Mine roadway bottom plate anchoring and top injection type pre-stressed anchor cable reinforcing device
By setting drilling and casing components under the bottom plate of the mine tunnel, combined with anchoring agent and cement slurry, the problems of low installation efficiency and poor tightening effect of anchor cable reinforcement devices in the prior art are solved, and more efficient reinforcement and simplification are achieved installation process.
Patent Information
- Application Number
- CN202420829805.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-22
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The mixing head diameter of the existing mine tunnel bottom plate lower anchor prestressed anchor cable reinforcement device has a large diameter, resulting in a long drilling operation time, reducing installation efficiency, and a single reinforcement method and poor tightening effect.
A prestressed anchor cable reinforcement device for lower anchors on the bottom plate of mine tunnels was designed. By setting drilling holes one and drilling hole two, anchoring agent and stable cement slurry are used for reinforcement, and the anchor cable is lifted through casing assembly and wedge member. The friction and fastening force of the body simplifies the device structure and facilitates installation.
The drilling length is shortened, the deployment speed is improved, the tightening force and structural strength of reinforcement are improved, and the installation process is simplified.
Smart Images

Figure CN222045825U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of mine tunnel floor heave prevention and control, in particular to a mine tunnel floor plate lower anchor upper injection type prestressed anchor cable reinforcement device. Background Art
[0002] In mining projects, the safety and stability of underground tunnels are crucial to ensuring production and the safety of workers' lives and property. However, due to the influence of geological conditions, tunnel structures and mining activities, the tunnel floor is often subjected to various forms of extrusion, deformation and damage, which seriously threatens the operation of the mine and the safety of workers. Therefore, a prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel is designed.
[0003] China Utility Model Patent Publication No.: CN 203189049 U, discloses: a prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel, the prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel uses anchor cables to reinforce the bottom plate of the tunnel, because the anchor cables can be bent, anchor cables of any length can be mixed with resin anchoring agents in the bottom plate drilled holes, and can provide effective anchoring for the bottom plate of the tunnel under any geological conditions, realize timely and active support, and prevent and control the bottom bulge of the tunnel, but the prestressed anchor cable reinforcement device for the bottom plate of the mine tunnel has a large diameter of the stirring head and a high requirement for the borehole diameter, resulting in a long drilling operation time, reducing the installation efficiency, and relying on the combination of anchor cables and resin anchoring agents to improve the reinforcement effect, the reinforcement means are relatively single, and the tightening effect is poor. Summary of the invention
[0004] The utility model aims to provide a prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel, which can solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel, which is arranged on a rock stratum, wherein a borehole 1 is opened inside the rock stratum, and a borehole 2 is opened at the upper end of the rock stratum, the interior of the borehole 1 is filled with an anchoring agent, the interior of the borehole 2 is filled with stabilizing cement slurry, an anchor cable body is arranged inside the borehole 1, a mounting part is arranged at the upper end of the anchor cable body, a rigging is arranged on the outside of the anchor cable body, a casing assembly is arranged at the upper end of the rigging, and a wedge is arranged inside the casing assembly.
[0006] Preferably, the rigging includes a limit plate, a circular tube, a sealing plate, a spiral sheet, a grouting pipe, a grouting hole and a limit ring, the lower end of the limit plate is fixedly connected to the circular tube, the lower end of the circular tube is fixedly connected to the sealing plate, the outer side of the circular tube is fixedly connected to the spiral sheet, the lower end of the limit plate is fixedly connected to the grouting pipe, the upper end of the limit plate is provided with a grouting hole, and the upper end of the limit plate is fixedly connected to the limit ring.
[0007] Preferably, the inner diameter of the borehole one is larger than the diameter of the anchor body, the inner diameter of the borehole two is larger than the diameter of the spiral sheet, the inner diameter of the borehole two is smaller than the diameter of the limit plate, and the sealing plate is adapted to the borehole two.
[0008] Preferably, the sleeve assembly comprises a sleeve body, a groove, a bevel and a long groove, the lower end of the sleeve body is provided with a groove, the inner wall of the sleeve body is provided with a bevel, and the outer side of the sleeve body is provided with a long groove.
