Sunken elevator shaft of reconstructed community under sandbar geology and construction method of sunken elevator shaft
By using cement mixing piles and crown beam structures in the sand geological reconstruction community, the foundation pit excavation and support structure during the construction of a sunken elevator shaft have a great impact on the structure, cannot be constructed through dry methods, and the foundation bearing capacity is insufficient. The problem of poor anti-float and water stopping effect has achieved stable foundations and efficient water stopping, ensuring the construction safety and structural stability of the elevator shaft.
Patent Information
- Application Number
- CN202411286317.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-13
- Publication Date
- 2024-11-22
AI Technical Summary
In the Shazhou subgeological reconstruction community, the sinking elevator shaft faces the problems of foundation pit excavation and support structures having a great impact on the surrounding structures, inability to dry construction, insufficient foundation bearing capacity, poor anti-float and water stopping effects during construction. .
The cement mixing pile and crown beam structure is adopted to improve the base soil quality through the bottom seal pile, and the inner pile and outer pile form a double-layer water-stop curtain, the cast pile strengthens the gap, and combines self-containing anti-seepage concrete and planting net to realize dry construction and Stable foundation and enhance the support structure's resistance to side pressure.
It effectively reduces the impact of foundation pit construction on the structure, realizes dry construction, enhances the foundation bearing capacity and water stop effect, ensures the floating resistance of the elevator shaft, and reduces the impact of construction on the surrounding environment.
Smart Images

Figure CN118997128A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a sunken elevator shaft, and in particular to a sunken elevator shaft for a community rebuilt under sandbar geology and a construction method thereof. Background Art
[0002] With the needs of urban construction, in order to improve the living environment of community residents, some old residential buildings need to add elevators. Currently, most of the rebuilt communities are old communities with non-walkable roofs, so sunken elevator shafts are often used. The reconstruction of the sunken elevator shaft in the community needs to focus on the impact of foundation pit construction on the structure and the bearing capacity requirements of the foundation for elevator installation construction.
[0003] For sandbar geology, the soil layers below the ground are silty clay, silt, gravel, and round gravel, and the groundwater level is very close to the ground (e.g., 0.3-0.5 m). When constructing a sunken elevator shaft in a residential area under sandbar geology, there are many problems, such as sandbar geology, proximity to structures, and restrictions on cost and protection measures. Generally, there are the following problems: 1) The elevator shaft is close to the building, the construction space is narrow, and the foundation pit construction has a greater impact on the foundation, which can easily cause foundation subsidence; 2) The groundwater level in the sandbar environment is high and the sand is soft, so a support structure needs to be built in a narrow space, and the support structure needs to consider resistance Problems such as extremely large lateral pressure, ensuring construction space in the pit, and the support structure's own sand fixation and water stopping; 3) The steel frame of the ground elevator passage requires the foundation of the surrounding sunken elevator shaft to be strengthened, which requires the space of the support structure. The construction of load-bearing piles to enhance the bearing capacity needs to fully consider the lack of space, structure disturbance and pile hole forming problems. The construction of load-bearing piles often cannot take into account the impact of anti-floating and sinking shaft chamber structure; 4) The shaft chamber foundation pit is designed for a special environment and needs to face the impact of disturbance, settlement caused by precipitation, and surrounding water stopping capabilities. It is also necessary to consider the realization of self-lowering and water stopping in the pit. It is often unable to solve the waterless construction environment in the pit during shaft chamber construction.
[0004] From the above, we can see that when constructing a sunken elevator shaft in a residential area under Shazhou geology, we are currently faced with problems such as "the excavation of the foundation pit and the construction of the support structure are likely to affect the surrounding structures", "dry construction is impossible", "the bearing capacity of the foundation required for installing the elevator is restricted by the size of the elevator shaft", and "the anti-floating and water-stopping effects are poor". Summary of the invention
[0005] The purpose of the present invention is to provide a method for constructing a sunken elevator shaft in a residential area rebuilt under sandbar geology, and a sunken elevator shaft in a residential area rebuilt under sandbar geology. The present invention rationally utilizes the sand and soil characteristics of the sandbar area, effectively reduces the impact of foundation pit excavation and support structure construction on surrounding structures, realizes dry construction, can provide the required foundation bearing capacity for installing elevators, and can ensure anti-floating and water-stopping effects.
