Track foundation structure

By using composite foundation or pile foundation and prefabricated pull beam connection support in the track foundation structure, the problems of unreasonable stress and difficult construction of the track foundation structure in the existing technology are solved, and the stability and construction of the track are achieved The efficiency improvement is suitable for multiple parallel tracks in large raw material fields.

CN221988985UActive Publication Date: 2024-11-12MCC CAPITAL ENGINEERING & RESEARCH INC LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420578965.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-25
Publication Date
2024-11-12
Estimated Expiration
2034-03-25

AI Technical Summary

Technical Problem

The existing track infrastructure has problems such as unreasonable overall stress, insufficient structural reliability, large concrete usage, poor economy, inconvenient construction and long cycles in large raw material fields, resulting in serious deformation of the track and affecting production.

Method used

A rail foundation structure consisting of rail foundation brackets and pull beams on both sides is designed. The composite foundation or pile foundation is used below the bracket. The pull beam is connected to the bracket to reduce horizontal displacement. The U-shaped groove structure is used for filling gravel adjustments. The pull beam can be used for As the basis of belt conveyor, it is prefabricated to save construction cycle.

Benefits of technology

This structure reduces vertical settlement and horizontal displacement of the track, enhances integrity, saves concrete usage and construction time, improves the reliability and economy of use, and is suitable for multiple parallel tracks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221988985U_ABST
    Figure CN221988985U_ABST
Patent Text Reader

Abstract

The utility model discloses a track foundation structure which comprises a first track foundation support and a second track foundation support, the first track foundation support comprises a first bottom wall, and a first inner side wall and a first outer side wall are arranged on the two sides of the first bottom wall. A first containing groove is defined by the first bottom wall, the first inner side wall and the first outer side wall. The second track foundation support comprises a second bottom wall, a second inner side wall and a second outer side wall are arranged on the two sides of the second bottom wall, and a second containing groove is defined by the second bottom wall, the second inner side wall and the second outer side wall. The straining beams are distributed at intervals in the second direction, each straining beam is provided with a first end and a second end which are opposite, and the first ends are connected with the first track foundation support and the second track foundation support. The track foundation structure is ingenious in overall structural design, reasonable in stress, high in use reliability and wide in application scene, materials can be saved, the construction difficulty is lowered, the construction period is shortened, and the cost is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of foundation structures, in particular to a track foundation structure. Background Art

[0002] In large-scale raw material yards, large stackers are generally used for operation. Stackers have large loads and high requirements for the flatness and deformation of the foundation. The common ballast track foundation will cause uneven vertical settlement and horizontal deformation of the track due to large deformation. During the use of stackers, track jams often occur. When the deformation is serious, the motor will burn out, affecting normal production.

[0003] At present, some solutions are provided in the existing technology. However, the current solutions have more or less the following problems: unreasonable overall force, the reliability of the structure needs to be improved; large amount of concrete is used, the economy is poor; the construction is inconvenient, and the construction period is long.

[0004] To this end, it is necessary to propose a track infrastructure that solves at least one of the above problems. Utility Model Content

[0005] In view of the defects existing in the prior art, a track foundation structure is provided in the embodiment of the utility model. The overall structural design of the track foundation structure is ingenious, the force is reasonable, the material can be saved, the construction difficulty and cycle can be reduced, the cost can be saved, the reliability of use is high, and the application scenarios are wide.

[0006] The specific technical solution of the implementation mode of the utility model is:

[0007] A track foundation structure, the track foundation structure comprising: a first track foundation bracket and a second track foundation bracket arranged at a predetermined distance along a first direction, the first track foundation bracket and the second track foundation bracket extending longitudinally along a second direction perpendicular to the first direction; the first track foundation bracket comprising: a first bottom wall, the first bottom wall having a first inner side wall close to the second track foundation bracket and a first outer side wall away from the second track foundation bracket on both sides, the first bottom wall, the first inner side wall and the first outer side wall forming a first accommodating groove; the second track foundation bracket comprising: a second bottom wall, the second bottom wall having a second inner side wall close to the first track foundation bracket and a second outer side wall away from the first track foundation bracket on both sides, the second bottom wall, the second inner side wall and the second outer side wall forming a second accommodating groove; a pull beam, the number of the pull beams is multiple, the multiple pull beams are spaced apart along the second direction, the pull beam has a first end and a second end opposite to each other, the first end is connected to the first track foundation bracket, and the second end is connected to the second track foundation bracket.

