Foam concrete lifting and widening embankment construction structure without traffic interruption in highway reconstruction and extension

Through temporary fence supporting steel pipe pile racks and prefabricated baffles, highway reconstruction and expansion without interruption of traffic have been achieved, construction noise, vibration and cost problems have been solved, construction efficiency and roadbed stability have been improved, and highway reconstruction has been ensured. Quality and safety of the expansion.

CN222083234UActive Publication Date: 2024-11-29HUBEI ROAD & BRIDGE GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420477113.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-12
Publication Date
2024-11-29
Estimated Expiration
2034-03-12

AI Technical Summary

Technical Problem

Highway renovation and expansion without interrupting traffic requires an effective traffic management plan to reduce the impact of construction noise and vibration on surrounding residents, while reducing costs and improving construction efficiency to ensure project quality.

Method used

Temporary fence support steel pipe pile racks, prefabricated baffles with brackets, fixed cantilever plates, guardrail bases, fixed auxiliary installation brackets, integrated blind pipe drainage system and prefabricated assembled foundation base plates, through these The structure achieves rapid installation and drainage, improving construction efficiency and safety.

Benefits of technology

It has achieved rapid widening and raising of road embankments during highway renovation and expansion, ensuring smooth traffic, reducing construction noise and vibration, improving construction efficiency and safety, reducing costs, and enhancing the stability and anti-solution capability of the roadbed.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083234U_ABST
    Figure CN222083234U_ABST
Patent Text Reader

Abstract

The utility model relates to a traffic-uninterrupted foam concrete lifting and widening embankment construction structure for highway reconstruction and extension, which comprises a temporary fence supporting steel pipe pile bent frame, a prefabricated baffle plate with a clamping support, a shaped cantilever plate, a guardrail base, a shaped auxiliary mounting bracket, an integral blind pipe drainage system and a prefabricated foundation slab, the temporary fence supporting steel pipe pile framed bent is arranged on an original roadbed at a medial strip, the prefabricated baffles with the clamping supports are arranged on the inner sides of the steel pipe piles, the shaped cantilever plates are arranged at the tops of the steel pipe piles and the prefabricated baffles, and the integral blind pipe drainage system is arranged at roadbed steps. The finalization auxiliary installation support is used for assisting installation of the prefabricated baffle with the clamping support, the prefabricated assembly type foundation bottom plate is arranged on the outer side face of the bottom of the roadbed step, and the prefabricated protection face plate is arranged on the outer side face of the prefabricated assembly type foundation bottom plate. The road reconstruction and extension project can be completed without interrupting traffic, convenience is provided for urban traffic development, and the method has wide application prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to a construction structure for raising and widening a foam concrete embankment during highway reconstruction and expansion without interrupting traffic, belongs to the field of civil engineering, and is suitable for the construction of raising and widening a foam concrete embankment during highway reconstruction and expansion without interrupting traffic. Background Art

[0002] Highway traffic plays a vital role in modern society. However, in order to adapt to the growing vehicle traffic and the needs of urban development, it is inevitable to renovate and expand existing roads. However, traditional highway renovation and expansion usually requires interrupting traffic, causing inconvenience to road users and surrounding residents. Therefore, it is imperative to find a renovation and expansion method that does not interrupt traffic. As a lightweight material, foam concrete has excellent thermal insulation, sound insulation and seismic resistance, and is widely used in roadbed and embankment engineering. In this context, exploring the method of using foam concrete to raise and widen embankments has become a forward-looking research task.

[0003] The technical principle of raising and widening the embankment with foamed concrete is based on the lightweight nature and excellent mechanical properties of the material. First, by injecting foamed concrete at the bottom of the embankment, the weight of the embankment is effectively reduced, thereby reducing the bearing pressure of the foundation. Secondly, foamed concrete has good compressive strength and can effectively support the road surface load. In this way, not only can the stability of the embankment be maintained during the reconstruction and expansion process, but the bearing capacity of the embankment can also be improved to meet the traffic needs of a larger flow rate. During the construction process, a segmented construction method can be adopted to ensure continuous and smooth traffic.

[0004] The implementation of the construction method of raising and widening the embankment with foamed concrete requires a series of scientific and reasonable steps. First, the embankment is carefully surveyed and designed to determine the construction plan. Then, foamed concrete is injected into the bottom of the embankment using professional equipment to gradually increase the height of the embankment. During the injection process, the stability of the embankment needs to be monitored to ensure that it does not cause danger to traffic. Finally, after the foamed concrete solidifies, the road surface can be repaved and rebuilt to meet the new traffic needs. Through scientific and reasonable construction methods, highway reconstruction and expansion projects can be completed without interrupting traffic, providing convenience for urban transportation development.

[0005] Although the method of highway reconstruction and expansion without interrupting traffic and using foam concrete to raise and widen the embankment has many advantages, it still needs to solve some technical problems: to carry out highway reconstruction and expansion without interrupting traffic, it is necessary to formulate an effective traffic management plan to ensure the safety of road users and construction workers. At the same time, it is necessary to consider the impact of noise and vibration that may be caused during the construction process on surrounding residents and formulate reasonable shock absorption and sound insulation measures; at the same time, the construction cost and benefit of using foam concrete to raise and widen the embankment are also factors that need to be considered. It is crucial to study how to reduce costs and improve construction efficiency while ensuring project quality for the solution of technical problems. Utility Model Content

[0006] The purpose of this application is to address the above-mentioned problems existing in the prior art and to provide a foam concrete raised and widened embankment construction structure for highway reconstruction and expansion without interrupting traffic.