[0006] The technical solution adopted by the present invention is: A construction method for a sunken elevator shaft in a residential area rebuilt under sandbar geology, comprising the following steps: S1. Preparation: Determine the arrangement of cast-in-place piles according to the position of the steel skeleton of the ground elevator passage and mark them on site; determine the size and arrangement of cement mixing piles according to the size and arrangement of cast-in-place piles and mark them on site; S2. Construction of cement mixing piles: Cement mixing piles are divided into bottom piles, inner piles, partition piles and outer piles according to different positions; bottom piles are distributed throughout the foundation pit area and are located below the elevator shaft bottom elevation, and are used to improve the soil below the elevator shaft bottom elevation; inner piles are distributed along the edge of the foundation pit, and outer piles are distributed in the outer circle of the inner piles, and the two are used to form a double-channel water-stop curtain; partition piles are distributed between the inner piles and the outer piles, and the inner piles, partition piles and outer piles surround the wall protection cavity of each cast-in-place pile; S3, bored pile construction: the pile hole is rotated and dug at the retaining wall cavity of each bored pile, the pile hole is cleaned, the steel cage is placed, and the bored pile is cast. The pile head steel bar of the bored pile is not wrapped with stirrups and the top elevation is near the bottom of the elevator shaft. The outer side of the bored pile in the retaining wall cavity is filled with cast concrete; S4, crown beam construction: dig intercepting ditches around the outer side of the outer piles to form an open surface for breaking the outer piles, then break the outer pile heads to leave space for the installation of the ring beam, then break the pile heads of the separation piles and cast-in-place piles to form space for the installation of the crown beam, and then carry out crown beam reinforcement binding, embedded parts installation, formwork support, and casting in sequence to obtain the crown beam. The crown beam connects the tops of all cast-in-place piles, and the embedded parts are connected to the pile head reinforcement of the cast-in-place piles and the crown beam reinforcement. The top of the embedded parts extends out of the top surface of the elevator shaft; S5. Excavation of foundation pit: excavate the foundation pit, clean the base, clean the impurities on the inner piles and bottom piles, roughen the contact surface between the bottom piles and the inner piles and the leveling layer, and remove impurities; S6. Treatment of the base and intercepting ditch: Find the water seepage points on the top surface of the bottom pile and the side wall of the inner pile and seal them until there are no obvious leakage points. Then pour the bottom concrete on the top surface of the bottom pile. The bottom concrete adopts self-compacting and anti-seepage underwater concrete. Then, after the bottom concrete solidifies to a certain extent, dig out a water collection pit. Then, after the bottom concrete solidifies to a certain extent, remove the mud skin of the bottom concrete. Plant reinforcement in the lateral cast-in-place pile body and use the embedded reinforcement to tie the steel mesh on the surface of the bottom concrete. Then lay a leveling layer on the bottom concrete. At the same time, cast the intercepting ditch cushion layer. S7, waterproof construction: hang mesh and plaster the side wall of the inner pile, and then construct the waterproof layer on the leveling layer and side wall; S8. Elevator shaft construction: The elevator shaft adopts an integrated ear cap structure, including a pool body and a ring beam plate located inside and outside the foundation pit respectively. The ring beam plate adopts an inner buckle top structure. The outer edge of the ring beam plate extends downward to the top of the outer pile, the middle is covered on the crown beam and the inner pile, and the inner edge is connected to the pool body. The pile head steel bars of the cast-in-place pile are located inside the ring beam plate and the ends are bent in all directions; a steel mesh is set inside the elevator shaft, and the hanging formwork system is used to cast and form it in one go; S9. Construction of intercepting ditch: After the concrete strength of the elevator shaft reaches a certain level, first remove the formwork system, then clean the intercepting ditch, then carry out hardening construction and lay the cover plate, and connect the intercepting ditch to the drainage facilities of the rebuilt community; S10. Elevator installation: After the concrete strength of the elevator shaft reaches a certain level, install the ground elevator passage, install the steel frame of the ground elevator passage on the embedded parts, install a water pump in the sump, and connect the drainage pipe of the water pump to the intercepting ditch.
[0007] In step S2, the bottom piles are constructed continuously from the center of the foundation pit to the outside and the piles are engaged in a plum blossom shape. After the bottom piles are constructed, the inner piles, the partition piles and the outer piles are constructed continuously from the inside to the outside and the piles are engaged with each other. The engagement depth of the inner piles and the bottom piles can ensure the net distance between the subsequent elevator car and the side wall of the elevator shaft.
[0008] In step S2, the upper end of the bottom pile is located a certain distance below the elevator shaft bottom elevation, the length of the bottom pile is ≥3.5m, the pile diameter is 200~500mm, the pile body cement blending amount is 15%~18%, and the cement slurry water-cement ratio is 0.5~0.7; the length L of the inner pile, the partition pile and the outer pile is greater than the length of the cast-in-place pile and L / 3 is greater than the length from the ground to the elevator shaft bottom elevation, the pile body cement blending amount of the inner pile, the partition pile and the outer pile is 20%~25%, the cement slurry water-cement ratio is 0.5~0.55, and the pile diameter is 100~300mm; the bottom pile, the inner pile, the partition pile and the outer pile are made of 42.5 grade and above silicate cement.
[0009] In step S3, the concrete strength of the cast-in-place pile is ≥ C25 and 0.15% expansion agent is used.
[0010] In step S4, the cast-in-place piles and the partition piles are cut and broken at the outer pile positions to avoid damaging the inner piles. If the inner piles are damaged, the tops of the inner piles are re-formed, reinforced and concrete is poured and waterproofed.
[0011] In step S5, when excavating the foundation pit, a long-arm small excavator is used to dig downward from the center of the foundation pit area, and then dig around after digging to the top of the bottom pile.
[0012] In step S6, high-pressure grouting is used to seal the leakage point. The slurry uses cement-water glass slurry. The volume ratio of cement slurry: water glass solution is 1:1, the cement content is 15%~20%, the water-cement ratio of cement slurry is 0.65~0.75, the grouting speed is 20~30L / min, and 8% of the weight of cement anti-seepage agent is added; the bottom sealing concrete uses self-compacting and anti-seepage underwater concrete ≥P6C25, and 0.2%~0.3% expansion agent is added.
[0013] In step S8, the pool depth is ≧ elevator car height + 20-30 cm steel plate height to ensure that maintenance personnel can enter the top of the elevator car from the ground for maintenance.
[0014] After the construction is completed, the concrete and concrete blocks of the site panels will be removed, the garbage on the site will be cleaned up, and the original ecology of the surface will be restored.
