A method for regulating the settlement of the integral roadbed in the subway turnout area

Through real-time monitoring and automatic early warning system, combined with temporary reinforcement measures such as bent iron plates, gauge pull rod steel frames, as well as grouting and mechanical lifting technologies, settlement and rectification of subway switch areas has been solved, and the impact of track bed settlement on track is achieved. Safe and fast rectification effect.

CN112523017BActive Publication Date: 2024-12-06CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202011437550.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-10
Publication Date
2024-12-06
Estimated Expiration
2040-12-10

AI Technical Summary

Technical Problem

The subway bed settlement leads to uneven tracks, affecting the safety of train operations. The existing rectification methods have problems such as long construction period, high cost, construction environment pollution and single technology, and lack temporary reinforcement and rectification measures for different situations.

Method used

Real-time monitoring of settlement conditions, set settlement thresholds for automatic warning, and temporary adjustment and reinforcement, including reinforcement using bent thickened iron plates and gauge tie rod steel frames. After settlement is stable, grouting repair, mechanical lift + grouting repair is used. Or comprehensive improvement is carried out by chiseling and removing the splint and repouring the concrete platform.

Benefits of technology

It has realized rapid and economical rectification of the track bed without interrupting the operation of the train, ensuring that the track geometry meets safety requirements, solving the problem of single technical and difficult accuracy control of temporary reinforcement and subsequent rectification during settlement, and improving the The efficiency and safety of rectification.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112523017B_ABST
    Figure CN112523017B_ABST
Patent Text Reader

Abstract

A method for regulating the settlement of the overall roadbed in a subway turnout area, including real-time monitoring of the settlement of the roadbed in the settlement area and within a certain length range adjacent thereto; setting a settlement threshold, automatically monitoring and warning in real time when the roadbed settlement exceeds a certain value, and performing temporary adjustment and temporary reinforcement of the roadbed settlement when the roadbed settlement is not yet stable; after the roadbed settlement is stable, permanent regulation and repair technology is used to comprehensively regulate the overall roadbed of the turnout after the settlement is stable. The present invention temporarily adjusts the geometric shape and position of the turnout during the settlement so that the geometric shape and position of the turnout meets the requirements for safe driving; the gauge holding capacity and the integrity of the roadbed are strengthened through temporary reinforcement measures of gauge tie rod steel frames and steel support beams; according to different situations of the roadbed after the settlement is stable, grouting repair technology, mechanical lifting + grouting repair technology, and permanent regulation and repair technology of chiseling out the turnout sleepers and re-casting the concrete platform are used to comprehensively regulate the overall roadbed of the turnout after the settlement is stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of rail transportation, and in particular to a method for regulating the settlement of an integral roadbed in a subway turnout area. Background Art

[0002] The overall roadbed of subway tunnels has the advantages of stable operation, uniform stiffness, strong durability and small maintenance workload, and is widely used in urban rail transit in my country. Operation shows that the overall condition of the subway roadbed is good, but due to the complex geological conditions of some lines, inadequate quality control during the construction process, cross-project construction, groundwater and other factors, the overall roadbed of some parts of some lines has experienced different degrees of settlement, resulting in subway roadbed settlement diseases. Roadbed settlement will affect the smooth operation of trains and endanger driving safety in serious cases. As the weak link of the line, the turnout itself has problems such as uneven stiffness and harmful space, and has high requirements for line smoothness. In addition, the turnout area has a complex structure and many types of pipelines and equipment. The settlement of the overall roadbed in the turnout area will seriously affect the comfort and safety of driving, reduce the operating speed of trains and the traffic capacity of railway roads, and is one of the important hidden dangers for the safe operation of subways.

[0003] Traditional methods for remediating the sinking of the integral roadbed can be divided into two main categories. The first category is to interrupt traffic and completely renovate the roadbed in the diseased area. The second category is to take a series of measures such as adjusting fasteners or increasing the adjustable amount of fasteners, or pouring cement slurry on the base to remediate and lift the integral roadbed or rails while ensuring traffic. However, both of the above methods have certain shortcomings.

[0004] The method of overall renovation of the roadbed generally takes a long time to complete, which will lead to interruptions in train operations, and the maintenance cost is too high. The construction machinery is huge and requires many workers, which is not conducive to on-site organization and management. During the construction of long tunnels, ventilation is poor and the operation of large operating machinery produces serious harmful gases, dust and noise, causing construction environment pollution. At the same time, a large amount of tunnel waste will be generated, so it is generally not adopted.

[0005] At present, under the premise of not interrupting traffic, there are two main maintenance methods: one method is to increase the adjustable amount of the fasteners, such as thickening the cushion layer or thickening the iron pad, which can restore the smoothness of the track structure to a certain extent. Generally, the fasteners in the turnout area have a built-in height adjustment function, which can be adjusted by about +20mm, and is achieved by plugging height adjustment pads of different specifications under the iron pads of the fasteners. When adjusting by thickening the cushion layer, the cushion layer of the fastener needs to use an integral cushion layer to maintain the stability of the track structure. The use of layered pads will cause the cushion layer to burst out, and the track stability is poor; due to the different settlement amounts at different locations, the thickness of the integral cushion layer used for each fastener is different, and different integral pads need to be separately molded and made, which is costly and has high requirements for on-site construction; in addition, the increase in the adjustable amount of the fasteners by thickening the cushion layer is also limited. For track structures that continue to sink over a long period of operation, this treatment method has great limitations. When the height adjustment exceeds the designed height adjustment, it can be achieved through specially made thickened iron pads. For example, the thickness of the original designed iron pads can be thickened from 20mm to 30mm or more during manufacturing, thereby further increasing the height adjustment of the fasteners. However, thickening the iron pads will increase the length of the bolts, which are prone to shear damage and poor track structure stability. In addition, the above method will increase the height of the fasteners to a certain extent, which will affect the stability of the rails and may cause problems such as dynamic expansion of the track gauge and breakage of the spring bars, thus affecting the safety of train operations.

[0006] Another common method is to use improved cement-based materials for grouting and remediation, relying on the fluidity of the slurry itself to fill and reinforce the overall roadbed and tunnel bottom and the broken area at the tunnel bottom. The main problem with the current on-site construction of the grouting method is that most of the disease remediation construction belongs to the skylight point construction, and the skylight point construction time is short. Due to the influence of the existing line roadbed safety construction control, there are high requirements for grouting pressure, slurry characteristics, etc., which need to be filled densely and the grouting pressure must be controlled to be too high to avoid affecting the line shape and roadbed safety; it is necessary to ensure the good fluidity of the slurry, and it is necessary to put forward high requirements for the early setting time, strength and durability of the slurry. Therefore, the commonly used grouting method has high requirements for some related supporting processes and tooling during the operation process; under the premise of short time and high standards, it puts forward high requirements for disease remediation construction, which requires measures to be taken in the early stage of disease remediation construction to ensure and control the disease from continuing to develop, and provide necessary time and space for subsequent grouting reinforcement procedures. The quality of the later grouting reinforcement construction is also another important link to ensure the overall construction effect. The two need to be coordinated and unified to produce good results.