[0009] Preferably, the wedge-shaped member comprises an inclined tube and anti-slip ribs, and the interior of the inclined tube is fixedly connected with the anti-slip ribs.
[0010] Preferably, the inclined surface is matched with the inclined tube, and the outer wall of the inclined tube and the inner wall of the sleeve body are both provided with threads.
[0011] Preferably, the grouting pipe passes through the sealing plate and the limiting plate, and the groove is matched with the limiting ring.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] The utility model inserts the anchor cable body into the round tube through the provided drilling hole 1 and drilling hole 2, the anchor cable body is inserted into the drilling hole 1, the rigging is inserted into the drilling hole 2, an anchoring agent is injected into the drilling hole 1 through a grouting pipe, and a stable cement slurry is injected through the grouting hole, so as to facilitate reinforcement;
[0014] The utility model provides a sleeve assembly that cooperates with a wedge to fix the anchor cable body and the rigging, and the wedge is sleeved on the outside of the anchor cable body through the provided wedge, and the mounting piece is connected to the mounting equipment, and the anchor cable body is driven to rotate and inserted into the drill hole one, and the anti-skid ribs increase the friction with the anchor cable body, and the wedge rotates with the anchor cable body, and the sleeve body is inserted into the round tube through the provided sleeve body, and the wedge rotates with the anchor cable body and is threadedly connected with the sleeve body. As the wedge extends into the interior of the sleeve body, the enlarged tail of the inclined tube opens the outside of the sleeve body, and the sleeve assembly is tightened inside the round tube of the rigging, and the rigging and the sleeve assembly rotate with the anchor cable body, and the anchor cable body is mixed and combined with the anchoring agent, and the spiral sheet is mixed and combined with the stable cement slurry, thereby improving the fastening force, having high structural strength, a small aperture of the drill hole one, a short length of the drill hole two, low drilling difficulty, fast deployment speed, simple structure of the device, and easy installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the three-dimensional cross-sectional structure of the utility model;
[0016] Figure 2 This is an enlarged structural diagram of the anchor cable body and the mounting parts of the utility model;
[0017] Figure 3 This is a schematic diagram of the disassembled structure of the anchor cable body and the mounting parts of the utility model;
[0018] Figure 4 It is an enlarged structural diagram of the casing assembly and the wedge-shaped member of the utility model;
[0019] Figure 5 It is a schematic diagram of the three-dimensional cross-sectional structure of the sleeve assembly and the wedge-shaped member of the utility model.
[0020] Among them: 1. rock layer; 2. drilling hole 1; 3. drilling hole 2; 4. anchoring agent; 5. stabilizing cement slurry; 6. anchor cable body; 7. mounting parts; 8. rigging; 801. limit plate; 802. round tube; 803. sealing plate; 804. spiral sheet; 805. grouting pipe; 806. grouting hole; 807. limit ring; 9. casing assembly; 901. casing body; 902. groove; 903. inclined surface; 904. long groove; 10. wedge; 1001. inclined tube; 1002. anti-skid rib. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0022] Example 1
[0023] See also Figure 1-4 In the figure, a prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel is arranged on a rock layer 1. A borehole 2 is opened inside the rock layer 1, and a borehole 3 is opened at the upper end of the rock layer 1. The inside of the borehole 2 is filled with an anchoring agent 4, and the inside of the borehole 3 is filled with a stabilizing cement slurry 5. An anchor cable body 6 is arranged inside the borehole 2, and a mounting part 7 is arranged at the upper end of the anchor cable body 6. A rigging 8 is arranged on the outside of the anchor cable body 6, and a casing assembly 9 is arranged at the upper end of the rigging 8. A wedge 10 is arranged inside the casing assembly 9.
[0024] See also Figure 1-4In the figure, a prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel is arranged on a rock layer 1. A borehole 2 is opened inside the rock layer 1, and a borehole 3 is opened at the upper end of the rock layer 1. The inside of the borehole 2 is filled with an anchoring agent 4, and the inside of the borehole 3 is filled with a stabilizing cement slurry 5. An anchor cable body 6 is arranged inside the borehole 2, and a mounting part 7 is arranged at the upper end of the anchor cable body 6. A rigging 8 is arranged on the outside of the anchor cable body 6, and a casing assembly 9 is arranged at the upper end of the rigging 8. A wedge 10 is arranged inside the casing assembly 9.