[0015] A sunken elevator shaft for rebuilding a residential area under sandbar geology comprises cement mixing piles, cast-in-place piles, a crown beam, a base structure, a ditches, an elevator shaft, embedded parts and a water pump; the cement mixing piles are divided into bottom piles, inner piles, partition piles and outer piles according to different positions, the bottom piles are distributed throughout the foundation pit area and are located below the elevator shaft bottom elevation, the bottom piles are used to improve the soil below the elevator shaft bottom elevation, the inner piles are distributed along the foundation pit edge, the outer piles are distributed in the outer circle of the inner piles, the inner piles and the outer piles are used to form a double-channel water-stop curtain, the partition piles are distributed between the inner piles and the outer piles, and the inner piles, the partition piles and the outer piles form a retaining wall cavity; the cast-in-place piles are arranged around the foundation pit according to the position of the steel skeleton of the ground elevator passage, the cast-in-place piles are set in each retaining wall cavity, the pile head steel bars of the cast-in-place piles are not wrapped with stirrups and the top elevation is near below the top surface of the elevator shaft; the crown beam connects the top ends of all the cast-in-place piles; the base structure comprises bottom concrete arranged on the top surface of the bottom piles, a water collection opening on the bottom concrete The foundation pit is constructed by using the embedded bars on the lateral cast-in-place pile body to tie the steel mesh on the surface of the bottom concrete, a leveling layer is laid on the bottom concrete, and a waterproof layer is arranged on the leveling layer and the side wall of the inner pile. The bottom concrete adopts self-compacting and anti-seepage underwater concrete; the intercepting ditch is arranged around the outside of the outer pile and connected to the drainage facilities of the rebuilt community; the elevator shaft adopts an integrated ear cap structure, including a pool body and a ring beam plate located inside and outside the foundation pit respectively, the ring beam plate adopts an inner buckled top structure, the outer edge of the ring beam plate extends downward to the top of the outer pile, the middle is covered on the crown beam and the inner pile, and the inner edge is connected to the pool body, the pile head steel bars of the cast-in-place pile are located in the ring beam plate and the ends are bent in all directions, and a steel mesh is arranged inside the elevator shaft; the embedded parts are buried in the crown beam and connected to the pile head steel bars and the crown beam steel bars of the cast-in-place pile, the top of the embedded parts extends out of the ring beam plate, and the embedded parts are used to install the steel frame of the ground elevator passage; the water pump is installed in the sump and connected to the intercepting ditch through a drainage pipeline.
[0016] The beneficial effects of the present invention are: The present invention rationally utilizes the sandy soil characteristics of the sandbar area, sets cement mixing piles in the foundation pit area and around it, and processes the base structure, which can stabilize the sandy soil, improve the foundation (reduce foundation disturbance), and effectively reduce the impact of foundation pit excavation and support structure construction on surrounding structures, thereby realizing dry construction: the permeability of the base sandy soil is improved by the bottom sealing piles to achieve primary pressure resistance and water stopping, and the micro-expansion self-tightness and water resistance of the bottom sealing concrete is used to achieve secondary water stopping, which reduces the osmotic pressure layer by layer, enhances the water resistance, avoids the impact of precipitation construction on the surrounding environment, reduces the open drainage pressure, improves the bearing capacity of the base and the working surface, and realizes Dry construction ensures dry construction during the bottom sealing construction and guarantees the quality of the bottom sealing entity; the inner and outer piles form a double-layer water-stop curtain and the gaps are reinforced by the cement slurry of the cast-in-place piles, which effectively ensures the water-stop effect; the inner piles, separation piles and outer piles surround the wall protection cavity of the cast-in-place piles, which can not only form a stable wall protection structure, avoid the use of casings and the impact of hole collapse on surrounding structures during the drilling process, but also form a keel to resist pressure measurement and improve the support structure's ability to resist lateral pressure; an embedded steel mesh is set in the concrete of the leveling layer, which can effectively connect the leveling layer with the cast-in-place piles and the bottom sealing concrete, and withstand the water pressure on the top surface.
[0017] The present invention arranges cast-in-place piles and cap beams around the foundation pit, which can enhance the safety and stability of the support structure, prevent settlement and collapse around the foundation pit, and provide the foundation bearing capacity required for installing the elevator: the cast-in-place piles are arranged around the foundation pit according to the position of the steel skeleton of the ground elevator passage, which can not only bear the gravity of the ground elevator, but also play a supporting role, which can reduce the wall thickness of the elevator shaft and facilitate the construction of the elevator shaft; the cap beam can connect the cast-in-place piles into a whole, improve the overall bearing capacity and lateral pressure resistance of the cast-in-place piles, and can also connect the cast-in-place piles, the elevator shaft, the embedded parts and the steel skeleton of the elevator passage into a whole, so as to ensure the stability of the structure.
[0018] The structure and installation method of the elevator shaft in the present invention can ensure the anti-floating and water-stopping effects: the elevator shaft adopts an integrated ear cap structure, which is connected to the cast-in-place piles under the action of embedded parts and cast-in-place pile head steel bars, and the ring beam plate bears both the downward pressure of the ground elevator passage on the embedded parts and the downward pull of the cast-in-place pile head steel bars. This connection of pulling down and pressing up enhances the integrity of the elevator shaft and the foundation structure and its own anti-floating property. In addition, the ring beam plate adopts an inner buckled top structure, which can effectively prevent erosion of ditch water and has a certain water-stopping effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a top view of the cement mixing pile after construction in the embodiment of the present invention.
[0020] Figure 2 It is a top view of the bored pile after construction in the embodiment of the present invention.
[0021] Figure 3It is a top view after the crown beam construction, foundation pit excavation, base and intercepting ditch treatment, and waterproofing construction in the embodiment of the present invention.
[0022] Figure 4 yes Figure 3 Cross-section view at AA in the middle.
[0023] Figure 5 It is a top view of the elevator shaft during construction in an embodiment of the present invention.
[0024] Figure 6 yes Figure 5 Cross-section view at the middle BB.
[0025] Figure 7 It is a schematic diagram of the sunken elevator shaft after the construction is completed in the embodiment of the present invention.