[0007] At present, some inventions have been applied for the rapid repair technology of the subsidence disease of the ballastless track structure in China. Invention CN102018001427424 discloses a method for the treatment of ballastless track subsidence based on rope saw cutting; Invention CN2013100277170 discloses a system and method for lifting the subsidence of the railway ballastless track subsidence by injection method, mainly providing a lifting method and grouting sequence of a ballastless track structure; Invention CN2013103825961 discloses a grouting lifting rapid repair technology for the subsidence of ballastless track, mainly providing key construction parameters and lifting precision control technology during grouting construction. Invention CN102014000394604 discloses a method for lifting and repairing ballastless track with subsidence in curved sections, which is suitable for curved sections by further improving the grouting technology. Invention CN201510525458 discloses a method for treating integral roadbed and tunnel bottom defects based on combined support and grouting templates, which uses a combination of combined steel plates and grouting to treat roadbed settlement.

[0008] In order to rectify the subsidence of the ballast bed, the above existing inventions have mainly applied for related inventions from various angles of the grouting method, but there are still certain shortcomings. For example, the commonly used grouting construction is carried out in ditches and side ditches. There is a lack of targeted measures for sections where the subsidence of the ballast bed directly affects the unevenness of the rails. There is also a lack of temporary reinforcement transition treatment measures for different situations, and the rectification method is single. Generally speaking, differential settlement occurs in the civil foundation of the turnout area, which leads to deformation of the track structure in the turnout area. The track geometry changes caused by the settlement of the civil structure. The civil structure must be rectified first. After the deformation of the civil structure converges, the track structure can be finally rectified, such as by grouting. The above-mentioned inventive rectification technology often needs to be processed after the settlement of the lower foundation is stable. However, the actual situation on site is often that during or after the rectification of the civil structure, for some sections, the settlement of the lower foundation has not yet stabilized or the track geometry of the turnout area continues to exceed the limit during the settlement process. The track structure cannot be finally rectified, but it has a huge impact on the safety of driving. Therefore, some temporary reinforcement transition measures are needed to control the geometry of the track structure to ensure the safety of driving.

[0009] Therefore it is very necessary to invent a method for regulating the settlement of the integral roadbed in a subway turnout area to solve the above problems. Summary of the invention

[0010] In view of the technical defects and technical drawbacks in the prior art, the embodiment of the present invention provides a method for regulating the settlement of the integral roadbed in the turnout area of ​​a subway, which overcomes the above problems or at least partially solves the above problems. The specific scheme is as follows:

[0011] A method for treating the settlement of the integral roadbed in a subway turnout area, the method comprising:

[0012] Step 1: real-time monitoring of the settlement of the roadbed in the settlement area and within a certain length range adjacent thereto;

[0013] Step 2: Set a settlement threshold. When the roadbed settlement exceeds a certain value, automatic real-time monitoring and early warning are implemented, and temporary adjustment and reinforcement of the roadbed settlement are performed when the roadbed settlement is not yet stable.

[0014] Step 3: After temporary adjustment and temporary reinforcement, when the roadbed settlement is stable, permanent renovation and repair technology is used to comprehensively renovate the entire turnout roadbed after the settlement is stable.

[0015] Furthermore, in step 2, the temporary adjustment of the roadbed settlement is specifically performed as follows: a bent and thickened iron plate is added to the fasteners of the subway turnout, and the bent and thickened iron plate is installed on the original standard iron pad in the fasteners of the subway turnout in the abnormal settlement section. The fastener height is adjusted by the bent and thickened iron plate, and the number of fastener anchor bolts is increased. The bent and thickened iron plate is fixed to the switch sleeper by multiple fastener anchor bolts to share the additional force caused by the fastener height adjustment.

[0016] Furthermore, the bent and thickened iron plate includes a protrusion and side plates located on both sides of the protrusion and integrally formed with the protrusion, the rails of the abnormal settlement section are supported on the protrusion, the original standard iron pad in the fastener is located below the protrusion, a plurality of first screw holes are opened at relative positions on the side plate and the standard iron pad, and are fixed to the switch sleeper by a plurality of first fastener anchor bolts matching the first screw holes, a plurality of second screw holes are opened at relative positions on the protrusion and the standard iron pad, and are fixed to the switch sleeper by a plurality of second fastener anchor bolts matching the second screw holes.

[0017] Furthermore, in step 2, temporary reinforcement of the roadbed settlement is specifically performed by: using a gauge rod steel frame to fix the rails, the gauge rod steel frame is provided with two rail mounting positions, and the two rails of the subway turnout in the abnormal settlement section are respectively installed on the two rail mounting positions of the gauge rod steel frame to keep the track gauge unchanged.

[0018] Furthermore, the gauge rod steel frame includes an I-beam and a gauge rod. There are two I-beams, which are respectively arranged on both sides of the rail along the length direction of the rail in the section with abnormal settlement. Both ends of the gauge rod are respectively connected to the two I-beams. There are multiple gauge rods, and the multiple gauge rods are arranged at intervals along the length direction of the rail in the section with abnormal settlement. Two concave grooves are fixedly installed on the gauge rod as rail mounting positions. Two rails are respectively embedded in the two concave grooves of the gauge rod. The two rails are respectively fixed by the two concave grooves, so that the gauges of the two rails remain unchanged.

[0019] Furthermore, in step 2, temporary reinforcement of the roadbed settlement is specifically performed by setting a steel support beam, wherein the steel support beam is located outside the rail of the abnormal settlement section and is set along the length direction of the rail of the abnormal settlement section, and the steel support beam is fixedly connected to multiple switch sleepers of the abnormal settlement section.

[0020] Furthermore, in step 3, the permanent remediation and repair technology is a grouting repair technology, a repair technology combining mechanical lifting + grouting repair, or a repair technology of chiseling out the switch sleepers and re-pouring the concrete platform.

[0021] Further, step 3 is specifically: using a water drill method to take samples to check whether there is a gap between the roadbed and the civil structure in the turnout area. If so, a grouting repair technology is used to permanently control the roadbed settlement. The repair technology specifically includes the following steps:

[0022] Step 311, survey the settlement of the track bed on site, install elevation measurement equipment, measure the elevation of the ballastless track structure in the settlement area, formulate a specific lifting plan based on the measurement results and engineering needs, and establish a monitoring network for lifting points;

[0023] Step 312, performing sealing grouting treatment on the longitudinal and transverse cracks of the ballast bed, the cracks at the junction of the ditch and the ballast bed, the water seepage positions of the ballast bed expansion joints, and the damaged positions in the ditch;

[0024] Step 313, marking the grouting hole position according to the established lifting plan, and then drilling, cleaning the dust on the site in time during drilling, and using a plugging piece to plug the grouting hole;

[0025] Step 314, removing the plugging member on the upper part of the grouting hole, injecting the grouting material from the grouting pipe into the lower structure of the ballastless track according to the set grouting lifting process parameters and grouting process, and lifting the track structure. During the lifting process, the elevation of the track structure is monitored in real time through the installed elevation monitoring equipment;

[0026] Step 315, during the grouting lifting process, the grouting pressure is strictly controlled to avoid the back arch of the roadbed after grouting; the grouting sequence is to first grout the middle lifting hole, and then grout the filling holes on both sides and the middle filling hole in turn; the lifting hole grouting starts from the lowest point of the track structure elevation in turn; when the track structure is lifted to the height set for this grouting lifting, the grouting is stopped immediately; after the lifting hole grouting is completed, the filling holes in the middle and both sides of the line are grouted to ensure that the grouting material is evenly and densely filled in the lower part of the track structure;

[0027] Step 316: If the single lifting height does not reach the set lifting height, repeat the processes of steps D and E, and finally lift the roadbed to a suitable position through multiple lifting.