[0007] In order to achieve the above application purpose, this application adopts the following technical solutions: The construction structure of the foam concrete raised widening embankment for highway reconstruction and expansion without interrupting traffic includes a temporary enclosure supporting steel pipe pile rack, a prefabricated baffle with a bracket, a standardized cantilever plate, a guardrail base, a standardized auxiliary installation bracket, an integral blind pipe drainage system and a prefabricated assembled foundation bottom plate;

[0008] The temporary enclosure supporting steel pipe pile rack is set on the original roadbed at the central dividing strip, including diagonal braces and steel pipe piles. Diagonal braces are set on the sides of the steel pipe piles, and the bottom of the diagonal braces is supported on the original roadbed;

[0009] The prefabricated baffle is arranged on the inner side of the steel pipe pile, and includes a semicircular bracket, a prefabricated baffle, and a cable. The outer side of the prefabricated baffle is provided with a semicircular bracket, and the inner side of the prefabricated baffle is provided with a cable, and the other end of the cable is anchored in the original roadbed; the shape of the semicircular bracket adopts an arc design, which is linearly consistent with the side of the steel pipe pile;

[0010] The standardized cantilever plate is arranged on the top of the steel pipe pile and the prefabricated baffle plate, and includes the standardized cantilever plate, the drainage groove, the drainage groove water pipe hole, and the steel pipe pile plug hole. The top of the standardized cantilever plate is provided with a steel pipe pile plug hole, the edge of the standardized cantilever plate is provided with a drainage groove, and the drainage groove water pipe hole is arranged at the bottom of the drainage groove;

[0011] The guardrail base is arranged above the shaped cantilever plate, a guardrail is arranged on the top of the guardrail base, and a guardrail handrail is arranged on the top of the guardrail;

[0012] The integrated blind pipe drainage system is installed at the roadbed step, including horizontal pipes, vertical pipes, longitudinal long pipes, and transverse pipes. The transverse pipes are connected to the center of the side of the horizontal pipe in sequence, one end of the horizontal pipe is connected to the center of the side of the vertical pipe, one end of the horizontal pipe is connected to the end of the vertical pipe, and the end of the longitudinal long pipe is connected to the end of the outermost vertical pipe;

[0013] The standardized auxiliary installation bracket is used to assist the installation of the prefabricated baffle with a bracket, and is placed on the top of the original roadbed on the construction side, including an inverted U-shaped clamping piece, a telescopic support rod, a telescopic jack, a prefabricated baffle, a lifting column, an adjustment jack, and a support base; an adjustment jack is provided on the top of the support base, a lifting column is provided on the top of the adjustment jack, a telescopic jack is provided on the side of the top of the lifting column, the telescopic jack is connected to the telescopic support rod, and the end of the telescopic support rod is connected to the inner side of the inverted U-shaped clamping piece;

[0014] The prefabricated assembled foundation slab is arranged on the bottom outer side of the roadbed step, and a prefabricated protective panel is arranged on the outer side of the prefabricated assembled foundation slab.

[0015] Furthermore, a pile hole is provided at the central dividing strip on the top of the original roadbed, and the steel pipe pile is inserted into the pile hole. A blind ditch drainage diversion groove is provided on the top of the original roadbed at the bottom of the steel pipe pile; the top of the steel pipe pile passes through the steel pipe pile insertion hole and is secured with fixing bolts; the semicircular bracket is clamped on the side of the steel pipe pile, and the inverted U-shaped clamp is clamped on the top of the prefabricated baffle.

[0016] Furthermore, an anchor cable is provided on the inner side of the prefabricated guard panel, and the other end of the anchor cable is anchored on the original roadbed; a foam concrete embankment is provided on the top of the original roadbed between the prefabricated baffle and the prefabricated guard panel.

[0017] Furthermore, the inner side surface of the prefabricated guard panel is provided with dowels, which are inserted into the dowel reserved holes on the bottom outer side surface of the roadbed step; the bottom sides of the prefabricated guard panel and the prefabricated assembled foundation slab are respectively provided with guard panel reserved holes and foundation slab reserved holes, and the longitudinal long tube passes through the guard panel reserved holes and the foundation slab reserved holes in turn.

[0018] Furthermore, a horizontal hole of the original roadbed and a vertical hole of the original roadbed are arranged in sequence below the roadbed step, and a horizontal pipe and a vertical pipe are arranged in the horizontal hole of the original roadbed and the vertical hole of the original roadbed in sequence.

[0019] Furthermore, when the original roadbed encounters a river channel, a steel frame is provided on the outer side of the prefabricated assembled foundation bottom plate, a shelf groove is provided on the top of the steel frame, a cast-in-place pile is provided on the bottom of the steel frame, and the gabion stone cage is placed in the shelf groove.

[0020] Furthermore, a standardized cantilever plate reserved hole is provided in the standardized cantilever plate, and an inverted L-shaped drain pipe is installed in the standardized cantilever plate reserved hole. The top of the standardized cantilever plate reserved hole is connected to the drainage trough water pipe hole, and the bottom of the inverted L-shaped drain pipe is located in the blind ditch drainage diversion trough.

