Zero-carbon tunnel design device and method based on life cycle theory
Through the zero-carbon tunnel design device and method based on the full-life cycle theory, the carbon emissions in the tunnel construction and operation and maintenance stages are calculated and optimized, combined with carbon offset measures, a zero-carbon tunnel optimization design scheme for the full-life cycle is generated, and the tunnel is solved The carbon emission problem has achieved the goal of zero carbon emissions.
Patent Information
- Application Number
- CN202411446824.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-16
- Publication Date
- 2025-02-11
AI Technical Summary
The existing technology has not yet formed a systematic standard system for tunnel carbon emissions, and no scholars have proposed a complete definition, model and implementation method of 'zero carbon tunnel'. How to design zero carbon tunnels based on the full life cycle theory is an urgent need. The problem solved.
Provide a zero-carbon tunnel design device and method based on full life cycle theory. By calculating the carbon emissions in the tunnel construction and operation and maintenance stages, and combining carbon offset measures, relevant parameters are optimized to generate zero-carbon tunnel optimization for full life cycle. Design plan.
The design scheme for optimizing the design based on the carbon emissions of the tunnel's entire life cycle and generating zero-carbon tunnels has been achieved, solving the problem of tunnel carbon emissions and achieving the goal of zero-carbon emissions.
Smart Images

Figure CN119416311A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a tunnel design method, and in particular to a zero-carbon tunnel design device and method based on full life cycle theory. Background Art
[0002] With the rapid development of highway construction, the scale of highway tunnels has continued to expand and the number of tunnels has continued to rise. The energy consumption and greenhouse gas emissions generated by these tunnels during construction and operation have become an environmental issue that cannot be ignored. Studies have shown that the carbon emissions per kilometer of tunnel sections are usually 4-5 times that of open sections. The large-scale construction of tunnels not only consumes a lot of resources, but also causes significant carbon emissions.
[0003] At present, the research on tunnel carbon emissions is still in its infancy, and a systematic standard system for tunnel carbon emissions has not yet been formed. It is generally believed internationally that making full use of renewable energy and carbon sinks in and around the building site, combined with a carbon offset mechanism, so that the total carbon emissions are less than or equal to zero can be called zero carbon. "Zero carbon tunnel" is the "ultimate goal" of tunnel carbon emission control at present, but no scholar has yet proposed a complete definition, model and implementation method of "zero carbon tunnel".
[0004] Therefore, how to design a zero-carbon tunnel based on the full life cycle theory is an urgent problem to be solved. Summary of the invention
[0005] The present invention is made to solve the above-mentioned problems, and aims to provide a zero-carbon tunnel design device and method based on the full life cycle theory.
[0006] The invention provides a zero-carbon tunnel design device based on the full life cycle theory, which is used for generating a zero-carbon tunnel optimization design scheme according to tunnel construction data, tunnel operation and maintenance data and carbon offset measures data, and has the following characteristics, including: a carbon emission calculation module in the construction stage, which is used for calculating the total carbon emission in the tunnel construction stage according to the tunnel construction data; a carbon emission calculation module in the operation and maintenance stage, which is used for calculating the total carbon emission in the tunnel operation and maintenance stage according to the tunnel operation and maintenance data and the carbon offset measures data; a judgment module, which is used for judging whether the sum of the total carbon emission in the tunnel construction stage and the total carbon emission in the tunnel operation and maintenance stage is less than or equal to zero; a parameter optimization module, which is used for optimizing the tunnel construction data, the tunnel operation and maintenance data and the carbon offset measures data; a control module, which is used for controlling the operation of the carbon emission calculation module in the construction stage, the carbon emission calculation module in the operation and maintenance stage, the judgment module and the parameter optimization module, and optimizing the tunnel construction data, the tunnel operation and maintenance data and the carbon offset measures data until the sum of the total carbon emission in the tunnel construction stage and the total carbon emission in the tunnel operation and maintenance stage is less than or equal to zero, and then the optimized tunnel construction data, the tunnel operation and maintenance data and the carbon offset measures data are used as the zero-carbon tunnel optimization design scheme.