[0008] In a preferred embodiment, the first end of the tension beam is connected to the first inner side wall of the first track base support, and the second end of the tension beam is connected to the second inner side wall of the second track base support.

[0009] In a preferred embodiment, the first end of the pull beam is connected to the first bottom wall of the first track base support, the second end of the pull beam is connected to the second bottom wall of the second track base support, and the pull beam has relative upper and lower surfaces along a third direction perpendicular to the first direction and the second direction, and the upper surface is provided with a pier.

[0010] In a preferred embodiment, the tension beam is also provided with a connection portion for positioning the belt conveyor.

[0011] In a preferred embodiment, the first inner side wall and the first outer side wall are located on both sides of the first bottom wall and are perpendicular to the first bottom wall, and the first receiving groove is used to accommodate a gravel cushion layer; the second inner side wall and the second outer side wall are located on both sides of the second bottom wall and are perpendicular to the second bottom wall, and the second receiving groove is used to accommodate a gravel cushion layer.

[0012] In a preferred embodiment, at least one pile foundation is respectively disposed on the first bottom wall and the second bottom wall.

[0013] In a preferred embodiment, a mattress layer is disposed on the first bottom wall and the second bottom wall respectively, and a reinforcement pile is disposed on a side of the mattress layer facing away from the first bottom wall or the second bottom wall.

[0014] In a preferred embodiment, the track infrastructure structure can be used in multiple parallel tracks, and a first intermediate side wall is also provided on the first bottom wall, the first intermediate side wall is located between the first inner side wall and the first outer side wall, the first intermediate side wall, the first inner side wall and a portion of the first bottom wall are arranged to form a first inner accommodating groove, and the first intermediate side wall, the first outer side wall and a portion of the first bottom wall are arranged to form a first outer accommodating groove; a second intermediate side wall is also provided on the second bottom wall, the second intermediate side wall is located between the second inner side wall and the second outer side wall, the second intermediate side wall, the second inner side wall and a portion of the second bottom wall are arranged to form a second inner accommodating groove, and the second intermediate side wall, the second outer side wall and a portion of the second bottom wall are arranged to form a second outer accommodating groove.

[0015] In a preferred embodiment, a cantilever plate is further provided on at least one of the first outer side wall and the second outer side wall.

[0016] In a preferred embodiment, the tension beam is a prefabricated tension beam, and a splicing structure is formed between the first inner side wall, the second inner side wall and the tension beam.

[0017] In a preferred embodiment, the splicing structure includes any one of the following or a combination thereof: a keyway matching mechanism, a hole-shaft matching mechanism.

[0018] In a preferred embodiment, a shear groove is provided at the top end of the first inner side wall or the second inner side wall, and pins are provided on both sides of the shear groove along the first direction; shear keys matching with the shear groove and reserved holes matching with the pin gap are provided at both ends of the tension beam, and a filling layer is provided in the annular gap between the pin and the reserved hole.

[0019] In a preferred embodiment, the diameter of the reserved hole is 5 mm larger than the diameter of the pin.

[0020] The technical solution of the utility model has the following significant beneficial effects:

[0021] The track infrastructure provided in the embodiment of the present application mainly includes: track infrastructure brackets located on both sides and a tension beam arranged between the track infrastructure brackets. The specific effects of the track infrastructure are as follows:

[0022] 1. Using composite foundation or pile foundation under the track foundation support can reduce the vertical settlement of the track.

[0023] 2. Setting tension beams on the two track foundation supports can reduce horizontal displacement, enhance the integrity in the horizontal direction, and enable coordinated deformation in the horizontal direction.