[0021] Compared with the prior art, the utility model has the following outstanding advantages and significant effects:

[0022] 1. The prefabricated baffle with a clip in the utility model has an ingenious structural design, and utilizes the semicircular clip on the side of the baffle to achieve rapid positioning and fixing, which greatly improves the construction efficiency and makes it feasible to widen the embankment during the highway reconstruction and expansion process without interrupting traffic.

[0023] 2. The utility model adopts a standardized cantilever plate to quickly install the guardrail. By setting the drainage trough and the inverted L-shaped drainage pipe, the foam concrete can be raised and widened to achieve rapid drainage of rainwater in the roadbed, thus ensuring the stability of the roadbed.

[0024] 3. The utility model adopts the anti-scour technology of cast-in-place piles and steel frame gabion cages in the waterside section. By utilizing the shelving groove of the steel frame, the gabion cages can be quickly stacked and stabilized, thereby improving the anti-scour capacity of the roadbed in the temporary waterside section.

[0025] 4. The utility model adopts a standardized auxiliary installation prefabricated baffle bracket structure, which has a simple structure and can achieve rapid positioning. The inverted U-shaped clamping piece is quickly adjusted by a jack to stabilize the prefabricated baffle, which greatly improves construction efficiency and construction safety.

[0026] 5. The utility model adopts an integral blind pipe drainage system, which solves the problem of blockage of drainage holes in traditional drainage construction by connecting the drainage pipes at the roadbed vertically, horizontally and vertically, and improves the stability of the roadbed soil. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a three-dimensional schematic diagram of the utility model. Figure 1 ;

[0028] Figure 2 This is a schematic elevation diagram of the utility model. Figure 1 ;

[0029] Figure 3 It is a three-dimensional schematic diagram of the utility model. Figure 2 ;

[0030] Figure 4 This is a schematic elevation diagram of the utility model. Figure 2 ;

[0031] Figure 5 It is a three-dimensional schematic diagram of the construction of prefabricated baffles assisted by steel sheet piles and standardized brackets in the roadbed;

[0032] Figure 6 It is a schematic elevation diagram of the construction of prefabricated baffles assisted by steel sheet piles and standardized brackets in the roadbed;

[0033] Figure 7 It is a three-dimensional schematic diagram of the roadbed lead hole;

[0034] Figure 8It is a three-dimensional schematic diagram of the structure of the prefabricated baffle bracket for the standardized auxiliary installation;

[0035] Fig. 9 It is a three-dimensional schematic diagram of the standardized guardrail construction;

[0036] Fig.10 It is a three-dimensional schematic diagram of the shaped cantilever slab;

[0037] Fig.11 It is a three-dimensional schematic diagram of the prefabricated foundation slab;

[0038] Fig.12 It is a three-dimensional schematic diagram of an inverted L-shaped drain pipe;

[0039] Fig.13 It is a three-dimensional schematic diagram of the integral blind pipe drainage system.

[0040] In the figure, 1, roadbed step; 2, original roadbed; 3, pile hole; 4, diagonal brace; 5, blind ditch drainage diversion channel; 6, semicircular bracket; 7, steel pipe pile; 8, inverted U-shaped clamp; 9, telescopic support rod; 10, telescopic jack; 11, prefabricated baffle; 12, cable; 13, lifting column; 14, adjustment jack; 15, support base; 16, inverted L-shaped drainage pipe; 17, stereotyped cantilever plate; 18, fixing bolt; 19, guardrail handrail; 20, guardrail; 21, diversion channel; 22, guardrail base; 23, anchor cable; 24, prefabricated guard plate; 25, prefabricated Prefabricated foundation slab; 26. Shelving trough; 27. Steel frame; 28. Cast-in-place piles; 29. ​​Foam concrete embankment; 30. Gabion stone cage; 31. Standardized cantilever slab reserved holes; 32. Drainage trough water pipe holes; 33. Guard plate reserved holes; 34. Foundation slab reserved holes; 35. Inserted reinforcement; 36. Inserted reinforcement reserved holes; 37. Horizontal holes of original roadbed; 38. Vertical holes of original roadbed; 39. Horizontal pipe; 40. Vertical pipe; 41. Steel pipe pile insertion hole; 42. Integral blind pipe drainage system; 43. Longitudinal long pipe; 44. Horizontal pipe; 45. Standardized auxiliary installation bracket. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of this application.

[0042] Those skilled in the art should understand that, in the disclosure of the present application, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, which are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be understood as limiting the present application.

[0043] like Figure 1-13 As shown, the construction structure of the foam concrete raised widening embankment for the highway reconstruction and expansion without interrupting traffic includes a temporary enclosure supporting steel pipe pile rack, a prefabricated baffle 11 with a bracket, a standardized cantilever plate 17, a guardrail base 22, a standardized auxiliary installation bracket 45, an integral blind pipe drainage system 42 and a prefabricated assembled foundation bottom plate 25;

[0044] The temporary enclosure supporting steel pipe pile rack is arranged on the original roadbed 2 at the central dividing strip, including diagonal braces 4 and steel pipe piles 7. The steel pipe piles 7 are provided with diagonal braces 4 on the side, and the bottom of the diagonal braces 4 is supported on the original roadbed 2.

