Tension-compression assembled beam string steel support system
By introducing a tension-pressure-type prefabricated string beam system into the foundation pit steel support system, combining tensile connection devices and embedded metal parts, the problem of pressure and tension-free support of the foundation pit steel support system is solved, and the foundation pit is supported. Two-way stiffness and construction convenience improve overall safety and environmental protection.
Patent Information
- Application Number
- CN202010776759.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-05
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2040-08-05
AI Technical Summary
The existing foundation pit steel support system can only be subjected to pressure but not tension, resulting in the expansion of the enclosure structure in deep foundation pits with poor soil quality, making it difficult to deal with uncertainty and may have safety problems.
The steel support system of tension-pressure-type prefabricated string beam is adopted. By combining the embedded metal parts in the concrete beam with the tensile connection device, a combined string beam system can be formed that can be bidirectional stiffness inside and outside the pit. The steel purlin is eliminated and the steel components are directly connected with the Concrete beams are connected in tension.
The integrity and safety of the foundation pit support system have been improved, and the problem of traditional steel support being compressed and not being stretched is solved, construction errors have been reduced, construction convenience and efficiency have been improved, and the safety of foundation pit construction has been ensured. Environmental protection.
Smart Images

Figure CN111877360B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a tension-compression assembled beam-string steel support system, belonging to the technical field of building construction. Background Art
[0002] In order to ensure the safety of underground structure construction and the surrounding environment of the foundation pit, support, reinforcement and protection measures are adopted for the side walls of the foundation pit and the surrounding environment. Whether it is a deep foundation pit project for high-rise buildings or subway construction, since most of them are excavated in cities, there are usually various structures such as traffic arteries, existing buildings or pipelines around the foundation pit. In order to ensure the safety of the surrounding environment of the foundation pit and meet the needs of construction period and environmental protection, the steel support structure system is widely used in urban foundation pit support.
[0003] In the prior art, the steel support system of the foundation pit can only bear compression but not tension. For deep foundation pits, if there is silt outside the pit, or if the excavation on both sides of the positive corner support of the foundation pit is unbalanced, or if there are multiple supports, the retaining structure may expand outward under different working conditions such as excavation and replacement of supports, causing the retaining structure to separate from the support, which is inconsistent with the calculated force assumptions, making it difficult to cope with the uncertainty of foundation pit excavation, and may cause foundation pit safety issues. Summary of the invention
[0004] The purpose of the present invention is to provide a tension-compression steel support system, which increases the tension resistance of the system on the basis of the existing support system in the foundation pit with compression resistance to form a new steel-concrete composite beam string system. No steel purlin is required, and the truss steel support is directly connected to the concrete in tension and compression, and the tension rod is connected to the concrete beam in tension and compression through the strut to form a new composite beam string system, so that the whole steel support system has bidirectional rigidity both inside and outside the pit in the foundation pit support, with stronger integrity and higher safety. At the same time, the steel purlin in the traditional steel support system is eliminated, which makes the construction convenient, the force is clear, and it is more economical.
[0005] The present invention adopts the following technical solutions:
[0006] A tension-compression assembled girder steel support system comprises a concrete beam 10 and a tensile connection device 3; a metal part is embedded in the concrete beam in a foundation pit, and the metal part partially extends upward from the concrete beam 10; a tensile steel section 301 is arranged at the end of a tensile arm 306 of the tensile connection device 3, and after the tensile arm 306 passes through the metal part, the tensile steel section 301 is pressed against the back of the metal part to realize a tensile connection; Note: "metal part" is necessary here, but it is not necessarily only a metal part, and it can also be a mixture of a metal part and concrete, the tensile arm 306 is relatively fixed to a support prestressing device 1; the support prestressing device 1 applies pressure to the concrete beam.
[0007] Preferably, the metal part is one of a steel bar and an embedded steel section 307 .
[0008] Preferably, the metal member extends upward from the portion of the concrete beam 10 and is cast integrally with the concrete beam 10 to form a tensile member 303 .
[0009] A tension-compression assembled beam string steel support system, wherein no steel purlin is arranged in the foundation pit, and the tensile connection device 3 is directly connected to the concrete beam 10.