[0025] In this embodiment: the anchor cable body 6 is reinforced by the provided rigging 8 .
[0026] Working principle: when in use, drill hole 1 2 and drill hole 2 3 are opened on the rock layer 1, the wedge 10 is sleeved on the outside of the anchor cable body 6, the casing body 901 is inserted into the round tube 802, the anchor cable body 6 is inserted into the drill hole 1 2, the rigging 8 is inserted into the drill hole 2 3, the anchoring agent 4 is injected into the drill hole 1 2 through the grouting pipe 805, the stabilizing cement slurry 5 is injected through the grouting hole 806, the anchor cable body 5 connects the mounting part 7 with the mounting equipment, the anchor cable body 6 is driven to rotate and inserted into the drill hole 1 2, the anti-skid rib 1002 is lifted and connected to the anchor cable body 6, the wedge 10 rotates with the anchor body 6, the wedge 10 rotates with the anchor body 6, and is threadedly connected to the casing body 901. As the wedge 10 extends into the interior of the casing body 901, the enlarged tail of the inclined tube 1001 opens the outside of the casing body 901, and tightens the casing assembly 9 inside the round tube 802 of the rigging 8. The rigging 8 and the casing assembly 9 rotate with the anchor body 6, the anchor body 6 and the anchor agent 4 are mixed and combined, and the spiral piece 804 is mixed and combined with the stabilizing cement slurry 5, thereby improving the fastening force.
[0027] Example 2
[0028] See also Figure 1-5 This embodiment further explains Example 1. In the figure, the inner diameter of borehole 1 2 is larger than the diameter of the anchor body 6, the inner diameter of borehole 2 3 is larger than the diameter of the spiral piece 804, the inner diameter of borehole 2 3 is smaller than the diameter of the limit plate 801, and the sealing plate 803 is compatible with borehole 2 3.
[0029] In this embodiment: through the set drilling hole 2 and drilling hole 2 3, the anchor body 6 is inserted into the circular tube 802, the anchor body 6 is inserted into the drilling hole 2, the rigging 8 is inserted into the drilling hole 2 3, the anchoring agent 4 is injected into the drilling hole 2 through the grouting pipe 805, and the stabilizing cement slurry 5 is injected through the grouting hole 806 to facilitate reinforcement.
[0030] See also Figure 3-5In the figure, the sleeve assembly 9 includes a sleeve body 901, a groove 902, a slope 903 and a long groove 904. The lower end of the sleeve body 901 is provided with a groove 902, the inner wall of the sleeve body 901 is provided with a slope 903, and the outer side of the sleeve body 901 is provided with a long groove 904.
[0031] In this embodiment, the anchor cable body 6 and the rigging 8 are fixed by means of the sleeve assembly 9 which cooperates with the wedge-shaped member 10 .
[0032] See also Figure 3-5 In the figure, the wedge-shaped member 10 includes an inclined tube 1001 and an anti-slip rib 1002 , and the interior of the inclined tube 1001 is fixedly connected with the anti-slip rib 1002 .
[0033] In this embodiment: by setting the wedge-shaped piece 10, the wedge-shaped piece 10 is sleeved on the outside of the anchor body 6, the mounting piece 7 is connected to the mounting equipment, the anchor body 6 is driven to rotate and inserted into the drill hole 2, the anti-slip ribs 1002 increase the friction with the anchor body 6, and the wedge-shaped piece 10 rotates with the anchor body 6.
[0034] See also Figure 3-5 In the figure, the inclined surface 903 is matched with the inclined tube 1001, and the outer wall of the inclined tube 1001 and the inner wall of the sleeve body 901 are both provided with threads.