[0007] In the zero-carbon tunnel design device based on the full life cycle theory provided by the present invention, it can also have the following features: wherein the tunnel construction data includes the total number of building material types, the consumption of each type of building material, the total number of transportation methods, the distance generated by each type of building material and each type of transportation, the total number of energy types and the consumption of each type of energy, and the calculation expression of the total carbon emission in the tunnel construction stage is: C C =C CM +C CT +C CC ,
[0008] Where C C is the total carbon emission during the tunnel construction phase, a is the total number of building materials, U i is the consumption of the i-th building material, is the loss rate of the i-th building material, F i is the carbon emission factor of the i-th building material production stage, b is the total number of transportation modes, D i,j is the distance generated by transporting the i-th building material using the j-th mode of transportation, F j is the carbon emission factor per unit weight of transportation distance under the jth mode of transportation, c is the total number of energy types, Q i is the consumption of the i-th energy source, F i1 is the carbon emission factor of the i-th energy production process, F i2is the carbon emission factor of the i-th energy use process.
[0009] In the zero-carbon tunnel design device based on the full life cycle theory provided by the present invention, it can also have the following characteristics: wherein, the tunnel operation and maintenance data include tunnel operation sub-data and tunnel maintenance sub-data, and the carbon emission calculation module in the operation and maintenance stage includes: an operation stage carbon emission calculation unit, which is used to calculate the carbon emissions in the tunnel operation stage according to the tunnel operation sub-data; a maintenance stage carbon emission calculation unit, which is used to calculate the carbon emissions in the tunnel maintenance stage according to the tunnel maintenance sub-data; a carbon offset calculation unit, which is used to calculate the carbon offset in the tunnel site according to the carbon offset measures data; and a total amount calculation unit, which is used to calculate the total amount of carbon emissions in the tunnel operation and maintenance stage according to the carbon emissions in the tunnel operation stage, the carbon emissions in the tunnel maintenance stage and the carbon offset in the tunnel site.
[0010] In the zero-carbon tunnel design device based on the full life cycle theory provided by the present invention, there may also be such a feature: wherein the tunnel operation sub-data includes the total number of lamp types, the number of each type of lamps, the lighting time of each type of lamps, the total number of fan types, the number of each type of fans and the operating time of each type of fans, and the calculation expression of the carbon emissions in the tunnel operation stage is: Where C OO is the carbon emission during the tunnel operation phase, d is the total number of lamp types, n Li is the number of the i-th type of lamps, P Li is the power of the i-th lamp, t Li is the lighting time of the i-th lamp, e is the total number of fan types, n Vj is the number of the j-th type of fans, P Vj is the power of the j-th fan, t Vj is the operating time of the jth fan, and F is the carbon emission factor.
[0011] In the zero-carbon tunnel design device based on the full life cycle theory provided by the present invention, there may also be such a feature: wherein the tunnel maintenance sub-data includes the number of major repairs, the number of minor repairs, the total number of building material types, the consumption of each type of building material, the total number of transportation methods and the distance generated by each type of transportation of each type of building material, and the calculation expression of the carbon emission in the tunnel maintenance stage is:
[0012] Where C OM is the carbon emission during the tunnel maintenance phase, L is the number of major repairs, d is the total number of building materials, and U i is the consumption of the i-th building material, the loss rate of the i-th building material, F iis the carbon emission factor of the i-th building material production stage, e is the total number of transportation modes, D j is the distance generated by transporting the i-th building material using the j-th mode of transportation, F j is the carbon emission factor per unit weight of transportation distance under the jth mode of transportation, S is the number of minor repairs, f is the total number of maintenance types, E k is the maintenance energy consumption, F k is the carbon emission factor.
[0013] In the zero-carbon tunnel design device based on the full life cycle theory provided by the present invention, it can also have the following features: wherein the carbon offset measure data includes the annual solar radiation illumination on the surface of the photovoltaic cell, the photovoltaic cell conversion efficiency, the photovoltaic cell loss efficiency, the net area of the photovoltaic panel, the total number of vegetation types and the area of each type of vegetation. The calculation expression of the carbon offset amount in the tunnel site is: Where C OC is the carbon offset in the tunnel site, I is the annual solar radiation on the surface of the photovoltaic cell, K E is the photovoltaic cell conversion efficiency, K S is the photovoltaic cell loss efficiency, A p is the net area of PV panels, F is the carbon emission factor of electricity, g is the total number of vegetation types, C vi is the carbon sink of the i-th vegetation in the tunnel site, m vi The area of the i-th vegetation within the tunnel site.
