Construction progress supervision system and method of building decoration engineering based on BIM

Through the BIM-based construction progress supervision system for building decoration projects, the problems of information lag and inaccurate progress in traditional construction management methods are solved, and all-round dynamic supervision of sports venues and gym decoration projects are achieved, construction efficiency and resource allocation are improved, and high-quality and on-time delivery of the project is ensured.

CN119204623BActive Publication Date: 2025-02-28SHENZHEN XINYIHUA ARCHITECTURE DECORATE ENG CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411729581.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-11-29
Publication Date
2025-02-28
Estimated Expiration
2044-11-29

AI Technical Summary

Technical Problem

Traditional construction management methods have problems such as lag in information, inaccurate construction progress, and unreasonable resource allocation in sports venues and gym decoration projects, making it difficult to achieve accurate construction progress supervision and high-quality decoration effects.

Method used

The construction progress supervision system of building decoration engineering based on BIM can achieve comprehensive dynamic supervision of construction progress through the coordinated work of BIM model construction module, construction intensity data acquisition module, environmental adaptability monitoring module, resource investment monitoring module, construction progress prediction and analysis module and report generation module.

Benefits of technology

Through real-time data acquisition and analysis, the system calculates the coefficients of construction intensity, environmental adaptability and resource investment, predicts construction progress deviations and generates visual reports, which significantly improves the real-time, accuracy and integration of construction data, optimizes construction efficiency and resource allocation, and ensures high-quality and on-time delivery of the project.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119204623B_ABST
    Figure CN119204623B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction progress supervision system and method for a building decoration project based on BIM, and relates to the technical field of progress supervision. During operation of the system, a three-dimensional BIM model is generated through architectural design drawings of real venues in combination with detailed requirements of each construction area, the building structure and decoration effect are displayed, the construction progress and real-time data are associated, construction intensity-related data are collected and analyzed, the construction intensity coefficient Sq is calculated, construction environment data is collected and the impact of the environment on the construction progress and efficiency is analyzed, the environmental adaptation coefficient Eadapt is calculated, the input of manpower, materials and equipment is monitored in real time, the resource input coefficient Rin is calculated, and the progress prediction index Jdyc is calculated based on the BIM model and real-time collected data, the deviation between the current construction progress and the target progress is analyzed, the actual progress is compared with the planned progress, potential progress deviations are identified and early warnings are given, the data of each module are integrated, and a visual progress report and analysis chart are generated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of progress supervision, and in particular to a construction progress supervision system and method for a building decoration project based on BIM. Background Art

[0002] The construction progress supervision system of building decoration projects based on BIM is an intelligent construction management tool widely used in the field of building decoration in recent years. BIM (Building Information Modeling) technology integrates all information of building projects from design, construction to operation and maintenance through the establishment of digital three-dimensional models, providing data support and management capabilities for the entire life cycle. Compared with the traditional construction management model, BIM technology can more intuitively display the building structure and decoration effects, and realize dynamic monitoring of the construction process through real-time data association. Among various construction projects, the decoration projects of stadiums and gyms are particularly complex, involving construction coordination and precise management of different functional areas. Such projects usually include multiple areas such as auditoriums, main venues, and fitness equipment areas. The construction is difficult, the time requirements are strict, and the standards for visual effects and functional zoning are high. Therefore, BIM technology is greatly needed to ensure the accuracy of the construction progress and the consistency of the decoration effects.

[0003] In the specific decoration projects of stadiums and gyms, traditional construction management methods usually rely on manual data recording and regular progress reports, which have problems such as information lag, inaccurate construction progress, and unreasonable resource allocation. Especially in the face of complex construction environments and high-standard decoration requirements, there is a lack of automated data collection and analysis methods. For example, data such as workers' working hours and equipment utilization rates are often difficult to summarize and analyze in a timely manner, resulting in inaccurate assessments of construction intensity; at the same time, the influence of environmental factors such as temperature, humidity, and air quality is often ignored, and the adaptability of the construction environment is not effectively controlled. In addition, the lack of real-time monitoring of project resources leads to frequent material shortages or waste of resources, which affects the construction progress and overall quality. Under the traditional management model, there is often a large deviation between the actual progress of the construction project and the target progress. There is a lack of accurate progress warning mechanism, and it is impossible to detect and correct the deviation of the construction progress in time, which increases the risk of construction period. Summary of the invention

[0004] In view of the deficiencies in the prior art, the present invention provides a BIM-based building decoration project construction progress supervision system and method, which solves the problems mentioned in the background technology.

[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions: a BIM-based building decoration project construction progress supervision system, including a BIM model building module, a construction intensity data acquisition module, an environmental adaptability monitoring module, a resource input monitoring module, a construction progress prediction and analysis module and a report generation module;

[0006] The BIM model building module is responsible for the creation and maintenance of BIM models of stadiums and gyms. It generates a three-dimensional BIM model through the architectural design drawings of real venues and the detailed requirements of each construction area to display the building structure and decoration effects, and associate the construction progress with real-time data.