[0028] Furthermore, step 3 is to use a water drilling method to take samples to check whether there is any gap between the roadbed and the civil structure in the turnout area. If there is no gap, a repair technology combining mechanical lifting + grouting repair is used to permanently control the roadbed settlement. The repair technology specifically includes the following steps:

[0029] Step 321, investigating the general situation of the area with abnormal roadbed settlement and determining the length of the section with abnormal roadbed settlement;

[0030] Step 322. Remove the fasteners and rails within the abnormal settlement length range;

[0031] Step 323, planting reinforcement and installing anchors on the roadbed in the turnout area, continuously installing a certain number of jacks on both sides of the roadbed bottom plate in the abnormal settlement section, and debugging the jacks;

[0032] Step 324, placing the distribution beam across the track on the debugged jack;

[0033] Step 325, connect and fix the suspension rod to the distribution beam, and then use a jack to lift the distribution beam to achieve the lifting of the track;

[0034] Step 326, after the lifting height reaches the required level, grouting material is poured into the gap formed between the raised ballast bed and the structural bottom plate, and the ballast bed settlement is permanently rectified through grouting repair technology.

[0035] Further, step 3 is specifically to use a water drill method to take samples to check whether there is any gap between the roadbed and the civil structure in the turnout area. If there is no gap, and the number of on-site jacking equipment and installation space are limited or the construction time is insufficient, the roadbed settlement is permanently rectified by chiseling out the turnout sleepers and re-casting the concrete platform repair technology. The repair technology specifically includes the following steps:

[0036] Step 331, measuring the elevation of the ballastless track structure in the settlement area, and according to the settlement monitoring results, determining the switch sleepers to be removed by "cutting one every three times" and marking them on site;

[0037] Step 332, removing the fasteners above the marked switch sleepers;

[0038] Step 333, the marked switch sleeper and a certain range of concrete around it are chiseled out, the width and length of the chiseled pit are the same as the bottom of the original switch sleeper, the depth is to the bottom surface of the switch sleeper, and the connecting steel bars of the original switch sleeper extending into the ballast around the pit are retained;

[0039] Step 334, cleaning the foundation pit and the surface of the track bed after the switch sleepers are removed;

[0040] Step 335, using square timbers to provide temporary support on the ballast surface on both sides of the removed turnout sleeper;

[0041] Step 336, the newly laid steel bars in the pit are connected to the connecting steel bars originally extending into the roadbed and located around the pit by welding and anchoring, steel bars are implanted through drilling holes at the bottom of the pit, the steel bars are tied to form a steel cage, and an interface agent is applied around the pit to strengthen the bonding effect between the new and old concrete;

[0042] Step 337, reinstall the fasteners and plastic sleeves of the original switch sleepers where the switch sleepers are removed, adjust the track joint shape and position, install templates around the fasteners, and pour concrete;

[0043] Step 338, when the concrete solidifies to a certain strength, the formwork and fasteners are removed to leave the rails suspended in the air to prevent the newly poured concrete platform from being damaged by premature stress;

[0044] Step 339, pour concrete again. When the newly poured concrete meets the load-bearing requirements, reinstall the fasteners, remove the square timbers, and re-measure the line geometry, and the line resumes normal operation.

[0045] The present invention has the following beneficial effects:

[0046] 1. The present invention provides a method for regulating the settlement of the overall roadbed in the turnout area of ​​a subway. During the period when the roadbed settlement in the turnout area has not yet stabilized, a temporary adjustment measure of raising the fastener with a specially made bent iron pad is adopted to ensure that the geometric position of the line during the roadbed settlement meets the requirements for safe driving. The adjustment method and tooling of the bent iron pad of the present invention can increase the number of anchor bolts at the fastener position, share the additional force caused by the fastener height adjustment, and stabilize the original fastener at the same time, avoiding the unfavorable force on the anchor bolt caused by the corresponding lengthening of the bolt after the fastener height adjustment, the occurrence of shear damage, and the dynamic expansion of the track gauge and the breakage of the spring bar caused by the fastener height adjustment.

[0047] On the basis of temporary adjustment measures, temporary reinforcement measures such as adding gauge tie rod steel frames and steel support beams were adopted to strengthen the track gauge holding capacity and overall stability of the line, avoiding the deterioration of the geometric shape of the roadbed during the roadbed settlement period, which threatens driving safety, and enhancing the ability of the existing turnout track structure to resist roadbed settlement deformation. The shortcomings of the existing regulation measures, such as the lack of temporary reinforcement transition treatment measures for different situations and the single regulation method, were solved.

[0048] 2. During the period of roadbed settlement, the present invention uses high-precision monitoring equipment such as video monitoring system, electronic level, etc. to monitor the overall settlement and uneven settlement of the track structure in the turnout settlement area and strengthen the analysis of monitoring data, grasp the settlement change curve, predict the settlement trend, set the early warning threshold for early warning, establish a roadbed settlement monitoring, early warning, and prediction system, and form a roadbed settlement monitoring platform to ensure that the geometric shape and position of the track meets the safety requirements during the line driving process; at the same time, it also ensures the precision control of the ballastless track structure lifting and balanced support in the subsequent permanent remediation measures. It solves the problem that the timing of remediation cannot be grasped and the precision of remediation cannot be controlled in the existing remediation measures.

[0049] 3. According to the different situations of the track structure in the turnout area after the ballast settlement is stabilized, the present invention adopts grouting repair technology, mechanical lifting + grouting repair technology, and chiseling out the switch sleepers and re-casting the concrete platform repair technology to carry out systematic and comprehensive remediation of the overall ballast settlement in the turnout area, thereby solving the problems of single remediation technology, lack of specificity, limited installation space or insufficient construction time in traditional remediation measures.

[0050] 4. The present invention organically combines temporary measures and reinforcement measures during the roadbed settlement period with a series of remediation measures after the settlement is stabilized, systematically remediates the settlement damage of the entire roadbed in the subway turnout area, and completely solves the damage problem of the entire roadbed in the turnout area at different settlement periods.