[0014] The zero-carbon tunnel design device based on the full life cycle theory provided by the present invention may also have the following features: wherein the calculation expression of the total carbon emission in the tunnel operation and maintenance stage is: C O =C OO +C OM -C OC , where C O is the total carbon emissions during the tunnel operation and maintenance phase, C OO is the carbon emission during the tunnel operation phase, C OM is the carbon emission during the tunnel maintenance phase, C OC is the carbon offset within the tunnel site.
[0015] The present invention also provides a zero-carbon tunnel design method based on the full life cycle theory, which is used to generate a zero-carbon tunnel optimization design scheme based on tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data, and has the following characteristics, including the following steps: Step S1, based on the tunnel construction data, calculate the total carbon emissions in the tunnel construction stage; Step S2, based on the tunnel operation and maintenance data and the carbon offset measures data, calculate the total carbon emissions in the tunnel operation and maintenance stage; Step S3, determine whether the sum of the total carbon emissions in the tunnel construction stage and the total carbon emissions in the tunnel operation and maintenance stage is less than or equal to zero, if so, execute step S5, if not, execute step S4; Step S4, optimize the tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data; Step S5, use the optimized tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data as the zero-carbon tunnel optimization design scheme.
[0016] Functions and Effects of the Invention
[0017] According to the zero-carbon tunnel design device and method based on the full life cycle theory involved in the present invention, on the one hand, according to the characteristics of the tunnel, the carbon emissions in the tunnel construction stage and the tunnel operation and maintenance stage are calculated, thereby obtaining the carbon emissions of the tunnel throughout its life cycle; on the other hand, by optimizing the parameters related to tunnel construction, tunnel operation and maintenance, and carbon offset, an optimized design scheme for a zero-carbon tunnel throughout its life cycle is generated. Therefore, the zero-carbon tunnel design device and method based on the full life cycle theory of the present invention can generate a design scheme for a zero-carbon tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 is a block diagram of a zero-carbon tunnel design device based on the full life cycle theory in an embodiment of the present invention;
[0019] Figure 2 It is a flow chart of a zero-carbon tunnel design method based on the full life cycle theory in an embodiment of the present invention;
[0020] Figure 3 It is a schematic diagram of carbon reduction measures outside the tunnel in an embodiment of the present invention. DETAILED DESCRIPTION
[0021] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the following embodiments and drawings specifically illustrate the zero-carbon tunnel design device and method based on the full life cycle theory of the present invention.
[0022] In this embodiment, a zero-carbon tunnel design device based on the full life cycle theory is provided, which is used to generate a zero-carbon tunnel optimization design plan based on tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data.
[0023] Among them, tunnel construction data includes the total number of building material types, the consumption of each type of building material, the total number of transportation methods, the distance generated by each type of transportation of each type of building material, the total number of energy types and the consumption of each type of energy.
[0024] Tunnel operation and maintenance data includes tunnel operation sub-data and tunnel maintenance sub-data. Tunnel operation sub-data includes the total number of lamp types, the number of each type of lamps, the lighting time of each type of lamps, the total number of fan types, the number of each type of fans, and the operating time of each type of fans. Tunnel maintenance sub-data includes the number of major repairs, the number of minor repairs, the total number of building materials, the consumption of each type of building materials, the total number of transportation methods, and the distance generated by each type of transportation of each type of building materials.
[0025] Data on carbon offset measures include annual solar radiation on the surface of PV cells, PV cell conversion efficiency, PV cell loss efficiency, net area of PV panels, total number of vegetation types and area of each type of vegetation.
[0026] Figure 1 It is a block diagram of a zero-carbon tunnel design device based on the full life cycle theory in an embodiment of the present invention.
[0027] like Figure 1 As shown, the zero-carbon tunnel design device 100 based on the full life cycle theory includes a carbon emission calculation module 10 for the construction phase, a carbon emission calculation module 20 for the operation and maintenance phase, a judgment module 30, a parameter optimization module 40 and a control module 50.
[0028] The carbon emission calculation module 10 during the construction phase is used to calculate the total carbon emission during the tunnel construction phase based on the tunnel construction data.