[0024] 3. The tension beam can also be used as the foundation of the belt conveyor, which can reduce the settlement of the belt conveyor foundation and save the amount of concrete used in the belt conveyor foundation.

[0025] 4. The U-shaped groove structure is filled with gravel, which can be adjusted when the track settles or deforms.

[0026] 5. The side wall of the U-shaped groove structure can be used as a force transmission component to save concrete.

[0027] 6. U-shaped trough structure and tension beam can be prefabricated to save construction period.

[0028] With reference to the following description and drawings, specific embodiments of the present invention are disclosed in detail, indicating the manner in which the principles of the present invention can be adopted. It should be understood that the embodiments of the present invention are not limited in scope. Within the spirit and scope of the appended claims, the embodiments of the present invention include many changes, modifications and equivalents. Features described and / or shown for one embodiment can be used in one or more other embodiments in the same or similar manner, combined with features in other embodiments, or replace features in other embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] The drawings described herein are only for explanation purposes and are not intended to limit the scope of the present invention in any way. In addition, the shapes and proportional dimensions of the components in the drawings are only for illustration purposes to help understand the present invention, and are not intended to specifically limit the shapes and proportional dimensions of the components of the present invention. Under the guidance of the present invention, those skilled in the art can select various possible shapes and proportional dimensions to implement the present invention according to specific circumstances.

[0030] Figure 1 A schematic diagram of an application scenario of a track infrastructure provided in an embodiment of the present application;

[0031] Figure 2 A partial top view of a track infrastructure structure provided in an embodiment of the present application;

[0032] Figure 3 for Figure 2 Section view of the tension beam at AA in the middle;

[0033] Figure 4 for Figure 2 The first cross-sectional view at the middle BB;

[0034] Figure 5 for Figure 2 The second cross-sectional view at the middle BB;

[0035] Figure 6 for Figure 2 The third cross-sectional view at the middle BB;

[0036] Figure 7 for Figure 2 The fourth cross-sectional view at the middle BB;

[0037] Figure 8 for Figure 2 The fifth cross-sectional view at the middle BB;

[0038] Fig. 9 for Figure 2 The sixth cross-sectional view at the middle BB;

[0039] Fig.10 for Fig. 9 Schematic diagram of the decomposition.

[0040] Reference numerals of the present application:

[0041] 100. Track infrastructure;

[0042] 1A, first track foundation support;

[0043] 11. a first bottom wall;

[0044] 121, first inner side wall;

[0045] 122, first outer side wall;

[0046] 1B, second track foundation bracket;

[0047] 16. second bottom wall;

[0048] 171, second inner side wall;

[0049] 172, second outer side wall;

[0050] 181, first intermediate side wall;

[0051] 182, second intermediate side wall;

[0052] 191, first content storage slot;

[0053] 192, first outer containing tank;

[0054] 193, second content storage slot;

[0055] 194, second outer receiving tank;

[0056] 14. Pins;

[0057] 15. Shear groove;

[0058] 53. Reserved hole;

[0059] 54. Shear key;

[0060] 13. Cantilever board;

[0061] 2. Crushed stone cushion;

[0062] 3. Sleepers;

[0063] 4. Track;

[0064] 5. Pull beam;

[0065] 51. Connecting part;

[0066] 61. Reinforcement piles;

[0067] 62. Mattress layer;

[0068] 7. Pile foundation;

[0069] X, first direction;

[0070] Y, second direction;

[0071] Z, third direction;

[0072] 200. Stacker-reclaimer;

[0073] 300. Belt conveyor. DETAILED DESCRIPTION

[0074] The technical solution of the present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be understood that these embodiments are only used to illustrate the present invention and are not used to limit the scope of the present invention. After reading the present invention, various equivalent forms of modifications to the present invention by those skilled in the art fall within the scope defined by the claims attached to this application.

[0075] It should be noted that when an element is referred to as being "disposed on" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used herein are for illustrative purposes only and are not intended to be the only implementation method.