[0051] 5. The remediation method of the present invention for different settlement periods has the advantages of low operating difficulty, simple construction process, fast construction, practicality and reliability, cost-effectiveness, strong process controllability, high implementation efficiency, high safety performance, no impact on subway operation, strong adaptability, etc. It can meet the requirements of narrow idle space and short operation time for existing line construction, is suitable for reinforcement and remediation of lines at different settlement stages, and provides a fast, convenient, practical and economical method for solving ballastless track settlement problems within the window time, ensuring the normal operation of the line.

[0052] 6. The present invention does not require the use of large-scale construction equipment, and the construction process of each treatment method is simple, with fewer on-site workers. It can achieve accurate lifting of the elevation of the ballastless track structure and rapid repair of the track smoothness, and reduce the damage to the roadbed and the impact of the bottom plate before and after the train passes, achieving the purpose of effectively controlling the development speed of the disease and quickly and efficiently treating the roadbed settlement. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] Figure 1 A flow chart of a method for regulating the settlement of the integral roadbed in a subway turnout area provided by an embodiment of the present invention;

[0054] Figure 2 An overall remediation idea diagram provided for an embodiment of the present invention;

[0055] Figure 3 A simplified diagram of an example of a bent iron pad provided in an embodiment of the present invention;

[0056] Figure 4 A three-dimensional diagram of an example of a bent iron pad provided in an embodiment of the present invention;

[0057] Figure 5 A three-dimensional exploded view of an example of a bent iron pad provided in an embodiment of the present invention;

[0058] Figure 6 A simplified diagram of a gauge tie rod steel frame provided in an embodiment of the present invention;

[0059] Figure 7 A three-dimensional diagram of an example of a gauge tie rod steel frame provided by an embodiment of the present invention;

[0060] Figure 8 A three-dimensional schematic diagram of a gauge tie rod steel frame provided in an embodiment of the present invention;

[0061] Fig. 9 A simplified diagram of a steel joist provided in an embodiment of the present invention;

[0062] Fig.10 A three-dimensional schematic diagram of a steel joist provided in an embodiment of the present invention;

[0063] Fig.11 A grouting repair process flow chart provided by an embodiment of the present invention;

[0064] Fig.12 A schematic cross-sectional view of a grouting hole provided in an embodiment of the present invention;

[0065] Fig.13 A schematic diagram of a plum blossom arrangement of grouting lifting grouting holes and grouting filling grouting holes provided in an embodiment of the present invention;

[0066] Fig.14 A process flow chart of mechanical lifting + grouting repair provided by an embodiment of the present invention;

[0067] Fig.15 A three-dimensional schematic diagram of a mechanical lifting + grouting repair process provided by an embodiment of the present invention;

[0068] Fig.16 A schematic diagram of a repair technology for removing switch sleepers and re-pouring a concrete platform provided by an embodiment of the present invention;

[0069] Fig.17 A flowchart of the repair technology of removing the switch sleepers and re-pouring the concrete platform provided in an embodiment of the present invention;

[0070] In the figure: 1. rail, 2. bent iron pad, 3. insulating buffer pad, 4. ballast bed, 5. lifting grouting hole, 6. filling grouting hole, 7. standard iron pad, 8. switch sleeper, 9. steel support beam, 10. fastener, 11. concrete platform, 12. gauge rod, 13. I-beam, 14. gauge rod steel frame, 15. second fastener anchor bolt, 16. first fastener anchor bolt, 17. hanger, 18. nut, 19. jack, 20. distribution beam, 21. anchor bolt. DETAILED DESCRIPTION

[0071] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the present invention, not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0072] like Figure 1-2 As shown, as a first embodiment of the present invention, a method for regulating the settlement of the integral roadbed in a subway turnout area is provided, comprising:

[0073] Step 1: Establish an overall roadbed settlement monitoring platform in the turnout area, and monitor the settlement of the roadbed 4 in the settlement area and within a certain length range adjacent thereto in real time through the roadbed settlement monitoring platform;

[0074] Step 2, setting a settlement threshold value, when the settlement of the roadbed 4 exceeds a certain value, realizing automatic real-time monitoring and early warning, and performing temporary adjustment and temporary reinforcement of the settlement of the roadbed 4 when the settlement of the roadbed 4 is not yet stable;

[0075] Step 3, after temporary adjustment and temporary reinforcement, when the settlement of the roadbed 4 is stable, permanent regulation and repair technology is used to comprehensively regulate the entire roadbed 4 of the turnout after the settlement is stable.

[0076] Wherein, in step 1, the overall roadbed 4 settlement monitoring platform of the turnout area includes a roadbed 4 settlement monitoring, early warning and prediction system.

[0077] Through on-site investigation of the settlement area of ​​the entire roadbed 4 in the turnout area, settlement observation points are set up along the longitudinal distribution on the roadbed 4 in the settlement area and within a certain length range adjacent to it. Measuring equipment such as video monitoring system and electronic level are used to monitor the longitudinal, lateral and vertical displacement changes of the track in real time, focusing on the overall settlement and related settlement of the roadbed 4, and establishing a roadbed 4 settlement monitoring system.

[0078] Based on the settlement observation of the track structure, the early warning values ​​of uneven settlement and overall settlement are proposed, and the roadbed 4 settlement early warning system is established. By setting the settlement threshold, when the roadbed 4 settlement exceeds a certain value, automatic real-time monitoring and early warning are realized to ensure the safe operation of the line. The specific early warning value should be determined by simulation calculation based on the actual situation of the work site and combined with existing experience. For example, a certain work site adopts an uneven settlement index of 15mm / 20m and a maximum overall settlement of 30mm. Once the early warning value is exceeded, the operating unit will be alarmed in time, and the line will be further restricted accordingly. In serious cases, the line will be suspended.

[0079] Increase the frequency of checking the geometry of the track surface with a push car on the diseased point and strengthen the observation and analysis of the continuous settlement of the civil structure, especially during the continuous settlement of the civil structure, strengthen the analysis of monitoring data, master the settlement change curve, predict the settlement trend, and deal with abnormal conditions in time, and establish a prediction system for the roadbed settlement. According to the monitoring situation, take speed limit measures for operating trains (reference speed is 25-35km / h). If the settlement converges and stabilizes before reaching the limit, the civil engineering will not be rectified. If the settlement continues to develop and reaches the specified limit, the civil engineering will be rectified.

[0080] The switch area integral ballast 4 settlement monitoring, early warning and prediction system can be used not only in the ballast 4 settlement regulation stage, but also in the subsequent switch area line safety operation stage to ensure the safe service of the line switch area.

[0081] As a second embodiment of the present invention, in step 2, the temporary adjustment measures during the period when the settlement of the roadbed 4 has not yet stabilized are specifically:

[0082] The temporary adjustment measure during the settlement of the ballast bed 4 is to raise the fastener 10 through the specially made bent iron pad 2 to temporarily adjust the geometric position of the turnout during the settlement.

[0083] The bent iron pad 2 is a specially made bent and thickened iron pad, made of the same material as the original standard iron pad 7 of the turnout fastener 10, and is welded to the original standard iron pad 7 of the turnout fastener 10. The same anchor bolt holes are reserved in the rail support platform (i.e., the turnout sleeper 8) to facilitate the existing fastener 10 anchor to be screwed in and fixed.

