Construction method for dismantling hollow slab girder of approach bridge superstructure
Through the combination of core drilling machine, disc saw and bridge tray machine, the hollow plate beams of the upper structure of the guide bridge are cut and removed span by span, which solves the problem of large floating boats being unable to be used in small waters, and achieves a fast and safe dismantling process to avoid Ruins pollution and safety risks.
Patent Information
- Application Number
- CN202411185693.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-11-22
AI Technical Summary
In some cases where there are dams or bridges with small water areas upstream and downstream, large floating boats or floating cranes cannot be used to remove hollow plate beams of the upper structure of the guide bridge, resulting in difficulty in demolition.
The core drilling machine and disk saw combined with rope saw were used to cut the hinge joints of hollow plate beams, and the bridge frame was used to remove them span by span to ensure that the removal sequence was the middle beam, the secondary edge beam, and the edge beam, which was achieved through wire rope suspenders and hydraulic systems. Safe and fast removal and lifting.
Fast and safe removal of hollow plate beams has been achieved, avoiding the ruin pollution caused by blasting and the safety risks of large tonnage cranes, and improving the removal efficiency and safety.
Smart Images

Figure CN118997030A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, in particular to a method for dismantling a hollow slab beam of an approach bridge superstructure. Background Art
[0002] The approach bridge refers to the bridge span located at both ends of the main bridge, which replaces the high embankment. It is the part that connects the approach bridge abutment to the bridge span of the main bridge. For example, the land bridges on both sides of the river are called approach bridges. The purpose of making the approach bridge long is to reduce the downward component of the gravity of the car parallel to the bridge deck of the approach bridge.
[0003] The hollow slab of a bridge is one of the bridge span structures and is a concrete component. There are two traditional methods for dismantling the hollow slab of a bridge: on-site blasting or using a crane for dismantling. The blasting method is troublesome to clean up the rubble, and the use of a large-tonnage crane is not possible due to the load capacity limitation of the old approach bridge surface layer, and the safety is relatively general. Therefore, a construction method for dismantling the hollow slab beam of the approach bridge superstructure is proposed. Summary of the invention
[0004] In view of the deficiencies in the prior art, the present invention provides a method for dismantling the hollow slab beam of the upper structure of an approach bridge, which solves the problem that some bridges with dams upstream and downstream or smaller waters cannot be dismantled because large floating vessels and floating cranes cannot enter the construction area.
[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: 1. A construction method for dismantling hollow slab beams of a bridge approach superstructure, characterized in that it includes the following operating steps:
[0006] Step 1. Determine the demolition order: number each span of hollow slab beams and determine the demolition order as middle beam first, then side beam, and finally side beam;
[0007] Step 2. Preparation before demolition: Use a core drill with a disk saw or a rope saw to cut the hinge joints between the hollow slab beams;
[0008] Step 3, the process of demolition: the hollow slab beam is demolished span by span using a bridge erection machine, and after demolition, it is directly hoisted to the beam transport vehicle and transported to the demolition site for demolition;
[0009] a. Binding beam: Install wire rope slings at 1 / 3 of both ends of the hollow slab beam. Lift slowly at first. When the hollow slab beam is separated from the support, both sides of the bridge erection machine should be raised and lowered synchronously to keep the hollow slab beam horizontal during the lifting process;
[0010] b. After the hollow slab beam of the previous span is dismantled, the bridge-erecting machine will retreat one span to dismantle the next span.
[0011] Preferably, in Step 2, the surveyor lays out the center line of the hinge joint before cutting, and the two longitudinal hinge joints of the hollow slab beams to be removed first in each span are cut by a rope saw with a cutting depth of 90 cm, and the hinge joints of the remaining hollow slab beams in each span and the continuous transverse hinge joints of the bridge deck are cut by a disk saw with a cutting depth of 10 cm.
[0012] Preferably, the hinged joints between beams at the cap beam cannot be cut with a rope saw due to space constraints, so a core drill is used to drill holes, and the holes are drilled in rows, with a total of 5 rows of holes, and the diameter of each hole is 10 cm.