[0029] Among them, the calculation expression of the total carbon emissions during the tunnel construction phase is:
[0030] C C =C CM +C CT +C CC ,
[0031]
[0032] Where C C is the total carbon emission during the tunnel construction phase, a is the total number of building materials, U i is the consumption of the i-th building material, is the loss rate of the i-th building material, F i is the carbon emission factor of the i-th building material production stage, b is the total number of transportation modes, D i,j is the distance generated by transporting the i-th building material using the j-th mode of transportation, F jis the carbon emission factor per unit weight of transportation distance under the jth mode of transportation, c is the total number of energy types, Q i is the consumption of the i-th energy source, F i1 is the carbon emission factor of the i-th energy production process, F i2 is the carbon emission factor of the i-th energy use process.
[0033] The carbon emission calculation module 20 during the operation and maintenance phase calculates the total carbon emission during the operation and maintenance phase of the tunnel based on the tunnel operation and maintenance data and the carbon offset measures data.
[0034] The operation and maintenance phase carbon emission calculation module 20 includes an operation phase carbon emission calculation unit 201 , a maintenance phase carbon emission calculation unit 202 , a carbon offset calculation unit 203 and a total amount calculation unit 204 .
[0035] The operation phase carbon emission calculation unit 201 is used to calculate the carbon emission amount in the tunnel operation phase according to the tunnel operation sub-data.
[0036] Among them, the calculation expression of carbon emissions in the tunnel operation stage is:
[0037]
[0038] Where C OO is the carbon emission during the tunnel operation phase, d is the total number of lamp types, n Li is the number of the i-th type of lamps, P Li is the power of the i-th lamp, t Li is the lighting time of the i-th lamp, e is the total number of fan types, n Vj is the number of the j-th type of fans, P Vj is the power of the j-th fan, t Vj is the operating time of the jth fan, and F is the carbon emission factor.
[0039] The maintenance phase carbon emission calculation unit 202 is used to calculate the tunnel maintenance phase carbon emission according to the tunnel maintenance sub-data.
[0040] Among them, the calculation expression of carbon emissions in the tunnel maintenance stage is:
[0041]
[0042] Where C OM is the carbon emission during the tunnel maintenance phase, L is the number of major repairs, d is the total number of building materials, and U i is the consumption of the i-th building material, the loss rate of the i-th building material, F i is the carbon emission factor of the i-th building material production stage, e is the total number of transportation modes, D jis the distance generated by transporting the i-th building material using the j-th mode of transportation, F j is the carbon emission factor per unit weight of transportation distance under the jth mode of transportation, S is the number of minor repairs, f is the total number of maintenance types, E k is the maintenance energy consumption, F k is the carbon emission factor.
[0043] The carbon offset calculation unit 203 is used to calculate the carbon offset amount in the tunnel site according to the carbon offset measure data.
[0044] The calculation expression of carbon offset in the tunnel site is:
[0045]
[0046] Where C OC is the carbon offset in the tunnel site, I is the annual solar radiation on the surface of the photovoltaic cell, K E is the photovoltaic cell conversion efficiency, K S is the photovoltaic cell loss efficiency, A p is the net area of PV panels, F is the carbon emission factor of electricity, g is the total number of vegetation types, C vi is the carbon sink of the i-th vegetation in the tunnel site, m vi The area of the i-th vegetation within the tunnel site.
[0047] The total amount calculation unit 204 is used to calculate the total amount of carbon emissions during the tunnel operation and maintenance stage based on the carbon emissions during the tunnel operation stage, the carbon emissions during the tunnel maintenance stage and the carbon offset within the tunnel site.
[0048] Among them, the calculation expression of the total carbon emissions during the tunnel operation and maintenance stage is:
[0049] C O =C OO +C OM -C OC ,
[0050] Where C O is the total carbon emissions during the tunnel operation and maintenance phase, C OO is the carbon emission during the tunnel operation phase, C OM is the carbon emission during the tunnel maintenance phase, C OC is the carbon offset within the tunnel site.
[0051] The judgment module 30 is used to judge whether the sum of the total carbon emissions during the tunnel construction phase and the total carbon emissions during the tunnel operation and maintenance phase is less than or equal to zero.
[0052] The parameter optimization module 40 is used to optimize tunnel construction data, tunnel operation and maintenance data, and carbon offset measure data.
[0053] The control module 50 is used to control the operation of the carbon emission calculation module 10 in the construction phase, the carbon emission calculation module 20 in the operation and maintenance phase, the judgment module 30 and the parameter optimization module 40, and optimize the tunnel construction data, tunnel operation and maintenance data and carbon offset measures data until the sum of the total carbon emissions in the tunnel construction phase and the total carbon emissions in the tunnel operation and maintenance phase is less than or equal to zero. The optimized tunnel construction data, tunnel operation and maintenance data and carbon offset measures data are used as the zero-carbon tunnel optimization design plan.