[0026] In the figure: 1- bottom pile; 2- inner pile; 3- partition pile; 4- outer pile; 5- cast-in-place pile; 6- steel cage; 7- cast-in-place concrete; 8- embedded parts; 9- crown beam; 10- waterproof layer; 11- bottom concrete; 12- leveling layer; 13- embedded steel bar; 14- steel mesh; 15- sump; 16- intercepting ditch cushion layer; 17- intercepting ditch; 18- ring beam plate; 19- inner support rod; 20- formwork; 21- tank body; 22- steel mesh; 23- water pump; 24- elevator car; 25- steel frame; 26- glass shed. DETAILED DESCRIPTION
[0027] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0028] Embodiment 1 This embodiment discloses a construction method for a sunken elevator shaft in a residential area under sandbar geology, comprising the following steps: S1. Preparation: Determine the arrangement of the cast-in-place piles 5 according to the position of the steel skeleton 25 of the ground elevator passage and mark them on site; determine the size and arrangement of the cement mixing piles according to the size and arrangement of the cast-in-place piles 5 and mark them on site; for other unfinished matters, refer to the three major preparations of conventional organization, materials, and technology, such as three connections and one equality.
[0029] S2. Cement mixing pile construction: Figure 1 As shown, cement mixing piles are divided into bottom piles 1, inner piles 2, partition piles 3 and outer piles 4 according to different positions; the bottom piles 1 are distributed throughout the foundation pit area and are located below the elevator shaft bottom elevation, and are used to improve the soil below the elevator shaft bottom elevation; the inner piles 2 are distributed along the edge of the foundation pit, and the outer piles 4 are distributed in the outer circle of the inner piles 2, and the two are used to form a double-channel water-stop curtain; the partition piles 3 are distributed between the inner piles 2 and the outer piles 4, and the inner piles 2, the partition piles 3 and the outer piles 4 surround the wall protection cavity of each cast-in-place pile 5 (in this embodiment, ensure that the short side clearance of the wall protection cavity is greater than the pile diameter of the cast-in-place pile 5 + 2cm); other matters not covered are implemented according to the usual design and specification requirements.
[0030] Among them, trial pile work is carried out before the construction of cement mixing piles to determine the optimal mixing amount of cement.
[0031] Among them, preferably, the bottom piles 1 are constructed continuously from the center of the foundation pit to the outside and the piles are engaged in a plum blossom shape. After the bottom piles 1 are constructed, the inner piles 2, the partition piles 3 and the outer piles 4 are constructed continuously in order from the inside to the outside (if interrupted for some reason, it should be resumed within 2 hours) and the piles are engaged. The engagement depth of the inner piles 2 and the bottom piles 1 can ensure the net distance between the subsequent elevator car 24 and the side wall of the elevator shaft.
[0032] Among them, preferably, the upper end of the bottom sealing pile 1 is located a certain distance (-300mm) below the elevator shaft bottom elevation, the length of the bottom sealing pile 1 is ≥3.5m, the pile diameter is 200~500mm, the pile body cement blending amount is 15%~18%, and the cement slurry water-cement ratio is 0.5~0.7; the length L of the inner pile 2, the partition pile 3 and the outer pile 4 is greater than the length of the cast-in-place pile 5 and L / 3 is greater than the length from the ground to the elevator shaft bottom elevation, the pile body cement blending amount of the inner pile 2, the partition pile 3 and the outer pile 4 is 20%~25%, the cement slurry water-cement ratio is 0.5~0.55, and the pile diameter is 100~300mm; the bottom sealing pile 1, the inner pile 2, the partition pile 3 and the outer pile 4 are made of 42.5 grade or above silicate cement, and it is advisable to have a unified pile diameter.
[0033] Among them, preferably, the single pile bearing capacity characteristic value of the bottom pile 1 is required to reach 180KN, and the compressive strength of the composite foundation is required to reach 150Kpa; the unconfined compressive strength of the inner pile 2, the separation pile 3 and the outer pile 4 at 28d pile body is required to reach above 5.0Mpa, and the unconfined compressive strength of the pile body at 90d pile body is required to reach above 8MPa.
[0034] S3, cast-in-place pile 5 construction: Figure 2 As shown, a pile hole is drilled in the retaining wall cavity of each bored pile 5, the pile hole is cleaned, a steel cage 6 is placed, and the bored pile 5 is cast in turn. The pile head steel bars (e.g., about 50 cm) of the bored pile 5 are not wrapped with stirrups and the top elevation is below the top surface of the elevator shaft (e.g., about -5 cm). The outer side of the bored pile 5 in the retaining wall cavity is filled with poured concrete 7. Other matters not covered are implemented according to the usual design and specification requirements.
[0035] The inner wall of the pile hole and the soil at the bottom of the pile are cleaned to ensure the quality of the combination of the cast-in-place pile 5 with the inner pile 2, the partition pile 3, and the outer pile 4; the top elevation of the steel cage 6 is below the top surface of the elevator shaft, which is convenient for the subsequent construction of the ring beam slab 18; the pile head steel bars are not wrapped around the stirrups to avoid subsequent interference with the embedded parts 8.
[0036] Among them, preferably, the verticality and pile position deviation should be ensured during the rotary excavation process to avoid damage to the inner pile 2, the partition pile 3, and the outer pile 4. If the drill gets stuck or the rotary excavation becomes difficult during the rotary excavation process, the deviation should be adjusted in time.
[0037] Preferably, the concrete strength of the cast-in-place pile 5 is ≥ C25 and 0.15% expansion agent is used.