[0045] Among them, a pile hole 3 is provided at the central dividing strip at the top of the original roadbed 2, and a steel pipe pile 7 is inserted into the pile hole 3. A blind ditch drainage diversion groove 5 is provided at the top of the original roadbed 2 at the bottom of the steel pipe pile 7; the top of the steel pipe pile 7 passes through the steel pipe pile insertion hole 41 and is fixed with a fixing bolt 18; the semicircular bracket 6 is clamped on the side of the steel pipe pile 7, and the inverted U-shaped clamping piece 8 is clamped on the top of the prefabricated baffle 11. The original roadbed horizontal hole 37 and the original roadbed vertical hole 38 are arranged in sequence below the roadbed step 1, and the horizontal pipe 39 and the vertical pipe 40 are arranged in the original roadbed horizontal hole 37 and the original roadbed vertical hole 38 in sequence.

[0046] Preferably, a standardized cantilever plate reserved hole 31 is provided in the standardized cantilever plate 17, and the inverted L-shaped drain pipe 16 is installed in the standardized cantilever plate reserved hole 31. The top of the standardized cantilever plate reserved hole 31 is connected to the drainage trough water pipe hole 32, and the bottom of the inverted L-shaped drain pipe 16 is located in the blind ditch drainage diversion trough 5.

[0047] The prefabricated baffle 11 is arranged on the inner side of the steel pipe pile 7, and includes a semicircular bracket 6, a prefabricated baffle 11, and a cable 12. The outer side of the prefabricated baffle 11 is provided with a semicircular bracket 6, and the inner side of the prefabricated baffle 11 is provided with a cable 12, and the other end of the cable 12 is anchored in the original roadbed 2; the shape of the semicircular bracket 6 is designed in an arc shape, which is linearly consistent with the side of the steel pipe pile 7;

[0048] The shaped cantilever plate 17 is arranged on the top of the steel pipe pile 7 and the prefabricated baffle plate 11, and includes the shaped cantilever plate 17, the drainage groove 21, the drainage groove water pipe hole 32, and the steel pipe pile insertion hole 41. The top of the shaped cantilever plate 17 is provided with the steel pipe pile insertion hole 41, the edge of the shaped cantilever plate 17 is provided with the drainage groove 21, and the drainage groove water pipe hole 32 is arranged at the bottom of the drainage groove 21;

[0049] The guardrail base 22 is arranged above the shaped cantilever plate 17, the top of the guardrail base 22 is provided with a guardrail 20, and the top of the guardrail 20 is provided with a guardrail handrail 19;

[0050] The integrated blind pipe drainage system 42 is arranged at the roadbed step 1, and includes a horizontal pipe 39, a vertical pipe 40, a longitudinal long pipe 43, and a transverse pipe 44. The transverse pipe 44 is connected to the center of the side of the horizontal pipe 39 in sequence, one end of the horizontal pipe 39 is connected to the center of the side of the vertical pipe 40, one end of the horizontal pipe 39 is connected to the end of the vertical pipe 40, and the end of the longitudinal long pipe 43 is connected to the end of the outermost vertical pipe 40;

[0051] The standardized auxiliary installation bracket 45 is used to assist the installation of the prefabricated baffle 11 with a card holder, and is placed on the top of the original roadbed 2 on the construction side, including an inverted U-shaped clamping piece 8, a telescopic support rod 9, a telescopic jack 10, a prefabricated baffle 11, a lifting column 13, an adjustment jack 14, and a support base 15; the top of the support base 15 is provided with an adjustment jack 14, the top of the adjustment jack 14 is provided with a lifting column 13, the top side of the lifting column 13 is provided with a telescopic jack 10, the telescopic jack 10 is connected to the telescopic support rod 9, and the end of the telescopic support rod 9 is connected to the inner side of the inverted U-shaped clamping piece 8;

[0052] The prefabricated assembled foundation slab 25 is arranged on the outer side of the bottom of the roadbed step 1 , and a prefabricated protective panel 24 is arranged on the outer side of the prefabricated assembled foundation slab 25 .

[0053] Among them, the inner side of the prefabricated guard panel 24 is provided with an anchor cable 23, and the other end of the anchor cable 23 is anchored on the original roadbed 2; a foam concrete embankment 29 is provided on the top of the original roadbed 2 between the prefabricated baffle 11 and the prefabricated guard panel 24. The inner side of the prefabricated guard panel 24 is provided with a dowel 35, and the dowel 35 is inserted into the dowel reserved hole 36 on the bottom outer side of the roadbed step 1; the bottom sides of the prefabricated guard panel 24 and the prefabricated assembled foundation bottom plate 25 are respectively provided with a guard panel reserved hole 33 and a foundation bottom plate reserved hole 34, and the longitudinal long tube 43 passes through the guard panel reserved hole 33 and the foundation bottom plate reserved hole 34 in sequence.

[0054] Preferably, when the original roadbed 2 encounters a river channel, a steel frame 27 is provided on the outer side of the prefabricated assembled foundation bottom plate 25, a shelf groove 26 is provided on the top of the steel frame 27, a cast-in-place pile 28 is provided on the bottom of the steel frame 27, and a gabion stone cage 30 is placed in the shelf groove 26.

