Negative pressure drainage film bag grouting anchor rod and negative pressure drainage anchoring construction method
By designing negative pressure drainage membrane bag grouting anchors, combined with negative pressure suction and grouting expansion deformation, the drainage and reinforcement problems in water-rich and low-permeability areas are solved, achieving efficient stability and safety assurance for underground engineering.
Patent Information
- Application Number
- CN202410922611.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-11-15
AI Technical Summary
In existing underground emergency rescue and risk prevention projects, conventional drainage holes cannot effectively drain groundwater in water-rich and low-permeability areas, leading to frequent engineering accidents. Furthermore, conventional grouting reinforcement methods are difficult to apply effectively to water-rich loose strata, affecting the stability of the surrounding rock and the reinforcement effect.
The negative pressure drainage membrane bag grouting anchor bolt is adopted, which includes a middle negative pressure suction section, a front end drainage sealing section and a rear end drainage reinforcement section. Through negative pressure suction and grouting expansion deformation, groundwater is directionally driven away, forming a sealed state at both ends, thereby improving drainage efficiency and reinforcement effect.
It effectively reduces the water content of the surrounding rock, improves the strength and integrity of the surrounding rock, ensures the stability of tunnel excavation, achieves efficient drainage and reinforcement, reduces the risk of water and mud inrush, and shortens the construction period.
Smart Images

Figure CN118959057A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of deep water-rich loose stratum engineering, and in particular to a negative pressure drainage membrane bag grouting anchor rod and a negative pressure anchoring construction method. Background Art
[0002] In the management of engineering problems in deep water-rich loose strata, drainage and reinforcement are two key issues that need to be solved urgently.
[0003] First of all, drainage can effectively reduce the moisture content of surrounding rock, improve the strength of surrounding rock, and ensure the stability of tunnel excavation. The specific functions of drainage are:
[0004] (1) Drainage can effectively reduce the hydrostatic pressure behind the support and increase the safety reserve of the existing support;
[0005] (2) Drainage can effectively improve the strength and self-bearing capacity of the surrounding rock, and further reduce the surrounding rock pressure behind the support;
[0006] (3) Drainage can improve the treatment effect of subsequent grouting reinforcement and ensure the slurry concentration and slurry diffusion effect.
[0007] It can be seen that drainage is an important content and core point of underground engineering rescue, which greatly affects the treatment effect of underground rescue projects and risk prevention and control projects.
[0008] However, in existing underground rescue and risk prevention projects, drainage is usually carried out by drilling drainage holes. Although drainage holes can be effectively used in medium and high seepage areas connected by seepage channels, low permeability and void blocking make it difficult for water to penetrate into drainage holes under the action of self-weight and be discharged in water-rich and low-permeability areas. On the one hand, it is difficult for water to be discharged by itself in low-permeability areas; on the other hand, water is enriched in high-water-rich and low-permeability areas, which increases the difficulty of risk management; more importantly, it is difficult for water to flow out of high-water-rich and low-permeability areas, and there is usually no water on the surface; even if there is a small amount of water, the water out of the drainage hole is clear. This will not only mislead experts' judgment, but also rashly open the tunnel face for observation, which may bring serious risks of water and mud inrush; further, due to the water-rich and low-permeability characteristics of the area, it is difficult to effectively grout and reinforce. For high-water-rich and low-permeability areas, comprehensive judgment should be made in combination with engineering geophysical exploration to determine the lithology and water content behind the tunnel face. At the same time, try to avoid drilling observation windows to disturb the surrounding rock and cause water and mud inrush accidents.
[0009] In summary, the commonly used method of arranging drainage holes for free drainage cannot effectively drain groundwater from water-rich low-permeability areas, resulting in frequent risks of engineering accidents.
