vertical spacing.

[0016] In order to facilitate the lifting of the introduction device and to facilitate the connection of the steel cage to the introduction device, specifically: at least two upper lifting rings and at least two lower lifting rings are set on the outside of the casing, and the steel cage is connected to the lower lifting rings by a tether.

[0017] Specifically: the guide rod is solid round steel, solid square steel, round steel pipe or square steel pipe.

[0018] The beneficial effects of the long spiral bored pile reinforcement planting structure of the present invention are as follows: the vibration motor is installed on the vibration motor installation surface of the introduction device, and the vibration load is transmitted to the force transmission rod through the introduction rod, and then transmitted to the lower part of the steel cage, so that the main force point of the steel cage during the implantation process is at the bottom of the steel cage rather than at the top. In addition, the role of the roller helps to implant the steel cage into the designed position, thereby improving the success rate of the long spiral bored pile reinforcement planting.

[0019] The present invention also provides a method for planting reinforcement in long spiral bored piles, the purpose of which is to improve the success rate of planting reinforcement in long spiral bored piles and improve the construction quality of long spiral bored piles. The technical solution adopted by the present invention is: the method for planting reinforcement in long spiral bored piles includes the following steps:

[0020] S1. Prepare a steel cage for long spiral bored piles. The steel cage is the steel cage for the long spiral bored piles described in the first subject. A force transmission rod is fixedly installed at or near the bottom of the steel cage. The force transmission rod is arranged inside the steel cage. The plane corresponding to the force transmission rod is perpendicular to the centerline of the pile body.

[0021] S2. Assemble the introduction device and the steel cage to obtain the above-mentioned second subject long spiral bored pile reinforcement structure, and install the vibration motor on the vibration motor installation surface.

[0022] S3. After completing the drilling and concrete pouring of the long spiral bored pile, the steel cage together with the introduction device is hoisted to the top of the pile hole where the reinforcement is to be planted, and the steel cage is implanted into the concrete in the pile hole.

[0023] S4. When the steel cage is implanted to the designed elevation, or cannot be inserted further, pull out the guide device and add concrete to the pile hole.

[0024] In order to ensure the stability of the guide rod during the implantation into the steel cage, further: in S2, at least one limiting rib is provided inside the steel cage to limit the horizontal movement of the guide rod, the two ends of the limiting rib are tied or welded to the steel cage, and the middle of the limiting rib is in point contact with the guide rod. For example, the limiting rib has two bending angles, both of which are obtuse angles and are inner angles on the same side. 3 to 4 limiting ribs are arranged uniformly horizontally and staggered vertically around the guide rod. The spacing L2 of the limiting ribs is calculated according to the formula L2 = 120i / μ·(235 / σ p ) 0.5 Determine, where: i is the radius of gyration of the lead-in rod, μ is the length factor of the lead-in rod, μ = 2.0, σ p is the nominal yield strength of the imported rod material.

[0025] Furthermore, the long spiral bored pile reinforcement method also includes reinforcement resistance F u And the anchor bolt F D Calculation and control of F u ≤F D , reinforcement resistance F u The calculation formula is: F u=F1+F2+F3+F4+F5+F6, where: F1 is the buoyancy of the steel cage and the introduction device in the concrete, F2 is the friction resistance of the pile hole side wall to the steel cage, F3 is the friction resistance between the spiral reinforcement and the concrete mixture, F4 is the friction resistance between the main reinforcement and the concrete mixture, F5 is the friction resistance of the introduction rod, and F6 is the friction resistance of the reinforcing ring reinforcement; the anchoring force F D The calculation formula is: F D =F g +F c +Fa, where: F g is the deadweight of the steel cage, F c is the deadweight of the induction device, F a For vibration load.

[0026] Furthermore, the buoyancy force F1 = ρ·g·(V s +V d ), ρ c is the density of fresh concrete, V s is the volume of the steel cage, V d is the volume of the guide rod; friction resistance F2 = f·Ws, Ws is the total weight of the steel cage, roller and pad, f is the friction coefficient; friction resistance F3 = τ y ·A s , A s is the sum of the horizontal projection areas of the spiral reinforcements in each layer, τ y is the yield shear stress of fresh concrete; friction resistance F4=τ y ·A mb , A mb is the total area of ​​the main reinforcement; friction resistance F5=(ρ c -ρ w )·A mb ,ρ w is the density of water; friction resistance F6 = τ y ·A st , A st is the total area of ​​the reinforcement ring. For example, the yield shear stress τ of fresh concrete y The calculation formula is: S f is the slump flow value of fresh concrete, and V is the slump expansion velocity of fresh concrete.