[0054] The following describes the process of using the zero-carbon tunnel design device 100 based on the full life cycle theory to perform the zero-carbon tunnel design method based on the full life cycle theory in conjunction with the accompanying drawings.
[0055] Figure 2 It is a flow chart of a zero-carbon tunnel design method based on the full life cycle theory in an embodiment of the present invention.
[0056] like Figure 2 As shown in the figure, the zero-carbon tunnel design method based on the full life cycle theory includes the following steps:
[0057] Step S1, using the construction phase carbon emission calculation module 10 to calculate the total carbon emission during the tunnel construction phase according to the tunnel construction data.
[0058] Step S2, using the operation and maintenance phase carbon emission calculation module 20 to calculate the total carbon emission during the tunnel operation and maintenance phase according to the tunnel operation and maintenance data and the carbon offset measures data.
[0059] Step S3, using the judgment module 30 to judge whether the sum of the total carbon emissions during the tunnel construction phase and the total carbon emissions during the tunnel operation and maintenance phase is less than or equal to zero, if so, execute step S5, if not, execute step S4.
[0060] Step S4, using the parameter optimization module 40 to optimize the tunnel construction data, tunnel operation and maintenance data and carbon offset measures data, and executing step S1.
[0061] Step S5, using the control module 50 to use the optimized tunnel construction data, tunnel operation and maintenance data and carbon offset measures data as a zero-carbon tunnel optimization design solution.
[0062] The following is a test tunnel in East China to further illustrate the zero-carbon tunnel design method based on the full life cycle theory.
[0063] In this embodiment, the middle section of the test tunnel of 1 km is used as the basic calculation unit. The inner diameter of the tunnel is about 12 m, the lining thickness is about 1 m, the clearance is about 5 m, and the slope is 0.5%. It is a single-hole, two-lane highway tunnel.
[0064] In this embodiment, the initial tunnel construction data is calculated based on the above data combined with existing tunnel engineering documents, such as "JTG-T3821-2018 Highway Engineering Estimation Indicators" and the like; the lamps inside the tunnel are arranged symmetrically, with an interval of 20m and a power of 50W, and the lamps are operated all day throughout the year. The jet fans in the tunnel are arranged symmetrically, with an interval of 200m and a power of 50W, and operate for 12 hours a day. The renovation work during the operation and maintenance period mainly considers the renovation of the tunnel lining, and considers completing the replacement of the tunnel lining once within the 100-year operation period, so as to calculate the initial tunnel operation and maintenance data; the initial carbon offset measures data are calculated based on the site data around the tunnel.
[0065] Figure 3 It is a schematic diagram of carbon reduction measures outside the tunnel in an embodiment of the present invention.
[0066] like Figure 3 As shown, the carbon reduction measures outside the tunnel include vegetation coverage, photovoltaic power generation, light-guiding facilities and tunnel entrance light-reduction facilities. Among them, the site data around the tunnel includes vegetation coverage data, i.e., the area of green plants that can be distributed on the land around the tunnel, and photovoltaic power generation data, i.e., the area where solar photovoltaic panels can be laid. In this embodiment, light-guiding facilities and tunnel entrance light-reduction facilities are configured as specific types of lamps in the zero-carbon tunnel optimization design plan.
[0067] According to the above initial tunnel construction data, tunnel operation and maintenance data and carbon offset measures data, the total carbon emissions during the tunnel construction phase were calculated using a zero-carbon tunnel design device based on the full life cycle theory. 4 tCO 2eq The carbon emissions during the tunnel operation phase are 28.33tCO 2eq / year, the carbon emissions in the tunnel maintenance phase in the first year were 90.72t CO 2eq The carbon offset in the tunnel site is 79.06tCO 2eq / year, that is, the total carbon emissions during the tunnel operation and maintenance phase are approximately 39.99tCO 2eq / Year.
[0068] Because 2.86×10 4 tCO 2eq +39.99tCO 2eq / year>0, so the control module 50 controls the parameter optimization module 40 to optimize the parameters of the tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data. After multiple iterations, the sum of the total carbon emissions in the tunnel construction phase and the total carbon emissions in the tunnel operation and maintenance phase is less than or equal to zero.