[0010] Secondly, timely and effective reinforcement measures are necessary to maintain the stability of the surrounding rock and ensure the safety of the tunnel project. However, for low-permeability and water-rich strata, conventional advance drainage is slow to take effect and has a long construction period. The surrounding rock around the drainage hole may further reduce its strength during the drainage process, which is prone to frequent uncertain engineering problems. Conventional grouting reinforcement solutions require a long curing time and a low water content, making it difficult for conventional grouting reinforcement methods to be effectively applied to water-rich loose strata. Summary of the invention
[0011] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is to provide a negative pressure drainage membrane bag grouting anchor rod and a negative pressure drainage anchor construction method, which can improve the drainage efficiency of deep water-rich loose strata, and at the same time can timely and effectively reinforce the surrounding rock, maintain the strength of the surrounding rock, and ensure the stability of tunnel excavation.
[0012] In order to achieve the above object, the present invention is implemented through the following technical scheme: a negative pressure drainage membrane bag grouting anchor rod, comprising:
[0013] A middle negative pressure suction part, the middle negative pressure suction part comprises a middle negative pressure suction rod and a negative pressure suction drainage pipe, the middle negative pressure suction rod is a hollow rod, a plurality of water-permeable through holes are opened on the middle negative pressure suction rod, groundwater can enter the negative pressure suction drainage pipe through the water-permeable through holes, and the negative pressure suction drainage pipe is connected with the inner cavity of the middle negative pressure suction rod;
[0014] The head end drainage plugging part includes a head end sealing connector and a head end drainage body, wherein the head end sealing connector plugs and is connected to the head end of the middle negative pressure suction rod, and the head end drainage body is connected to the head end sealing connector and can directionally drive away groundwater through grouting expansion and deformation; and
[0015] The tail end drainage reinforcement part includes a tail end connection component and a tail end drainage body. The tail end connection component blocks and is connected to the tail end of the middle negative pressure suction rod. The tail end drainage body is connected to the tail end connection component and can directionally drive away groundwater through grouting expansion deformation.
[0016] Furthermore, the head-end drainage body includes a head-end membrane bag and a head-end feed pipe, the head-end drainage body is a bag body, the head-end membrane bag can be elastically deformed, the bag mouth of the head-end membrane bag is sealed and fixedly connected to the head-end sealing connector, and the head-end feed pipe is connected to the head-end membrane bag.
[0017] Furthermore, the head-end drainage body also includes a head-end hollow tube and a head-end mounting piece; the head-end hollow tube is sealed and connected to the middle negative pressure suction rod through the head-end sealing connector, the head-end mounting piece is sealed and fixedly connected to the other end of the head-end hollow tube, and a plurality of first through holes are provided on the side wall of the head-end hollow tube; the head-end membrane bag is sleeved on the outside of the head-end hollow tube, the bottom of the head-end membrane bag is fixed on the head-end mounting piece, and the head-end feed pipe is fixed on the head-end mounting piece and extends into the interior of the head-end hollow tube.
[0018] Furthermore, the negative pressure suction drainage pipe is fixed on the head end mounting piece, and sequentially passes through the head end mounting piece, the head end hollow tube, and the head end sealing head to enter the middle negative pressure suction rod.
[0019] Furthermore, the middle negative pressure suction part also includes a filter layer, which is wrapped around the middle negative pressure suction rod and is used to filter the groundwater entering the middle negative pressure suction rod.
[0020] Furthermore, the middle negative pressure suction part also includes a rolling belt, which is sleeved outside the reverse filter layer and is used to sleeve and fix the reverse filter layer on the middle negative pressure suction rod.
[0021] Furthermore, the tail end drainage body includes a tail end membrane bag and a tail end feed pipe, the tail end drainage body is a bag body, the tail end membrane bag can be elastically deformed, the bag mouth of the tail end membrane bag is sealed and fixedly connected to the tail end connecting assembly, and the tail end feed pipe sequentially passes through the head end drainage sealing part, the middle negative pressure suction part and the tail end connecting assembly to be connected with the head end membrane bag.
[0022] Furthermore, it also includes a drill bit, and the drill bit is detachably connected to the tail end connecting assembly.
[0023] Furthermore, the plug-in tube is plug-fitted with the drill bit.