[0027] The beneficial effects of the long spiral bored pile reinforcement method of the present invention are: it can reduce the risk of long spiral bored pile reinforcement failure, improve the construction quality of long spiral bored piles, and reduce construction quality problems caused by inadequately planted reinforcement. According to this method, it is possible to break through the American standard limit of 18 meters for the maximum construction depth of long spiral bored piles, thereby achieving the goals of saving construction time and project costs, improving the construction quality of pile foundations, expanding the application range of long spiral bored piles, and enhancing the competitiveness of enterprises. The present invention can also supplement and improve the technical standard for long spiral bored piles (JGJT 419-2018).

[0028] The present invention also provides a method for addressing under-placement of rebar in long spiral bored piles. According to the third subject matter of the long spiral bored pile rebar planting method, a rebar cage is embedded in the concrete within the pile hole, but the rebar cage is not embedded to the designed elevation. The allowable length of the under-placement of the rebar is 0.5 to 0.7 times the length of the section of the pile structure free of bending moment and shear force. For example, the allowable length of the under-placement of the rebar is 3 meters. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] FIG1 is a schematic cross-sectional view of a long spiral bored pile at the position of a force transmission rod according to the present invention.

[0030] FIG2 is a schematic diagram of an introduction device in the present invention.

[0031] FIG3 is a side view of FIG2 .

[0032] FIG4 is a schematic diagram showing the matching relationship between the limiting rib and the guide rod in the present invention.

[0033] FIG5 is a schematic diagram of another embodiment of the force transmission rod in the present invention.

[0034] Drawing reference numerals: main reinforcement 1, spiral reinforcement 2, roller 3, pile hole side wall 4, force transmission rod 5, reinforcing ring reinforcement 6, top cover plate 7, casing 8, guide rod 9, positioning structure 10, limiting reinforcement 11, upper lifting ring 12, lower lifting ring 13. DETAILED DESCRIPTION

[0035] The present invention will be further described below with reference to the accompanying drawings.

[0036] The first subject of the present invention is a long spiral bored pile, see Figure 1, which includes a cylindrical pile body, which is a reinforced concrete structure. The pile body contains a steel cage, which includes multiple main bars 1 arranged vertically, and spiral bars 2 wrapped around the outside of the main bars 1 and arranged in a spiral structure. Since the pile body is long, the steel cage is also correspondingly long. The main bars 1 generally need to be overlapped. The overlap length of the main bars 1 depends on the diameter of the main bars 1 and the grade of the concrete. For example, for concrete with C30 cylindrical compressive strength, a overlap length of 62D is used, where D is the diameter of the main bars 1. The main bars 1 are overlapped and need to be welded at the upper and lower locations. The welding length must be at least 50 mm to ensure the overlap strength. According to the stress of the long spiral bored pile, the main bars 1 in the upper section of the steel cage are thicker than the main bars 1 in the lower section. Compared with the lower section of the pile body, the upper section bears greater bending moment and shear force, so the spacing of the spiral bars 2 in the upper section of the steel cage is smaller than that in the lower section of the steel cage, that is, the spiral bars 2 in the upper section of the steel cage are arranged more densely.

[0037] To reduce frictional resistance between the cage and the sidewalls 4 of the pile hole during its implantation, at least three rollers 3 are mounted on the outside of the cage. The rollers' rotational planes pass through the cage's centerline, and the rollers' rotational direction is vertical. The projections of each roller 3 on a horizontal cross-section circumferentially circumferentially circumferentially align with the cage's centerline. The rollers 3 also limit the cage's position within the pile hole, ensuring the thickness of the rebar protective layer and aligning or nearly aligning the cage's centerline with the pile's centerline. The rollers 3 are completely located within the pile, preventing them from interfering with the cage's implantation. Ultimately, the rollers 3 are embedded in concrete, typically concrete or reinforced concrete. The inner and outer surfaces of the rollers 3 can be concrete or other materials. For example, the inner and outer rings of the rollers 3 are made of PCV tubing, with concrete or reinforced concrete between the inner and outer rings. In order to ensure that the center line of the pile body coincides with the center line of the reinforcement cage, the diameter of the circle corresponding to the projection of the point of each roller 3 farthest from the center line of the reinforcement cage on the horizontal section is equal to the diameter of the pile body.