[0007] The construction intensity data collection module is used to collect and analyze construction intensity related data to reflect the construction intensity situation within a unit time, collect daily working hours, task completion and construction frequency data, automatically transmit them to the system, and calculate the construction intensity coefficient Sq in combination with the equipment utilization rate and the construction area progress rate;

[0008] The environmental adaptability monitoring module is used to collect construction environment data and analyze the impact of the environment on construction progress and efficiency, and calculate the environmental adaptability coefficient E adapt , which is convenient for judging whether the construction environment meets the progress requirements;

[0009] The resource input monitoring module is used to monitor the input of manpower, materials and equipment in real time to ensure the rational allocation of resources. in , ensure the effective use of construction resources in key areas and reduce resource waste;

[0010] The construction progress prediction and analysis module is used to analyze the deviation between the current construction progress and the target progress based on the BIM model and real-time data collection, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings by calculating the progress prediction index Jdyc;

[0011] The report generation module is used to integrate the data of each module and generate visual progress reports and analysis charts for reference by management.

[0012] Preferably, the BIM model building module includes a model creation unit, a construction area refinement unit and a data association unit;

[0013] The model creation unit is used to establish a three-dimensional BIM model based on the real venue architectural design drawings, including structural information of all construction areas, including auditoriums, main venues and equipment installation areas;

[0014] The construction area refinement unit is used to add the decoration effect and material property information to the model in combination with the detailed requirements of each construction area;

[0015] The data association unit is used to associate real-time construction data and progress information to ensure that the BIM model is updated synchronously with the on-site situation so that the model reflects the current construction status.

[0016] Preferably, the construction intensity data acquisition module includes a data acquisition unit;

[0017] The data collection unit is used to collect daily working hours, task completion and construction frequency data through the clock-in system, intelligent management platform and equipment monitoring system to obtain: worker working hours T work 、Single task completion amount V task , Construction area progress rate R area , Equipment utilization rate U equip and construction frequency F work , the collected construction intensity data is automatically uploaded to the system, and the construction intensity coefficient Sq is calculated based on the collected data;

[0018] The construction intensity coefficient Sq is calculated by the following formula:

[0019] ;

[0020] Where, T work represents the working hours of workers, V task Indicates the amount of completion of a single task, R area represents the construction area progress rate, U equip Indicates the equipment utilization rate, F work Indicates the construction frequency.

[0021] Preferably, the environmental adaptability monitoring module includes an environmental data acquisition unit;

[0022] The environmental data acquisition unit is used to collect environmental temperature, humidity, noise level, air quality and light intensity using temperature and humidity sensors, noise monitors and air quality detectors to obtain: environmental temperature T env 、Ambient humidity H env , Noise level N level , air quality index AQI and light intensity L intensity , clean and analyze the collected environmental data, and calculate the environmental adaptation coefficient E based on the environmental data adapt ;

[0023] The environmental adaptability coefficient E adapt Calculated by the following formula:

[0024] ;

[0025] Where, T env Indicates the ambient temperature, H env Indicates ambient humidity, N level represents noise level, AQI represents air quality index, L intensity Indicates light intensity.

[0026] Preferably, the resource input monitoring module includes a resource data acquisition unit;

[0027] The resource data collection unit is used to collect data on the number of workers, material inventory, and equipment operation rate, and obtain: the number of workers N workers 、Material inventory M stock , Equipment operation rate O equip , Equipment maintenance frequency F repair and material transport frequency F transport , real-time monitoring of resource consumption and allocation, automatic generation of key area resource allocation reports, and calculation of resource input coefficient R based on resource data in ;

[0028] The resource input coefficient R in Calculated by the following formula:

[0029] ;

[0030] Where N workers represents the number of workers, M stock Indicates the material inventory, O equip Indicates the equipment operation rate, F repair Indicates the frequency of equipment maintenance, F transport Indicates the material transportation frequency.

[0031] Preferably, the construction progress prediction and analysis module includes a data input unit, a construction progress warning unit and an automated progress analysis unit;

[0032] The data input unit is used to obtain the correlation coefficients of construction intensity, environmental adaptability and resource input, and import them into the BIM model to calculate the progress prediction index Jdyc;

[0033] The progress prediction index Jdyc is calculated by the following formula:

[0034] ;

[0035] In the formula, Sq represents the construction strength coefficient, E adapt Represents the environmental adaptability coefficient, R in Represents the resource input coefficient.