[0024] A negative pressure drainage anchor construction method, using any one of the negative pressure drainage membrane bag grouting anchor rods described above, comprises the following steps:
[0025] Investigate the geological conditions at the construction site and design and manufacture the specific dimensions of the negative pressure drainage membrane bag grouting anchor rods;
[0026] Pre-drilled holes;
[0027] Drive the negative pressure drainage membrane bag grouting anchor rod into the drilled hole;
[0028] Inject grout into the tail end drainage body to drain and reinforce it;
[0029] Grouting is performed into the drainage body at the head end to drain and seal the water;
[0030] The negative pressure suction part in the middle is connected with the negative pressure device to carry out negative pressure pumping and drainage;
[0031] After negative pressure pumping and drainage, reverse grouting reinforcement is carried out in the middle negative pressure suction part.
[0032] Beneficial effects of the present invention:
[0033] The above-mentioned negative pressure drainage membrane bag grouting anchor rod and negative pressure drainage anchoring construction method:
[0034] During the expansion and deformation process of the tail end drainage reinforcement part, the groundwater can be effectively driven away in a directional manner, the water-cement ratio of the slurry under water-rich conditions can be maintained and improved, and the grouting reinforcement effect under water-rich conditions can be ensured. At the same time, since the volume of the tail end drainage reinforcement part increases after solidification after grouting, the strength of the entire anchor end at the bottom of the anchor bolt can be ensured;
[0035] During the expansion and deformation of the head-end drainage plugging part, the groundwater can be effectively driven away in a directional manner, the water-cement ratio of the slurry under water-rich conditions can be maintained and improved, and the grouting reinforcement effect under water-rich conditions can be ensured; at the same time, the head-end drainage plugging part, which solidifies and expands after grouting, squeezes the surrounding rock, which can effectively block the drainage holes on the surrounding rock and achieve the airtightness of the drainage holes. In addition, the head-end drainage plugging part and the tail-end drainage reinforcement part form a sealed state at both ends of the borehole, thereby effectively improving the negative pressure drainage suction effect of the middle negative pressure suction part.
[0036] The negative pressure suction part in the middle adopts the negative pressure drainage method, which can efficiently and continuously advance the drainage, effectively reduce the water content of the surrounding rock, and continuously improve the strength and integrity of the tunnel surrounding rock; in addition, it can further improve the strength of the surrounding rock, and can also effectively strengthen the slurry reinforcement strength of the head end drainage plugging part and the tail end drainage reinforcement part. It can be seen that since negative pressure drainage can enhance the reinforcement effect of the head end drainage plugging part and the tail end drainage reinforcement part, and the head end drainage plugging part and the tail end drainage reinforcement part can improve the efficiency of negative pressure drainage, the two complement each other and work together to achieve the effect of 1+1 greater than 2. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the specific implementation of the present invention, the following will briefly introduce the drawings required for use in the specific implementation. In all the drawings, each element or part is not necessarily drawn according to the actual scale.