[0010] Preferably, the tensile arm 306 is L-shaped, with one end being arranged transversely and fixed relative to the metal member, and the other end being arranged downward and connected to a prestressed connector 308 , and the prestressed connector 308 is fixedly connected to the steel support 305 .
[0011] Furthermore, the tensile arm 306 is L-shaped, one end of which is arranged horizontally and fixed relatively to the concrete tensile member, and the other end of which is arranged downward and connected to the prestressed connection member 308, the prestressed connection.
[0012] Preferably, the portion where the tensile arm 306 passes through the metal member / tensile member 303 is provided with an adjusting device 302, and the adjusting device 302 can adjust its own length to adjust the tightness of the connection between the tensile steel section 301 and the tensile member 303 / metal member.
[0013] Preferably, an axial force monitoring box 304 is provided at the front end of the prestressing device 1 .
[0014] Preferably, the rear end of the prestressing device 1 is fixedly connected to the prestressing connector.
[0015] Preferably, a combined beam string system 6 is further included, and the tensile connection device 3 is connected to the prestressed connection piece 308 at the end of each strut 5 of the combined beam string system 6.
[0016] Preferably, it further comprises a tensile truss support system 13 , and each prestressed connection member 308 of the tensile truss support system 13 is provided with the tensile connection device 3 .
[0017] The beneficial effects of the present invention are:
[0018] 1) It solves the problem that traditional steel supports are only subjected to compression but not tension. In deep foundation pits with poor soil quality, it can replace the first concrete support ("the first concrete support" refers to the top layer of support from 0 meters underground to n meters underground. Due to the high tensile strength requirements, steel supports are generally not used in the prior art but pure concrete supports are used). By using the tension-compression assembled beam-string steel support system of the present application, the first support can also be made of steel support, so that multiple steel supports can form an integrated support system, making the entire support system more stable and safe.
[0019] 2) By replacing the first support, the matching problem between the first concrete support and multiple steel supports is solved, and the advantages of steel supports such as safety, environmental protection and time saving are maximized.
[0020] 3) The tension rods of the combined beam string system are embedded in the concrete through pre-anchoring and combined with the concrete to form a whole. The support rods are connected to the concrete beams in tension and compression, and have dual stiffness in the directions inside and outside the pit, making the entire combined structure more integrated and stable.
[0021] 4) The steel purlin in the traditional steel support is eliminated, and a new steel-concrete composite steel support system is formed by directly combining steel components and concrete beams. The connection is more reliable, the construction is convenient, the force is clear, the system is more integrated and safer; the impact of the concrete beam construction error on the installation of the support structure is reduced, the construction is more convenient and the accuracy is higher.
[0022] 5) The tensile truss support system is composed of multiple unit structures. Each unit can also be disassembled into small components. It has a high degree of assembly and can be disassembled according to site conditions. It is convenient for construction and assembly and has high flexibility.
[0023] 6) Since there is no steel purlin, the construction of the tensile truss support system and the beam string system does not interfere with each other and can be carried out in parallel, which increases construction convenience, improves flexibility, improves construction efficiency, and reduces construction period.
[0024] 7) The end connection unit is equipped with an axial force monitoring box, which can monitor the changes in the axial force of the steel support in real time and has an early warning function, making the foundation pit construction safer.
[0025] 8) The internal support of the steel structure is connected to the concrete beam in tension and compression. The nodes can be subjected to both compression and tension. The steel support and the concrete enclosure structure are more closely integrated, making the entire system more integrated and safer.
[0026] 9) An adjusting device is provided at the portion where the tensile arm passes through the embedded steel section. The adjusting device can adjust its own length and thus the tightness of the connection between the tensile steel section and the tensile member, thereby improving applicability and reliability. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is an overall plan view of the tension-compression type assembled beam string steel support system of the present invention.
[0028] Figure 2 It is a partial plan view of the tension-compression type assembled beam string steel support system of the present invention.
[0029] Figure 3 yes Figure 1 A partial enlarged view of .
[0030] Figure 4 This is a plan view of the tensile connection device after installation.
[0031] Figure 5 yes Figure 3 1-1 cross-sectional view in.