[0036] Preferably, the construction progress warning unit is used to compare the progress prediction index Jdyc with the preset standard threshold Z and the preset standard threshold X, to perform a graded evaluation on the execution of the construction progress, and then formulate a specific improvement strategy;

[0037] The progress prediction index Jdyc ≥ the preset standard threshold Z, and the first construction status level is obtained. The construction progress exceeds the expected progress by more than 20%, and no significant adjustment is required;

[0038] The preset standard threshold value X≤progress prediction index Jdyc<preset standard threshold value Z, and the second construction status level is obtained. The construction progress meets the standard, but there is a deviation and needs to be adjusted;

[0039] The progress prediction index Jdyc < the preset standard threshold X, and the third construction status level is obtained. The construction progress is more than 20% lower than the standard, there is a deviation, and immediate intervention measures are required.

[0040] Preferably, the automated progress analysis unit is used to perform real-time analysis on the difference between the actual progress and the planned progress, and provide automated deviation feedback.

[0041] Preferably, the report generation module includes a data integration unit and a visualization unit;

[0042] The data integration unit is used to integrate the real-time data of each module to ensure that the report information is comprehensive and accurate and to support subsequent data analysis and presentation;

[0043] The visualization unit is used to generate visual progress reports through charts, curves and 3D displays, so that the management can intuitively understand the construction progress and problems, and provide decision support for the management based on progress forecasts, deviation analysis and resource allocation suggestions.

[0044] The construction progress supervision method of building decoration engineering based on BIM includes the following steps:

[0045] Step 1: Responsible for the creation and maintenance of BIM models of sports venues and gyms. Through the architectural design drawings of real venues and the detailed requirements of each construction area, a three-dimensional BIM model is generated to display the building structure and decoration effects, and to associate the construction progress with real-time data;

[0046] Step 2: Collect and analyze construction intensity-related data to reflect the construction intensity within a unit of time. Collect daily working hours, task completion, and construction frequency data, and automatically transmit them to the system. Combined with equipment utilization rate and construction area progress rate, calculate the construction intensity coefficient Sq;

[0047] Step 3: Collect construction environment data and analyze the impact of the environment on construction progress and efficiency, and calculate the environmental adaptability coefficient E adapt , which is convenient for judging whether the construction environment meets the progress requirements;

[0048] Step 4: Real-time monitoring of the input of manpower, materials and equipment to ensure the rational allocation of resources, and calculate the resource input coefficient R in , ensure the effective use of construction resources in key areas and reduce resource waste;

[0049] Step 5: Based on the BIM model and real-time data collection, by calculating the progress prediction index Jdyc, analyze the deviation between the current construction progress and the target progress, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings;

[0050] Step 6: Integrate data from each module and generate visual progress reports and analysis charts for management reference.

[0051] The present invention provides a construction progress supervision system and method for building decoration engineering based on BIM, which has the following beneficial effects:

[0052] (1) When the system is running, it generates a three-dimensional BIM model through the architectural design drawings of the real venue and the detailed requirements of each construction area. It displays the building structure and decoration effect, associates the construction progress and real-time data, collects and analyzes the construction intensity related data, calculates the construction intensity coefficient Sq, collects the construction environment data and analyzes the impact of the environment on the construction progress and efficiency, calculates the environmental adaptability coefficient Eadapt, monitors the input of manpower, materials and equipment in real time, calculates the resource input coefficient Rin, calculates the progress prediction index Jdyc based on the BIM model and real-time data collection, analyzes the deviation between the current construction progress and the target progress, compares the actual progress with the planned progress, identifies potential progress deviations and gives early warnings, integrates the data of each module, and generates visual progress reports and analysis charts.

[0053] (2) The BIM-based construction progress supervision system for building decoration projects realizes all-round dynamic supervision of the decoration projects of stadiums and gyms through the collaborative work of the BIM model construction module, construction intensity data collection module, environmental adaptability monitoring module, resource input monitoring module, construction progress prediction and analysis module, and report generation module. First, the system constructs a three-dimensional venue model in the BIM model, and combines the construction status with real-time data to effectively display the structure and decoration progress of each area. The automated collection and analysis of core parameters such as construction intensity, environmental adaptability, and resource input help to achieve refined management of the construction process, ensure the rational allocation of various resources and the suitability of the construction environment, and effectively optimize construction efficiency and on-site management.

[0054] (3) Compared with traditional methods, the system significantly improves the real-time, accuracy and integration of construction data. Traditional construction management methods rely heavily on manual data recording and regular reporting, which results in information lag and data deviation. The BIM-based system can automatically collect and analyze key data through intelligent monitoring equipment, calculate the construction intensity coefficient, environmental adaptability coefficient and resource input coefficient, evaluate the difference between the construction progress and the planned progress in real time, dynamically adjust resource allocation, and achieve more efficient construction organization. Especially in complex stadium and gym decoration projects, the system can automatically generate early warnings based on real-time data and progress prediction index Jdyc, provide immediate deviation analysis and improvement suggestions, and ensure that the project is carried out within a reasonable progress range.