[0076] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those generally understood by those skilled in the art to which this application belongs. The terms used herein in the specification of this application are only for the purpose of describing specific embodiments and are not intended to limit this application. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0077] The utility model provides a track foundation structure, which has an ingenious overall structural design, reasonable force, can save materials, reduce construction difficulty and period, save costs, has high reliability in use, and has a wide range of application scenarios.

[0078] Please refer to Figures 1 to 10In an embodiment of the present application specification, a track infrastructure 100 is provided, and the track infrastructure 100 may include: a first track foundation bracket 1A and a second track foundation bracket 1B arranged at a predetermined distance along a first direction X, and the first track foundation bracket 1A and the second track foundation bracket 1B extend longitudinally along a second direction Y perpendicular to the first direction X; the first track foundation bracket 1A includes: a first bottom wall 11, and both sides of the first bottom wall 11 are provided with a first inner side wall 121 close to the second track foundation bracket 1B and a first outer side wall 122 away from the second track foundation bracket 1B, the first bottom wall 11 and the first inner side wall 121 and the first The outer side wall 122 is arranged to form a first accommodating groove; the second track base bracket 1B includes: a second bottom wall 16, and the second bottom wall 16 is provided with a second inner side wall 171 close to the first track base bracket 1A and a second outer side wall 172 away from the first track base bracket 1A on both sides, and the second bottom wall 16 and the second inner side wall 171 and the second outer side wall 172 are arranged to form a second accommodating groove; a pull beam 5, the number of the pull beams 5 is multiple, and the multiple pull beams 5 are spaced apart along the second direction Y, and the pull beam 5 has a first end and a second end opposite to each other, the first end is connected to the first track base bracket 1A, and the second end is connected to the second track base bracket 1B.

[0079] In the embodiment of the present application, the track infrastructure 100 may include a first track foundation bracket 1A and a second track foundation bracket 1B, and the first track foundation bracket 1A and the second track foundation bracket 1B are spaced apart by a predetermined distance along the first direction X. The predetermined distance of the interval may be determined according to the track spacing distance of the stacking feeder, and the present application does not make any specific limitation thereto.

[0080] The first track base bracket 1A and the second track base bracket 1B both extend longitudinally along the second direction Y. The first track base bracket 1A and the second track base bracket 1B have similar structures, which can be symmetrical structures.

[0081] Among them, the cross-section of the first track base bracket 1A can be U-shaped as a whole, and the first track base bracket 1A includes: a first bottom wall 11, and the first bottom wall 11 is provided with a first inner wall 121 close to the second track base bracket 1B and a first outer wall 122 away from the second track base bracket 1B on both sides, and the first bottom wall 11, the first inner wall 121 and the first outer wall 122 are surrounded to form a first accommodating groove.

[0082] Specifically, the first inner wall 121 and the first outer wall 122 are located on both sides of the first bottom wall 11 and are perpendicular to the first bottom wall 11. The first track foundation support 1A is a U-shaped groove structure composed of reinforced concrete, wherein the first bottom wall 11 is a concrete floor, and the first inner wall 121 and the first outer wall 122 can be concrete side walls. When the stacker 200 walks on the track 4, the concrete side walls can be used as force transmission components to transfer the load to the pile top.

[0083] Specifically, a cantilever plate 13 may be provided on the top of the U-shaped groove structure as required. For example, a cantilever plate 13 may be provided on the first outer side wall 122 to serve as a walking passage for the roadbed. The cantilever plate 13 may specifically be a concrete cantilever plate 13, and the cantilever plate 13 is integrally formed with the U-shaped groove structure.

[0084] The U-shaped groove structure is filled with crushed stones to form a crushed stone cushion layer 2. A reinforced concrete prefabricated sleeper 3 is laid on the crushed stone cushion layer 2, and a track 4 is laid on the sleeper 3. When the track 4 sinks or deforms, the height of the track 4 can be maintained by adjusting the amount of crushed stones in the U-shaped groove.