[0055] Example 2

[0056] Based on the structure of Example 1, the construction method of the highway reconstruction and expansion without interrupting traffic with foam concrete raised and widened embankment in this embodiment includes the following steps:

[0057] S00, component customization and traffic diversion:

[0058] Customize the prefabricated assembled foundation slab 25, prefabricated protective panel 24, horizontal pipe 39, vertical pipe 40, longitudinal long pipe 43, prefabricated baffle 11 with bracket and transverse pipe 44 in the factory; at the same time, carry out half-width traffic diversion construction at the central dividing strip of the original roadbed 2;

[0059] S10, Steel Pipe Pile 7 Drilling Hole:

[0060] Pile holes 3 are constructed on the top of the original roadbed 2 at the central dividing strip;

[0061] S20, Steel Pipe Pile 7 Construction:

[0062] The steel pipe piles 7 are hoisted into the pile holes 3 in sequence by a crane, and at the same time, the diagonal braces 4 are constructed on the outside of the steel pipe piles 7 so that the bottom of the diagonal braces 4 is supported on the original roadbed 2;

[0063] Among them, a standardized cantilever plate reserved hole 31 is provided in the standardized cantilever plate 17, and the inverted L-shaped drain pipe 16 is installed in the standardized cantilever plate reserved hole 31. The top of the standardized cantilever plate reserved hole 31 is connected to the drainage trough water pipe hole 32, and the bottom of the inverted L-shaped drain pipe 16 is located in the blind ditch drainage diversion trough 5.

[0064] S30, standardization auxiliary installation bracket 45 construction:

[0065] Assemble a standardized auxiliary installation bracket 45 on the top of the original roadbed 2 on the construction side, and the standardized auxiliary installation bracket 45 is used to assist the installation of the prefabricated baffle 11;

[0066] Among them, the support base 15 is placed in the specified position, and then the telescopic strut 9 is installed on the top of the lifting column 13, and the inverted U-shaped clamping piece 8 is installed at the end of the telescopic strut 9; wherein, an adjustment jack 14 is provided on the top of the support base 15, and a lifting column 13 is provided on the top of the adjustment jack 14, and a telescopic jack 10 is provided on the side of the top of the lifting column 13, and the telescopic jack 10 is connected to the telescopic strut 9, and the end of the telescopic strut 9 is connected to the inner side of the inverted U-shaped clamping piece 8.

[0067] In step S30, by placing the support base 15 at a specified position and installing thereon a set of adjustable support structures consisting of an adjustment jack 14, a lifting column 13, a telescopic jack 10 and a telescopic support rod 9, the structure has the following effects:

[0068] Precise positioning and height adjustment: The support base 15 can ensure that the entire auxiliary support structure is firmly placed in the required position. The height of the support base 15 can be flexibly fine-tuned by adjusting the jack 14 to adapt to different construction conditions and requirements.

[0069] Dynamic support and load-bearing capacity: The telescopic jack 10 on the top of the lifting column 13 enables the telescopic support rod 9 to be accurately adjusted in height according to the progress of the installation of the prefabricated baffle 11, so as to provide sufficient support force to ensure the stability and safety of the prefabricated baffle 11 during the lifting process.

[0070] Fixing function: The end of the telescopic support rod 9 is connected to the inverted U-shaped fixing piece 8. This design facilitates the prefabricated baffle 11 to be firmly and quickly fixed at a predetermined position, which not only simplifies the installation process, but also enhances the overall rigidity and stability of the baffle after installation.

[0071] Improved construction flexibility and efficiency: Due to its retractable and adjustable design, the system can better cope with construction needs under different working conditions, improving operational convenience and work efficiency during the construction process.

[0072] S40, construction of prefabricated baffle 11:

[0073] The prefabricated baffle 11 is hoisted to the inner side of the steel pipe pile 7 by a crane, and then the prefabricated baffle 11 is stabilized by the inverted U-shaped clamping piece 8 on the outer side of the prefabricated baffle 11, and then the cable 12 is constructed on the inner side of the prefabricated baffle 11, and the other end of the cable 12 is anchored in the original roadbed 2; the semicircular bracket 6 is clamped on the side of the steel pipe pile 7, the telescopic jack 10 and the adjustment jack 14 are started to adjust the inverted U-shaped clamping piece 8 to a suitable position, and then the inverted U-shaped clamping piece 8 is clamped on the top of the prefabricated baffle 11, and then the cable 12 is constructed on the outer side of the prefabricated baffle 11. The shape of the semicircular bracket 6 adopts an arc design, which is linearly consistent with the side of the steel pipe pile 7.

[0074] The coordinated construction method using the semicircular card holder 6, the telescopic jack 10 and the adjustment jack 14 has the following significant effects:

[0075] Precise positioning and fixing: By inserting the semicircular bracket 6 onto the side of the steel pipe pile 7, the position of the prefabricated baffle 11 can be accurately pre-positioned, and with the help of the linkage effect of the telescopic jack 10 and the adjustment jack 14, the inverted U-shaped clamping piece 8 can be accurately adjusted to the predetermined position to ensure that the connection between the prefabricated baffle 11 and the steel pipe pile 7 is tight and stable during installation.

