A steel pipe pile construction technology

By adopting steel pipe pile construction technology in subway guide holes, including drilling, infusion and static load testing and testing, the problems of low construction efficiency and difficulty in quality inspection in narrow spaces are solved, and efficient construction progress and quality control are achieved, reducing the number of times. labour risks and costs.

CN115434305BActive Publication Date: 2024-11-22CHINA RAILWAY NO 3 GRP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211112801.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-14
Publication Date
2024-11-22
Estimated Expiration
2042-09-14

AI Technical Summary

Technical Problem

During the construction of subway lines, due to the narrow space of the guide hole, the construction efficiency is low and the quality inspection is difficult, so effective static load tests cannot be carried out, which affects the construction progress and quality.

Method used

A steel pipe pile construction technology is adopted, including ground interview piles, advance drilling grating, drilling, hole cleaning, steel pipe placement, concrete pouring, pile bottom grouting and pile foundation inspection, and the bearing capacity is carried out through lifting devices and hydraulic jacks. Test, use side piles as the restraining end for static load tests to ensure construction quality.

Benefits of technology

Mechanized construction and quality control in narrow spaces have been achieved, labor difficulty and risks have been reduced, construction progress has been accelerated, funds have been saved by 1.1 million yuan, and construction quality has been improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115434305B_ABST
    Figure CN115434305B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of subway engineering technology, and provides a steel pipe pile construction process, including the following steps: S1, ground pile test for verifying stratum parameters; S2, advance drilling of grids; S3, drilling; S4, hole cleaning; S5, placing steel pipes; S6, concrete pouring; S8, pile bottom grouting; S9, pile foundation detection, erecting a crossbeam, connecting the crossbeam with a column pile, and providing a force for the crossbeam away from the pile foundation through a lifting device, and adjusting the force applied by the lifting device to test the pile foundation bearing capacity. By using the side pile as a constraint end, using a back pressure crossbeam and a jack for bearing capacity detection, a method for static load test detection in a narrow space is provided, which solves the problem that static load test cannot be performed in a narrow space, and the quality is more reliable compared with the traditional method of being unable to test; mechanized construction and construction quality control in a narrow space are realized, and the construction progress and construction quality of micro steel pipe piles in a narrow space are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of subway engineering technology, and specifically relates to a steel pipe pile construction process. Background Art

[0002] At present, during the construction of subway lines, due to the narrow space in the guide tunnel, large equipment cannot be used for construction, and the construction efficiency is low.

[0003] Patent CN113481973A discloses a construction method for steel pipe piles in subway stations, which includes the following steps: S1, hardening and leveling the guide hole; S2, determining the pile position and drilling the hole; S3, coring the steel pipe pile; S4, drilling: after coring, a crawler drill is used to drill the hole. During the drilling process, the flatness of the drill rig and the verticality of the active drill rod are checked, and the drill bit and drill rod joints are checked regularly. The drilling should be done at a low speed and low pressure, and the verticality is controlled by setting a hanging hammer on the drill arm; S5, one-time hole cleaning; S6, measuring the hole depth and inspecting the hole; S7, placing the steel pipe; S8, hanging the grouting pipe; S9, checking the sinking thickness; S10, pouring concrete; S11, connecting the piles, pouring the test blocks, and installing the longitudinal reinforcement at the top of the pile; S12, grouting at the bottom of the pile. Although this patent solves the problems of drilling verticality not meeting the design specification requirements, the difficulty in controlling the thickness of the sediment, and the problem of the concrete of the steel pipe piles not being dense enough, the construction efficiency is low and there are still certain difficulties in quality inspection, which can easily lead to extended construction period and slow down the construction progress. Summary of the invention

[0004] The present invention aims to solve the problems of inconvenient construction of steel pipe columns in narrow spaces, difficult quality inspection and low construction efficiency in the prior art, and provides a steel pipe pile construction process. The technical solution adopted by the present invention is as follows:

[0005] A steel pipe pile construction process comprises the following steps:

[0006] S1, ground test pile, used to verify formation parameters;

[0007] S2, advanced grille drilling;

[0008] S3, drilling;

[0009] S4, clear hole;

[0010] S5, placing steel pipes;

[0011] S6, concrete pouring;

[0012] S8, grouting at the pile bottom;

[0013] S9, pile foundation testing, erecting a crossbeam, connecting the crossbeam to the column pile, and using a lifting device to provide the crossbeam with a force away from the pile foundation, and adjusting the force applied by the lifting device to test the bearing capacity of the pile foundation.

