Ground solidifying device for building construction
By using a combination of vibration, reinforcement, extrusion and fixing devices in construction, the problems of loose foundation and water overflow are solved, the foundation stability and construction quality are improved, and the construction process is simplified.
Patent Information
- Application Number
- CN202411730263.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-29
- Publication Date
- 2025-01-10
AI Technical Summary
During the foundation curing process in traditional construction, the gravel or sand and gravel structure is loose, the strength is low, and the soil moisture content is high, a large amount of water will overflow during the vibration process, affecting the construction quality and subsequent floor hardening.
Design a floor curing device including vibration, reinforcement, extrusion and fixing devices. By installing a reinforcement device on the vibrator, the extrusion device extrudes the inner wall of the pothole, and extracts the excess through the fixing device. Water is collected by using a water collecting device.
Improve foundation stability and construction quality, avoid ground mud, and simplify subsequent ground hardening construction process.
Smart Images

Figure CN119287868A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, in particular to a ground solidifying device for building construction. Background Art
[0002] During the construction process, the ground surface needs to be solidified to increase the stability of the upper buildings. Loose foundation soil will reduce its bearing capacity, causing building settlement and structural damage, which will not only increase the difficulty of construction, but also cause greater safety hazards. Therefore, it is necessary to strengthen the foundation before construction to reduce the probability of the above situation. In traditional reinforcement technology, vibration, impact or water flushing are used to make holes in the foundation, and crushed stone or sand and gravel are filled to form a dense pile body, which forms a composite foundation with the original foundation soil to enhance the foundation strength. However, the structure of crushed stone or sand and gravel is loose and the strength is low. If the water content in the soil is high, a large amount of water will overflow during the vibration process, affecting the construction quality. Water overflows on the ground, causing the ground soil to be muddy, affecting the subsequent ground hardening construction. Summary of the invention
[0003] In order to overcome the shortcomings of the background technology, the present invention discloses a ground solidifying device for construction. The present invention arranges a reinforcing device, an extruding device and a fixing device on a vibrating device, and arranges a water collecting device on the fixing device, so as to achieve the purpose of solidifying the ground in the construction area and draining excess moisture.
[0004] In order to achieve the above-mentioned object of the invention, the present invention adopts the following technical scheme: A ground solidification device for construction includes a vibration device, a reinforcement device, an extrusion device, a fixing device and a water collection device. The vibration device is composed of a vibrator and a limit ring. The limit ring is distributed on the side of the vibrator. The reinforcement device is arranged in the vibrator. The reinforcement device runs through the vibrator and injects polyurethane foaming agent into the gravel of the ground pit. The extrusion device is installed on the side of the vibrator and is placed in the pit by the vibrator. The extrusion device squeezes the inner wall of the pit. The fixing device is composed of two symmetrically arranged shells. The lower end surfaces of the two shells are provided with insertion rods, which are inserted into the ground. Water collection devices are arranged on the shells on both sides. The water collection devices are used to discharge the seepage water generated after the soil is squeezed.
[0005] The vibrator is provided with a through hole, the reinforcement device is arranged in the through hole of the vibrator, the limiting rings are equidistantly distributed in an annular manner on the side of the lower end of the vibrator, each limiting ring is provided with an extrusion device, and the lower end of the extrusion device is arranged in the corresponding limiting ring.
[0006] The reinforcement device comprises a fixed tube, the lower end of which is sealed and provided with spikes, the side of which is provided with discharge holes, the side of which is provided with a block, and the block abuts against the inner wall of the through hole of the vibrator.
[0007] A coaxial injection pipe is arranged inside the fixed pipe, the injection pipe is threadedly connected with the fixed pipe, and the upper end of the injection pipe passes through the upper end of the fixed pipe.
[0008] The extrusion device comprises arc-shaped pressing plates, each of which is distributed in a ring around the axis of the vibrator, the lower end of the pressing plate is arranged in the corresponding limiting ring, and the convex surface of the pressing plate abuts against the inner wall of the limiting ring.
[0009] A connecting groove is arranged at the lower end of the pressing plate, and a supporting plate rotatably connected thereto is arranged in the connecting groove.
[0010] The shell is a hollow structure, with a slot provided at one end of the shell near the vibrator, the vibrator is arranged in the two slots, the shell is provided with through holes penetrating its upper end face and lower end face, and each through hole is provided with a water collecting device.
[0011] A fixing ring is distributed on the upper end surface of the shell, the fixing ring is arranged corresponding to the through hole, the fixing ring is communicated with the corresponding through hole, and a reinforcing rib is distributed on the lower end surface of the shell.