[0038] S4, crown beam 9 construction: Figure 3 and Figure 4 As shown, a ditches 17 is excavated around the outer side of the outer pile 4 (e.g., the excavation depth is 50 cm) to form an open surface for breaking the outer pile 4, and then the pile head of the outer pile 4 is broken to leave installation space for the ring beam 18, and then the pile heads of the partition pile 3 and the cast-in-place pile 5 are broken to form installation space for the crown beam 9, and then the crown beam 9 is successively reinforced with steel bars, embedded parts 8 are installed, formwork is supported, and cast to obtain the crown beam 9, the crown beam 9 connects the top ends of all the cast-in-place piles 5, the embedded parts 8 are connected to the pile head steel bars of the cast-in-place pile 5 and the steel bars of the crown beam 9, and the top end of the embedded parts 8 extends out of the top surface of the elevator shaft; other matters not covered are implemented according to the usual design and specification requirements.
[0039] Preferably, the breaking height of the outer pile 4 is equal to the thickness of the ring beam plate 18 at the location, the height of the crown beam 9 is 20-30 cm, and the width is equal to the diameter of the bored pile 5 .
[0040] Preferably, the cast-in-place piles 5 and the partition piles 3 are cut and broken at the position of the outer piles 4 to avoid damaging the inner piles 2. If the inner piles 2 are damaged, the top of the inner piles 2 is re-formed and reinforced with steel bars 13, concrete is poured, and waterproofing is applied.
[0041] S5. Excavation of foundation pit: Figure 3 and Figure 4 As shown, after the foundation pit is excavated and the base is cleaned out, the impurities on the inner piles 2 and the bottom piles 1 are cleaned, and the contact surfaces between the bottom piles 1 and the inner piles 2 and the leveling layer 12 are roughened and the impurities are removed; other matters not covered are implemented according to the usual design and specification requirements.
[0042] Preferably, when excavating the foundation pit, a long-arm small excavator is used to dig downward from the center of the foundation pit area, and then dig around after digging to the top of the bottom sealing pile 1.
[0043] Among them, preferably, the excavated soil should be piled at a place more than twice the depth of the foundation pit, or transported out as it is excavated.
[0044] Among them, preferably, after the base is cleaned out, open drainage is used to pump out and flush and clean floating sand, residue, pumice and other impurities on the inner pile 2 and the bottom pile 1, and after roughening, the floating scum on the ground at the pile head of the bottom pile 1 is removed.
[0045] S6, base and intercepting ditch 17 treatment: Figure 3 and Figure 4As shown, the seepage points on the top surface of the bottom pile 1 and the side wall of the inner pile 2 are found and sealed until there is no obvious leakage point, and then the bottom concrete 11 is poured on the top surface of the bottom pile 1. The bottom concrete 11 adopts self-compacting and waterproof underwater concrete, and then after the bottom concrete 11 solidifies to a certain extent (e.g., strength ≥3.5MPa), a water collection pit 15 (e.g., 15cm) is dug, and then after the bottom concrete 11 solidifies to a certain extent (e.g., strength ≥75% of concrete strength), the mud skin of the bottom concrete 11 is removed, and the pile body of the lateral cast-in-place pile 5 is planted with steel bars 13 and steel mesh 14 is tied on the surface of the bottom concrete 11 by using the planted steel bars 13, and then a leveling layer 12 is laid on the bottom concrete 11; at the same time, a drainage ditch cushion layer 16 is poured; other unfinished matters are implemented according to the usual design and specification requirements.
[0046] The base treatment and the intercepting ditch 17 treatment are carried out simultaneously, which can save time. The intercepting ditch cushion layer 16 and the leveling layer 12 use the same concrete.
[0047] Among them, preferably, the steel mesh 14 adopts 8@200; the leveling layer is 128cm and uses ≥P3C15 impermeable concrete.
[0048] Among them, preferably, high-pressure grouting is used to seal the leakage points, the slurry adopts cement-water glass (sodium silicate) slurry, the cement slurry: water glass solution is 1:1 (volume ratio), the cement content is 15%~20%, the water-cement ratio of cement slurry is 0.65~0.75, the grouting speed is 20~30L / min, and 8% anti-seepage agent is added based on the weight of cement; the bottom sealing concrete 11 adopts self-compacting and anti-seepage underwater concrete ≥P6C25, and 0.2%~0.3% expansion agent is added.
[0049] S7. Waterproof construction: Figure 3 and Figure 4 As shown, the side wall of the inner pile 2 is subjected to mesh plastering, and then the leveling layer 12 and the side wall are subjected to waterproofing layer 10 construction; other matters not covered are implemented according to the usual design and specification requirements.
[0050] Among them, preferably, the plaster mortar is added with 8Kg / m 3 Steel fiber>M15 anti-cracking mortar, waterproof layer 10 uses waterproof membrane.
[0051] S8. Elevator shaft construction: Figure 5 and Figure 6As shown, the elevator shaft adopts an integrated ear cap structure, including a pool body 21 and a ring beam plate 18 respectively located inside and outside the foundation pit. The ring beam plate 18 adopts an inner buckled top structure. The outer edge of the ring beam plate 18 extends downward to the top of the outer pile 4, covers the crown beam 9 and the inner pile 2 in the middle, and the inner edge is connected to the pool body 21. The pile head steel bars of the cast-in-place pile 5 are located in the ring beam plate 18 and the ends are bent in all directions; a steel mesh 22 is arranged inside the elevator shaft, and a hanging formwork system (generally including a formwork 20, an inner support rod 19 and a suspension frame) is used for one-time casting and forming; other matters not covered are implemented in accordance with normal design and specification requirements.
[0052] Preferably, the elevator shaft is 15-30 cm thick and has a double layer of 16@150 steel mesh 22.
[0053] Preferably, the depth of the pool body 21 is ≧the height of the elevator car 24 + the height of the 20-30 cm steel plate, so as to ensure that maintenance personnel can enter the top of the elevator car 24 from the ground for maintenance.