[0085] Similarly, the cross-section of the second track base bracket 1B can be U-shaped as a whole, and the second track base bracket 1B includes: a second bottom wall 16, and the second bottom wall 16 is provided with a second inner wall 171 close to the first track base bracket 1A and a second outer wall 172 away from the first track base bracket 1A on both sides, and the second bottom wall 16, the second inner wall 171 and the second outer wall 172 are surrounded to form a second accommodating groove.

[0086] Specifically, the second inner wall 171 and the second outer wall 172 are located on both sides of the second bottom wall 16 and are perpendicular to the second bottom wall 16. The second track foundation bracket 1B is a U-shaped groove structure composed of reinforced concrete, wherein the second bottom wall 16 is a concrete floor, and the second inner wall 171 and the second outer wall 172 can be concrete side walls. When the stacker 200 walks on the track 4, the concrete side walls can be used as force transmission components to transfer the load to the pile top.

[0087] Specifically, a cantilever plate 13 may be provided on the top of the U-shaped groove structure as required. For example, a cantilever plate 13 may be provided on the second outer side wall 172 to serve as a walking passage for the roadbed. The cantilever plate 13 may specifically be a concrete cantilever plate 13, and the cantilever plate 13 is integrally formed with the U-shaped groove structure.

[0088] like Figure 3As shown, a plurality of tension beams 5 are further provided between the first track foundation support 1A and the second track foundation support 1B. The plurality of tension beams 5 are spaced apart along the second direction Y, and the tension beams 5 have a first end and a second end opposite to each other, the first end is connected to the first track foundation support 1A, and the second end is connected to the second track foundation support 1B. Specifically, the tension beam 5 may be a concrete tension beam 5. By providing the tension beam 5 between the two track foundation supports, the horizontal displacement can be reduced, the integrity in the horizontal direction can be enhanced, and the horizontal direction can be deformed cooperatively.

[0089] The connection positions of the tension beam 5 and the first track base support 1A and the second track base support 1B can be at different positions.

[0090] like Figure 4 , Figure 5 and Figure 6 As shown, in one embodiment, the first end of the tension beam 5 is connected to the first inner wall 121 of the first track base support 1A, and the second end of the tension beam 5 is connected to the second inner wall 171 of the second track base support 1B.

[0091] In this embodiment, both ends of the tension beam 5 can be connected to the inner side walls of the track foundation support respectively, and the side walls of the track foundation support with the U-shaped groove structure can be used as force transmission components, which can save the amount of concrete.

[0092] Or, if Figure 7 As shown, in another embodiment, the first end of the tension beam 5 is connected to the first bottom wall 11 of the first track base support 1A, and the second end of the tension beam 5 is connected to the second bottom wall 16 of the second track base support 1B, and the tension beam 5 has relative upper and lower surfaces along a third direction Z perpendicular to the first direction X and the second direction Y, and the upper surface is provided with a pier.

[0093] In this embodiment, the two ends of the tension beam 5 are respectively connected to the first bottom wall 11 and the second bottom wall 16. At this time, a pier with a certain height can be set on the upper surface of the tension beam 5, and the highest position of the pier can be flush or nearly flush with the upper surface of the first track foundation bracket 1A and the second track foundation bracket 1B.

[0094] See also Figure 7 or Figure 8 As shown, further, the tension beam 5 is provided with a connection portion 51 for positioning the belt conveyor 300 .

[0095] Please refer to Figure 4 and Figure 8 , for example Figure 4In the embodiment shown, when the tension beam 5 is connected to the top of the first inner wall 121 and the second inner wall 171, the connection portion 51 can be a pre-embedded steel plate arranged on the tension beam 5, and the pre-embedded steel plate is welded to the legs of the belt conveyor 300, and the tension beam 5 can also serve as the foundation of the belt conveyor 300. When the concrete tension beam 5 can serve as the foundation of the belt conveyor 300, the settlement of the foundation of the belt conveyor 300 can be reduced, and the amount of concrete used for the foundation of the belt conveyor 300 can be saved.