[0069] Among them, the optimized parameters include the total number of building material types used in tunnel construction and maintenance, the consumption of various building materials, the total number of transportation methods, the distance and total number of energy types generated by various types of building materials and transportation, the consumption of various types of energy in tunnel operation, the total number of lamps, the number of various lamps, the lighting time of various lamps, the total number of wind turbines, the number of various wind turbines and the operating time of various wind turbines, as well as the annual solar radiation irradiance on the surface of carbon-offset photovoltaic cells, photovoltaic cell conversion efficiency, photovoltaic cell loss efficiency, net area of photovoltaic panels, the total number of vegetation types and the area of various vegetation types.
[0070] Functions and Effects of the Embodiments
[0071] According to the zero-carbon tunnel design device and method based on the full life cycle theory involved in this embodiment, on the one hand, according to the characteristics of the tunnel, the carbon emissions in the tunnel construction stage and the tunnel operation and maintenance stage are calculated, so as to obtain the carbon emissions of the tunnel throughout its life cycle; on the other hand, by optimizing the parameters related to tunnel construction, tunnel operation and maintenance, and carbon offset, a zero-carbon tunnel optimization design scheme for the entire life cycle is generated. In short, this method can generate a design scheme for a zero-carbon tunnel.
[0072] Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A zero-carbon tunnel design device based on the full life cycle theory, used to generate a zero-carbon tunnel optimization design scheme based on tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data, characterized in that: include: A carbon emission calculation module for the construction phase, used to calculate the total carbon emission for the tunnel construction phase based on the tunnel construction data; A carbon emission calculation module for the operation and maintenance phase, which calculates the total carbon emission for the tunnel operation and maintenance phase according to the tunnel operation and maintenance data and the carbon offset measures data; A judgment module, used to judge whether the sum of the total carbon emissions during the tunnel construction phase and the total carbon emissions during the tunnel operation and maintenance phase is less than or equal to zero; A parameter optimization module, used for optimizing the tunnel construction data, the tunnel operation and maintenance data, and the carbon offset measures data; A control module is used to control the operation of the carbon emission calculation module in the construction phase, the carbon emission calculation module in the operation and maintenance phase, the judgment module and the parameter optimization module, and optimize the tunnel construction data, the tunnel operation and maintenance data and the carbon offset measures data until the sum of the total carbon emissions in the tunnel construction phase and the total carbon emissions in the tunnel operation and maintenance phase is less than or equal to zero, and the optimized tunnel construction data, the tunnel operation and maintenance data and the carbon offset measures data are used as the zero-carbon tunnel optimization design plan.
2. The zero-carbon tunnel design device based on the full life cycle theory according to claim 1 is characterized in that: in, The tunnel construction data includes the total number of building material types, the consumption of each type of building material, the total number of transportation methods, the distance generated by each type of transportation of each type of building material, the total number of energy types and the consumption of each type of energy, The calculation expression of the total carbon emissions during the tunnel construction phase is: C C =C CM +C CT +C CC , Where C C is the total carbon emissions during the tunnel construction phase, a is the total number of building materials, U i is the consumption of the i-th building material, is the loss rate of the i-th building material, F i is the carbon emission factor of the i-th building material production stage, b is the total number of transportation modes, D i,j is the distance generated by transporting the i-th building material using the j-th mode of transportation, F j is the carbon emission factor per unit weight of transportation distance under the jth mode of transportation, c is the total number of energy types, Q i is the consumption of the i-th energy source, F i1 is the carbon emission factor of the i-th energy production process, F i2 is the carbon emission factor of the i-th energy use process.
3. According to the zero-carbon tunnel design device based on the full life cycle theory of claim 1, Features: in, The tunnel operation and maintenance data includes tunnel operation sub-data and tunnel maintenance sub-data. The carbon emission calculation module in the operation and maintenance phase includes: An operation phase carbon emission calculation unit, used to calculate the tunnel operation phase carbon emission according to the tunnel operation sub-data; A maintenance phase carbon emission calculation unit, used for calculating the tunnel maintenance phase carbon emission according to the tunnel maintenance sub-data; A carbon offset calculation unit, used to calculate the carbon offset amount in the tunnel site according to the carbon offset measure data; The total amount calculation unit is used to calculate the total amount of carbon emissions in the tunnel operation and maintenance stage according to the carbon emissions in the tunnel operation stage, the carbon emissions in the tunnel maintenance stage and the carbon offset in the tunnel site.