[0014] Preferably, in step S8, the lifting device is a hydraulic jack.

[0015] Preferably, in step S6, a grout overflow hole is reserved during pouring, and in step S8, the crossbeam is connected to the pile foundation by passing a steel wire rope through the grout overflow hole and then connecting the crossbeam.

[0016] Preferably, the lifting device is arranged between two adjacent pile foundations, and the two pile foundations on both sides of the lifting device are connected to the cross beam through two steel wire ropes respectively.

[0017] Preferably, the diameter of the grouting hole is 10%-15% of the diameter of the pile foundation.

[0018] Preferably, the diameter of the steel wire rope is 60%-80% of the diameter of the overflow hole.

[0019] Preferably, after the first injection in step S6, the road is cleaned.

[0020] Preferably, step S8 also includes performing low strain testing on the pile foundation.

[0021] Preferably, before step S6, a perfusion test block is prepared in advance.

[0022] Compared with the prior art, the present invention is suitable for the construction of steel pipe columns in narrow spaces such as subway tunnels, realizing mechanized construction and construction quality control in narrow spaces, and ensuring the construction progress and quality of micro steel pipe piles in narrow spaces; by using side piles as constraint ends and adopting back-pressure beams and jacks for bearing capacity detection, a method for static load testing in narrow spaces is provided, which solves the problem that static load testing cannot be performed in narrow spaces. Compared with the traditional method that cannot be tested, the quality is more reliable.

[0023] This application reduced the difficulty and risk of manual labor during the construction of Huajing Road Station on Guangzhou Metro Line 11, ensured the construction quality, accelerated the construction progress, saved 1.1 million yuan, and was friendly to the social environment. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is a simplified schematic diagram of the steel pipe pile construction process for this application.

[0025] Figure 2 Detailed flowchart of the embodiment of the present application. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Specific embodiment:

[0028] like Figure 1-2 As shown, a steel pipe pile construction process specifically includes:

[0029] Preparation process outside the pilot tunnel:

[0030] Ground test piles to verify formation parameters;

[0031] Working steps in the pilot tunnel:

[0032] Step 1: Hardening and leveling the pilot tunnel: After the initial support of the pilot tunnel is completed, 15cm thick C20 concrete is hardened on the bottom of the pilot tunnel to make the ground solid and flat, and drainage ditches are built to facilitate the discharge of drilling slag slurry during the drilling construction process;

[0033] Step 2: Use a benchtop drill to locate the pile and drill holes: According to the construction drawings and the on-site wire control points, use a total station to stake out the position of the steel pipe piles of the side piles, and use the point-changing method to re-measure the pile coordinates and elevations to ensure the accuracy of the pile coordinates and elevations. After the measurement and stakeout is completed, first use a benchtop drill to align the hole position, break the initial support at the bottom of the pilot hole to drill holes, and achieve advanced drilling of the grid to prevent serious wear of the drill bit;

[0034] Step 3: Coring of steel pipe piles: Use XY-1A geological drilling rig to coring and record rock samples at the bottom of the pile to ensure that the stratum at the bottom of the pile meets the design requirements;

[0035] Step 4: Position and calibrate the drilling rig; preferably use a crawler hydraulic anchor drilling rig model KS-800.

[0036] Step 5: Drilling: After coring, use crawler drilling rig to drill holes. The drill bit diameter is 330mm and the drill rod specification is Φ89×1500mm.