[0038] The roller 3 can be directly inserted into the spiral rebar 2, with the section of spiral rebar 2 through which the roller 3 is inserted also serving as its rotating shaft. Alternatively, the roller 3 can be equipped with a dedicated rotating shaft, which the roller 3 is inserted into. The ends of the rotating shaft are fixed to the rebar cage, for example, by welding the ends of the rotating shaft to the main rebar 1. The roller 3 can also be replaced by a spacer, which is directly fixed to the outside of the rebar cage. For example, the spacer is provided with a slot that matches the rebar cage and is fixed to the rebar cage by snapping. The thickness of the spacer is consistent with the distance between the rebar cage and the pile hole sidewall 4. The spacer is made of the same material as the roller 3, and can be concrete or reinforced concrete. To avoid the problem that the spacing between the spiral ribs 2 in the upper section of the steel cage is too small, making it impossible to install the roller 3 in the gap between the spiral ribs 2 or to directly insert the roller 3 into the spiral ribs 2, the lower section of the steel cage is provided with a roller 3, which is inserted into the spiral ribs 2, or the roller 3 is inserted into the rotating shaft, and the two ends of the rotating shaft are fixed to the steel cage; at least one pad is fixedly installed on the outer side of the upper section of the steel cage, and the thickness of the pad is consistent with the distance between the steel cage and the pile hole side wall 4. In order to limit the periphery of the upper section of the steel cage, at least three pads are distributed around the steel cage. The arrangement of the pads in the upper section of the steel cage can also be the same as the arrangement of the roller 3 in the lower section of the steel cage.

[0039] To apply vibration loads to the bottom of the cage via the introduction device, a force transmission rod 5 is fixedly mounted at or near the bottom of the cage. The force transmission rod 5 is positioned within the cage, with the plane corresponding to the force transmission rod 5 perpendicular to the cage centerline. The force transmission rod 5 can be placed at the bottom of the cage or at a location within 85% of the pile length and welded to the cage. The force transmission rod 5 receives the vibration loads from the introduction device and transmits them to the bottom of the cage to overcome the resistance of the rebar. For example, as shown in Figure 1, the force transmission rod 5 is shaped like a cross. As another example, as shown in Figure 5, the force transmission rod 5 includes a main rod and auxiliary rods connected to either side of the main rod. One end of the auxiliary rod is welded to the main rod and perpendicular to the main rod, which is perpendicular to the cage centerline. Alternatively, the force transmission rod 5 can be shaped like a cross. This structure allows the force transmission rod 5 to transfer the vibration load to the center of the cage as much as possible, evenly distributing the vibration load to the surrounding area of ​​the cage. The force transmission rod 5 needs to be composed of a steel bar with a diameter greater than or equal to that of the main reinforcement 1 , and its size needs to be calculated according to the pile depth and the magnitude of the vibration load.

[0040] To improve the cage's ability to resist deformation, reinforcing rings 6 are interspersed on its inner side. The plane corresponding to these rings is perpendicular to the cage's centerline. These rings are secured to the cage, typically by welding or by tying and welding. To prevent the force-transmitting rods 5 from vibrating and falling off, reinforcing rings 6 are also installed where the force-transmitting rods 5 are located. These rods, reinforcing rings 6, and the cage are securely connected, with the force-transmitting rods 5 secured to the top of the rings. For example, the rings consist of two 12mm diameter steel bars spaced 2m apart, with additional rings added at the top and bottom of the cage.

[0041] The following explanation uses the cross-shaped dowel rod 5 as an example. Dowel rod 5 consists of two dowel rods welded together in a flat surface, with zero spacing between them. The design criteria for the dowel rods are: The tensile and shear stresses on the dowel rods are calculated as concentrated loads, the bending moments are less than the allowable tensile and shear stresses of the dowel rod material, and the deformation of the dowel rods is less than 1 / 250 of the calculated span. For spiral bored piles with a diameter of 600 mm and a length of 800 mm, the design results of the dowel rods, provided that the design criteria are met, are shown in Table 1.

[0042] Table 1 Calculation table of force transmission rods.

[0043] Table 1 shows that: First, when the dowel rod diameter is 25mm, an 800mm pile can only transmit a 2kN vibration load; whereas, a 600mm diameter pile can transmit a 5kN vibration load without significant deformation. This means that, given the same dowel rod diameter, a smaller-diameter pile can transmit a greater vibration load. Second, a larger-diameter pile requires a larger-diameter dowel rod to meet design requirements. Third, a smaller-diameter pile can transmit up to 10kN vibration load when using a larger-diameter dowel rod. In one project, both 600mm and 800mm piles were used, but both employed 25mm-diameter dowel rods. As a result, 85% of the 800mm piles had inadequate rebar, while 15% of the 600mm piles had inadequate rebar. The calculation results in Table 1 reflect the reason why large-diameter piles often experience under-installed reinforcement more frequently than small-diameter piles. If the diameter of the dowel rod is too small, it will deform significantly, failing to achieve the intended purpose of rebar installation. Table 1 and the above analysis demonstrate the importance of conducting dowel rod design verification.