[0076] Efficient installation and enhanced safety: Using mechanical force (telescopic jack 10) to adjust the inverted U-shaped clamping piece 8 not only greatly improves the work efficiency of the installation of the prefabricated baffle 11, but also reduces the safety risks that may be caused by manual operation, thereby enhancing the safety of the construction site.

[0077] Improved structural stability: After the inverted U-shaped clamping piece 8 is firmly clamped on the top of the prefabricated baffle 11, combined with the construction of the cable 12, the road load can be effectively transmitted and dispersed, so that a stable force system is formed between the prefabricated baffle 11 and the foam concrete embankment 29, thereby improving the bearing capacity and deformation resistance of the entire widened embankment structure.

[0078] S50, integral blind pipe drainage system 42 construction:

[0079] An integral blind pipe drainage system 42 is installed at the roadbed step 1, and the transverse pipe 44 is connected to the center of the side of the horizontal pipe 39 in sequence, one end of the horizontal pipe 39 is connected to the center of the side of the vertical pipe 40, one end of the horizontal pipe 39 is connected to the end of the vertical pipe 40, and the end of the longitudinal long pipe 43 is connected to the end of the outermost vertical pipe 40. At the same time, the longitudinal long pipe 43 is passed through the reserved hole 33 of the guard plate and the reserved hole 34 of the foundation bottom plate in sequence; wherein, the original roadbed horizontal hole 37 and the original roadbed vertical hole 38 are arranged in sequence below the roadbed step 1, and the horizontal pipe 39 and the vertical pipe 40 are arranged in the original roadbed horizontal hole 37 and the original roadbed vertical hole 38 in sequence.

[0080] In this embodiment, the pipe connection method and arrangement have the following effects:

[0081] Drainage system construction: A complete underground drainage system is formed through the orderly connection between the transverse pipe 44, the horizontal pipe 39, the vertical pipe 40 and the longitudinal long pipe 43. This structure can ensure that the water accumulated inside the roadbed and the groundwater can be effectively discharged, prevent the accumulation of water from damaging the widened foam concrete embankment 29, and ensure the stability and durability of the embankment.

[0082] Structural synergy: The pipes pass through the reserved holes of the prefabricated protective panels 24 and the reserved holes of the foundation slab 34, which means that the drainage system is closely integrated with the main structure of the embankment. In this way, when the foam concrete is filled, the pipes can be embedded in it without affecting the overall structural strength, while ensuring the normal use and maintenance of the drainage system.

[0083] Improved drainage efficiency: Through the rational layout of multi-directional drainage pipes, the water in different areas can be effectively collected and quickly discharged, the water retention time can be reduced, and the foundation softening or frost heave problems caused by water infiltration can be reduced, thereby improving the safety performance and service life of the entire embankment project.

[0084] Convenience of construction: The pre-designed pipeline connection sequence and position simplifies the on-site construction process, making the installation process more standardized, reducing the difficulty of construction, saving work time and costs.

[0085] S60, Prefabricated foundation slab 25 construction:

[0086] Insert the dowel 35 of the prefabricated protective panel 24 into the dowel reserved hole 36 on the outer side of the bottom of the roadbed step 1;

[0087] When the original roadbed 2 at the joint is constructed near water, a steel frame 27 is constructed on the outer side of the prefabricated assembled foundation bottom plate 25, and the gabion stone cage 30 is placed in the shelving groove 26 of the steel frame 27;

[0088] The bottom sides of the prefabricated protective panel 24 and the prefabricated assembled base slab 25 are respectively provided with a protective panel reserved hole 33 and a base slab reserved hole 34;

[0089] In step S50, the original roadbed horizontal hole 37 and the original roadbed vertical hole 38 are designed to be set below the roadbed step 1, and the horizontal pipe 39 and the vertical pipe 40 are placed in these holes in sequence, which has the following effects:

[0090] Optimize the layout of the drainage system: The arrangement of the horizontal pipes 39 and the vertical pipes 40 forms a three-dimensional drainage network. The horizontal pipes 39 are mainly responsible for collecting and guiding the water flowing horizontally on the surface or inside the embankment, while the vertical pipes 40 play the role of quickly discharging the water downward. This layout can effectively improve the drainage efficiency in the entire embankment area and prevent the long-term retention of water from affecting the stability of the embankment.

[0091] Protect the embankment structure: By reserving holes in the original roadbed 2 and installing drainage pipes in advance, it can be ensured that the drainage facilities will not be damaged by construction operations during the foam concrete filling process. At the same time, it can also ensure that the foam concrete is in close contact with the drainage pipes, thereby enhancing the integrity and waterproof performance of the embankment.

[0092] Reduce foundation damage: Timely drainage of accumulated water inside and around the embankment can lower the groundwater level and reduce the softening effect of water on the foundation soil, thereby maintaining the stability and bearing capacity of the embankment foundation and extending the service life of the road.

[0093] Easy to repair and maintain: The pre-planned and built-in drainage system makes it more convenient to carry out later repair and maintenance. The drainage facilities can be inspected and maintained without large-scale excavation of the road surface, which greatly reduces maintenance costs and the impact on road traffic.