[0038] Figure 1 A schematic diagram of a negative pressure drainage membrane bag grouting anchor rod provided by one embodiment of the present invention;
[0039] Figure 2 for Figure 1 A schematic diagram of the middle negative pressure suction portion of the negative pressure drainage membrane bag grouting anchor shown;
[0040] Figure 3 for Figure 1A schematic cross-sectional view of the middle negative pressure suction portion of the negative pressure drainage membrane bag grouting anchor shown;
[0041] Figure 4 for Figure 1 A schematic diagram of the drainage plugging portion at the head end of the negative pressure drainage membrane bag grouting anchor shown;
[0042] Figure 5 for Figure 1 A schematic diagram of the tail end drainage reinforcement portion of the negative pressure drainage membrane bag grouting anchor shown;
[0043] Figure 6 for Figure 1 The schematic diagram of anchoring the negative pressure drainage membrane bag grouting anchor rod into the water-rich loose stratum shown;
[0044] Figure 7 for Figure 1 Schematic diagram of multiple negative pressure drainage membrane bag grouting anchor rods anchored into a loose water-rich stratum;
[0045] Figure 8 A schematic diagram of a negative pressure anchoring construction method provided by an embodiment of the present invention;
[0046] Reference numerals:
[0047] 1. Sump; 2. Negative pressure device; 3. Drainage pump; 4. Carrying rechargeable lithium battery; 5. First drainage pipe;
[0048] 100, middle negative pressure suction part; 110, middle negative pressure suction rod; 120, negative pressure suction drainage pipe; 130, reverse filter layer; 140, rolling belt;
[0049] 200, head end drainage plugging part; 210, head end sealing connector; 220, head end drainage body; 221, head end membrane bag; 222, head end feed pipe; 223, head end hollow tube; 224, head end mounting piece;
[0050] 300, tail end drainage reinforcement part; 310, tail end connection assembly; 311, first accommodating chamber; 320, tail end drainage body; 321, tail end membrane bag; 322, tail end feed pipe;
[0051] 400. Drill bit. DETAILED DESCRIPTION
[0052] The following embodiments of the technical solution of the present invention are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and are therefore only used as examples, and cannot be used to limit the protection scope of the present invention.
[0053] See also Figures 1 to 4The present invention provides a negative pressure drainage membrane bag grouting anchor rod, including a middle negative pressure suction part 100, a head end drainage sealing part 200 and a tail end drainage reinforcement part 300.
[0054] Specifically, the middle negative pressure suction part 100 includes a middle negative pressure suction rod 110 and a negative pressure suction drainage pipe 120. The middle negative pressure suction rod 110 is a hollow rod, and a plurality of water-permeable through holes are opened on the middle negative pressure suction rod 110, through which groundwater can enter the negative pressure suction drainage pipe 120. The negative pressure suction drainage pipe 120 is connected to the inner cavity of the middle negative pressure suction rod 110.
[0055] The head end drainage plugging part 200 includes a head end sealing connector 210 and a head end drainage body 220. The head end sealing connector 210 plugs and is connected to the head end of the middle negative pressure suction rod 110. The head end drainage body 220 is connected to the head end sealing connector 210, and can expel groundwater in a direction through grouting expansion and deformation. The tail end drainage reinforcement part 300 includes a tail end connection assembly 310 and a tail end drainage body 320. The tail end connection assembly 310 plugs and is connected to the tail end of the middle negative pressure suction rod 110, and the tail end drainage body 320 is connected to the tail end connection assembly 310, and can expel groundwater in a direction through grouting expansion and deformation.
[0056] In the specific implementation, the head end sealing connector 210, the head end mounting part 224, and the tail end connecting component 310 can all use the sealing bolt sealing joints commonly used in the prior art. The use of sealing bolt sealing joints can save processing costs. At the same time, the parts can be quickly installed through threads, which is convenient for installation and saves time.
[0057] When in use, first select a location according to the soil quality and design conditions, and then pre-drill a hole. Then, place the tail end drainage reinforcement part 300 of the negative pressure drainage membrane bag grouting anchor rod downward, and place the negative pressure drainage membrane bag grouting anchor rod in the predetermined position in the borehole; then, drive the tail end drainage reinforcement part 300 to expand and deform outward through grouting; then drive the head end drainage plugging part 200 to expand and deform outward through grouting, and finally connect the negative pressure suction drainage pipe 120 of the middle negative pressure suction part 100 with the external negative pressure device 2 for negative pressure suction, and the groundwater enters the middle negative pressure suction rod 110 through the water-permeable through hole on the middle negative pressure suction rod 110, and is discharged through the negative pressure suction drainage pipe 120. After the drainage is completed, the negative pressure suction drainage pipe 120 can be connected to the external grouting device, and grouting is injected into the middle negative pressure suction rod 110 through the negative pressure suction drainage pipe 120.