[0055] (4) The BIM-based construction progress supervision system has greatly improved the accuracy and response speed of project management through intelligent data collection, progress analysis and report generation, providing more scientific decision-making support for management. The application of this system not only enables dynamic supervision of the project throughout the entire process, reduces the risk of progress delays and resource waste, but also ensures the high quality and on-time delivery of the project, truly transforming the advantages of BIM technology into actual benefits in engineering project management. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] Figure 1 This is a block diagram of the construction progress supervision system of building decoration engineering based on BIM of the present invention;

[0057] Figure 2 It is a schematic diagram of the steps of the method for supervising the construction progress of building decoration engineering based on BIM of the present invention. DETAILED DESCRIPTION

[0058] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0059] Example 1

[0060] The present invention provides a construction progress supervision system for building decoration projects based on BIM. Figure 1 , including BIM model building module, construction intensity data collection module, environmental adaptability monitoring module, resource input monitoring module, construction progress prediction and analysis module and report generation module;

[0061] The BIM model building module is responsible for the creation and maintenance of BIM models of stadiums and gyms. It generates a three-dimensional BIM model through the architectural design drawings of real venues and the detailed requirements of each construction area to display the building structure and decoration effects, and associate the construction progress with real-time data.

[0062] The construction intensity data collection module is used to collect and analyze construction intensity related data to reflect the construction intensity situation within a unit time, collect daily working hours, task completion and construction frequency data, automatically transmit them to the system, and calculate the construction intensity coefficient Sq in combination with the equipment utilization rate and the construction area progress rate;

[0063] The environmental adaptability monitoring module is used to collect construction environment data and analyze the impact of the environment on construction progress and efficiency, and calculate the environmental adaptability coefficient E adapt , which is convenient for judging whether the construction environment meets the progress requirements;

[0064] The resource input monitoring module is used to monitor the input of manpower, materials and equipment in real time to ensure the rational allocation of resources. in , ensure the effective use of construction resources in key areas and reduce resource waste;

[0065] The construction progress prediction and analysis module is used to analyze the deviation between the current construction progress and the target progress based on the BIM model and real-time data collection, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings by calculating the progress prediction index Jdyc;

[0066] The report generation module is used to integrate the data of each module and generate visual progress reports and analysis charts for reference by management.

[0067] In this embodiment, a three-dimensional BIM model is generated through the architectural design drawings of the real venue, combined with the detailed requirements of each construction area, to display the building structure and decoration effect, associate the construction progress and real-time data, collect and analyze the construction intensity related data, calculate the construction intensity coefficient Sq, collect construction environment data and analyze the impact of the environment on the construction progress and efficiency, calculate the environmental adaptability coefficient Eadapt, monitor the input of manpower, materials and equipment in real time, calculate the resource input coefficient Rin, calculate the progress prediction index Jdyc based on the BIM model and real-time collected data, analyze the deviation between the current construction progress and the target progress, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings, integrate the data of each module, and generate visual progress reports and analysis charts.

[0068] Example 2

[0069] This embodiment is explained in Example 1, please refer to Figure 1 ,Specifically: the BIM model building module includes a model creation unit, a construction area refinement unit and a data association unit;

[0070] The model creation unit is used to establish a three-dimensional BIM model based on the real venue architectural design drawings, including structural information of all construction areas, including auditoriums, main venues and equipment installation areas;

[0071] The construction area refinement unit is used to add the decoration effect and material property information to the model in combination with the detailed requirements of each construction area;

[0072] The data association unit is used to associate real-time construction data and progress information to ensure that the BIM model is updated synchronously with the on-site situation so that the model reflects the current construction status.

[0073] In this embodiment, the BIM model construction module realizes the refined modeling and dynamic management of the decoration projects of stadiums and gyms through the collaborative work of the model creation unit, the construction area refinement unit and the data association unit, which has significant beneficial effects. First, the three-dimensional BIM model established by the model creation unit based on the real architectural design drawings can fully display the structural information of all construction areas, so that the construction party and management personnel can intuitively understand the overall structural layout in the virtual space; secondly, the construction area refinement unit adds the decorative effects and material properties of each area to the model to ensure that the model not only has structural information, but also contains the visual and quality details of the decoration and materials, providing strong support for accurate guidance of construction. In addition, the data association unit directly associates real-time construction data and progress information to the BIM model, so that the model can be updated synchronously with the construction process, reflecting the current construction status, facilitating the management to control the project progress in real time, and quickly identify and adjust construction deviations. This module greatly improves the efficiency, accuracy and management transparency of the decoration project, optimizes resource allocation, and ensures the reliability of the construction progress and the high-quality completion of the decoration effect.