[0044] Table 1 also shows that for 800mm diameter piles, a single steel bar cannot transmit vibration loads exceeding 10kN. To increase the bending modulus of the dowel bar, two bars can be welded together to form a single dowel bar. For example, the weld width should be twice the bar diameter, with three welds. Two 25mm diameter bars, under the same span conditions as shown in Table 1, can transmit a vibration load of 22.5kN without causing excessive deformation. Two 28mm diameter bars, acting as dowel bars, can transmit a vibration load of 31.5kN.

[0045] The second subject of this invention is a long spiral bored pile reinforcement structure, which aims to improve the success rate of long spiral bored pile reinforcement. The long spiral bored pile reinforcement structure includes an introduction device and a reinforcement cage for the long spiral bored pile described in the first subject. A force transmission rod 5, which cooperates with the introduction device, is fixedly mounted at or near the bottom of the reinforcement cage. The force transmission rod 5 is disposed within the reinforcement cage, and the plane corresponding to the force transmission rod 5 is perpendicular to the centerline of the pile.

[0046] Referring to Figures 2 and 3, the introduction device includes a top cover plate 7, a casing 8 and an introduction rod 9. To ensure strength, the top cover plate 7, the casing 8 and the introduction rod 9 are all made of steel, for example, Q235 steel. The top surface of the top cover plate 7 is the vibration motor mounting surface, which is used to install the vibration motor. The installation position of the vibration motor is located at the center of the top cover plate 7. For example, the vibration motor is a two-stage vibration motor with an adjustable vibration load of 1 to 10 kN. The vibration motor is connected to the top cover plate 7 by bolts. The casing 8 is a cylinder, and the diameter of the casing 8 is adapted to the diameter of the steel cage. One end of the casing 8 is fixedly connected to the bottom surface of the top cover plate 7, for example, by welding. A lifting piece is set on the outside of the casing 8, and there are at least two lifting pieces, and generally three or more are set to ensure balance. The lifting piece is used for both lifting the introduction device and connecting it to the steel cage. For example, at least two upper lifting rings 12 and at least two lower lifting rings 13 are set on the outside of the casing 8. The upper lifting rings 12 are used to be connected to the hook of the crane through a tether and lifted, and the lower lifting rings 13 are used to be connected to the steel cage through a tether.

[0047] The upper end of the guide rod 9 is fixedly connected to the bottom surface of the top cover plate 7, and the center line of the casing 8 coincides with the center line of the guide rod 9. In order to ensure stability, the guide rod 9 and the top cover plate 7 are generally welded. The casing 8 serves to limit the movement of the upper part of the steel cage within a smaller range. The inner diameter of the casing 8 is adapted to the outer diameter of the steel cage, and the upper section of the steel cage is inserted into the casing 8; or, the outer diameter of the casing 8 is adapted to the inner diameter of the steel cage, and the upper section of the steel cage is sleeved on the outside of the casing 8. The lower end of the guide rod 9 is closed and provided with a locking structure 10. The locking structure 10 is locked in the center position of the force transmission rod 5. The steel cage is connected to the lifting part, for example, the steel cage is connected to the lower lifting ring 13 by a tether. The locking structure 10 is used to ensure that the point of action of the introduction rod 9 on the force transmission rod 5 is always located at the center position of the force transmission rod 5. For example, the lower end of the introduction rod 9 is sealed by welding a steel plate, and two 3mm thick steel plates are welded to the lower end of the introduction rod 9 as the locking structure 10. The two steel plates can be freely inserted into the force transmission rod 5.

[0048] The guide rod 9 plays the role of transmitting vibration loads and can be solid round steel, solid square steel, round steel pipe, square steel pipe, etc. For example, the guide rod 9 is composed of a steel plate with a thickness of 4 mm. The guide rod 9 is a large flexibility rod, and its size and dimensions need to be calculated and meet the verification requirements of the critical pressure of the flexible rod and the total load. The cross-sectional area of ​​the guide rod 9 should not be too large, otherwise it will increase the resistance of the embedded reinforcement and increase the amount of concrete poured after the guide device is pulled out. The selection of the size of the guide rod 9 depends on the pile length and the length of the guide rod 9. The setting of the guide rod 9 and the vibration load is one of the key technologies in the construction of long spiral bored piles, but there is no clear provision in domestic and foreign standards for this.