[0058] By using the above-mentioned negative pressure drainage membrane bag grouting anchor rod, the tail end drainage reinforcement part 300 can effectively and directionally drive away groundwater during the expansion and deformation process, maintain and improve the water-cement ratio of the slurry under water-rich conditions, and ensure the grouting reinforcement effect under water-rich conditions. At the same time, since the volume of the tail end drainage reinforcement part 300 increases after solidification after grouting, the strength of the anchoring end at the bottom of the entire anchor rod can be ensured.
[0059] During the expansion and deformation of the head end drainage plugging part 200, the groundwater can also be effectively driven away in a directional manner, the water-cement ratio of the slurry under water-rich conditions can be maintained and improved, and the grouting reinforcement effect under water-rich conditions can be ensured; at the same time, the head end drainage plugging part 200, which solidifies and expands after grouting, squeezes the surrounding rock, which can effectively block the drainage holes on the surrounding rock and achieve the airtightness of the drainage holes. In addition, the head end drainage plugging part 200 and the tail end drainage reinforcement part 300 form a sealed state at both ends of the drill hole, thereby effectively improving the negative pressure drainage suction effect of the middle negative pressure suction part 100.
[0060] The middle negative pressure suction part 100 adopts a negative pressure drainage method, which can efficiently and continuously advance the drainage, effectively reduce the water content of the surrounding rock, and continuously improve the strength and integrity of the tunnel surrounding rock; in addition, it can further improve the strength of the surrounding rock, and can also effectively strengthen the slurry reinforcement strength of the head end drainage plugging part 200 and the tail end drainage reinforcement part 300. It can be seen that since negative pressure drainage can enhance the reinforcement effect of the head end drainage plugging part 200 and the tail end drainage reinforcement part 300, and the head end drainage plugging part 200 and the tail end drainage reinforcement part 300 can improve the negative pressure drainage efficiency, the two complement each other and work together to achieve the effect of 1+1 greater than 2.
[0061] Specifically in the present embodiment, the head-end drainage body 220 includes a head-end membrane bag 221 and a head-end feed pipe 222. The head-end drainage body 220 is a bag body. The head-end membrane bag 221 can be elastically deformed. The bag mouth of the head-end membrane bag 221 is sealed and fixedly connected to the head-end sealing connector 210. The head-end feed pipe 222 is connected to the head-end membrane bag 221.
[0062] When in use, slurry can be injected into the head end membrane bag 221 through the head end feed pipe 222. The head end membrane bag 221 is a bag body. Since the head end membrane bag 221 can be folded and deformed, it is convenient to place the head end drainage body 220 into the drill hole. At the same time, since the head end membrane bag 221 is a flexible body, it can improve the fit with the inner wall of the surrounding rock, thereby improving the sealing of the drainage hole on the surrounding rock. Of course, in other embodiments, the head end drainage body 220 can also adopt other expansion bodies, such as using multiple movable plates to splice the head end drainage body 220 circumferentially to form a sphere, and connecting the plates through elastic bodies, which can also achieve expansion grouting.
[0063] As a preferred embodiment, the head end drainage body 220 also includes a head end hollow tube 223 and a head end mounting piece 224. The head end hollow tube 223 is sealed and connected to the middle negative pressure suction rod 110 through the head end sealing connector 210. The head end mounting piece 224 is sealed and fixedly connected to the other end of the head end hollow tube 223. A plurality of first through holes are provided on the side wall of the head end hollow tube 223; the head end membrane bag 221 is sleeved outside the head end hollow tube 223, the bottom of the head end membrane bag 221 is fixed on the head end mounting piece 224, and the head end feed pipe 222 is fixed on the head end mounting piece 224 and extends into the head end hollow tube 223.
[0064] The first end hollow tube 223 and the first end mounting piece 224 can effectively support and regulate the position of the first end membrane bag 221 to prevent the first end membrane bag 221 from moving around in the drill bit 400. After grouting in the first end membrane bag 221, the anchoring effect can be further improved.