[0094] Preferably, when the original roadbed 2 encounters a river channel, a steel frame 27 is provided on the outer side of the prefabricated assembled foundation bottom plate 25, a shelf groove 26 is provided on the top of the steel frame 27, a cast-in-place pile 28 is provided on the bottom of the steel frame 27, and a gabion stone cage 30 is placed in the shelf groove 26.

[0095] S70, Prefabricated Sheathing Panel 24 Construction:

[0096] A prefabricated protective panel 24 is constructed on the outer side of the prefabricated assembled foundation bottom plate 25, and an anchor cable 23 is constructed on the inner side of the prefabricated protective panel 24, and the other end of the anchor cable 23 is anchored on the original roadbed 2;

[0097] S80, Foam concrete embankment 29 widening and filling construction:

[0098] Fill the foam concrete embankment 29 on the original roadbed 2 between the prefabricated protective panel 24 and the prefabricated baffle 11;

[0099] S90, construction of standardized cantilever slab 17:

[0100] The steel pipe pile 7 is passed through the steel pipe pile insertion hole 41 at the top of the stereotyped cantilever plate 17 and fixed with the fixing bolt 18; at the same time, the bottom of the inverted L-shaped drainage pipe 16 is inserted into the blind ditch drainage diversion groove 5;

[0101] The edge of the shaped cantilever plate 17 is provided with a drainage groove 21, and the bottom of the drainage groove 21 is provided with a drainage groove water pipe hole 32;

[0102] S100, guardrail 20 construction:

[0103] Install the guardrail base 22 on the top of the finalized cantilever plate 17, and then construct the guardrail 20;

[0104] Among them, a guardrail base 22 is provided under the guardrail 20 , a guardrail handrail 19 is provided on the top of the guardrail 20 , and the guardrail base 22 is arranged above the standardized cantilever plate 17 .

[0105] S110, roadbed widening construction on the other side:

[0106] Traffic is diverted to the widened foam concrete embankment 29, and then steps S50-S100 are repeated to carry out the roadbed widening construction on the other side.

[0107] The parts not described in detail in this application are prior art, so this application does not describe them in detail.

[0108] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.

[0109] Although this article uses more roadbed steps 1, original roadbed 2, pile holes 3, diagonal braces 4, blind ditch drainage diversion trough 5, semicircular brackets 6, steel pipe piles 7, inverted U-shaped clamps 8, telescopic struts 9, telescopic jacks 10, prefabricated baffles 11, cables 12, lifting columns 13, adjustment jacks 14, support bases 15, inverted L-shaped drainage pipes 16, standardized cantilever plates 17, fixing bolts 18, guardrail handrails 19, guardrails 20, diversion troughs 21, guardrail bases 22, anchor cables 23, prefabricated guard panels 24, prefabricated assembled foundation slabs 25, shelves The terms such as slot 26, steel frame 27, cast-in-place pile 28, foam concrete embankment 29, gabion stone cage 30, pre-set hole 31 of standardized cantilever plate, water pipe hole 32 of drainage trough, pre-set hole 33 of protective plate, pre-set hole 34 of foundation bottom plate, dowel 35, dowel pre-set hole 36, horizontal hole 37 of original roadbed, vertical hole 38 of original roadbed, horizontal pipe 39, vertical pipe 40, steel pipe pile hole 41, integral blind pipe drainage system 42, longitudinal long pipe 43, transverse pipe 44, and standardized auxiliary mounting bracket 45 are used, but the possibility of using other terms is not excluded. The use of these terms is only for the purpose of more conveniently describing and explaining the essence of this application; interpreting them as any additional restrictions is contrary to the spirit of this application.

[0110] The present application is not limited to the above-mentioned optimal implementation mode. Anyone can derive other forms of products under the inspiration of this application. However, no matter what changes are made in the shape or structure, all technical solutions that are the same or similar to those of the present application fall within the protection scope of the present application.