[0074] Example 3

[0075] This embodiment is explained in Example 1, please refer to Figure 1 ,Specifically: the construction intensity data acquisition module includes a data acquisition unit;

[0076] The data collection unit is used to collect daily working hours, task completion and construction frequency data through the clock-in system, intelligent management platform and equipment monitoring system to obtain: worker working hours T work 、Single task completion amount V task , Construction area progress rate R area , Equipment utilization rate U equip and construction frequency F work, the collected construction intensity data is automatically uploaded to the system, and the construction intensity coefficient Sq is calculated based on the collected data;

[0077] The construction intensity coefficient Sq is calculated by the following formula:

[0078] ;

[0079] Where, T work represents the working hours of workers, V task Indicates the amount of completion of a single task, R area represents the construction area progress rate, U equip Indicates the equipment utilization rate, F work Indicates the construction frequency.

[0080] Worker working hours T work : Average daily working hours of workers (hours);

[0081] Single task completion amount V task : The amount of completion of a single task, reflecting the workload of the task;

[0082] Construction area progress rate R area : Construction area progress rate, that is, the proportion of construction that has been completed;

[0083] Equipment utilization rate U equip : Equipment utilization rate, which indicates the utilization rate of the equipment during the working cycle;

[0084] Construction frequency F work : Construction frequency, the number of construction times per day, indicating the construction density;

[0085] The environmental adaptability monitoring module includes an environmental data acquisition unit;

[0086] The environmental data acquisition unit is used to collect environmental temperature, humidity, noise level, air quality and light intensity using temperature and humidity sensors, noise monitors and air quality detectors to obtain: environmental temperature T env 、Ambient humidity H env , Noise level N level , air quality index AQI and light intensity L intensity , clean and analyze the collected environmental data, and calculate the environmental adaptation coefficient E based on the environmental data adapt ;

[0087] The environmental adaptability coefficient E adapt Calculated by the following formula:

[0088] ;

[0089] Where, Tenv Indicates the ambient temperature, H env Indicates ambient humidity, N level represents noise level, AQI represents air quality index, L intensity Indicates light intensity.

[0090] Ambient temperature T env : Ambient temperature (℃);

[0091] Optimum construction temperature T opt : The best construction temperature is 22℃ by default;

[0092] Ambient humidity H env : Ambient humidity (%);

[0093] Optimum construction humidity H opt : Optimal construction humidity (default 50%);

[0094] Noise level N level : noise level (dB);

[0095] Air Quality Index AQI: Air Quality Index;

[0096] Light intensity L intensity Light intensity (lux).

[0097] The resource input monitoring module includes a resource data acquisition unit;

[0098] The resource data collection unit is used to collect data on the number of workers, material inventory, and equipment operation rate, and obtain: the number of workers N workers 、Material inventory M stock , Equipment operation rate O equip , Equipment maintenance frequency F repair and material transport frequency F transport , real-time monitoring of resource consumption and allocation, automatic generation of key area resource allocation reports, and calculation of resource input coefficient R based on resource data in ;

[0099] Number of workers N workers : number of workers;

[0100] Material inventory M stock : Material inventory;

[0101] Equipment operation rate equip : Equipment operation rate, that is, the proportion of equipment operation time during the construction period;

[0102] Equipment maintenance frequency F repair : Equipment maintenance frequency, reflecting equipment stability;

[0103] Material transportation frequency F transport : Material transportation frequency, indicating the continuity of material supply;

[0104] The resource input coefficient R in Calculated by the following formula:

[0105] ;

[0106] Where N workers represents the number of workers, M stock Indicates the material inventory, O equip Indicates the equipment operation rate, F repair Indicates the frequency of equipment maintenance, F transport Indicates the material transportation frequency.

[0107] This formula multiplies each coefficient to comprehensively evaluate the impact of construction intensity, environmental conditions and resource input on the construction progress, and then calculates the construction progress prediction index. The larger the value, the more conducive the current construction conditions are to proceed as planned;

[0108] The construction progress prediction and analysis module includes a data input unit, a construction progress warning unit and an automated progress analysis unit;

[0109] The data input unit is used to obtain the correlation coefficients of construction intensity, environmental adaptability and resource input, and import them into the BIM model to calculate the progress prediction index Jdyc;

[0110] The progress prediction index Jdyc is calculated by the following formula:

[0111] ;

[0112] In the formula, Sq represents the construction strength coefficient, E adapt Represents the environmental adaptability coefficient, R in Represents the resource input coefficient.