[0013] Preferably, before cutting with a rope saw, a rope saw hole is cut first, the hole diameter is 10 cm, the number is 1, and the hoisting hole is drilled using a core drill, the drilled hole is a triangular hole, there are 3 holes in total, and the single diameter is 10 cm.
[0014] Preferably, the bridge-building machine described in Step 3 is a double-longitudinal beam bridge-building machine, comprising a longitudinal beam, a lifting trolley, a middle support device, a front support leg, a rear support leg, a middle auxiliary support leg, a hydraulic system and an electronic control system. The middle support device, the front support leg, the rear support leg and the middle auxiliary support leg are located at the bottom of the longitudinal beam, and the lifting trolley includes a front lifting trolley and a rear lifting trolley, which are located at the top of the longitudinal beam.
[0015] Preferably, the method for retreating the bridge erecting machine in Step 3 comprises the following steps:
[0016] b1. Start the hydraulic system, retract the jacks of the front and rear outriggers, make the longitudinal beam completely fall on the middle support device and the middle auxiliary outriggers, check whether the bridge erector is level and stable, and move the bridge erector backward if all is well;
[0017] b2. Start the electric control system of the double-layer wheel box on the top of the middle support device to drive the longitudinal beam to move backward, and the rear lifting trolley will move backward synchronously with the longitudinal beam. At the same time, start the front lifting trolley to move backward synchronously, and its position will remain above the middle support device;
[0018] b3. When the rear outrigger moves to the front of the rear span beam, the longitudinal beam stops moving backward, and the rear outrigger and front outrigger are lowered in turn to complete the back movement.
[0019] The present invention provides a construction method for dismantling hollow slab beams of the upper structure of an approach bridge. It has the following beneficial effects:
[0020] The present invention adopts a core drilling machine in cooperation with a disk saw and a rope saw to cut the hinge joints between the hollow slab beams in the demolition sequence, and cooperates with a bridge erecting machine to adopt a span-by-span demolition method to realize the demolition construction of the hollow slab beam. The demolition speed is fast, and the division according to the hinge joints is more convenient and quick. Compared with the blasting method, no ruins and greater pollution will be generated, and the tonnage of the bridge erecting machine is relatively small, so the safety is higher when hoisting the hollow slab beam. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A diagram showing the sequence of dismantling hollow slab beams of each span in a method for dismantling hollow slab beams of a bridge approach superstructure according to the present invention;
[0022] Figure 2 It is a schematic diagram of the removal of the hinged joint of the approach bridge in a construction method for dismantling the hollow slab beam of the upper structure of the approach bridge according to the present invention;
[0023] Figure 3 It is a schematic diagram of the station position of the bridge erection machine for hoisting the first span hollow slab girder in a construction method for dismantling the hollow slab girder of the upper structure of the approach bridge according to the present invention;
[0024] Figure 4 The present invention is a schematic diagram of the station position of the bridge erection machine for hoisting the hollow slab girder of the second span in the hollow slab girder removal construction method of the upper structure of the approach bridge of the present invention.
[0025] Legend
[0026] 1. Longitudinal beam; 2. Lifting trolley; 3. Front outrigger; 4. Middle support device; 5. Middle auxiliary outrigger; 6. Rear outrigger. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] Example:
[0029] like Figure 1-Figure 4 As shown, an embodiment of the present invention provides a construction method for dismantling a hollow slab beam of an approach bridge superstructure, comprising the following steps:
[0030] Step 1. Determine the demolition order: number each span of hollow slab beams and determine the demolition order as middle beam first, then side beam, and finally side beam;
[0031] Step 2. Preparation before demolition: Use a core drill with a disk saw or a rope saw to cut the hinge joints between the hollow slab beams;
[0032] Step 3, the process of demolition: the hollow slab beam is demolished span by span using a bridge erection machine, and after demolition, it is directly hoisted to the beam transport vehicle and transported to the demolition site for demolition;
[0033] a. Binding beam: Install wire rope slings at 1 / 3 of both ends of the hollow slab beam. Lift slowly at first. When the hollow slab beam is separated from the support, both sides of the bridge erection machine should be raised and lowered synchronously to keep the hollow slab beam horizontal during the lifting process;
[0034] b. After the hollow slab beam of the previous span is dismantled, the bridge-erecting machine will retreat one span to dismantle the next span.