[0096] Please refer to Figure 7 , for example Figure 7 In the embodiment shown, the tension beam 5 is connected between the first bottom wall 11 and the second bottom wall 16. At this time, the connection portion 51 can be set on the pier of the tension beam 5. Specifically, the connection portion 51 can be an embedded steel plate set on the pier. The embedded steel plate is welded to the legs of the belt conveyor 300. The tension beam 5 can also serve as the foundation of the belt conveyor 300.

[0097] The track foundation structure 100 provided by the utility model can be a natural foundation, a composite foundation or a pile foundation 7, and is applicable to a wide range of scenarios. When a natural foundation is used, the U-shaped groove can be directly located on the bearing layer.

[0098] like Figure 5 or Figure 6 As shown, in some embodiments, at least one pile foundation 7 is respectively disposed on the first bottom wall 11 and the second bottom wall 16 .

[0099] In this embodiment, when the track infrastructure 100 foundation adopts a pile foundation 7, the pile foundation 7 can be arranged on the first bottom wall 11 and the second bottom wall 16. Specifically, the number of the pile foundations 7 on the first bottom wall 11 and the second bottom wall 16 can be one or more.

[0100] like Figure 6 As shown, for each side bottom wall, the number of pile foundations 7 can be two. Figure 5 As shown, when the diameter of the pile foundation 7 is large, the double piles can also be replaced by a single pile. In general, the number of the pile foundation 7 can be determined comprehensively according to the support strength requirements.

[0101] like Figure 4 As shown, in some other embodiments, a mattress layer 62 is provided on the first bottom wall 11 and the second bottom wall 16 , respectively, and a reinforcement pile 61 is provided on the side of the mattress layer 62 facing away from the first bottom wall 11 or the second bottom wall 16 .

[0102] In this embodiment, when the track infrastructure 100 adopts a composite foundation, a cushion layer 62 and reinforcement piles 61 can be sequentially arranged on the first bottom wall 11 and the second bottom wall 16 from top to bottom to form a composite foundation.

[0103] When a composite foundation or a pile foundation 7 is used below the foundation, the settlement of the track along the third direction Z (vertical direction) can be reduced.

[0104] like Figure 8 As shown, the track infrastructure 100 can be used in multiple parallel tracks. A first intermediate side wall 181 is further provided on the first bottom wall 11, and the first intermediate side wall 181 is located between the first inner side wall 121 and the first outer side wall 122. The first intermediate side wall 181, the first inner side wall 121 and a part of the first bottom wall 11 are arranged to form a first inner receiving groove 191, and the first intermediate side wall 181, the first outer side wall 122 and a part of the first bottom wall 11 are arranged to form a first outer receiving groove 192; a second intermediate side wall 182 is further provided on the second bottom wall 16, and the second intermediate side wall 182 is located between the second inner side wall 171 and the second outer side wall 172. The second intermediate side wall 182, the second inner side wall 171 and a part of the second bottom wall 16 are arranged to form a second inner receiving groove 193, and the second intermediate side wall 182, the second outer side wall 172 and a part of the second bottom wall 16 are arranged to form a second outer receiving groove 194.

[0105] In this embodiment, the track infrastructure 100 can be applied to multiple parallel tracks, that is, when there are multiple tracks, multiple U-shaped groove structures can be set on each side. For example, taking the track infrastructure 100 applied to two parallel tracks as an example, the track infrastructure support on one side can be provided with two U-shaped groove structures.

[0106] Please refer to Fig. 9 and Fig.10 In some embodiments, the tension beam 5 is a prefabricated tension beam 5 , and a splicing structure is formed between the first inner side wall 121 , the second inner side wall 171 and the tension beam 5 .

[0107] Wherein, the splicing structure may include any one of the following or a combination thereof: a keyway matching mechanism, a hole-shaft matching mechanism.