[0113] In this embodiment, through the combination of the construction intensity data acquisition module, the environmental adaptability monitoring module, the resource input monitoring module and the construction progress prediction and analysis module, the system realizes comprehensive dynamic supervision of the construction progress, which has significant beneficial effects. First, the construction intensity data acquisition module accurately obtains data such as workers' working hours, task completion and equipment utilization rate through an automated data acquisition unit, ensuring the real-time calculation of the construction intensity coefficient Sq and effectively reflecting the construction intensity situation. Secondly, the environmental adaptability monitoring module uses a sensor network to collect parameters such as temperature and humidity, noise level and air quality of the construction environment, and calculates the environmental adaptability coefficient E. adapt, ensuring that the construction environment meets efficiency requirements, and helping to provide early warning or adjustment plans under adverse conditions. In addition, the resource input monitoring module can monitor the resource input status in real time, by generating resource allocation reports and calculating the resource input coefficient R in , optimize the reasonable allocation of manpower, materials and equipment, and avoid waste of resources. Finally, the construction progress prediction and analysis module integrates all the above coefficients, calculates the progress prediction index Jdyc, and issues a progress deviation warning. The system realizes intelligent management and dynamic feedback of the construction process, ensuring that the project is completed on schedule with high efficiency and quality, and providing a scientific decision-making basis for the management.

[0114] Example 4

[0115] This embodiment is explained in Example 1, please refer to Figure 1 Specifically: the construction progress warning unit is used to compare the progress prediction index Jdyc with the preset standard threshold Z and the preset standard threshold X, to perform a graded evaluation on the execution of the construction progress, and then formulate a specific improvement strategy;

[0116] The progress prediction index Jdyc ≥ the preset standard threshold Z, and the first construction status level is obtained. The construction progress exceeds the expected progress by more than 20%, and no significant adjustment is required. Since environmental factors may change over time, it is necessary to continuously monitor the temperature, humidity, noise and air quality of the construction environment to ensure that the environmental adaptability remains at a high level. For areas that are close to completion, the work standards can be appropriately improved and details can be polished, such as improving the decoration effect and improving the accuracy of equipment debugging, to ensure the overall project quality;

[0117] The preset standard threshold value X≤progress prediction index Jdyc<preset standard threshold value Z, and the second construction status level is obtained. The construction progress meets the standard, but there are deviations and adjustments are needed. For areas with slightly insufficient resource allocation, an appropriate number of construction personnel and material reserves can be added, and equipment maintenance can be ensured in time to avoid resource bottlenecks. The construction plan for inefficient areas can be fine-tuned, for example, the working hours of key nodes can be appropriately extended to ensure completion within the established construction period. For construction environments that do not meet the optimal conditions, temporary environmental control measures (such as installing mobile air conditioners or adding ventilation equipment) can be added to improve the comfort and efficiency of construction personnel;

[0118] The progress prediction index Jdyc < the preset standard threshold X, and the third construction status level is obtained. The construction progress is more than 20% lower than the standard, and there is a deviation. Immediate intervention measures are required to quickly deploy additional construction personnel and materials to key areas to ensure that key nodes are completed on time. At the same time, construction hours are increased, such as implementing a shift system, re-evaluating the construction task arrangement, optimizing the process and concentrating it on the delayed area, ensuring an increase in construction frequency and task completion, and directly improving the temperature, humidity and air quality in the construction area by using environmental control equipment (such as large air conditioners, dehumidifiers, etc.) to ensure the adaptability and comfort of the working environment of construction personnel.

[0119] The automated progress analysis unit is used to perform real-time analysis on the difference between the actual progress and the planned progress, and provide automated deviation feedback.

[0120] The report generation module includes a data integration unit and a visualization unit;

[0121] The data integration unit is used to integrate the real-time data of each module to ensure that the report information is comprehensive and accurate and to support subsequent data analysis and presentation;

[0122] The visualization unit is used to generate visual progress reports through charts, curves and 3D displays, so that the management can intuitively understand the construction progress and problems, and provide decision support for the management based on progress forecasts, deviation analysis and resource allocation suggestions.

[0123] In this embodiment, the design of the construction progress warning unit, the automated progress analysis unit and the report generation module enables the system to have efficient and accurate construction progress monitoring and feedback functions, which produces significant beneficial effects. Through the construction progress warning unit, the progress prediction index Jdyc is compared with the preset thresholds Z and X, and the system can grade and evaluate the construction status, and then automatically formulate corresponding improvement strategies: when the construction progress exceeds the expectation and does not need to be adjusted, the progress has a slight deviation and needs to be adjusted moderately, or the progress is significantly lower than the standard and needs immediate intervention, the management can obtain clear guidance plans to ensure that the project is advanced on schedule. The automated progress analysis unit further provides automated deviation feedback by real-time analysis of the difference between the actual progress and the planned progress, so that potential problems can be quickly discovered and corrected, significantly reducing the risks caused by construction delays. At the same time, the report generation module integrates the data of each module to form a comprehensive and accurate real-time report. Through the visualization unit, the management can intuitively understand the current construction progress, deviation and resource allocation suggestions through charts, curves and 3D models to ensure comprehensive control of the construction status. Overall, the system's progress warning, automatic analysis and visual display have greatly improved the accuracy and response speed of construction management, effectively ensuring the reliability of construction progress and the possibility of project completion on schedule.