[0054] S9, construction of intercepting ditch 17: Figure 5 and Figure 6 As shown, after the concrete strength of the elevator shaft reaches a certain level (e.g., more than 50%), the formwork system is first dismantled, then the intercepting ditch 17 is cleaned, and then hardening construction (e.g., masonry) is carried out and the cover plate is laid. The intercepting ditch 17 is connected to the drainage facilities of the rebuilt community (e.g., drainage well); other matters not covered are implemented according to the usual design and specification requirements.
[0055] Among them, preferably, the cover plate adopts a concrete grate with a thickness of ≧10 cm.
[0056] S10, Elevator installation: Figure 7 As shown, after the concrete strength of the elevator shaft reaches a certain level (ru, above 75%), the ground elevator passage (including steel frame 25, glass shed 26, elevator car 24, etc.) is installed, the steel frame 25 of the ground elevator passage is installed on the embedded part 8, and the water pump 23 is installed in the sump 15, and the drainage pipeline of the water pump 23 is connected to the intercepting ditch 17.
[0057] S11. Site restoration: After the construction is completed, the concrete and concrete blocks of the site panels will be removed, the garbage on the site will be cleaned up, and the original ecology of the surface will be restored.
[0058] Embodiment 2 This embodiment discloses a sunken elevator shaft for rebuilding a residential area under sandbar geology, comprising cement mixing piles, cast-in-place piles 5, crown beams 9, a base structure, a water intercepting ditch 17, an elevator shaft, embedded parts 8 and a water pump 23; wherein: The cement mixing piles are divided into bottom piles 1, inner piles 2, partition piles 3 and outer piles 4 according to different positions. The bottom piles 1 are distributed throughout the foundation pit area and are located below the elevator shaft bottom elevation. The bottom piles 1 are used to improve the soil below the elevator shaft bottom elevation. The inner piles 2 are distributed along the edge of the foundation pit. The outer piles 4 are distributed in the outer circle of the inner piles 2. The inner piles 2 and the outer piles 4 are used to form a double-channel water-stop curtain. The partition piles 3 are distributed between the inner piles 2 and the outer piles 4. The inner piles 2, the partition piles 3 and the outer piles 4 form a wall protection cavity. The cast-in-place piles 5 are arranged around the foundation pit according to the position of the steel skeleton 25 of the ground elevator passage. The cast-in-place piles 5 are set in each retaining wall cavity. The pile head steel bars of the cast-in-place piles 5 are not wrapped with stirrups and the top elevation is near the bottom of the elevator shaft top surface. The crown beam 9 connects the top ends of all the cast-in-place piles 5; The base structure includes a bottom concrete 11 arranged on the top surface of the bottom pile 1, a sump 15 opened on the bottom concrete 11, a steel mesh 14 tied to the surface of the bottom concrete 11 by using the embedded steel bars 13 on the pile body of the lateral cast-in-place pile 5, a leveling layer 12 laid on the bottom concrete 11, and a waterproof layer 10 arranged on the leveling layer 12 and the side wall of the inner pile 2. The bottom concrete 11 adopts self-compacting and impermeable underwater concrete; The intercepting ditch 17 is arranged around the outer side of the outer pile 4 and connected to the drainage facilities of the rebuilt community; The elevator shaft adopts an integrated ear cap structure, including a pool body 21 and a ring beam plate 18 located inside and outside the foundation pit respectively. The ring beam plate 18 adopts an inner buckle top structure. The outer edge of the ring beam plate 18 extends downward to the top of the outer pile 4, covers the crown beam 9 and the inner pile 2 in the middle, and the inner edge is connected to the pool body 21. The pile head steel bars of the cast-in-place pile 5 are located in the ring beam plate 18 and the ends are bent in all directions. A steel mesh 22 is arranged inside the elevator shaft; The embedded part 8 is embedded in the crown beam 9 and connected with the pile head reinforcement of the cast-in-place pile 5 and the crown beam 9 reinforcement. The top of the embedded part 8 extends out of the ring beam plate 18. The embedded part 8 is used to install the steel skeleton 25 of the ground elevator passage. The water pump 23 is installed in the sump 15 and connected to the intercepting ditch 17 through a drainage pipeline.
[0059] The present invention rationally utilizes the sandy soil characteristics of the sandbar area, sets cement mixing piles in the foundation pit area and around it, and processes the base structure, which can stabilize the sandy soil, improve the foundation (reduce foundation disturbance), and effectively reduce the impact of foundation pit excavation and support structure construction on surrounding structures, thus realizing dry construction: The bottom pile 1 improves the permeability of the base sand to achieve primary pressure resistance and water stopping, and the micro-expansion self-tightness and anti-seepage of the bottom concrete 11 achieves secondary water stopping, reduces the osmotic pressure layer by layer, enhances the anti-seepage, avoids the impact of precipitation construction on the surrounding environment, reduces the open drainage pressure, improves the bearing capacity of the base and the working surface, realizes dry construction, ensures dry land construction during the bottom construction, and ensures the quality of the bottom entity; The inner pile 2 and the outer pile 4 form a double-layer water-stop curtain and the gap is reinforced by the cement slurry of the cast-in-place pile 5, which effectively ensures the water-stop effect; The inner pile 2, the partition pile 3 and the outer pile 4 form a wall protection cavity of the cast-in-place pile 5, which can not only form a stable wall protection structure, avoid the use of casing and the influence of the hole collapse on the surrounding structures during the hole forming process, but also form a keel to resist pressure measurement, thereby improving the lateral pressure resistance of the support structure; An embedded steel mesh 14 is arranged in the concrete of the leveling layer 12, which can effectively connect the leveling layer 12 with the cast-in-place piles 5 and the bottom sealing concrete 11, and bear the water pressure on the top surface.