[0084] The bent iron pad 2 has a certain number of bolt holes reserved on the bent pads on both sides of the rail support platform, which can increase the number of anchor bolts at the position of the fastener 10 as a whole, share the additional force caused by the fastener 10 being raised, and stabilize the original fastener 10, avoiding the anchor bolts being sheared due to the corresponding lengthening of the bolts after the fastener 10 is raised, and avoiding the problems of dynamic expansion of the track gauge and breakage of the spring bar caused by the fastener 10 being adjusted too high. Figure 3 to Figure 5As shown, in this example, four first screw holes are reserved on each side plate of the bent iron pad 2 on both sides of the rail support platform, and are fixed to the switch sleeper 8 by multiple first fastener anchor bolts 16 matching the first screw holes, and multiple second screw holes are opened at relative positions on the raised portion and the standard iron pad 7, and are fixed to the switch sleeper 8 by multiple second fastener anchor bolts 15 matching the second screw holes.

[0085] The bolts on the bent iron pad 2 are made of alloy steel to improve the strength of the bolts and avoid the problem that the fastener anchor bolts are easily damaged and fail.

[0086] The insulating buffer plate 3 can be filled under the bent iron plate 2 as needed to provide a buffer between the standard iron plate 7 and the concrete ballast 4, while increasing the insulation between the rail 1 and the ballast 4 to avoid stray current leakage.

[0087] In addition, during the period of continuous settlement of the track bed 4, in addition to the above-mentioned temporary adjustment measures for the track structure, corresponding temporary reinforcement measures are also taken for the track structure to avoid exceeding the limit of track geometry.

[0088] The temporary reinforcement measures include temporarily reinforcing the turnout track structure through the gauge tie rod steel frame 14. Gauge tie rods 12 are densely arranged in the turnout area, and a certain number of gauge tie rods 12 are assembled into a steel frame to ensure the integrity of the turnout rail parts and strengthen the gauge holding capacity, such as Figure 6 to Figure 8 shown.

[0089] The gauge tie rod steel frame 14 is composed of a certain number of gauge tie rods 12 and I-beams 13. In this example, there are multiple gauge tie rods 12 with a spacing of 650 mm. The gauge tie rods 12 are arranged transversely along the line. Both ends of the gauge tie rods 12 are welded to the I-beams 13, and the I-beams 13 are arranged longitudinally along the line.

[0090] The I-beam 13 can be bolted and anchored to the surface of the ballast bed 4 to strengthen the overall constraint of the gauge tie rod steel frame 14 on the ballast bed 4 and the rails 1 .

[0091] The temporary reinforcement measures also include temporary reinforcement through steel joists 9 to strengthen the ability of the roadbed 4 to resist settlement and deformation, and improve the overall rigidity and integrity of the roadbed 4. Figure 9-10 shown.

[0092] The steel support beam 9 is an I-beam structure, located outside the line rail 1, and fixed to multiple switch sleepers 8 or to the ballast 4 on both sides of the settlement joint through anchors such as anchor bolts 21 to integrally reinforce the ballast 4. The I-beam size of the steel support beam 9 in this example is 300 mm wide, 20 mm thick at the flange, 300 mm high, and 20 mm thick at the web.

[0093] The length of the steel joist 9 can be determined according to the settlement area on site. In this example, the steel joist 9 is 3 m long.

[0094] While adopting the above-mentioned temporary adjustment and strengthening measures, during the period of continuous settlement of the civil engineering structure, the inspection frequency of the renovated part is increased, the inspection is strengthened, and the height adjustment amount of the fastener 10 is adjusted in time according to the measurement data of the rail car, and bent iron pads 2 of different thicknesses are selected.

[0095] As the third embodiment of the present invention, after the civil engineering settlement deformation converges and stabilizes, permanent remediation measures are taken for the integral roadbed 4 in the settlement area. The permanent remediation methods after the roadbed 4 settlement is stabilized include grouting repair technology, mechanical lifting + grouting repair technology, and chiseling out the switch sleepers and re-casting the concrete platform repair technology (three parallel permanent repair technologies). By combining temporary adjustment, reinforcement measures and permanent remediation methods, the settlement disease of the roadbed 4 in the turnout area is comprehensively rectified. The permanent remediation measures after the roadbed 4 settlement is stabilized are specifically described below.

[0096] 1) Permanent remediation measures after the ballast 4 settlement is stabilized: grouting repair technology

[0097] The water drilling method is used to take samples to check whether there is any gap between the roadbed 4 and the civil structure in the turnout area. If so, the grouting repair technology is used to permanently control the settlement of the roadbed 4.

[0098] The grouting repair technology includes grouting materials, equipment and tooling, and related construction processes and steps. The repair technology specifically uses high-pressure grouting equipment and grouting pipes. Under certain grouting equipment process parameters such as grouting pressure, temperature and flow, the polymer grouting material with good filling, rapid coagulation and expansion characteristics is injected into the empty position between the ballast bed 4 and the structural base plate through a grouting pipe pre-installed in the grouting hole in a certain grouting sequence. The grouting pressure and the expansion force of the injected slurry are used to lift the upper track structure. During the grouting process, precise measuring devices such as electronic levels are used to monitor the longitudinal, lateral and vertical displacement changes of the track structure in real time, so as to achieve precision control of the lifting and balanced support of the subsided ballastless track structure and ensure that the geometric shape and position of the track meet the requirements. Figure 11 to Figure 13 shown.

[0099] The grouting material should have excellent hydrophilicity, permeability, and expansion properties, good wettability and curing and bonding properties for clay particles in a water environment, good bonding strength after curing, and meet the long-term operation vibration requirements of subway trains. It has high tensile and shear strengths, and is not easily diluted by water to produce dispersion during the grouting process, and is non-toxic, pollution-free, aging-resistant, and quick-setting. For example, organic EAA (ethylene acrylic acid copolymer), polyurethane, epoxy resin, etc., inorganic water glass-cement system, sulphoaluminate system, etc.

[0100] The number of rows and row spacing of the grouting holes are determined according to the track structure size and the expansion radius of the grouting material. The grouting holes are drilled by a water-grinding drill and arranged in a plum blossom shape. The grouting holes are generally divided into two types: lifting grouting holes 5 and filling grouting holes 6. The lifting grouting holes 5 are located in the middle of the line, and the filling grouting holes 6 are distributed on both sides of the line and in the middle of the line. The middle grouting hole is set vertically downward, and the grouting holes on both sides of the line are set obliquely toward the middle of the line.

[0101] The grouting repair technology, before grouting reinforcement of the roadbed slab, first performs closed grouting treatment on the longitudinal and transverse cracks in the roadbed 4, the cracks at the junction of the ditch and the roadbed 4, the water seepage positions of the expansion joints of the roadbed 4, and the damaged positions in the ditch, to avoid the occurrence of slurry leakage and slurry leakage during the grouting process, while ensuring the maximum filling of the slurry at the bottom of the roadbed 4 to achieve the best reinforcement effect.