[0065] In this embodiment, the tail end drainage body 320 includes a tail end membrane bag 321 and a tail end feed pipe 322. The tail end drainage body 320 is a bag body, and the tail end membrane bag 321 can be elastically deformed. The bag mouth of the tail end membrane bag 321 is sealed and fixedly connected to the tail end connection component 310. The tail end feed pipe 322 passes through the head end drainage blocking part 200, the middle negative pressure suction part 100 and the tail end connection component 310 in sequence and communicates with the head end membrane bag 221.
[0066] In a specific implementation, a first accommodating cavity can be opened on the end surface of the tail end connection component 310 of the tail end membrane bag 321, and the tail end membrane bag 321 can be folded inside to facilitate the storage of the tail end membrane bag 321 and prevent the tail end membrane bag 321 from being broken during the process of inserting into the drilling hole.
[0067] Similarly, when in use, slurry can be injected into the tail end membrane bag 321 through the tail end feeding pipe 322. The tail end membrane bag 321 is a bag body. Since the head end membrane bag 221 can be folded and deformed, it is convenient to place the head end drainage body 220 into the drill hole. At the same time, since the head end membrane bag 221 is a flexible body, it can improve the fit with the inner wall of the surrounding rock and improve the sealing of the drainage hole on the surrounding rock. Of course, in other embodiments, the tail end drainage body 320 can also be in the form of other expansion bodies.
[0068] As a preferred embodiment, the middle negative pressure suction rod 110 further includes a filter layer 130 , which is wrapped around the outside of the middle negative pressure suction rod 110 and is used to filter the groundwater entering the middle negative pressure suction rod 120 .
[0069] In specific implementation, the filter layer 130 can be fine sand or filter cloth. If filter cloth is used, the filter cloth can be wrapped around the outer wall of the middle negative pressure suction rod 110. If fine sand is used, the fine sand needs to be fixed in a water-permeable bag, and then the bag is wrapped around the outer wall of the middle negative pressure suction rod 110. The filter layer 130 can prevent the loss of fine particles and achieve continuous drainage.
[0070] As a more preferred embodiment, the middle negative pressure suction rod 110 further includes a rolling belt 140. The rolling belt 140 is sleeved outside the filter layer 130, and is used to sleeve and fix the filter layer 130 on the middle negative pressure suction rod 110, so as to improve the stability of the filter layer 130.
[0071] It should be noted that, in a specific implementation, the negative pressure suction drainage pipe 120 is fixed on the head end mounting member 224, and sequentially passes through the head end mounting member 224, the head end hollow tube 223, and the head end sealing head to enter the middle negative pressure suction rod 110. The negative pressure suction drainage pipe 120 can be placed in a standardized manner.
[0072] The negative pressure device 2 can use a portable lithium battery vacuum pump, and the vacuum pump uses a portable rechargeable lithium battery 4 as energy. By replacing a large-capacity lithium battery, the long-term negative pressure demand can be met, solving the problem of poor construction environment and unstable energy in underground engineering.
[0073] In the specific implementation, the water sucked out by the negative pressure can be collected into the sump 1 at the lower position by gravity through the first drainage pipe 5, and the water can be centrally drained on time through the drainage pump 3. The drainage efficiency can be effectively improved, and the whole process is smoother.
[0074] As another preferred embodiment, the negative pressure drainage membrane bag grouting anchor rod further includes a drill bit 400. The drill bit 400 is detachably connected to the tail end connection assembly 310. In this embodiment, the plug-in tube and the drill bit 400 can be plugged in and matched. Of course, magnetic connection or other methods can also be used, as long as the drill bit 400 can be easily separated after the tail end membrane bag 321 is expanded.
[0075] When placing the anchor rod in the drill hole, one end of the drill bit 400 is inserted first. The drill bit 400 can play a guiding role. When it reaches the required position, grouting is injected into the tail end membrane bag 321. After the tail end membrane bag 321 expands, the drill bit 400 can be pushed forward until the drill bit 400 is detached.
[0076] It should be noted that, in the specific implementation, the head end sealing connector, the head end mounting piece, and the tail end connection assembly can all use the bolt sealing head connection method commonly used in the prior art, and the head end drainage plugging part, the middle negative pressure suction part, and the tail end drainage reinforcement part can be spliced together in sequence. Of course, they can also be connected together by welding or clamping.