[0060] The present invention arranges cast-in-place piles 5 and crown beams 9 around the foundation pit, which can enhance the safety and stability of the support structure, prevent the surrounding of the foundation pit from settling and collapsing, and provide the foundation bearing capacity required for installing the elevator: The cast-in-place piles 5 are arranged around the foundation pit according to the position of the steel skeleton 25 of the ground elevator passage, which can not only bear the gravity of the ground elevator, but also play a supporting role, which can reduce the wall thickness of the elevator shaft and facilitate the construction of the elevator shaft; The cap beam 9 can not only connect the bored piles 5 into a whole, thereby improving the overall bearing capacity and lateral pressure resistance of the bored piles 5, but also connect the bored piles 5, the elevator shaft, the embedded parts 8 and the steel skeleton 25 of the elevator passage into a whole, thereby ensuring the stability of the structure.
[0061] The structure and installation method of the elevator shaft in the present invention can ensure the anti-floating and water-stopping effects: The elevator shaft adopts an integrated ear cap structure, which is connected to the cast-in-place pile 5 under the action of the embedded parts 8 and the steel bars at the head of the cast-in-place pile 5. The ring beam 18 bears both the downward pressure of the ground elevator passage on the embedded parts 8 and the downward pull of the steel bars at the head of the cast-in-place pile 5. This connection of pulling down and pressing up enhances the integrity of the elevator shaft and the foundation structure and its own anti-floating property. In addition, the ring beam 18 adopts an inner buckled top structure, which can effectively prevent erosion by ditch water and has a certain water-stopping effect.
[0062] The embodiments described above are part of the embodiments of the present application, rather than all of the embodiments. The detailed description of the embodiments of the present application is not intended to limit the scope of the present application for protection, but merely represents the selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application.
Claims
1. A method for constructing a sunken elevator shaft in a residential area under sandbar geology, characterized in that: Includes steps: S1. Preparation: Determine the arrangement of cast-in-place piles according to the position of the steel skeleton of the ground elevator passage and mark them on site; determine the size and arrangement of cement mixing piles according to the size and arrangement of cast-in-place piles and mark them on site; S2. Construction of cement mixing piles: Cement mixing piles are divided into bottom piles, inner piles, partition piles and outer piles according to different positions; bottom piles are distributed throughout the foundation pit area and are located below the elevator shaft bottom elevation, and are used to improve the soil below the elevator shaft bottom elevation; inner piles are distributed along the edge of the foundation pit, and outer piles are distributed in the outer circle of the inner piles, and the two are used to form a double-channel water-stop curtain; partition piles are distributed between the inner piles and the outer piles, and the inner piles, partition piles and outer piles surround the wall protection cavity of each cast-in-place pile; S3, bored pile construction: the pile hole is rotated and dug at the retaining wall cavity of each bored pile, the pile hole is cleaned, the steel cage is placed, and the bored pile is cast. The pile head steel bar of the bored pile is not wrapped with stirrups and the top elevation is near the bottom of the elevator shaft. The outer side of the bored pile in the retaining wall cavity is filled with cast concrete; S4, crown beam construction: dig intercepting ditches around the outer side of the outer piles to form an open surface for breaking the outer piles, then break the outer pile heads to leave space for the installation of the ring beam, then break the pile heads of the separation piles and cast-in-place piles to form space for the installation of the crown beam, and then carry out crown beam reinforcement binding, embedded parts installation, formwork support, and casting in sequence to obtain the crown beam. The crown beam connects the tops of all cast-in-place piles, and the embedded parts are connected to the pile head reinforcement of the cast-in-place piles and the crown beam reinforcement. The top of the embedded parts extends out of the top surface of the elevator shaft; S5. Excavation of foundation pit: excavate the foundation pit, clean the base, clean the impurities on the inner piles and bottom piles, roughen the contact surface between the bottom piles and the inner piles and the leveling layer, and remove impurities; S6. Treatment of the base and intercepting ditch: Find the water seepage points on the top surface of the bottom pile and the side wall of the inner pile and seal them until there are no obvious leakage points. Then pour the bottom concrete on the top surface of the bottom pile. The bottom concrete adopts self-compacting and anti-seepage underwater concrete. Then, after the bottom concrete solidifies to a certain extent, dig out a water collection pit. Then, after the bottom concrete solidifies to a certain extent, remove the mud skin of the bottom concrete. Plant reinforcement in the lateral cast-in-place pile body and use the embedded reinforcement to tie the steel mesh on the surface of the bottom concrete. Then lay a leveling layer on the bottom concrete. At the same time, cast the intercepting ditch cushion layer. S7, waterproof construction: hang mesh and plaster the side wall of the inner pile, and then construct the waterproof layer on the leveling layer and side wall; S8. Elevator shaft construction: The elevator shaft adopts an integrated ear cap structure, including a pool body and a ring beam plate located inside and outside the foundation pit respectively. The ring beam plate adopts an inner buckle top structure. The outer edge of the ring beam plate extends downward to the top of the outer pile, the middle is covered on the crown beam and the inner pile, and the inner edge is connected to the pool body. The pile head steel bars of the cast-in-place pile are located inside the ring beam plate and the ends are bent in all directions; a steel mesh is set inside the elevator shaft, and the hanging formwork system is used to cast and form it in one go; S9. Construction of intercepting ditch: After the concrete strength of the elevator shaft reaches a certain level, first remove the formwork system, then clean the intercepting ditch, then carry out hardening construction and lay the cover plate, and connect the intercepting ditch to the drainage facilities of the rebuilt community; S10. Elevator installation: After the concrete strength of the elevator shaft reaches a certain level, install the ground elevator passage, install the steel frame of the ground elevator passage on the embedded parts, install a water pump in the sump, and connect the drainage pipe of the water pump to the intercepting ditch.