[0037] Step 6: One-time hole cleaning: After drilling to the designed hole depth, stop drilling and use high-pressure air circulation to blow out the sediment at the bottom of the hole. At the same time, in order to ensure the maximum hole cleaning, it is necessary to inject clean water into the hole to ensure that the sediment thickness can meet the design and specification requirements; the mud is precipitated and discharged through the preset ditch, thereby reducing the adverse effects of environmental factors.

[0038] Step 7: Measure hole depth and inspect the hole: After the hole is cleaned, check the hole diameter, hole verticality, hole depth and sediment thickness. If the sediment thickness at the bottom of the pile does not meet the requirements after the hole is cleaned, arrange to clean the hole again until the sediment thickness meets the requirements.

[0039] Step 8. Laying down steel pipes: When the drilling depth reaches the design and meets the requirements, use a winch to lower the steel pipe and fix it at the hole with a pipe clamp, leaving 50cm of the pipe exposed. Then, hoist the next section and connect the two sections together with threads. When lowering the pipe, the pipe joints in adjacent holes should be staggered front and back to avoid stress on the joints in the same section. The number of joints in the same section shall not exceed 50% of the total number of steel pipes, and the steel pipe joints in two adjacent holes shall be staggered by at least 1m.

[0040] Step 9. Check the sediment thickness: Check the sediment thickness at the bottom of the hole. When the sediment thickness meets the design and specification requirements, proceed to the next process. When the sediment thickness does not meet the design and specification requirements, perform a second hole cleaning and use high-pressure air circulation to blow out the sediment at the bottom of the hole until the sediment thickness meets the design and specification requirements.

[0041] Step 10. Hanging and placing grouting pipes: To ensure the compactness of the bottom of the steel pipe pile, post-grouting construction of the pile bottom is required. Before pouring concrete, the grouting pipes are hung in the steel pipe pile. The grouting pipes are arranged along the depth of the pile and one pipe is set. The grouting pipe needs to extend 20cm from the top of the pile to facilitate the subsequent grouting connection. Threaded connections are used between pipe sections, and the bottom of the pipe is sealed with tape to prevent blockage of the grouting pipe when pouring test block concrete. The grouting pipe is a φ21.3×2.8mm galvanized steel pipe.

[0042] Step 11: Install the conduit. Conduct trial assembly and preparation of the conduit in advance, and then install the conduit on the steel pipe piles.

[0043] Step 12: Install the funnel. Install the funnel on the conduit to facilitate the concentration of concrete.

[0044] Step 13: The first pouring of concrete: Before pouring concrete, drain the water at the bottom of the hole, use a ground pump to pour a sufficient amount of concrete, and vibrate the concrete when it reaches the hole mouth until fresh concrete returns from the hole mouth; pour the part below the ground during the first pouring.

[0045] Step 14: Welding of steel pipe columns.

[0046] Step 15: Second pouring of concrete: The second pouring is to pour the column base on the ground. Furthermore, before pouring, a pouring test block is made in advance. After the first pouring, the pump pipe is removed and the road is cleared.

[0047] Step 16: Install the reserved steel bars at the top of the column.

[0048] Step 17, post-grouting at the pile bottom: the grouting operation should be carried out 2 days after the pile is formed, and no later than 30 days after the pile is formed; the distance between the grouting operation point and the drilling operation point should be no less than 8-10m; the water-cement ratio of the grouting slurry is 0.5-0.6, and ordinary Portland cement is used for cement. The grouting pressure is not less than 1MPa, ensuring that the pressure breaks the tape and the slurry is forced out of the pipe. The grouting flow rate does not exceed 75L / min; when the grouting pressure reaches or exceeds the design requirements, the grouting is terminated; when the grouting pressure is lower than the normal value for a long time or grouting or grouting in the surrounding pile holes occurs, intermittent grouting should be changed to intermittent grouting with an interval of 30-60min, or the slurry water-cement ratio can be lowered.