[0108] Specifically, a shear groove 15 is provided at the top of the first inner wall 121 or the second inner wall 171, and pins 14 are provided on both sides of the shear groove 15 along the first direction X; shear keys 54 cooperating with the shear groove 15 and reserved holes 53 cooperating with the pins 14 are provided at both ends of the tension beam 5, and a filling layer is provided in the annular gap between the pins 14 and the reserved holes 53.

[0109] When the track infrastructure 100 adopts a prefabricated structure, the U-shaped groove structure is pre-embedded with an iron pin at the joint of the tension beam 5, and a shear groove 15 is reserved. A hole 53 and a shear key 54 are reserved at the end of the prefabricated tension beam 5 and the corresponding position of the iron pin, and the hole diameter is 5mm larger than the diameter of the iron pin. After the installation is completed, high-strength grouting material is poured into the reserved hole 53 for closed connection. Among them, the size of the shear key 54 and the iron pin can be calculated and determined according to the design strength requirements.

[0110] The track infrastructure 100 provided in the present application is easy to construct and can be formed by pouring concrete in one step. In addition, the U-shaped groove structure and the tension beam 5 can be prefabricated to save construction period.

[0111] When the prefabrication construction method is adopted, the construction method of the track infrastructure 100 includes:

[0112] Step S10: Install the shear key 54 and the reserved hole 53 at the end of the tension beam 5 in coordination with the shear groove 15 and the pin 14 of the first inner side wall 121 and the second inner side wall 171;

[0113] Step S12: After the installation is completed, pour grouting material into the reserved hole 53 to achieve a closed connection.

[0114] In this embodiment, the construction method of the track infrastructure 100 adopts a prefabricated manner. According to the construction parameter requirements, the pull beam 5 can be prefabricated first, and a U-shaped groove structure can be pre-set at the position where the track infrastructure 100 needs to be set. The prefabricated pull beam 5 and the track infrastructure 100 can be connected later. The overall operation is simple and the construction period can be controlled in a shorter time.

[0115] The track infrastructure 100 provided in the embodiments of the present application can bring the following beneficial effects:

[0116] 1. Using a composite foundation or pile foundation 7 below the track foundation bracket can reduce the vertical settlement of the track.

[0117] 2. The two track foundation brackets are provided with tension beams 5 to reduce horizontal displacement, enhance the integrity in the horizontal direction, and enable coordinated deformation in the horizontal direction.

[0118] 3. The tension beam 5 can also serve as the foundation of the belt conveyor 300, which can reduce the settlement of the foundation of the belt conveyor 300 and save the amount of concrete used in the foundation of the belt conveyor 300.

[0119] 4. The U-shaped groove structure is filled with crushed stones, which can be adjusted when the track 4 sinks or deforms.

[0120] 5. The side wall of the U-shaped groove structure can be used as a force transmission component to save concrete.

[0121] 6. The U-shaped groove structure and the tension beam 5 can be made in a prefabricated manner, thus saving construction period.

[0122] It should be noted that, in the description of this application, the terms "first", "second", etc. are only used for descriptive purposes and to distinguish similar objects. There is no order of precedence between the two, and they cannot be understood as indicating or implying relative importance. In addition, in the description of this application, unless otherwise specified, the meaning of "plurality" is two or more.

[0123] The above-mentioned various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other. Each embodiment focuses on the differences from other embodiments.

[0124] The above are only a few embodiments of the present invention. Although the embodiments disclosed by the present invention are as above, the contents are only embodiments adopted for facilitating the understanding of the present invention and are not used to limit the present invention. Any technician in the technical field to which the present invention belongs can make any modification and change in the form and details of the implementation without departing from the spirit and scope disclosed by the present invention, but the scope of patent protection of the present invention shall still be subject to the scope defined by the attached claims.