[0077] See also Figure 5 The present invention also provides a negative pressure drainage anchor construction method, the specific steps are:
[0078] S110. Investigate the geological conditions at the construction site and design and manufacture the specific dimensions of the negative pressure drainage membrane bag grouting anchor rods;
[0079] Specifically, the diameter and height of the middle negative pressure suction rod need to be designed according to the geological conditions, and the required sizes of the head end drainage sealing part and the tail end drainage reinforcement part are calculated; during production, the head end drainage sealing part, the middle negative pressure suction part and the tail end drainage reinforcement part can be spliced with bolt sealing heads.
[0080] S120, pre-drilling; specifically, drilling is performed until a preset time, and the number of holes drilled is determined according to the geological conditions on site;
[0081] S130, driving the negative pressure drainage membrane bag grouting anchor rod into the drilled hole;
[0082] S140, injecting grout into the tail end drainage body 320 to drain and reinforce it;
[0083] S150, injecting grout into the head end drainage body 220 to drain and seal;
[0084] S160, connecting the middle negative pressure suction part 100 with the negative pressure device 2 to perform negative pressure pumping and drainage;
[0085] S170, after negative pressure pumping and drainage, reverse grouting reinforcement is performed into the middle negative pressure suction part 100.
[0086] Adopt the above-mentioned negative pressure drainage membrane bag grouting anchor rod and negative pressure drainage anchor construction method:
[0087] During the expansion and deformation process of the tail end drainage reinforcement part 300, the groundwater can be effectively driven away in a directional manner, the water-cement ratio of the slurry under water-rich conditions can be maintained and improved, and the grouting reinforcement effect under water-rich conditions can be ensured. At the same time, since the volume of the tail end drainage reinforcement part 300 increases after solidification after grouting, the strength of the anchoring end at the bottom of the entire anchor bolt can be ensured;
[0088] During the expansion and deformation of the head end drainage plugging part 200, the groundwater can also be effectively driven away in a directional manner, the water-cement ratio of the slurry under water-rich conditions can be maintained and improved, and the grouting reinforcement effect under water-rich conditions can be ensured; at the same time, the head end drainage plugging part 200, which solidifies and expands after grouting, squeezes the surrounding rock, which can effectively block the drainage holes on the surrounding rock and achieve the airtightness of the drainage holes. In addition, the head end drainage plugging part 200 and the tail end drainage reinforcement part 300 form a sealed state at both ends of the drill hole, thereby effectively improving the negative pressure drainage suction effect of the middle negative pressure suction part 100.
[0089] The middle negative pressure suction part 100 adopts a negative pressure drainage method, which can efficiently and continuously advance the drainage, effectively reduce the water content of the surrounding rock, and continuously improve the strength and integrity of the tunnel surrounding rock; in addition, it can further improve the strength of the surrounding rock, and can also effectively strengthen the slurry reinforcement strength of the head end drainage plugging part 200 and the tail end drainage reinforcement part 300. It can be seen that since negative pressure drainage can enhance the reinforcement effect of the head end drainage plugging part 200 and the tail end drainage reinforcement part 300, and the head end drainage plugging part 200 and the tail end drainage reinforcement part 300 can improve the negative pressure drainage efficiency, the two complement each other and work together to achieve the effect of 1+1 greater than 2.
[0090] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention.
Claims
1. A negative pressure drainage membrane bag grouting anchor, characterized in that: include: A middle negative pressure suction part, the middle negative pressure suction part comprises a middle negative pressure suction rod and a negative pressure suction drainage pipe, the middle negative pressure suction rod is a hollow rod, a plurality of water-permeable through holes are opened on the middle negative pressure suction rod, groundwater can enter the negative pressure suction drainage pipe through the water-permeable through holes, and the negative pressure suction drainage pipe is connected with the inner cavity of the middle negative pressure suction rod; The head end drainage plugging part includes a head end sealing connector and a head end drainage body, wherein the head end sealing connector plugs and is connected to the head end of the middle negative pressure suction rod, and the head end drainage body is connected to the head end sealing connector and can directionally drive away groundwater through grouting expansion and deformation; and The tail end drainage reinforcement part includes a tail end connection component and a tail end drainage body. The tail end connection component blocks and is connected to the tail end of the middle negative pressure suction rod. The tail end drainage body is connected to the tail end connection component and can directionally drive away groundwater through grouting expansion deformation.