[0049] Step 18: Column foundation detection: Set up a crossbeam in the pilot hole, connect the crossbeam to the column pile, and use a lifting device to provide the crossbeam with a force away from the pile foundation. Adjust the force applied by the lifting device to test the bearing capacity of the pile foundation. Furthermore, perform low-strain detection on the pile foundation in the pilot hole.

[0050] Furthermore, the lifting device is a hydraulic jack.

[0051] Furthermore, an overflow hole is reserved during pouring, and a steel wire rope is passed through the overflow hole and then connected to the crossbeam to achieve connection between the crossbeam and the pile foundation.

[0052] Furthermore, the lifting device is arranged between two adjacent pile foundations, and the two pile foundations on both sides of the lifting device are connected to the cross beam through two steel wire ropes respectively.

[0053] Furthermore, the diameter of a single overflow hole is 10%-15% of the diameter of the pile foundation, and each pile foundation is provided with two overflow holes.

[0054] Furthermore, the diameter of the steel wire rope is 60%-80% of the diameter of the overflow hole.

[0055] Furthermore, the diameter of the overflow hole is 5 cm and the diameter of the wire rope is 3 cm.

[0056] By using side piles (columns on the edge) as constraint ends and adopting beams and jacks to test the bearing capacity, a method for static load testing in narrow spaces is provided, which solves the problem that static load testing cannot be performed in narrow spaces. Compared with traditional methods, the quality is more reliable.

[0057] The present invention is suitable for the construction of steel pipe columns in narrow spaces such as subway tunnels, realizing mechanized construction and construction quality control in narrow spaces, ensuring the construction progress and construction quality of micro steel pipe piles in narrow spaces; during the construction of Huajing Road Station of Guangzhou Metro Line 11, it reduced manual difficulty and risk, ensured construction quality, accelerated construction progress, saved 1.1 million yuan, and was friendly to the social environment.

[0058] Finally, it should be noted that the above content is only used to illustrate the technical solution of the present invention, rather than to limit the scope of protection of the present invention. Simple modifications or equivalent substitutions of the technical solution of the present invention by ordinary technicians in this field do not deviate from the essence and scope of the technical solution of the present invention.

Claims

1. A steel pipe pile construction process, characterized in that: The following steps are involved: S1, ground test pile; verify the formation parameters; S2, advanced grille drilling; S3, drilling; S4, clear hole; S5, placing steel pipes; S6, concrete pouring, including: the first pouring of concrete: the first pouring of the part below the ground, the welding of steel pipe columns, the second pouring of concrete: the second pouring of the column base on the ground, and the pre-preparation of pouring test blocks before pouring; S7, post-grouting at the pile bottom; S8, pile foundation testing: erecting a crossbeam, connecting the crossbeam to the pile foundation, and providing a force for the crossbeam to move away from the pile foundation through a lifting device, and adjusting the force applied by the lifting device to test the bearing capacity of the pile foundation; In step S6, a grouting hole is reserved when pouring the test block, and the crossbeam is connected to the pile foundation by passing a steel wire rope through the grouting hole and then connecting the crossbeam; The lifting device is arranged between two adjacent pile foundations, and the two pile foundations on both sides of the lifting device are connected to the crossbeam through two steel wire ropes respectively; The diameter of the overflow hole is 10%-15% of the pile foundation diameter; The diameter of the wire rope is 60%-80% of the diameter of the overflow hole.

2. A steel pipe pile construction process according to claim 1, characterized in that: In step S8, the lifting device is a hydraulic jack.

3. A steel pipe pile construction process according to claim 1, characterized in that: The diameter of the overflow hole is 5cm and the diameter of the wire rope is 3cm.

4. A steel pipe pile construction process according to claim 1, characterized in that: After the first pouring is completed in step S6, the road is cleaned.

5. A steel pipe pile construction process according to claim 1, characterized in that: Step S8 also includes performing low strain testing on the pile foundation.

6. A steel pipe pile construction process according to claim 1, characterized in that: Before step S6, a perfusion test block is prepared in advance.