[0124] Example 5

[0125] For the construction progress supervision method of building decoration engineering based on BIM, please refer to Figure 2 , specifically: including the following steps:

[0126] Step 1: Responsible for the creation and maintenance of BIM models of sports venues and gyms. Through the architectural design drawings of real venues and the detailed requirements of each construction area, a three-dimensional BIM model is generated to display the building structure and decoration effects, and to associate the construction progress with real-time data;

[0127] Step 2: Collect and analyze construction intensity-related data to reflect the construction intensity within a unit of time. Collect daily working hours, task completion, and construction frequency data, and automatically transmit them to the system. Combined with equipment utilization rate and construction area progress rate, calculate the construction intensity coefficient Sq;

[0128] Step 3: Collect construction environment data and analyze the impact of the environment on construction progress and efficiency, and calculate the environmental adaptability coefficient E adapt , which is convenient for judging whether the construction environment meets the progress requirements;

[0129] Step 4: Real-time monitoring of the input of manpower, materials and equipment to ensure the rational allocation of resources, and calculate the resource input coefficient R in , ensure the effective use of construction resources in key areas and reduce resource waste;

[0130] Step 5: Based on the BIM model and real-time data collection, by calculating the progress prediction index Jdyc, analyze the deviation between the current construction progress and the target progress, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings;

[0131] Step 6: Integrate data from each module and generate visual progress reports and analysis charts for management reference.

[0132] In this embodiment, the construction progress supervision system of building decoration engineering based on BIM has significant beneficial effects by implementing BIM model construction, data collection, progress analysis and visual reporting in steps. First, the three-dimensional BIM model established in step 1 is based on the real venue design drawings. It not only shows the building structure and decoration effect, but also dynamically associates the construction progress and real-time data, laying the foundation for subsequent monitoring and analysis. Secondly, through the real-time collection and coefficient calculation of construction intensity, environmental adaptability and resource input data achieved in steps 2 to 4, the system can dynamically evaluate various construction parameters, ensure construction efficiency, environmental adaptability and rationality of resource allocation, and help to keep the construction going smoothly and avoid waste of resources.

[0133] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. The construction progress supervision system of building decoration engineering based on BIM is characterized by: It includes BIM model building module, construction intensity data collection module, environmental adaptability monitoring module, resource input monitoring module, construction progress prediction and analysis module and report generation module; The BIM model building module is responsible for the creation and maintenance of BIM models of stadiums and gyms. It generates a three-dimensional BIM model through the architectural design drawings of real venues and the detailed requirements of each construction area to display the building structure and decoration effects, and associate the construction progress with real-time data. The construction intensity data collection module is used to collect and analyze construction intensity related data to reflect the construction intensity situation within a unit time, collect daily working hours, task completion and construction frequency data, automatically transmit them to the system, and calculate the construction intensity coefficient Sq in combination with the equipment utilization rate and the construction area progress rate; The environmental adaptability monitoring module is used to collect construction environment data and analyze the impact of the environment on construction progress and efficiency, and calculate the environmental adaptability coefficient E adapt , which is convenient for judging whether the construction environment meets the progress requirements; The resource input monitoring module is used to monitor the input of manpower, materials and equipment in real time to ensure the rational allocation of resources. in , ensure the effective use of construction resources in key areas and reduce resource waste; The construction progress prediction and analysis module is used to analyze the deviation between the current construction progress and the target progress based on the BIM model and real-time data collection, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings by calculating the progress prediction index Jdyc; The report generation module is used to integrate the data of each module and generate visual progress reports and analysis charts for reference by the management; The BIM model construction module includes a model creation unit, a construction area refinement unit and a data association unit; The model creation unit is used to establish a three-dimensional BIM model based on the real venue architectural design drawings, including structural information of all construction areas, including auditoriums, main venues and equipment installation areas; The construction area refinement unit is used to add the decoration effect and material property information to the model in combination with the detailed requirements of each construction area; The data association unit is used to associate real-time construction data and progress information to ensure that the BIM model is updated synchronously with the on-site situation so that the model reflects the current construction status; The construction intensity data acquisition module includes a data acquisition unit; The data collection unit is used to collect daily working hours, task completion and construction frequency data through the clock-in system, intelligent management platform and equipment monitoring system to obtain: worker working hours T work 、Single task completion amount V task , Construction area progress rate R area , Equipment utilization rate U equip and construction frequency F work , the collected construction intensity data is automatically uploaded to the system, and the construction intensity coefficient Sq is calculated based on the collected data; The construction intensity coefficient Sq is calculated by the following formula: ; Where, T work represents the working hours of workers, V task Indicates the amount of completion of a single task, R area represents the construction area progress rate, U equip Indicates the equipment utilization rate, F work Indicates the construction frequency; The environmental adaptability monitoring module includes an environmental data acquisition unit; The environmental data acquisition unit is used to collect environmental temperature, humidity, noise level, air quality and light intensity using temperature and humidity sensors, noise monitors and air quality detectors to obtain: environmental temperature T env 、Ambient humidity H env , Noise level N level , air quality index AQI and light intensity L intensity , clean and analyze the collected environmental data, and calculate the environmental adaptation coefficient E based on the environmental data adapt ; The environmental adaptability coefficient E adapt Calculated by the following formula: ; Where, T env Indicates the ambient temperature, H env Indicates ambient humidity, N level represents noise level, AQI represents air quality index, L intensity Represents the light intensity, T opt Indicates the best construction temperature, H opt Indicates the best construction humidity; The resource input monitoring module includes a resource data acquisition unit; The resource data collection unit is used to collect data on the number of workers, material inventory, and equipment operation rate, and obtain: the number of workers N workers 、Material inventory M stock , Equipment operation rate O equip , Equipment maintenance frequency F repair and material transport frequency F transport , real-time monitoring of resource consumption and allocation, automatic generation of key area resource allocation reports, and calculation of resource input coefficient R based on resource data in ; The resource input coefficient R in Calculated by the following formula: ; Where N workers represents the number of workers, M stock Indicates the material inventory, O equip Indicates the equipment operation rate, F repair Indicates the frequency of equipment maintenance, F transport Indicates the frequency of material transportation; The construction progress prediction and analysis module includes a data input unit, a construction progress warning unit and an automated progress analysis unit; The data input unit is used to obtain the correlation coefficients of construction intensity, environmental adaptability and resource input, and import them into the BIM model to calculate the progress prediction index Jdyc; The progress prediction index Jdyc is calculated by the following formula: ; In the formula, Sq represents the construction strength coefficient, E adapt Represents the environmental adaptability coefficient, R in Represents the resource input coefficient.