[0102] The grouting repair technology described above has the following grouting sequence: first grouting the lifting grouting hole 5, and then grouting the filling grouting holes 6 on both sides and in the middle of the line in turn; when grouting the lifting grouting hole 5, first grouting starts from the lifting grouting hole 5 at the lowest point of the line, and then grouting the lifting grouting holes 5 on both sides, and then grouting the filling grouting holes 6 on the left and right sides of the line in the order of plum blossom piles, and finally grouting the filling grouting holes 6 in the middle of the line.

[0103] The grouting and lifting rapid repair technology is composed of construction steps such as on-site survey, deployment of monitoring network, formulation of lifting plan, early sealing of track cracks and water seepage locations, drilling, equipment installation and commissioning, grouting and fine-tuning of track structure, etc., which specifically include the following aspects:

[0104] A. Investigate the settlement of the track bed 4 on site, install elevation measurement equipment, such as electronic level, to measure the elevation of the ballastless track structure in the settlement area, formulate a specific lifting plan based on the measurement results and project needs, and establish a monitoring network for lifting points.

[0105] B. Carry out closed grouting treatment on the longitudinal and transverse cracks of the ballast 4, the cracks at the junction of the ditch and the ballast 4, the water seepage position of the expansion joint of the ballast 4, and the damaged position in the ditch;

[0106] C. Mark the location of the grouting holes according to the established lifting plan, and then drill the holes. Clean the dust on site in time during drilling, and use plugging parts to plug the grouting holes;

[0107] D. Remove the plugging parts on the top of the grouting hole, and inject the grouting material from the grouting pipe into the lower structure of the ballastless track according to the set grouting lifting process parameters and grouting process, and lift the track structure. During the lifting process, the elevation of the track structure is monitored in real time through the installed elevation monitoring equipment.

[0108] E. During the grouting lifting process, the grouting pressure is strictly controlled to avoid the back arch of the roadbed 4 after grouting. The grouting sequence is to first grout the middle lifting grouting hole 5, and then grout the filling grouting holes 6 on both sides and the middle filling grouting hole 6 in turn. The grouting of the lifting grouting hole 5 starts from the lowest point of the track structure elevation; when the track structure is lifted to the height set for this grouting lifting, the grouting is stopped immediately; after the grouting of the lifting grouting hole 5 is completed, the filling grouting holes 6 in the middle and on both sides of the line are grouted to ensure that the grouting material is evenly and densely filled in the lower part of the track structure.

[0109] F. If the single lifting height does not reach the set lifting height, the steps D and E can be repeated. After multiple liftings, the ballast bed 4 is finally lifted to the appropriate position. After the grouting is stable, the fastener 10 fine-adjusts the turnout rail 1. At this time, the special tooling equipment used during the settlement period should be removed, such as the bent iron pad 2 on the fastener 10, the gauge tie rod steel frame 14 on the rail 1, and the steel support beam 9 on the ballast bed 4 or the turnout sleeper 8; the grouting pipe is removed, the grouting hole is sealed, the turnout geometry is re-measured, and the line is restored to traffic.

[0110] 2) Permanent remediation measures after the roadbed 4 settlement is stabilized: mechanical lifting + grouting repair technology

[0111] If sampling by water drilling finds that there is no gap between the turnout area ballast 4 and the structural bottom plate, there will be certain problems if the grouting repair technology is directly used. Since the concrete of the subway ballast 4 is generally fully paved to the tunnel side wall, the ballast 4 and the structural bottom plate are connected by roughening, and there is no gap at the interface between the new and old concrete. If sampling finds that there is no gap, it is difficult to inject slurry when the grouting repair technology is directly used. Figure 14 to Figure 16 As shown, at this time, a construction method of first supporting and then grouting reinforcement can be adopted, that is, the repair method combining mechanical lifting + grouting repair of the present invention can be used.

[0112] The repair technology combining mechanical lifting + grouting repair includes related equipment and related construction processes and steps. The repair technology combining mechanical lifting + grouting repair is characterized in that the repair technology combining mechanical lifting + grouting repair consists of the following construction steps: removing the fastener 10 and the rail 1, installing the distribution beam 20, debugging the jack 19, mechanical lifting and grouting, fine-tuning the track, installing the fastener 10 and the rail 1, and line detection and restoration. It specifically includes the following aspects:

[0113] A. First, investigate the general situation of the roadbed 4 diseased area and determine the length of the roadbed 4 diseased section;

[0114] B. Remove the fastener 10 and rail 1 within the length of the defect;

[0115] C. Plant reinforcement and install anchors on the roadbed 4 in the turnout area, and continuously install a certain number of jacks 19 on both sides of the bottom plate of the roadbed 4 in the diseased section, and debug them;

[0116] D. Place the distribution beam 20 across the track on the jack 19;

[0117] E. Connect and fix the suspension rod 17 to the distribution beam 20 through the nut 18, and then use the jack 19 to lift the distribution beam 20 to achieve the lifting of the track;

[0118] F. After the lifting height reaches the requirement, grouting material is poured into the gap formed between the raised roadbed 4 and the structural bottom plate; the grouting repair technical steps and construction process are the same as above;

[0119] G. Fine-tune the track bed plate;

[0120] H. When the strength of the grouting material reaches the design requirements, the slab is dropped and the jacking and grouting equipment is removed;

[0121] I. Install the fastener 10 and the rail 1;

[0122] J. Check the smoothness of the line and resume normal traffic when the requirements are met.

[0123] 3) Permanent remediation measures after the ballast 4 settlement is stabilized: chiseling out the switch sleepers and re-pour the concrete platform repair technology

[0124] If the number of on-site lifting equipment, installation space is limited or the construction time is insufficient, it is difficult to use mechanical lifting + grouting repair technology. The repair technology of chiseling out the switch sleepers and re-pour the concrete platform can be used, such as Fig.17 shown.

[0125] The repair technology of chiseling out the switch sleepers and re-casting the concrete platform includes equipment, tooling, and related construction processes and steps. The repair technology of chiseling out the switch sleepers and re-casting the concrete platform consists of the following construction steps: on-site survey to determine the switch sleepers 8 to be chiseled out, dismantling the fasteners 10 above the switch sleepers 8 to be chiseled out, chiseling out the concrete of the switch sleepers 8, cleaning the ballast plate, tying the steel cage, installing the fasteners 10 and plastic sleeves of the original switch sleepers 8, erecting the mold to cast concrete, dismantling the mold and taking out the fasteners 10, installing the fasteners 10 of the original switch sleepers 8, and re-measurement and restoration. It specifically includes the following aspects:

[0126] A. According to the results of on-site investigation and settlement monitoring, the tie 8 to be removed is determined by "cutting one every three times" and marked on site;

[0127] B. Remove the fastener 10 above the marked switch tie 8;

[0128] C. Remove the marked switch sleeper 8 and a certain range of concrete around it. The width and length of the pit are the same as the bottom of the original sleeper, and the depth is to the bottom of the sleeper. The connecting steel bars of the original switch sleeper 8 extending into the ballast 4 are retained around the pit;