[0012] The lower end surface of the shell is provided with water absorption holes, which are connected to the cavity of the shell. A drainage pipe is provided on the side of the shell, one end of the drainage pipe is connected to the cavity of the shell, and the other end of the drainage pipe is connected to a water pump. Longitudinally arranged support rods are distributed in the shell, and the two ends of the support rods are respectively connected to the top surface and the bottom surface of the inner wall of the shell.
[0013] The water collecting device comprises a water collecting pipe, the lower end of which is blocked, a spike is arranged at the lower end of the water collecting pipe, a perforation passes through the lower end of the water collecting pipe, water inlet holes are distributed on the side of the water collecting pipe, and a filter is arranged in each water inlet hole.
[0014] The ground solidification device for construction described in the present invention is highly practical and very convenient to use. By arranging the solidification device on the vibrator, after the pit is filled, a polyurethane foaming agent is injected into the gaps between the stones to solidify the loose stones and enhance the stability of the foundation; by arranging the extrusion device, the inner wall of the pit is squeezed to make excess water flow away from the pit, which is convenient for collection by the water collection device; by arranging the fixing device, it is convenient to put the stone into the pit while extracting excess water from the surface, so as to avoid muddy ground and facilitate the later ground hardening construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention; Figure 2 is a cross-sectional view of a curing device of the present invention; Figure 3 It is a side view of the extrusion device of the present invention; Figure 4 It is a schematic diagram of the three-dimensional structure of the fixing device of the present invention; Figure 5is a cross-sectional view of the fixing device of the present invention; In the figure: 1. vibration device; 101. vibrator; 102. limit ring; 2. reinforcement device; 201. fixing pipe; 202. discharge hole; 203. injection pipe; 204. clamping block; 3. extrusion device; 301. pressing plate; 302. connecting groove; 303. support plate; 4. fixing device; 401. shell; 402. clamping groove; 403. perforation; 404. fixing ring; 405. drain pipe; 406. insertion rod; 407. water absorption hole; 408. support rod; 409. reinforcing rib; 5. water collecting device; 501. water collecting pipe; 502. water inlet hole; 503. filter screen. DETAILED DESCRIPTION
[0016] The present invention can be explained in detail by the following examples, and the purpose of disclosing the present invention is to protect all technical improvements within the scope of the present invention.
[0017] Combined with Figures 1 to 5 A ground solidification device for construction includes a vibration device 1, a reinforcement device 2, an extrusion device 3, a fixing device 4 and a water collection device 5. The vibration device 1 is composed of a vibrator 101 and a limit ring 102. The limit ring 102 is distributed on the side of the vibrator 101. The vibrator 101 is provided with a reinforcement device 2, which penetrates the vibrator 101 and injects polyurethane foaming agent into the gravel of a ground pit. The extrusion device 3 is installed on the side of the vibrator 101 and is placed in the pit by the vibrator 101. The extrusion device 3 squeezes the inner wall of the pit. The fixing device 4 is composed of two symmetrically arranged shells 401. The lower end surfaces of the two shells 401 are provided with insertion rods 406, and the insertion rods 406 are inserted into the ground. Water collection devices 5 are provided on the shells 401 on both sides. The water collection devices 5 are used to discharge the seepage water generated after the soil is squeezed, thereby improving the ground solidification speed and the construction quality.
[0018] The vibrator 101 is provided with a through hole, the reinforcement device 2 is arranged in the through hole of the vibrator 101, and the limiting rings 102 are equidistantly distributed in a ring shape on the side of the lower end of the vibrator 101. Each limiting ring 102 is provided with an extrusion device 3, and the lower end of the extrusion device 3 is arranged in the corresponding limiting ring 102. After the extrusion device 3 moves with the vibrator 101, it is fixedly installed at the bottom of the pit.
[0019] The reinforcement device 2 includes a fixed pipe 201, the lower end of which is blocked, a spike is provided at the lower end of the fixed pipe 201, a discharge hole 202 is distributed on the side of the fixed pipe 201, a block 204 is distributed on the side of the lower end of the fixed pipe 201, and the block 204 abuts against the inner wall of the through hole of the vibrator 101. After the bottom of the vibrator 101 reaches the hard soil layer of the soil, the fixed pipe 201 is separated from the vibrator 101, and the fixed pipe 201 is installed at the bottom of the pit after the gravel is filled.
[0020] A coaxial injection pipe 203 is provided in the fixed pipe 201, and the injection pipe 203 is threadedly connected to the fixed pipe 201. The upper end of the injection pipe 203 passes through the upper end of the fixed pipe 201. The polyurethane foam is injected into the fixed pipe 201 through the injection pipe 203 and seeps into the gaps between the stones through the discharge hole 202 to fix the stones. After the polyurethane foam expands, it diffuses outward and squeezes the outer pressure plate 301.