[0035] In this embodiment: through the provision of the sleeve body 901, the sleeve body 901 is inserted into the round tube 802, the wedge 10 rotates with the anchor body 6 and is threadedly connected to the sleeve body 901, as the wedge 10 extends into the interior of the sleeve body 901, the enlarged tail of the inclined tube 1001 stretches the outer edge of the sleeve body 901, and the sleeve assembly 9 is tightened inside the round tube 802 of the rigging 8, the rigging 8 and the sleeve assembly 9 rotate with the anchor body 6, the anchor body 6 and the anchor agent 4 are stirred and combined, the spiral piece 804 and the stabilizing cement slurry 5 are stirred and combined, the spiral piece 804 improves the fastening force, the structure of the device is simple, and it is easy to install.
[0036] See also Figure 3-5 In the figure, the grouting pipe 805 passes through the sealing plate 803 and the limiting plate 801, and the groove 902 is adapted to the limiting ring 807.
[0037] In this embodiment, the sleeve assembly 9 and the rigging 8 are limited by the provided groove 902 and the limiting ring 807 .
[0038] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include"-"comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process-method-article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process-method-article or device.
[0039] Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A prestressed anchor cable reinforcement device for a mine tunnel floor, arranged on a rock layer (1), characterized in that: A borehole 1 (2) is provided inside the rock layer (1), a borehole 2 (3) is provided at the upper end of the rock layer (1), the interior of the borehole 1 (2) is filled with an anchoring agent (4), the interior of the borehole 2 (3) is filled with a stabilizing cement slurry (5), an anchor cable body (6) is provided inside the borehole 1 (2), a mounting member (7) is provided at the upper end of the anchor cable body (6), a rigging (8) is provided on the outer side of the anchor cable body (6), a casing assembly (9) is provided at the upper end of the rigging (8), and a wedge-shaped member (10) is provided inside the casing assembly (9).
2. The prestressed anchor cable reinforcement device for the bottom plate of a mine tunnel according to claim 1 is characterized by: The rigging (8) comprises a limit plate (801), a circular tube (802), a sealing plate (803), a spiral piece (804), a grouting pipe (805), a grouting hole (806) and a limit ring (807); the lower end of the limit plate (801) is fixedly connected to the circular tube (802); the lower end of the circular tube (802) is fixedly connected to the sealing plate (803); the outer side of the circular tube (802) is fixedly connected to the spiral piece (804); the lower end of the limit plate (801) is fixedly connected to the grouting pipe (805); the upper end of the limit plate (801) is provided with a grouting hole (806); and the upper end of the limit plate (801) is fixedly connected to the limit ring (807).
3. The device for reinforcing the bottom plate of a mine tunnel according to claim 2 is characterized by: The inner diameter of the borehole one (2) is greater than the diameter of the anchor cable body (6), the inner diameter of the borehole two (3) is greater than the diameter of the spiral sheet (804), the inner diameter of the borehole two (3) is smaller than the diameter of the limit plate (801), and the sealing plate (803) is compatible with the borehole two (3).
4. The device for reinforcing the bottom plate of a mine tunnel according to claim 3 is characterized by: The sleeve assembly (9) comprises a sleeve body (901), a groove (902), an inclined surface (903) and a long groove (904); the lower end of the sleeve body (901) is provided with a groove (902); the inner wall of the sleeve body (901) is provided with an inclined surface (903); and the outer side of the sleeve body (901) is provided with a long groove (904).
5. The device for reinforcing the bottom plate of a mine tunnel according to claim 4 is characterized by: The wedge-shaped member (10) comprises an inclined tube (1001) and anti-slip ribs (1002), and the interior of the inclined tube (1001) is fixedly connected with the anti-slip ribs (1002).
6. The device for reinforcing the bottom plate of a mine tunnel according to claim 5, characterized in that: The inclined surface (903) is matched with the inclined tube (1001), and the outer wall of the inclined tube (1001) and the inner wall of the sleeve body (901) are both provided with threads.
7. The device for reinforcing the bottom plate of a mine tunnel according to claim 6 is characterized by: The grouting pipe (805) passes through the sealing plate (803) and the limiting plate (801), and the groove (902) is matched with the limiting ring (807).
Citation Information
Cited By
A cable anchor securing device
WO2026137026A1