[0049] To ensure the stability of the guide rod 9 within the steel cage, at least one limiting rib 11 is provided inside the steel cage to restrict the horizontal movement of the guide rod 9. The ends of the limiting rib 11 are tied or welded to the steel cage, and the middle of the limiting rib 11 is in point contact with the guide rod 9. The spacing of the limiting ribs 11 is determined by calculation. For example, referring to Figure 4, the limiting rib 11 has two bending angles, both of which are obtuse and co-lateral internal angles. The limiting rib 11 is a steel bar with a diameter of 12 mm. When installing the limiting rib 11, it is necessary to ensure that the guide rod 9 is in the middle of the steel cage and that the ends of the limiting rib 11 are firmly connected to the steel cage to prevent the limiting rib 11 from being pulled out when the guide rod 9 is pulled out. Generally, 3 to 4 limiting ribs 11 are arranged evenly horizontally and staggered vertically around the guide rod 9. The limiting ribs 11 are evenly arranged horizontally around the guide rod 9 to limit the horizontal shaking of the guide rod 9. The limiting ribs 11 are staggered vertically around the guide rod 9 to avoid the problem of excessive resistance to planting due to the guide rod 9 being too concentrated. The limiting ribs 11 in the middle of the guide rod 9 are very important. The guide rod 9 is a highly flexible rod. Otherwise, the guide rod 9 will shake during the hoisting and planting process, which is prone to deviation and difficulty in transferring the load.

[0050] The criteria for determining the size of the lead-in rod 9 are: the critical compressive stress of the lead-in rod 9 is greater than the compressive stress corresponding to the maximum vibration pressure of the lead-in rod 9, including the deadweight load of the upper components of the lead-in rod 9; the critical pressure of the lead-in rod 9 is greater than the total load on the upper part of the lead-in rod 9, including the deadweight load and vibration load of the lead-in rod 9, and deducting the buoyancy of the lead-in rod 9 in the concrete; thick steel is used to increase the downward force and offset its own buoyancy; the minimum rod size that meets the above requirements.

[0051] The following examples illustrate the use of circular and square steel tubes as guide rods 9. For circular guide rods 9, the Euler formula can be used to calculate the dimensions of guide rods 9 of different lengths, as shown in Table 2. For square guide rods 9, the dimensions of guide rods 9 of different lengths are shown in Table 3. The square steel tubes are made of square steel that complies with the national standard GB / T 6728-2017.

[0052] Table 2: Design dimension calculation table of the guide rod as a round steel tube.

[0053] Table 3 Design dimension calculation table of the import rod which is a square steel tube.

[0054] As can be seen from Table 3, the guide rods 9 are all highly flexible rods. Calculations indicate that lateral supports are required every 2.7 meters. The guide rods 9 should not be too small, otherwise the critical compressive stress requirements will not be met. The guide rods 9 should also not be too large, as this will increase resistance to rebar placement, increase upward buoyancy, and require additional concrete injection. The guide rods 9 are square steel tubes, which form a planar contact with the retaining bars 11, achieving better results than the point contact of circular steel tubes. However, circular steel tubes are smaller, have less buoyancy in concrete, and facilitate rebar placement.

[0055] The third subject of the present invention is a method for planting reinforcement bars by using long spiral bored piles. The method comprises the following steps:

[0056] S1. Fabricate a reinforcement cage for a long spiral bored pile. The reinforcement cage is the same as the reinforcement cage for the long spiral bored pile described in the first topic. A force transmission rod 5 is fixedly mounted at or near the bottom of the reinforcement cage. Force transmission rod 5 is disposed within the reinforcement cage, with the plane corresponding to force transmission rod 5 perpendicular to the centerline of the pile. For a description of force transmission rod 5, refer to the descriptions of the two topics described above.

[0057] S2. Assemble the introduction device and the steel cage to obtain the above-mentioned second subject long spiral bored pile reinforcement structure, and install the vibration motor on the vibration motor installation surface.

[0058] S3. After completing the drilling and concrete pouring of the long spiral bored pile, the steel cage together with the introduction device is hoisted to the top of the pile hole where the reinforcement is to be planted, and the steel cage is implanted into the concrete in the pile hole.

[0059] S4. When the reinforcement cage is implanted to the designed elevation, or cannot be inserted further, pull out the guide device and add concrete to the pile hole.