2. The construction method of a sunken elevator shaft for rebuilding a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S2, the bottom piles are constructed continuously from the center of the foundation pit to the outside and the piles are engaged in a plum blossom shape. After the bottom piles are constructed, the inner piles, the partition piles and the outer piles are constructed continuously from the inside to the outside and the piles are engaged with each other. The engagement depth of the inner piles and the bottom piles can ensure the net distance between the subsequent elevator car and the side wall of the elevator shaft.
3. The construction method of a sunken elevator shaft for rebuilding a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S2, the upper end of the bottom pile is located a certain distance below the elevator shaft bottom elevation, the length of the bottom pile is ≥3.5m, the pile diameter is 200~500mm, the pile body cement blending amount is 15%~18%, and the cement slurry water-cement ratio is 0.5~0.7; the length L of the inner pile, the partition pile and the outer pile is greater than the length of the cast-in-place pile and L / 3 is greater than the length from the ground to the elevator shaft bottom elevation, the pile body cement blending amount of the inner pile, the partition pile and the outer pile is 20%~25%, the cement slurry water-cement ratio is 0.5~0.55, and the pile diameter is 100~300mm; the bottom pile, the inner pile, the partition pile and the outer pile are made of 42.5 grade and above silicate cement.
4. The method for constructing a sunken elevator shaft in a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S3, the concrete strength of the cast-in-place pile is ≥ C25 and 0.15% expansion agent is used.
5. The construction method of a sunken elevator shaft for rebuilding a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S4, the cast-in-place piles and the partition piles are cut and broken at the outer pile positions to avoid damaging the inner piles. If the inner piles are damaged, the tops of the inner piles are re-formed, reinforced and concrete is poured and waterproofed.
6. The method for constructing a sunken elevator shaft in a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S5, when excavating the foundation pit, a long-arm small excavator is used to dig downward from the center of the foundation pit area, and then dig around after digging to the top of the bottom pile.
7. The method for constructing a sunken elevator shaft in a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S6, high-pressure grouting is used to seal the leakage point. The slurry uses cement-water glass slurry. The volume ratio of cement slurry: water glass solution is 1:1, the cement content is 15%~20%, the water-cement ratio of cement slurry is 0.65~0.75, the grouting speed is 20~30L / min, and 8% of the weight of cement anti-seepage agent is added; the bottom sealing concrete uses self-compacting and anti-seepage underwater concrete ≥P6C25, and 0.2%~0.3% expansion agent is added.
8. The method for constructing a sunken elevator shaft in a residential area under sandbar geology as claimed in claim 1, characterized in that: In step S8, the pool depth is ≧ elevator car height + 20-30 cm steel plate height to ensure that maintenance personnel can enter the top of the elevator car from the ground for maintenance.
9. The method for constructing a sunken elevator shaft in a residential area under sandbar geology as claimed in claim 1, characterized in that: After the construction is completed, the concrete and concrete blocks of the site panels will be removed, the garbage on the site will be cleaned up, and the original ecology of the surface will be restored.
10. A sunken elevator shaft for rebuilding a residential area under sandbar geology, characterized by: It includes cement mixing piles, cast-in-place piles, crown beams, base structure, intercepting ditches, elevator shafts, embedded parts and water pumps; cement mixing piles are divided into bottom piles, inner piles, partition piles and outer piles according to different positions. The bottom piles are distributed throughout the foundation pit area and are located below the elevator shaft bottom elevation. The bottom piles are used to improve the soil below the elevator shaft bottom elevation. The inner piles are distributed along the edge of the foundation pit, and the outer piles are distributed in the outer circle of the inner piles. The inner piles and outer piles are used to form a double-channel water-stop curtain. The partition piles are distributed between the inner piles and the outer piles. The inner piles, partition piles and outer piles form a retaining wall cavity; the cast-in-place piles are arranged around the foundation pit according to the position of the steel skeleton of the ground elevator passage. The cast-in-place piles are set in each retaining wall cavity. The pile head steel bars of the cast-in-place piles are not wrapped with stirrups and the top elevation is near the bottom of the elevator shaft; the crown beam connects the tops of all cast-in-place piles; the base structure includes the bottom concrete set on the top of the bottom piles, the sump opened on the bottom concrete, and the lateral cast-in-place piles. The embedded reinforcement on the pile body is tied to the steel mesh on the surface of the bottom concrete, the leveling layer is laid on the bottom concrete, and the waterproof layer is arranged on the leveling layer and the side wall of the inner pile. The bottom concrete adopts self-tightening and anti-seepage underwater concrete; the intercepting ditch is arranged around the outside of the outer pile and connected to the drainage facilities of the rebuilt community; the elevator shaft adopts an integrated ear cap structure, including a pool body and a ring beam plate located inside and outside the foundation pit respectively. The ring beam plate adopts an internal buckled top structure. The outer edge of the ring beam plate extends downward to the top of the outer pile, the middle is covered on the crown beam and the inner pile, and the inner edge is connected to the pool body. The pile head steel bars of the cast-in-place pile are located in the ring beam plate and the ends are bent in all directions. A steel mesh is arranged inside the elevator shaft; the embedded parts are buried in the crown beam and connected to the pile head steel bars and the crown beam steel bars of the cast-in-place pile. The top of the embedded parts extends out of the ring beam plate. The embedded parts are used to install the steel frame of the ground elevator passage; the water pump is installed in the sump and connected to the intercepting ditch through a drainage pipe.