[0035] In Step 2, before cutting, the surveying personnel will lay out the center line of the hinge joint. The two longitudinal hinge joints of the hollow slab beams to be removed first in each span will be cut with a rope saw with a cutting depth of 90 cm. The remaining hinge joints of the hollow slab beams in each span and the continuous transverse hinge joints of the bridge deck will be cut with a disc saw with a cutting depth of 10 cm.
[0036] The hinge joints between beams at the cap beam cannot be cut by rope saw due to space constraints, so a core drill is used to drill holes. The holes are arranged in rows, with a total of 5 rows of holes, each with a diameter of 10 cm. The rows of holes mainly solve the problem of cutting the hinge joints between beams at the cap beam, and also play a guiding role in cutting the hinge joints.
[0037] Before cutting with a rope saw, a rope saw hole is cut first. The hole diameter is 10 cm and the number is 1. The hoisting hole is drilled with a core drill. The drilled hole is a triangular hole. There are 3 holes in total. The diameter of each hole is 10 cm. The drilling position is 0.2L away from the end of the beam.
[0038] The bridge-building machine in Step 3 is a double longitudinal beam bridge-building machine, which includes a longitudinal beam 1, a lifting trolley 2, a middle support device 4, a front support leg 3, a rear support leg 6, a middle auxiliary support leg 5, a hydraulic system and an electronic control system. The middle support device 4, the front support leg 3, the rear support leg 6, and the middle auxiliary support leg 5 are located at the bottom of the longitudinal beam 1, and the lifting trolley 2 includes a front lifting trolley and a rear lifting trolley, which are located at the top of the longitudinal beam 1.
[0039] Before the bridge erection machine is tested, it is necessary to check whether the direction of the motor meets the requirements. The direction of the motor of the operating mechanism must be the same, adjust the brake shoe and brake clearance of the winch, check whether the oil volume in each reducer is sufficient, and whether the oil nozzles, oil cups, oil pipes and oil circuits are unobstructed. The test run can only be carried out after everything has been checked and confirmed. The load test must be carried out before the bridge erection machine is erected.
[0040] No-load test
[0041] ① The lifting trolley moves back and forth along the longitudinal beam track several times without any load, and the wheels do not slip obviously. The starting and braking are normal and reliable.
[0042] ② Start the lifting mechanism, lift the empty hook up and down several times, the switch action should be sensitive and accurate.
[0043] ③ Open the two hoists to the middle of the span and move them several times within a range of 5m front and back. The starting and braking wheels must not slip and the operation must be smooth.
[0044] Static load test
[0045] Use a lifting trolley to stop at the middle of the span of the bridge erecting machine, lift the rated load, then lift 1.2 times the rated load 10 cm from the ground, hover for 10 minutes and then remove the load, check whether the longitudinal beam of the bridge erecting machine has residual deformation. After repeated several times, the longitudinal beam shall not have plastic deformation and return to a stable no-load state.
[0046] Dynamic load test
[0047] The lifting mechanism and the lifting trolley are repeatedly operated within a range of 5m with a load of 1.1 times the rated load, and the brakes of each braking mechanism are activated, whether the electrical control is sensitive, accurate, and reliable, whether the longitudinal beam vibration is normal, and whether the mechanism operates smoothly. After unloading, the mechanisms and longitudinal beams are free of damage and plastic deformation.
[0048] The method of retreating the bridge erecting machine in Step 3 includes the following steps:
[0049] b1. Start the hydraulic system, retract the jacks of the front outrigger 3 and the rear outrigger 6, and make the longitudinal beam 1 completely fall on the middle support device 4 and the middle auxiliary outrigger 5. Check whether the bridge erecting machine is horizontal and stable. If the inspection is correct, move the bridge erecting machine backward;
[0050] b2. Start the electric control system of the double-layer wheel box on the top of the middle support device 4, drive the longitudinal beam 1 to move backward, and the rear lifting trolley moves backward synchronously with the longitudinal beam 1. At the same time, start the front lifting trolley to move backward synchronously, and its position remains above the middle support device 4;
[0051] b3. When the rear outrigger 6 moves to the front of the rear span beam, the longitudinal beam 1 stops moving backward, and the rear outrigger 6 and the front outrigger 3 are lowered in turn to complete the back movement.