Claims

1. A track infrastructure, characterized in that: The track infrastructure structure comprises: a first track foundation bracket and a second track foundation bracket arranged at a predetermined distance along a first direction, the first track foundation bracket and the second track foundation bracket extending longitudinally along a second direction perpendicular to the first direction; The first track base bracket comprises: a first bottom wall, wherein two sides of the first bottom wall are provided with a first inner side wall close to the second track base bracket and a first outer side wall away from the second track base bracket, and the first bottom wall, the first inner side wall and the first outer side wall are surrounded to form a first receiving groove; The second track base bracket comprises: a second bottom wall, wherein the second bottom wall is provided with a second inner side wall close to the first track base bracket and a second outer side wall away from the first track base bracket on both sides, and the second bottom wall, the second inner side wall and the second outer side wall are surrounded to form a second accommodating groove; A pull beam, wherein there are multiple pull beams, and the multiple pull beams are spaced apart along the second direction. The pull beam has a first end and a second end opposite to each other, the first end is connected to the first track base support, and the second end is connected to the second track base support.

2. The track infrastructure according to claim 1, characterized in that The first end of the tension beam is connected to the first inner side wall of the first track base support, and the second end of the tension beam is connected to the second inner side wall of the second track base support.

3. The track infrastructure according to claim 1, characterized in that The first end of the tension beam is connected to the first bottom wall of the first track base support, the second end of the tension beam is connected to the second bottom wall of the second track base support, and the tension beam has an upper surface and a lower surface relative to each other along a third direction perpendicular to the first direction and the second direction, and a pier is provided on the upper surface.

4. The track infrastructure according to claim 2 or 3, characterized in that: The tension beam is also provided with a connection portion for positioning the belt conveyor.

5. The track infrastructure according to claim 1, characterized in that The first inner side wall and the first outer side wall are located on both sides of the first bottom wall and are perpendicular to the first bottom wall, and the first containing groove is used to contain a crushed stone cushion layer; The second inner side wall and the second outer side wall are located on both sides of the second bottom wall and are perpendicular to the second bottom wall. The second containing groove is used for containing a gravel cushion layer.

6. The track infrastructure according to claim 1, characterized in that At least one pile foundation is respectively arranged on the first bottom wall and the second bottom wall.

7. The track infrastructure according to claim 1, characterized in that A mattress layer is disposed on the first bottom wall and the second bottom wall respectively, and a reinforcement pile is disposed on a side of the mattress layer away from the first bottom wall or the second bottom wall.

8. The track infrastructure according to claim 1, characterized in that The track infrastructure structure can be applied to a plurality of parallel tracks. A first intermediate side wall is further provided on the first bottom wall. The first intermediate side wall is located between the first inner side wall and the first outer side wall. The first intermediate side wall, the first inner side wall and a portion of the first bottom wall are arranged to form a first inner receiving groove. The first intermediate side wall, the first outer side wall and a portion of the first bottom wall are arranged to form a first outer receiving groove. A second middle side wall is also provided on the second bottom wall, and the second middle side wall is located between the second inner side wall and the second outer side wall. The second middle side wall, the second inner side wall and a part of the second bottom wall are arranged to form a second inner accommodating groove, and the second middle side wall, the second outer side wall and a part of the second bottom wall are arranged to form a second outer accommodating groove.

9. The track infrastructure according to claim 1, characterized in that A cantilever plate is also provided on at least one of the first outer side wall and the second outer side wall.

10. The track infrastructure according to claim 1, characterized in that The tension beam is a prefabricated tension beam, and a splicing structure is formed between the first inner side wall, the second inner side wall and the tension beam.

11. The track infrastructure according to claim 10, characterized in that The splicing structure includes any one of the following or a combination thereof: a keyway matching mechanism, a hole-shaft matching mechanism.

12. The track infrastructure according to claim 11, characterized in that A shear groove is provided at the top end of the first inner wall or the second inner wall, and pins are provided on both sides of the shear groove along the first direction; shear keys matching with the shear groove and reserved holes matching with the pin gap are provided at both ends of the tension beam, and a filling layer is provided in the annular gap between the pin and the reserved hole.

13. The track infrastructure according to claim 12, characterized in that The diameter of the reserved hole is 5 mm larger than the diameter of the pin.

Citation Information

Cited By

  • Track foundation structure and construction method thereof

    CN118065181A