[0060] The resistance in the installation of the reinforcement cage in long spiral bored piles, i.e. the installation of the reinforcement cage, includes: the buoyancy F1 of the reinforcement cage and the guide rod 9 in the concrete mixture; the friction resistance between the reinforcement cage and the pile hole side wall 4, including the friction resistance of the roller 3 and the pad; the friction resistance F3 between the spiral reinforcement 2 and the concrete mixture; the friction resistance F4 between the main reinforcement 1 and the concrete mixture; the friction resistance F5 between the guide rod 9; the friction resistance of the reinforcing ring reinforcement 6; and other resistances. The combined force of the downward force is used as the reinforcement force F D , the resultant force of the upward force is taken as the reinforcement resistance F u The principle to ensure the success of rebar planting is F u ≤F D For the convenience of calculation, the reinforcement resistance F u The calculation formula is: F u =F1+F2+F3+F4+F5+F6, anchor bolt assist F D The calculation formula is: F D =F g +F c +Fa, where: F g is the deadweight of the steel cage, F c is the deadweight of the induction device, F a For vibration load, long spiral bored pile reinforcement method controls F u ≤F D .

[0061] The following is an explanation of the resistance of the steel cage embedded in the concrete. The buoyancy F1 mainly depends on the volume of the steel cage and the introduction rod 9, F1 = ρ·g·(V s +V d ), ρ c is the density of fresh concrete, V s is the volume of the steel cage, V d is the volume of the guide rod 9. Friction resistance F2 = f·Ws, Ws is the total weight of the steel cage, roller 3 and pad, and f is the friction coefficient. Friction resistance F3 = τ y ·A s , A s is the sum of the horizontal projection areas of the spiral ribs 2 in each layer, τ y is the yield shear stress of fresh concrete. Friction resistance F4=τ y ·A mb , Amb is the total area of ​​the main reinforcement 1. Friction resistance F5=(ρ c -ρ w )·A mb ,ρ w is the density of water, ρ c is the density of concrete, for example ρ c =2350kg / m 3 ,ρ w =1000kg / m 3 Friction resistance F6 = τ y ·A st , A st is the total area of ​​the reinforcing ring rib 6.

[0062] The reinforcement resistance F2~F6 is related to the viscosity of the concrete mixture and the shear yield stress τ y According to existing research, the shear yield stress of concrete τ y The formula is: Among them S f is the slump flow value of fresh concrete, and V is the slump expansion velocity of fresh concrete. Based on this formula, the shear yield stress corresponding to different slump flow values ​​can be calculated, as shown in Table 4.

[0063] Table 4 Shear yield stress corresponding to different slump flow values.

[0064] Rebar planting resistance F u The calculation results are shown in Table 5, where F=Fu.

[0065] Table 5 Rebar planting resistance F u And the anchor bolt F D calculation table.

[0066] The results in Table 5 show that the greatest resistance to rebar planting is the upward buoyancy of the cage and lead-in rod 9 in the concrete, followed by friction between the cage and the pile hole sidewall 4, and then the resistance to movement of the main bar 1 in the concrete. To reduce the resistance to rebar planting, a lead-in rod 9 with the smallest size and heaviest weight is required. Therefore, a round lead-in rod is more effective than a square one because its volume is smaller than that of a square one.

[0067] Long spiral bored piles inevitably lead to the problem of insufficient rebar planting. The main reasons for insufficient rebar planting are: (1) The force transmission rod 5 is not calculated, the size of the force transmission rod 5 is not clear, and the deformation of the force transmission rod 5 is significantly too large. (2) The load acting on the force transmission rod 5 is not at the center of the steel cage, the resistance to rebar planting increases, and the effect of the guide rod 9 becomes less obvious. (3) The size of the guide rod 9 is not calculated, and the limiting bar 11 is not set, resulting in excessive flexibility of the guide rod 9. During the rebar planting process, the steel cage and the guide rod 9 shake and the center is offset. The vibration load cannot reach the bottom of the steel cage, and the guide rod 9 does not really work. (4) The buoyancy of the guide rod 9 in the concrete is too large. (5) The speed of planting the steel cage is too fast, and the bottom of the steel cage encounters resistance, causing the steel cage to shake, the center of gravity to shift, and the bottom of the steel cage to be stuck. (6) The guide rod 9 is not connected to the force transmission rod 5. The vibration load of the top cover plate 7 does not act on the lower part of the steel cage, but on the upper part of the steel cage. However, the steel cage is a flexible system, and the upper load may not be completely transmitted to the bottom of the steel cage. The effect of the guide rod 9 is significantly weakened.