4. The zero-carbon tunnel design device based on the full life cycle theory according to claim 3 is characterized in that: in, The tunnel operation sub-data include the total number of lamp types, the number of each type of lamps, the lighting time of each type of lamps, the total number of fan types, the number of each type of fans and the operating time of each type of fans, The calculation expression of carbon emissions during the tunnel operation phase is: Where C OO is the carbon emission of the tunnel during operation, d is the total number of lamp types, n Li is the number of the i-th type of lamps, P Li is the power of the i-th lamp, t Li is the lighting time of the i-th lamp, e is the total number of fan types, n Vj is the number of the j-th type of fans, P Vj is the power of the j-th fan, t Vj is the operating time of the jth fan, and F is the carbon emission factor.
5. The zero-carbon tunnel design device based on the full life cycle theory according to claim 3 is characterized by: in, The tunnel maintenance sub-data includes the number of major repairs, the number of minor repairs, the total number of building material types, the consumption of each type of building material, the total number of transportation methods and the distance generated by each type of transportation of each type of building material, The calculation expression of carbon emissions during the tunnel maintenance phase is: Where C OM is the carbon emission during the tunnel maintenance phase, L is the number of major repairs, d is the total number of building materials, and U i is the consumption of the i-th building material, the loss rate of the i-th building material, F i is the carbon emission factor of the i-th building material production stage, e is the total number of transportation modes, D j is the distance generated by transporting the i-th building material using the j-th mode of transportation, F j is the carbon emission factor per unit weight of transportation distance under the jth mode of transportation, S is the number of minor repairs, f is the total number of maintenance types, E k is the maintenance energy consumption, F k is the carbon emission factor.
6. The zero-carbon tunnel design device based on the full life cycle theory according to claim 3 is characterized by: in, The carbon offset measures data include the annual solar radiation on the surface of photovoltaic cells, photovoltaic cell conversion efficiency, photovoltaic cell loss efficiency, net area of photovoltaic panels, total number of vegetation types and area of each type of vegetation. The calculation expression of carbon offset in the tunnel site is: Where C OC is the carbon offset in the tunnel site, I is the annual solar radiation on the surface of the photovoltaic cell, K E is the photovoltaic cell conversion efficiency, K S is the photovoltaic cell loss efficiency, A p is the net area of PV panels, F is the carbon emission factor of electricity, g is the total number of vegetation types, C vi is the carbon sink of the i-th vegetation in the tunnel site, m vi The area of the i-th vegetation within the tunnel site.
7. The zero-carbon tunnel design device based on the full life cycle theory according to claim 3 is characterized by: in, The calculation expression for the total carbon emissions during the tunnel operation and maintenance phase is: C O =C OO +C OM -C OC , Where C O is the total carbon emissions during the tunnel operation and maintenance phase, C OO is the carbon emission during the tunnel operation phase, C OM is the carbon emission during the tunnel maintenance phase, C OC is the carbon offset within the tunnel site.
8. A zero-carbon tunnel design method based on the full life cycle theory is used to generate a zero-carbon tunnel optimization design scheme based on tunnel construction data, tunnel operation and maintenance data, and carbon offset measures data, characterized in that: The following steps are involved: Step S1, calculating the total carbon emissions during the tunnel construction phase according to the tunnel construction data; Step S2, calculating the total carbon emissions during the tunnel operation and maintenance phase according to the tunnel operation and maintenance data and the carbon offset measures data; Step S3, determining whether the sum of the total carbon emissions during the tunnel construction phase and the total carbon emissions during the tunnel operation and maintenance phase is less than or equal to zero, if so, executing step S5, if not, executing step S4; Step S4, optimizing the tunnel construction data, the tunnel operation and maintenance data, and the carbon offset measures data; Step S5, using the optimized tunnel construction data, the tunnel operation and maintenance data, and the carbon offset measures data as the zero-carbon tunnel optimization design plan.
Citation Information
Patent Citations
Carbon accounting amount determination method, system and device, equipment and storage medium
CN110634084A
Implementation method for tunnel drainage power generation and carbon neutralization in tunnel in water-rich area
CN113605975A
Net zero carbon building computing system and method
CN116502011A
Highway tunnel carbon emission calculation and visualization method based on digital model
CN116894068A
Optimization system for constructing tunnel carbon emission model
CN118053509A