[0032] In the figure, 1. Prestressing device, 2. End tie rod, 3. Tensile connection device, 4. Intermediate tie rod, 5. Bracing rod, 6. Combined beam string system, 7. End connection unit, 8. Adjustable truss unit, 9. Tensile truss straight brace, 10. Concrete beam, 12. End tie rod, 13. Tensile truss support system, 14. Tensile truss angle brace, 15. Standard truss unit. 301. Tensile steel, 302. Adjustment device, 303. Tensile member, 304. Axial force monitoring box, 305. Steel support, 306. Tensile arm, 307. Embedded steel. DETAILED DESCRIPTION
[0033] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.
[0034] See also Figure 1-Figure 3 , the tension-compression steel support system includes a concrete beam 10, a tension truss support system 13, and a combined beam string system 6; the concrete beam 10 is arranged on the inner wall of the foundation pit; the combined beam string system 6 includes a strut 5, an intermediate tie rod 4, an end tie rod 2, a tension connection device 3, and a prestressing device; the end tie rod 2 is buried in the concrete; the intermediate tie rod 4, the end tie rod 2, and the strut 5 are all hinged; the end of the strut contains a prestressing device and is connected to the concrete beam 10 through the tension connection device 3. The tension truss support system 13 is divided into tension truss angle braces and tension truss straight braces, which are connected by multiple units, including standard truss units belonging to standard modules, adjustable truss units belonging to non-standard modules to adapt to different foundation pit size requirements, and the end connection units are connected to the concrete beam by tension and compression, which can withstand both the soil pressure transmitted from the soil and the tensile force that may occur under various construction conditions. The standard truss unit is composed of multiple chords + webs. The webs are hinged to the chords. The chords can be lattice-shaped or solid-web-shaped. The webs can be cross-shaped, diamond-shaped, etc. The end connection unit has a prestressing device, a tensile connection device, and an axial force monitoring box.
[0035] Specifically, see Figure 1-Figure 5A tension-compression assembled steel string beam support system includes a concrete beam 10 and a tensile connection device 3; a metal part is embedded in the concrete beam in the foundation pit, and the metal part partially extends upward from the concrete beam 10; a tensile steel 301 is arranged at the end of the tensile arm 306 of the tensile connection device 3, and after the tensile arm 306 passes through the metal part, the tensile steel 301 is pressed against the back of the metal part to achieve tensile connection; it should be noted that: the "metal part" here is necessary, but not necessarily only metal parts, and can also be a mixture of metal parts and concrete, the tensile arm 306 is relatively fixed to the support prestressing device 1; the support prestressing device 1 applies pressure to the concrete beam. No steel purlin is arranged in the foundation pit, and the tensile connection device 3 is directly connected to the concrete beam 10.
[0036] In this embodiment, if Figure 4-5 As shown, the metal part is embedded steel 307. It should be noted that the metal part can be embedded steel or steel bar, and can be cast integrally with the concrete beam to form an upwardly protruding (reinforced) concrete part, which is referred to as the tensile member 303 below.
[0037] In this embodiment, no steel purlin is provided in the foundation pit, and the tensile connection device 3 is directly connected to the concrete beam 10 .
[0038] In this embodiment, see Figure 5 The tensile arm 306 is L-shaped, one end of which is horizontally arranged and fixed relative to the metal member, and the other end is downwardly arranged and connected to the prestressed connector 308, and the prestressed connector 308 is fixedly connected to the steel support 305. For further information, see Figure 4-5 The portion where the tensile arm 306 passes through the metal piece is provided with an adjusting device 302, and the adjusting device 302 can adjust its own length to adjust the tightness of the connection between the tensile steel 301 and the metal piece.
[0039] In another embodiment, the tensile arm 306 is L-shaped, one end of which is disposed transversely and fixed relative to the tensile member 303. Figure 4 As shown, the other end is downwardly arranged and connected to the prestressed connector 308, and the prestressed connector 308 is fixedly connected to the steel support 305, as shown. Figure 5 As shown; as a further feature, the portion where the tensile arm 306 passes through the tensile member 303 is provided with an adjusting device 302, and the adjusting device 302 can adjust its own length to adjust the tightness of the connection between the tensile steel 301 and the tensile member 303.