[0129] D. Clean the foundation pit and the surface of the ballast plate after the switch sleeper 8 is removed;

[0130] E. Use square timber to provide temporary support on the four sides of the track bed on both sides of the removed sleeper;

[0131] F. Connect the newly laid steel bars in the pit to the connecting steel bars originally extending into the roadbed 4 and located around the pit by welding and anchoring, implant steel bars through drilling holes at the bottom of the pit, tie the steel bars to form a steel cage, apply interface agent around the pit to strengthen the bonding effect of new and old concrete;

[0132] G. Install the original switch sleeper 8 fastener 10 and plastic sleeve where the switch sleeper 8 is removed, adjust the track joint shape and position, and install the template around the fastener 10;

[0133] H. pouring concrete;

[0134] I. When the concrete solidifies to a certain strength, the formwork and fasteners 10 are removed to suspend the rail 1 in the air to prevent the newly poured concrete platform 11 from being damaged by premature stress;

[0135] J. Further curing of the concrete. When the newly poured concrete meets the load-bearing requirements, reinstall the fastener 10, remove the square timber, re-measure the line geometry, and resume normal operation of the line.

[0136] During the construction of the repair technology of chiseling out the switch sleepers and re-pouring the concrete platform, dust will be generated when the existing roadbed concrete is chiseled out. A special sprinkler should be configured to spray water while chiseling to reduce dust; at the same time, the station fan should be turned on to eliminate dust.

[0137] In the construction of the repair technology of chiseling out the switch sleepers and re-pouring the concrete platform, the cast-in-place concrete track support platform can consider using synthetic sleepers with connecting devices. Synthetic sleepers have the advantages of fast strength increase, easy drilling and installation of fasteners 10, convenient grooving and lowering, and pad height adjustment.

[0138] The present invention provides a method and tooling for regulating the settlement of the integral roadbed in a subway turnout area, and regulates and repairs the integral roadbed 4 of the turnout in different settlement periods. For the roadbed 4 during the settlement period, the fastener 10 is raised by a special bent iron pad 2, and the geometric shape and position of the turnout during the settlement period are temporarily adjusted so that the geometric shape and position of the turnout meet the requirements of safe driving; the gauge holding capacity and the integrity of the roadbed 4 are strengthened by temporary reinforcement measures such as the gauge tie rod steel frame 14 and the steel support beam 9; for different situations of the roadbed 4 after the settlement is stable, the grouting repair technology, mechanical lifting + grouting repair technology, and permanent regulation and repair technology of chiseling out the turnout sleepers and re-casting the concrete platform are used to comprehensively regulate the integral roadbed 4 of the turnout after the settlement is stable.

[0139] By adopting the temporary adjustment measure of raising the fastener 10 by using the specially made bent iron pad 2, it is ensured that the geometric position of the line meets the safe driving requirements during the period when the settlement of the ballast 4 has not yet stabilized. The adjustment method and tooling of the bent iron pad 2 of the present invention can increase the number of anchor bolts at the position of the fastener 10, share the additional force caused by the raising of the fastener 10, and stabilize the original fastener system at the same time, avoiding the unfavorable force on the anchor bolts caused by the corresponding lengthening of the bolts after the raising of the fastener 10, the occurrence of shear damage, and the dynamic expansion of the track gauge and the breakage of the spring bar caused by the excessive adjustment of the fastener 10.

[0140] On the basis of temporary adjustment measures, temporary reinforcement measures such as adding gauge tie rod steel frame 14 and steel support beam 9 are adopted to strengthen the gauge keeping ability and overall stability of the line, avoid the deterioration of the geometric shape of the roadbed 4 during the settlement of the roadbed 4, and threaten the driving safety, and enhance the ability of the existing turnout track structure to resist the settlement and deformation of the roadbed 4. The shortcomings of the existing regulation measures, such as the lack of temporary reinforcement transition treatment measures for different situations and the single regulation method, are solved.

[0141] During the settlement of the ballast bed 4, high-precision monitoring equipment such as video monitoring systems and electronic levels are used to monitor the overall settlement and uneven settlement of the track structure in the turnout settlement area, and strengthen the analysis of monitoring data, master the settlement change curve, predict the settlement trend, set early warning thresholds for early warning, establish a monitoring, early warning, and prediction system for the settlement of the ballast bed 4, and form a ballast bed 4 settlement monitoring platform to ensure that the geometric shape and position of the track during the line driving process meets the safety requirements; at the same time, it also ensures the precision control of the ballastless track structure lifting and balanced support in the subsequent permanent remediation measures. It solves the problem that the timing of remediation cannot be grasped and the remediation accuracy cannot be controlled in the existing remediation measures.

[0142] According to the different conditions of the track structure in the turnout area after the settlement of the ballast 4 has stabilized, grouting repair technology, mechanical lifting + grouting repair technology, and repair technology of removing the switch sleepers and re-pouring the concrete platform are used to carry out systematic and comprehensive remediation of the overall ballast 4 settlement in the turnout area, which solves the problems of single remediation technology, lack of specificity, limited installation space or insufficient construction time in traditional remediation methods.

[0143] The present invention organically combines temporary measures and reinforcement measures during the settlement period of the roadbed 4 with a series of remediation measures after the settlement is stabilized, systematically remediates the settlement disease of the entire roadbed 4 in the subway turnout area, and completely solves the disease problem of the entire roadbed 4 in the turnout area at different settlement periods.

[0144] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for regulating the settlement of the integral roadbed in a subway turnout area, characterized in that: The method comprises Step 1: real-time monitoring of the settlement of the roadbed in the settlement area and within a certain length range adjacent thereto; Step 2: Set a settlement threshold. When the roadbed settlement exceeds a certain value, automatic real-time monitoring and early warning are implemented, and temporary adjustment and reinforcement of the roadbed settlement are performed when the roadbed settlement is not yet stable. Step 3: After temporary adjustment and temporary reinforcement, when the roadbed settlement is stable, permanent remediation and repair technology is used to conduct comprehensive remediation of the turnout roadbed after the settlement is stable; Among them, in step 2, the temporary adjustment of the roadbed settlement is specifically as follows: adding a bent and thickened iron plate to the fastener of the subway turnout, the bent and thickened iron plate is installed on the original standard iron pad in the subway turnout fastener of the abnormal settlement section, the fastener height is increased by the bent and thickened iron plate, and the number of fastener anchor bolts is increased, and the bent and thickened iron plate is fixed to the turnout sleeper by multiple fastener anchor bolts to share the additional force caused by the fastener height adjustment; Among them, the bent and thickened iron plate includes a protrusion and side plates located on both sides of the protrusion and integrally formed with the protrusion, the rails of the abnormal settlement section are supported on the protrusion, the original standard iron pad in the fastener is located below the protrusion, a plurality of first screw holes are opened at relative positions on the side plate and the standard iron pad, and are fixed to the switch sleeper by a plurality of first fastener anchor bolts matching the first screw holes, a plurality of second screw holes are opened at relative positions on the protrusion and the standard iron pad, and are fixed to the switch sleeper by a plurality of second fastener anchor bolts matching the second screw holes.

2. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 1 is characterized in that: In step 2, temporary reinforcement of the roadbed settlement is specifically performed by fixing the rails using a gauge tie rod steel frame, wherein the gauge tie rod steel frame is provided with two rail mounting positions, and the two rails of the subway turnout in the abnormal settlement section are respectively installed on the two rail mounting positions of the gauge tie rod steel frame to keep the track gauge unchanged.

3. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 2 is characterized in that: The gauge rod steel frame includes an I-beam and a gauge rod. There are two I-beams, which are respectively arranged on both sides of the rail along the length direction of the rail in the section with abnormal settlement. Both ends of the gauge rod are respectively connected to the two I-beams. There are multiple gauge rods, and the multiple gauge rods are arranged at intervals along the length direction of the rail in the section with abnormal settlement. Two concave grooves are fixedly installed on the gauge rod as rail mounting positions. Two rails are respectively embedded in the two concave grooves of the gauge rod. The two rails are respectively fixed by the two concave grooves, so that the gauges of the two rails remain unchanged.

4. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 3 is characterized in that: In step 2, temporary reinforcement of the roadbed settlement is specifically performed by setting a steel support beam, which is located on the outside of the rails of the abnormal settlement section and is set along the length direction of the rails of the abnormal settlement section, and the steel support beam is fixedly connected to multiple switch sleepers in the abnormal settlement section.

5. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 1 is characterized in that: In step 3, the permanent remediation and repair technology is a grouting repair technology, a repair technology combining mechanical lifting + grouting repair, or a repair technology of chiseling out the switch sleepers and re-pouring the concrete platform.

6. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 1 is characterized in that: Step 3 is as follows: using the water drilling method to take samples to check whether there is any gap between the turnout roadbed and the civil structure. If so, using grouting repair technology to permanently control the roadbed settlement. The repair technology specifically includes the following steps: Step 311, survey the settlement of the track bed on site, install elevation measurement equipment, measure the elevation of the ballastless track structure in the settlement area, formulate a specific lifting plan based on the measurement results and engineering needs, and establish a monitoring network for lifting points; Step 312, performing sealing grouting treatment on the longitudinal and transverse cracks of the ballast bed, the cracks at the junction of the ditch and the ballast bed, the water seepage positions of the ballast bed expansion joints, and the damaged positions in the ditch; Step 313, marking the grouting hole position according to the established lifting plan, and then drilling, cleaning the dust on the site in time during drilling, and using a plugging piece to plug the grouting hole; Step 314, removing the plugging member on the upper part of the grouting hole, injecting the grouting material from the grouting pipe into the lower structure of the ballastless track according to the set grouting lifting process parameters and grouting process, and lifting the track structure. During the lifting process, the elevation of the track structure is monitored in real time through the installed elevation monitoring equipment; Step 315, during the grouting lifting process, the grouting pressure is strictly controlled to avoid the back arch of the roadbed after grouting; the grouting sequence is to first grout the middle lifting hole, and then grout the filling holes on both sides and the middle filling hole in turn; the lifting hole grouting starts from the lowest point of the track structure elevation in turn; when the track structure is lifted to the height set for this grouting lifting, the grouting is stopped immediately; after the lifting hole grouting is completed, the filling holes in the middle and both sides of the line are grouted to ensure that the grouting material is evenly and densely filled in the lower part of the track structure; Step 316: If the single lifting height does not reach the set lifting height, repeat the processes of steps 314 and 315, and finally lift the roadbed to a suitable position through multiple lifting.

7. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 1, characterized in that: The water drilling method is used to take samples to check whether there is any gap between the turnout area ballast and the civil structure. If there is no gap, a repair technology combining mechanical lifting + grouting repair is used to permanently control the ballast settlement. The repair technology specifically includes the following steps: Step 321, investigating the general situation of the area with abnormal roadbed settlement and determining the length of the section with abnormal roadbed settlement; Step 322. Remove the fasteners and rails within the abnormal settlement length range; Step 323, planting reinforcement and installing anchors on the roadbed in the turnout area, continuously installing a certain number of jacks on both sides of the roadbed bottom plate in the abnormal settlement section, and debugging the jacks; Step 324, placing the distribution beam across the track on the debugged jack; Step 325, connect and fix the suspension rod to the distribution beam, and then use a jack to lift the distribution beam to achieve the lifting of the track; Step 326, after the lifting height reaches the required level, grouting material is poured into the gap formed between the raised ballast bed and the structural bottom plate, and the ballast bed settlement is permanently rectified through grouting repair technology.

8. The method for treating the settlement of the integral roadbed in the subway turnout area according to claim 1 is characterized in that: The method includes using a water drill method to take samples to check whether there is a gap between the roadbed and the civil structure in the turnout area. If there is no gap, and the number of on-site jacking equipment and installation space are limited or the construction time is insufficient, the roadbed settlement is permanently rectified by chiseling out the turnout sleepers and re-casting the concrete platform repair technology. The repair technology specifically includes the following steps: Step 331, measuring the elevation of the ballastless track structure in the settlement area, determining the switch sleepers to be removed according to the settlement monitoring results, and marking them on site; Step 332, removing the fasteners above the marked switch sleepers; Step 333, the marked switch sleeper and a certain range of concrete around it are chiseled out, the width and length of the chiseled pit are the same as the bottom of the original switch sleeper, the depth is to the bottom surface of the switch sleeper, and the connecting steel bars of the original switch sleeper extending into the ballast around the pit are retained; Step 334, cleaning the foundation pit and the surface of the track bed after the switch sleepers are removed; Step 335, using square timbers to provide temporary support on the ballast surface on both sides of the removed turnout sleeper; Step 336, the newly laid steel bars in the pit are connected to the connecting steel bars originally extending into the roadbed and located around the pit by welding and anchoring, steel bars are implanted through drilling holes at the bottom of the pit, the steel bars are tied to form a steel cage, and an interface agent is applied around the pit to strengthen the bonding effect between the new and old concrete; Step 337, reinstall the fasteners and plastic sleeves of the original switch sleepers where the switch sleepers are removed, adjust the track joint shape and position, install templates around the fasteners, and pour concrete; Step 338, when the concrete solidifies to a certain strength, the formwork and fasteners are removed to leave the rails suspended in the air to prevent the newly poured concrete platform from being damaged by premature stress; Step 339, pour concrete again. When the newly poured concrete meets the load-bearing requirements, reinstall the fasteners, remove the square timbers, and re-measure the line geometry, and the line resumes normal operation.

Citation Information

Patent Citations

  • System and method for lifting sunken railway ballastless track bed by utilizing injection method

    CN103074828A

  • Grouting lifting rapid renovating technologies for ballastless track sedimentation

    CN103410063A

  • Monolithic roadbed and tunnel bottom disease treatment method based on combined support and grouting templates

    CN105220582A

  • Grouting, rectification and lifting method for transition section between embankment and abutment of rail

    CN107059496A

  • Regulating treatment method of railway tunnel integrated ballast bed subsidence

    CN107858871A