2. The negative pressure drainage membrane bag grouting anchor rod according to claim 1 is characterized in that: The first end drainage body includes a first end membrane bag and a first end feed pipe. The first end drainage body is a bag body. The first end membrane bag can be elastically deformed. The bag mouth of the first end membrane bag is sealed and fixedly connected to the first end sealing connector. The first end feed pipe is connected to the first end membrane bag.
3. The negative pressure drainage membrane bag grouting anchor rod according to claim 2 is characterized in that: The head-end drainage body also includes a head-end hollow tube and a head-end mounting piece; the head-end hollow tube is sealed and connected to the middle negative pressure suction rod through the head-end sealing connector, the head-end mounting piece is sealed and fixedly connected to the other end of the head-end hollow tube, and a plurality of first through holes are provided on the side wall of the head-end hollow tube; the head-end membrane bag is sleeved on the outside of the head-end hollow tube, the bottom of the head-end membrane bag is fixed on the head-end mounting piece, and the head-end feed pipe is fixed on the head-end mounting piece and extends into the interior of the head-end hollow tube.
4. The negative pressure drainage membrane bag grouting anchor rod according to claim 3 is characterized in that: The negative pressure suction drainage pipe is fixed on the head end mounting piece, and passes through the head end mounting piece, the head end hollow pipe, and the head end sealing head in sequence to enter the middle negative pressure suction rod.
5. The negative pressure drainage membrane bag grouting anchor rod according to claim 1 is characterized in that: The middle negative pressure suction part also includes a filter layer, which is wrapped around the middle negative pressure suction rod and is used to filter the groundwater entering the middle negative pressure suction rod.
6. The negative pressure drainage membrane bag grouting anchor rod according to claim 5 is characterized in that: The middle negative pressure suction part also includes a rolling belt, which is sleeved outside the reverse filter layer and is used to sleeve and fix the reverse filter layer on the middle negative pressure suction rod.
7. The negative pressure drainage membrane bag grouting anchor rod according to claim 1 is characterized in that: The tail end drainage body includes a tail end membrane bag and a tail end feed pipe. The tail end drainage body is a bag body. The tail end membrane bag can be elastically deformed. The bag mouth of the tail end membrane bag is sealed and fixedly connected to the tail end connecting assembly. The tail end feed pipe sequentially passes through the head end drainage sealing part, the middle negative pressure suction part and the tail end connecting assembly to be connected with the head end membrane bag.
8. The negative pressure drainage membrane bag grouting anchor rod according to claim 1 is characterized in that: It also includes a drill bit, and the drill bit is detachably connected to the tail end connecting assembly.
9. The negative pressure drainage membrane bag grouting anchor rod according to claim 8, characterized in that: The plug-in tube is plug-fitted with the drill bit.
10. A negative pressure drainage anchor construction method, using the negative pressure drainage membrane bag grouting anchor rod according to any one of claims 1 to 9, characterized in that: include: Investigate the geological conditions at the construction site and design and manufacture the specific dimensions of the negative pressure drainage membrane bag grouting anchor rods; Pre-drilled holes; Drive the negative pressure drainage membrane bag grouting anchor rod into the drilled hole; Inject grout into the tail end drainage body to drain and reinforce it; Grouting is performed into the drainage body at the head end to drain and seal the water; The negative pressure suction part in the middle is connected with the negative pressure device to carry out negative pressure pumping and drainage; After negative pressure pumping and drainage, reverse grouting reinforcement is carried out in the middle negative pressure suction part.