[0052] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction method for dismantling hollow slab beams of a bridge approach superstructure, characterized in that: The steps include: Step 1. Determine the demolition order: number each span of hollow slab beams and determine the demolition order as middle beam first, then side beam, and finally side beam; Step 2. Preparation before demolition: Use a core drill with a disk saw or a rope saw to cut the hinge joints between the hollow slab beams; Step 3, the process of demolition: the hollow slab beam is demolished span by span using a bridge erection machine, and after demolition, it is directly hoisted to the beam transport vehicle and transported to the demolition site for demolition; a. Binding beam: Install wire rope slings at 1 / 3 of both ends of the hollow slab beam. Lift slowly at first. When the hollow slab beam is separated from the support, both sides of the bridge erection machine should be raised and lowered synchronously to keep the hollow slab beam horizontal during the lifting process; b. After the hollow slab beam of the previous span is dismantled, the bridge-erecting machine will retreat one span to dismantle the next span.
2. The method for dismantling the hollow slab beam of the upper structure of the approach bridge according to claim 1, characterized in that: In Step 2, before cutting, the surveying personnel will lay out the center line of the hinge joint. The two longitudinal hinge joints of the hollow slab beams to be removed first in each span will be cut with a rope saw with a cutting depth of 90 cm. The remaining hinge joints of the hollow slab beams in each span and the continuous transverse hinge joints of the bridge deck will be cut with a disc saw with a cutting depth of 10 cm.
3. The method for dismantling the hollow slab beam of the upper structure of the approach bridge according to claim 2 is characterized by: The hinge joints between beams at the cap beam cannot be cut with a rope saw due to space constraints, so a core drill is used to drill holes. The holes are arranged in rows, with a total of 5 holes, and the diameter of each hole is 10 cm.
4. The method for dismantling the hollow slab beam of the upper structure of the approach bridge according to claim 2 is characterized by: Before cutting with a rope saw, a rope saw hole is cut first. The hole diameter is 10 cm and the number is 1. The hoisting hole is drilled with a core drill. The drilled hole is a triangular hole. There are 3 holes in total, and each hole has a diameter of 10 cm.
5. The method for dismantling the hollow slab beam of the upper structure of the approach bridge according to claim 1, characterized in that: The bridge erection machine described in Step 3 is a double longitudinal beam bridge erection machine, which includes a longitudinal beam (1), a lifting trolley (2), a middle support device (4), a front support leg (3), a rear support leg (6), a middle auxiliary support leg (5), a hydraulic system and an electronic control system. The middle support device (4), the front support leg (3), the rear support leg (6), and the middle auxiliary support leg (5) are located at the bottom of the longitudinal beam (1), and the lifting trolley (2) includes a front lifting trolley and a rear lifting trolley, which are located at the top of the longitudinal beam (1).
6. The method for dismantling the hollow slab beam of the upper structure of the approach bridge according to claim 5, characterized in that: The method for retreating the bridge erecting machine in Step 3 comprises the following steps: b1. Start the hydraulic system and retract the jacks of the front outrigger (3) and the rear outrigger (6) to make the longitudinal beam (1) completely fall on the middle support device (4) and the middle auxiliary outrigger (5). Check whether the bridge erecting machine is horizontal and stable. If the inspection is correct, move the bridge erecting machine backward; b2. Start the electric control system of the double-layer wheel box on the top of the middle support device (4), drive the longitudinal beam (1) to move backward, and the rear lifting trolley moves backward synchronously with the longitudinal beam (1). At the same time, start the front lifting trolley to move backward synchronously, and its position remains above the middle support device (4); b3. When the rear outrigger (6) moves to the front of the upper part of the rear span beam, the longitudinal beam (1) stops moving backward, and the rear outrigger (6) and the front outrigger (3) are lowered in sequence to complete the backward movement.