[0021] The extrusion device 3 includes arc-shaped pressing plates 301 , each of which is distributed in a ring around the axis of the vibrator 101 . The lower end of the pressing plate 301 is arranged in the corresponding limiting ring 102 , and the convex surface of the pressing plate 301 abuts against the inner wall of the limiting ring 102 .
[0022] The lower end of the pressure plate 301 is provided with a connecting groove 302, and a supporting plate 303 rotatably connected thereto is provided in the connecting groove 302. After the supporting plate 303 passes through the limiting ring 102, the supporting plate 303 is unfolded in the connecting groove 302, and the stone is pressed on the supporting plate 303 to fix the pressure plate 301 at the bottom of the pit.
[0023] The shell 401 is a hollow structure. A slot 402 is provided at one end of the shell 401 close to the vibrator 101. The vibrator 101 is arranged in the two slots 402. The shell 401 is provided with a through hole 403 passing through its upper end surface and lower end surface. A water collecting device 5 is provided in each through hole 403.
[0024] The upper end surface of the shell 401 is provided with a fixing ring 404, which is arranged corresponding to the through hole 403. The fixing ring 404 increases the strength of the upper end surface of the shell 401, and facilitates the water collecting pipe 501 to pass through the through hole 403. The fixing ring 404 is connected with the corresponding through hole 403. The lower end surface of the shell 401 is provided with a reinforcing rib 409, which increases the strength of the shell 401.
[0025] The lower end surface of the shell 401 is provided with water absorption holes 407, which are connected to the cavity of the shell 401. A drainage pipe 405 is provided on the side of the shell 401, one end of the drainage pipe 405 is connected to the cavity of the shell 401, and the other end of the drainage pipe 405 is connected to a pump. Excess moisture on the ground enters the shell 401 from the water absorption holes 407 and is discharged through the drainage pipe 405 for unified discharge, thereby avoiding muddy ground at the construction site, facilitating later ground solidification, and facilitating later superstructure construction. Longitudinally arranged support rods 408 are distributed in the shell 401, and the two ends of the support rods 408 are respectively connected to the top surface and the bottom surface of the inner wall of the shell 401.
[0026] The water collecting device 5 includes a water collecting pipe 501, the lower end of which is blocked, a spike is provided at the lower end of the water collecting pipe 501, the lower end of the water collecting pipe 501 passes through the perforation 403, and water inlet holes 502 are distributed on the side of the water collecting pipe 501. A filter screen 503 is provided in each water inlet hole 502. After the soil is squeezed, excess water enters the water collecting pipe 501 through the water inlet hole 502. The filter screen 503 prevents excessively large particles from entering the water collecting pipe 501 to form a blockage, and the excess water is discharged from the water collecting pipe 501 through a pump.
[0027] The ground solidification device for construction described in the embodiment is used. When in use, each pressing plate 301 is installed in the limiting ring 102, and the fixing pipe is installed in the vibrator 101. The vibrator 101 is lifted by a crane and a hole is made on the ground. After the end of the vibrator 101 enters the soil, the shell 401 is installed on the vibrator 101, and the insertion rod 406 is inserted into the ground, and the pump is connected to the drainage pipe 405. The vibrator 101 penetrates into the soil layer to bring the pressing plate 301 into the hole. The bottom of the pit is reached, and the vibrator 101 vibrates to compact the side soil layer to improve the soil structure. After the bottom of the vibrator 101 reaches the hard soil layer, the vibrator 101 is pulled upward while filling the pit with crushed stones. Then, the pressing plate 301 and the fixing pipe 201 are pressed downward to separate them from the limiting ring 102. After the support plate 303 passes through the limiting ring 102, the support plate 303 is unfolded in the connecting groove 302, and the stone is pressed on the support plate 303 to fix the pressing plate 301 at the bottom of the pit. The lower end of the fixing rod 201 is fixed by the stone. After the gravel is filled, the pump is turned on, and then the excess water enters the shell 401 from the water absorption hole 407, and is discharged through the drainage pipe 405 for unified discharge, so as to avoid muddy ground at the construction site, facilitate the later ground solidification, and facilitate the later superstructure construction. The excess water on the surface is collected by pressing the water collection pipe 501 into the soil layer through the perforation 403, and the injection pipe 203 is inserted into the bottom of the fixed pipe 201. Inject polyurethane foam, which seeps out through the discharge hole 202 into the gaps between the stones to fix the stones. After the polyurethane foam expands, it spreads outward to squeeze the outer pressure plate 301, and slowly pulls the injection pipe 203 upward to allow the polyurethane foam to fully enter the gaps between the stones. After the soil is squeezed, excess water enters the water collection pipe 501 through the water inlet hole 502. The filter 503 prevents oversized particles from entering the water collection pipe 501 to form a blockage, and the water is discharged from the water collection pipe 501 through the pump. The parts of the present invention that are not described in detail are prior art. Although the present invention is specifically demonstrated and introduced in conjunction with the preferred implementation scheme, there are many methods and approaches to specifically implement the technical solution. The above is only a preferred implementation scheme of the present invention, but technical personnel in the relevant field should understand that various changes can be made to the present invention in form and details without departing from the spirit and scope of the present invention as defined in the attached claims, and all of them are within the scope of protection of the present invention.