2. The BIM-based building decoration project construction progress supervision system according to claim 1 is characterized by: The construction progress warning unit is used to compare the progress prediction index Jdyc with the preset standard threshold Z and the preset standard threshold X, to perform a graded evaluation on the execution of the construction progress, and then formulate a specific improvement strategy; The progress prediction index Jdyc ≥ the preset standard threshold Z, and the first construction status level is obtained. The construction progress exceeds the expected progress by more than 20%, and no significant adjustment is required; The preset standard threshold value X≤progress prediction index Jdyc<preset standard threshold value Z, and the second construction status level is obtained. The construction progress meets the standard, but there is a deviation and needs to be adjusted; The progress prediction index Jdyc < the preset standard threshold X, and the third construction status level is obtained. The construction progress is more than 20% lower than the standard, there is a deviation, and immediate intervention measures are required.

3. The BIM-based building decoration project construction progress supervision system according to claim 1 is characterized by: The automated progress analysis unit is used to perform real-time analysis on the difference between the actual progress and the planned progress, and provide automated deviation feedback.

4. The BIM-based building decoration project construction progress supervision system according to claim 1 is characterized by: The report generation module includes a data integration unit and a visualization unit; The data integration unit is used to integrate the real-time data of each module to ensure that the report information is comprehensive and accurate and to support subsequent data analysis and presentation; The visualization unit is used to generate visual progress reports through charts, curves and 3D displays, so that the management can intuitively understand the construction progress and problems, and provide decision support for the management based on progress forecasts, deviation analysis and resource allocation suggestions.

5. A method for supervising the construction progress of a building decoration project based on BIM, applied to a system for supervising the construction progress of a building decoration project based on BIM as claimed in any one of claims 1 to 4, characterized in that: The following steps are involved: Step 1: Creation and maintenance of BIM models of sports venues and gyms. Through the architectural design drawings of real venues and the detailed requirements of each construction area, a three-dimensional BIM model is generated to display the building structure and decoration effects, and to associate the construction progress with real-time data; Step 2: Collect and analyze construction intensity-related data to reflect the construction intensity within a unit of time. Collect daily working hours, task completion, and construction frequency data, and automatically transmit them to the system. Combined with equipment utilization rate and construction area progress rate, calculate the construction intensity coefficient Sq; Step 3: Collect construction environment data and analyze the impact of the environment on construction progress and efficiency, and calculate the environmental adaptability coefficient E adapt , which is convenient for judging whether the construction environment meets the progress requirements; Step 4: Real-time monitoring of the input of manpower, materials and equipment to ensure the rational allocation of resources, and calculate the resource input coefficient R in , ensure the effective use of construction resources in key areas and reduce resource waste; Step 5: Based on the BIM model and real-time data collection, by calculating the progress prediction index Jdyc, analyze the deviation between the current construction progress and the target progress, compare the actual progress with the planned progress, identify potential progress deviations and give early warnings; Step 6: Integrate data from each module and generate visual progress reports and analysis charts for management reference.