[0040] In this embodiment, see Figure 4-5 An axial force monitoring box 304 is provided at the front end of the prestressing device 1.
[0041] In this embodiment, see Figure 4-5 The rear end of the prestressing device 1 is fixedly connected to the steel support 305 .
[0042] In this embodiment, see Figure 5 , the tensile steel 301 is an I-beam.
[0043] In this embodiment, see Figure 3 , further comprising a combined beam string system 6 , wherein the tensile connection device 3 is connected to the prestressed connection piece 308 at the end of each strut 5 of the combined beam string system 6 .
[0044] In this embodiment, see Figure 1-Figure 3 , further comprising a tensile truss support system 13, wherein each prestressed connection member 308 of the tensile truss support system 13 is provided with the tensile connection device 3.
[0045] "The first concrete support" refers to the topmost layer of support from 0 meters underground to n meters underground. Due to the high tensile strength requirements, pure concrete support is generally not used in the prior art instead of steel support. This application can replace the first concrete support in deep foundation pits with poor soil quality. The first support can also be made of steel support, so that multiple steel supports can form an integrated support system, making the entire support system more stable and safe. At the same time, by replacing the first support, the matching problem between the first concrete support and the multiple steel supports is solved, and the advantages of steel support in terms of safety, green environmental protection, and time saving are maximized. In addition, the end connection unit is equipped with an axial force monitoring box, which can monitor the changes in the axial force of the steel support in real time, and has an early warning function, making the foundation pit construction safer; the position where the tensile arm passes through the embedded steel is provided with an adjustment device, and the adjustment device can adjust its own length so as to adjust the tightness of the connection between the tensile arm and the embedded steel, thereby improving applicability and reliability.
[0046] The above are preferred embodiments of the present invention. Ordinary technicians in this field can also make various changes or improvements on this basis. Without departing from the overall concept of the present invention, these changes or improvements should fall within the scope of protection required by the present invention.
Claims
1. A tension-compression assembled beam string steel support system, characterized in that: It comprises a concrete beam (10) and a tensile connection device (3); A metal part is embedded in a concrete beam in a foundation pit, and a portion of the metal part extends upward from the concrete beam (10); A tensile steel (301) is arranged at the end of the tensile arm (306) of the tensile connection device (3); after the tensile arm (306) passes through the metal piece, the tensile steel (301) abuts against the back of the metal piece to achieve tensile connection; The tensile arm (306) is relatively fixed to the prestressing device (1); the supporting prestressing device (1) applies pressure to the concrete beam; The tensile arm (306) is L-shaped, one end of which is arranged horizontally and fixed relative to the metal member, and the other end of which is arranged downward and connected to the prestressed connector (308), and the prestressed connector (308) is fixedly connected to the steel support (305); The front end of the prestressing device (1) is provided with an axial force monitoring box (304); The rear end of the prestressing device (1) is fixedly connected to the prestressing connector.
2. The tension-compression assembled beam string steel support system according to claim 1, characterized in that: The metal part is one of a steel bar and a pre-buried steel section (307).
3. The tension-compression assembled beam string steel support system according to claim 1, characterized in that: The metal part and the concrete beam (10) are integrally cast to form a tensile member (303).
4. The tension-compression assembled beam string steel support system according to claim 1, characterized in that: No steel purlin is provided in the foundation pit, and the tensile connection device (3) is directly connected to the concrete beam (10).
5. The tension-compression assembled beam string steel support system according to claim 1 or 3, characterized in that: The portion where the tensile arm (306) passes through the metal piece is provided with an adjusting device (302), and the adjusting device (302) can adjust its own length to adjust the tightness of the connection between the tensile steel (301) and the metal piece.
6. The tension-compression assembled beam string steel support system according to claim 1, characterized in that: It also comprises a combined beam string system (6), wherein the tensile connection device (3) is connected to the prestressed connection piece (308) at the end of each strut (5) of the combined beam string system (6).
7. The tension-compression assembled beam string steel support system according to claim 1, characterized in that: It also comprises a tensile truss support system (13), wherein each prestressed connection member (308) of the tensile truss support system (13) is provided with the tensile connection device (3).