Claims

1. Highway reconstruction and expansion without interrupting traffic. Foam concrete raised and widened embankment construction structure. It is characterized in that It includes a temporary enclosure supporting steel pipe pile rack, a prefabricated baffle with a bracket (11), a standardized cantilever plate (17), a guardrail base (22), a standardized auxiliary installation bracket (45), an integral blind pipe drainage system (42) and a prefabricated assembled foundation bottom plate (25); The temporary enclosure supporting steel pipe pile rack is arranged on the original roadbed (2) at the central dividing strip, and comprises an inclined brace (4) and a steel pipe pile (7). The steel pipe pile (7) is provided with an inclined brace (4) on the side, and the bottom of the inclined brace (4) is supported on the original roadbed (2); The prefabricated baffle (11) is arranged on the inner side of the steel pipe pile (7), and comprises a semicircular bracket (6), a prefabricated baffle (11), and a cable (12); the outer side of the prefabricated baffle (11) is provided with a semicircular bracket (6), the inner side of the prefabricated baffle (11) is provided with a cable (12), and the other end of the cable (12) is anchored in the original roadbed (2); the shape of the semicircular bracket (6) is designed to be arc-shaped and linearly coincides with the side of the steel pipe pile (7); The shaped cantilever plate (17) is arranged on the top of the steel pipe pile (7) and the prefabricated baffle plate (11), and comprises the shaped cantilever plate (17), a drainage groove (21), a drainage groove water pipe hole (32), and a steel pipe pile insertion hole (41); the top of the shaped cantilever plate (17) is provided with a steel pipe pile insertion hole (41); the edge of the shaped cantilever plate (17) is provided with a drainage groove (21); and the drainage groove water pipe hole (32) is provided at the bottom of the drainage groove (21); The guardrail base (22) is arranged above the shaped cantilever plate (17), a guardrail (20) is arranged on the top of the guardrail base (22), and a guardrail handrail (19) is arranged on the top of the guardrail (20); The integrated blind pipe drainage system (42) is arranged at the roadbed step (1), and comprises a horizontal pipe (39), a vertical pipe (40), a longitudinal long pipe (43), and a transverse pipe (44); the transverse pipe (44) is connected to the center of the side of the horizontal pipe (39) in sequence; one end of the horizontal pipe (39) is connected to the center of the side of the vertical pipe (40); one end of the horizontal pipe (39) is connected to the end of the vertical pipe (40); and the end of the longitudinal long pipe (43) is connected to the end of the outermost vertical pipe (40); The standardized auxiliary installation bracket (45) is used to assist the installation of the prefabricated baffle (11) with a bracket, and is placed on the top of the original roadbed (2) on the construction side, and comprises an inverted U-shaped clamping piece (8), a telescopic support rod (9), a telescopic jack (10), a prefabricated baffle (11), a lifting column (13), an adjustment jack (14), and a support base (15); the top of the support base (15) is provided with an adjustment jack (14), the top of the adjustment jack (14) is provided with a lifting column (13), the top side of the lifting column (13) is provided with a telescopic jack (10), the telescopic jack (10) is connected to the telescopic support rod (9), and the end of the telescopic support rod (9) is connected to the inner side of the inverted U-shaped clamping piece (8); The prefabricated assembled foundation slab (25) is arranged on the outer side of the bottom of the roadbed step (1), and a prefabricated protective panel (24) is arranged on the outer side of the prefabricated assembled foundation slab (25).

2. According to claim 1, the construction structure of the foamed concrete raised and widened embankment for highway reconstruction and expansion without interrupting traffic, It is characterized in that A pile hole (3) is provided at the central dividing strip at the top of the original roadbed (2), a steel pipe pile (7) is inserted into the pile hole (3), and a blind ditch drainage diversion groove (5) is provided at the top of the original roadbed (2) at the bottom of the steel pipe pile (7); the top of the steel pipe pile (7) passes through the steel pipe pile insertion hole (41) and is fixed with a fixing bolt (18); the semicircular bracket (6) is clamped on the side of the steel pipe pile (7), and the inverted U-shaped clamping piece (8) is clamped on the top of the prefabricated baffle (11).

3. The construction structure of the foamed concrete raised and widened embankment for highway reconstruction and expansion without interrupting traffic according to claim 1, It is characterized in that An anchor cable (23) is provided on the inner side of the prefabricated protective panel (24), and the other end of the anchor cable (23) is anchored on the original roadbed (2); a foam concrete embankment (29) is provided on the top of the original roadbed (2) between the prefabricated baffle plate (11) and the prefabricated protective panel (24).

4. The construction structure of the foamed concrete embankment raised and widened for highway reconstruction and expansion without interrupting traffic according to claim 3, It is characterized in that The inner side surface of the prefabricated protective panel (24) is provided with a dowel (35), and the dowel (35) is inserted into a dowel reserved hole (36) on the bottom outer side surface of the roadbed step (1); the bottom sides of the prefabricated protective panel (24) and the prefabricated assembled foundation bottom plate (25) are respectively provided with a protective panel reserved hole (33) and a foundation bottom plate reserved hole (34), and the longitudinal long tube (43) passes through the protective panel reserved hole (33) and the foundation bottom plate reserved hole (34) in sequence.

5. The construction structure of the foamed concrete embankment raised and widened for highway reconstruction and expansion without interrupting traffic according to claim 4, It is characterized in that An original roadbed horizontal hole (37) and an original roadbed vertical hole (38) are sequentially arranged below the roadbed step (1), and the horizontal pipe (39) and the vertical pipe (40) are sequentially arranged in the original roadbed horizontal hole (37) and the original roadbed vertical hole (38).

6. The construction structure for raising and widening the embankment by foam concrete for highway reconstruction and expansion without interrupting traffic according to any one of claims 1 to 5, It is characterized in that When the original roadbed (2) encounters a river channel, a profiled steel frame (27) is provided on the outer side of the prefabricated assembled foundation bottom plate (25), a shelf groove (26) is provided on the top of the profiled steel frame (27), a cast-in-place pile (28) is provided on the bottom of the profiled steel frame (27), and a gabion stone cage (30) is placed in the shelf groove (26).

7. The construction structure of the highway reconstruction and expansion without interrupting traffic by foam concrete raised and widened embankment according to claim 1, It is characterized in that The standardized cantilever plate (17) is provided with a standardized cantilever plate reserved hole (31), the inverted L-shaped drainage pipe (16) is installed in the standardized cantilever plate reserved hole (31), the top of the standardized cantilever plate reserved hole (31) is connected to the drainage groove water pipe hole (32), and the bottom of the inverted L-shaped drainage pipe (16) is located in the blind ditch drainage diversion groove (5).