[0068] The present invention also provides a method for addressing under-placement reinforcement in long spiral bored piles, which is also the fourth subject of the present invention: a method for addressing under-placement reinforcement in long spiral bored piles. The method for addressing under-placement reinforcement in long spiral bored piles follows the method for addressing under-placement reinforcement in long spiral bored piles described in the third subject, wherein a reinforcement cage is embedded in the concrete within the pile hole, but the reinforcement cage is not embedded to the designed elevation. The allowable length for under-placement reinforcement is 0.5 to 0.7 times the length of the section of the pile foundation structure free of bending moment and shear force.

[0069] According to the structural characteristics of long spiral bored piles, when the designed depth of the pile foundation reaches a certain depth, the lower part of the pile foundation only bears pressure, without bending moment and shear force. According to the American standard FHWA-HIF-07-03 clause 5.6.4.1, it is not necessary to prepare steel bars within the depth range of the entire pile foundation. The steel cage is not implanted to the design elevation. According to the calculation results of the pile foundation structure, the length of the pile section without bending moment and shear force is marked as L, and 0.5L to 0.7L can be taken as the allowable length for the reinforcement to be not in place. A foreign project approved that it is acceptable if the reinforcement is not in place within 3 meters. For pile foundations where the reinforcement is not in place and exceeds the allowable length, additional pile foundation bearing capacity tests are required.

Claims

1. Long spiral drilling and grouting pile reinforcement method, characterized by: The steps include: S1. A steel cage for making long spiral bored piles, the steel cage comprising a plurality of main bars (1) arranged vertically, and spiral bars (2) wound around the outside of the main bars (1) and arranged in a spiral structure, characterized in that at least three rollers (3) are installed on the outside of the steel cage, the rollers (3) are located in the pile body, the rotating surface of the rollers (3) passes through the center line of the steel cage, the projections of the rollers (3) on the horizontal section are arranged around the circumference of the steel cage, and the center of the circle corresponding to the projection of the point farthest from the center line of the steel cage on the horizontal section coincides with the center of the steel cage; a force transmission rod (5) is fixedly installed at the bottom of the steel cage or at a position close to the bottom, the force transmission rod (5) is arranged inside the steel cage, and the plane corresponding to the force transmission rod (5) is perpendicular to the center line of the steel cage; S2, assembling the introduction device and the steel cage, inserting the upper section of the steel cage into the casing (8) or sleeved on the outside of the casing (8), the clamping structure (10) at the lower end of the introduction rod (9) is clamped in the center position of the force transmission rod (5), the steel cage is connected to the lifting part, and the vibration motor is installed on the vibration motor installation surface; The introduction device comprises a top cover plate (7), a casing (8) and an introduction rod (9); the top surface of the top cover plate (7) is a vibration motor installation surface; the casing (8) is a cylinder; the outer diameter of the casing (8) is adapted to the inner diameter of the steel cage; one end of the casing (8) is fixedly connected to the bottom surface of the top cover plate (7); a hanging piece is arranged on the outer side of the casing (8); the upper end of the introduction rod (9) is fixedly connected to the bottom surface of the top cover plate (7); the center line of the casing (8) coincides with the center line of the introduction rod (9); the lower end of the introduction rod (9) is closed and a clamping structure (10) is arranged; S3. After the drilling and concrete pouring of the long spiral bored pile are completed, the steel cage together with the introduction device is hoisted to the top of the pile hole to be planted, and the steel cage is implanted into the concrete in the pile hole; S4. When the steel cage is implanted to the designed elevation, or cannot be inserted downward, pull out the guide device and add concrete to the pile hole.

2. The long spiral drilling and grouting pile reinforcing bar planting method according to claim 1, characterized in that: The diameter of the circle corresponding to the projection of the point of each roller (3) farthest from the center line of the steel cage on the horizontal section is equal to the diameter of the pile body.

3. The long spiral drilling and grouting pile reinforcing bar planting method according to claim 1, characterized in that: The spacing of the spiral reinforcement (2) at the upper section of the steel cage is smaller than the spacing of the spiral reinforcement (2) at the lower section of the steel cage. The lower section of the steel cage is provided with a roller (3), the roller (3) is passed through the spiral reinforcement (2), or the roller (3) is passed through the rotating shaft, and both ends of the rotating shaft are fixed to the steel cage. At least one pad is fixedly provided on the outer side of the upper section of the steel cage, and the thickness of the pad is consistent with the distance between the steel cage and the side wall (4) of the pile hole.