Claims
1. A ground solidification device for construction, comprising a vibration device (1), a reinforcement device (2), an extrusion device (3), a fixing device (4) and a water collecting device (5), wherein the vibration device (1) is composed of a vibrator (101) and a limit ring (102), and is characterized in that: A limit ring (102) is distributed on the side of the vibrator (101). A reinforcement device (2) is provided inside the vibrator (101). The reinforcement device (2) penetrates the vibrator (101) and injects polyurethane foaming agent into the gravel in the pit on the ground. The extrusion device (3) is installed on the side of the vibrator (101) and is placed in the pit by the vibrator (101). The extrusion device (3) extrude the inner wall of the pit. The fixing device (4) is composed of two symmetrically arranged shells (401). The lower end surfaces of the two shells (401) are provided with insertion rods (406). The insertion rods (406) are inserted into the ground. Water collection devices (5) are provided on the shells (401) on both sides. The water collection devices (5) are used to discharge seepage water generated after the soil is squeezed.
2. The ground solidification device for construction according to claim 1, characterized in that: The vibrator (101) is provided with a through hole, the reinforcement device (2) is arranged in the through hole of the vibrator (101), the limiting rings (102) are equidistantly distributed in an annular manner on the side of the lower end of the vibrator (101), each limiting ring (102) is provided with an extrusion device (3), and the lower end of the extrusion device (3) is arranged in the corresponding limiting ring (102).
3. The ground solidification device for construction according to claim 2, characterized in that: The reinforcement device (2) comprises a fixed tube (201), the lower end of the fixed tube (201) is blocked, the lower end of the fixed tube (201) is provided with spikes, the side of the fixed tube (201) is provided with a discharge hole (202), the side of the lower end of the fixed tube (201) is provided with a clamping block (204), and the clamping block (204) abuts against the inner wall of the through hole of the vibrator (101).
4. The ground solidification device for construction according to claim 3, characterized in that: A coaxial injection pipe (203) is arranged inside the fixed pipe (201); the injection pipe (203) is threadedly connected to the fixed pipe (201); and the upper end of the injection pipe (203) passes through the upper end of the fixed pipe (201).
5. The ground solidification device for construction according to claim 2, characterized in that: The extrusion device (3) comprises a pressing plate (301) of an arc-shaped structure, each pressing plate (301) being distributed in a ring shape with the axis of the vibrator (101) as the center, the lower end of the pressing plate (301) being arranged in a corresponding limiting ring (102), and the convex surface of the pressing plate (301) abutting against the inner wall of the limiting ring (102).
6. The ground solidification device for construction according to claim 5, characterized in that: A connecting groove (302) is provided at the lower end of the pressing plate (301), and a supporting plate (303) rotatably connected thereto is provided in the connecting groove (302).
7. The ground solidification device for construction according to claim 1, characterized in that: The shell (401) is a hollow structure. A slot (402) is provided at one end of the shell (401) close to the vibrator (101). The vibrator (101) is arranged in the two slots (402). The shell (401) is provided with a through hole (403) penetrating the upper end surface and the lower end surface thereof. A water collecting device (5) is provided in each through hole (403).
8. The ground solidification device for construction according to claim 7, characterized in that: A fixing ring (404) is distributed on the upper end surface of the shell (401), the fixing ring (404) is arranged corresponding to the through hole (403), the fixing ring (404) is connected to the corresponding through hole (403), and a reinforcing rib (409) is distributed on the lower end surface of the shell (401).
9. The ground solidification device for construction according to claim 8, characterized in that: The lower end surface of the shell (401) is provided with water absorption holes (407), which are connected to the cavity of the shell (401). A drainage pipe (405) is provided on the side of the shell (401), one end of the drainage pipe (405) is connected to the cavity of the shell (401), and the other end of the drainage pipe (405) is connected to a water pump. A longitudinally arranged support rod (408) is distributed in the shell (401), and the two ends of the support rod (408) are respectively connected to the top surface and the bottom surface of the inner wall of the shell (401).
10. The ground solidification device for construction according to claim 7, characterized in that: The water collecting device (5) comprises a water collecting pipe (501), the lower end of the water collecting pipe (501) is blocked, a spike is provided at the lower end of the water collecting pipe (501), the lower end of the water collecting pipe (501) passes through a perforation (403), water inlet holes (502) are distributed on the side of the water collecting pipe (501), and a filter screen (503) is provided in each water inlet hole (502).