4. The long spiral drilling and grouting pile reinforcing bar planting method according to claim 1, characterized in that: The force transmission rod (5) is in a cross shape, or in a cross shape, or comprises a main rod and auxiliary rods connected to both sides of the main rod, and the main rod is perpendicular to the center line of the steel cage.

5. The long spiral drilling and grouting pile reinforcing bar planting method according to any one of claims 1 to 4, characterized in that: Reinforcement ring ribs (6) are also arranged at intervals on the inner side of the steel cage. The reinforcement ring ribs (6) are arranged on the inner side of the steel cage where the force transmission rod (5) is arranged. The force transmission rod (5), the reinforcement ring ribs (6) and the steel cage are fixedly connected, and the force transmission rod (5) is fixed to the upper part of the reinforcement ring rib (6).

6. The long spiral bored pile reinforcement method according to claim 5, characterized in that: In S2, at least one limiting rib (11) is provided inside the steel cage to limit the horizontal movement of the introduction rod (9), the two ends of the limiting rib (11) are tied or welded to the steel cage, and the middle part of the limiting rib (11) is in point contact with the introduction rod (9).

7. The long spiral drilling and grouting pile reinforcing bar planting method according to claim 6, characterized in that: The limiting rib (11) has two bending angles, both of which are obtuse angles and are inner angles on the same side. Three to four limiting ribs (11) are evenly arranged horizontally and staggered vertically around the guide rod (9). The spacing L2 of the limiting ribs (11) is calculated according to the formula L2=120i / μ·(235 / σ p ) 0.5 Determine, where: i is the radius of gyration of the introduction rod (9), μ is the length factor of the introduction rod (9), μ = 2.0, σ p is the nominal yield strength of the material of the lead-in rod (9).

8. The long spiral drilling and grouting pile reinforcing bar planting method according to claim 5, characterized in that: The long spiral bored pile reinforcement method also includes the reinforcement resistance F u And implant support F D Calculation and control of F u ≤F D , reinforcement resistance F u The calculation formula is: u =F1+F2+F3+F4+F5+F6, wherein: F1 is the buoyancy of the steel cage and the introduction device in the concrete, F2 is the friction resistance of the pile hole side wall (4) to the steel cage, F3 is the friction resistance of the spiral reinforcement (2) and the concrete mixture, F4 is the friction resistance of the main reinforcement (1) and the concrete mixture, F5 is the friction resistance of the introduction rod (9), and F6 is the friction resistance of the reinforcing ring reinforcement (6); the reinforcement booster F D The calculation formula is: D =F g +F c +Fa, where: F g is the deadweight of the steel cage, F c is the deadweight of the induction device, F a For vibration load.

9. The long spiral drilling and grouting pile reinforcement method according to claim 8, characterized in that: Buoyancy F1 = ρ·g·(V s +V d ), ρ c is the density of fresh concrete, V s is the volume of the steel cage, V d is the volume of the introduction rod (9); friction resistance F2 = f·Ws, Ws is the total weight of the steel cage, roller (3) and pad, f is the friction coefficient; friction resistance F3 = τ y ·A s , A s is the sum of the horizontal projection areas of the spiral ribs (2) in each layer, τ y is the yield shear stress of fresh concrete; friction resistance F4 = τ y ·A mb , A mb is the total area of ​​the main reinforcement (1); Friction resistance F5 = (ρ c -ρ w )·A mb , ρ w is the density of water; friction resistance F6 = τ y ·A st , A st is the total area of ​​the reinforcing ring rib (6).

10. A method for dealing with the problem of inadequate reinforcement of long spiral bored piles, characterized in that: According to the long spiral bored pile reinforcement method described in any one of claims 1 to 9 above, the steel cage is implanted into the concrete in the pile hole, but the steel cage is not implanted to the designed elevation, and 0.5 to 0.7 times the length of the section of the pile foundation structure without bending moment and shear force is taken as the allowable length for the reinforcement not to be in place.

Citation Information

Patent Citations

  • Cast-in situ bored pile post-inserted steel reinforcement cage multi-point delivery device and use method

    CN104975597A

  • Cast-in-place pile reinforcing cage positioning device and use method thereof

    CN110042828A

  • Reinforcement cage with positioning function and construction method

    CN110172967A

  • Steel bar planting method for long spiral drilling pressure grouting pile and treatment method for not-in-place steel bar planting

    CN116641369A

  • Concrete bored pile piling technology with implanted reinforced bar cage

    CN1773024A

Cited By

  • Welding anti-deformation positioning device for segmented butt joint of long spiral pressure grouting pile reinforcement cage

    CN122142664A