A kind of assembly type building top eaves gutter construction structure and construction method

By using prefabricated shear walls and external protective frames in prefabricated buildings, the problems of complexity and lack of safety in roof gutter construction are solved, and a simpler and safer construction process is achieved.

CN109914711BActive Publication Date: 2024-10-15CHINA METALLURGICAL CONSTR ENG GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910356637.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-04-29
Publication Date
2024-10-15
Estimated Expiration
2039-04-29

AI Technical Summary

Technical Problem

In the construction of prefabricated buildings, the construction process of top-floor gutters is complex and less safe. Existing technologies mostly use cast-in-place forms, which results in high construction difficulty and high safety risks.

Method used

A construction structure combining prefabricated shear walls and external protective frames is used. The vertical embedded steel bars of the prefabricated shear walls are connected to the gutter steel cages to build a steel pipe support frame and use flexible ropes to fix the nuts to simplify the disassembly process and improve safety. sex.

Benefits of technology

It reduces the difficulty of construction, improves construction safety, simplifies the operation process, avoids safety hazards of nuts falling, and improves construction efficiency and the convenience of reusable materials.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109914711B_ABST
    Figure CN109914711B_ABST
Patent Text Reader

Abstract

The present invention relates to a structure and method for constructing a gutter on the top floor of an assembled building, the structure comprising a vertical prefabricated shear wall; vertically, an external protective frame is connected to the middle of the outer side surface of the prefabricated shear wall, the external protective frame comprises a horizontal pedal, the upper surface of the pedal is connected to a vertical front guard plate, the front guard plate is flush with the side of the pedal away from the prefabricated shear wall; a plurality of vertical embedded steel bars extend from the upper surface of the prefabricated shear wall, the vertical embedded steel bars are connected to one end of the gutter steel cage, the other end of the gutter steel cage extends toward the front guard plate, a steel pipe support frame is provided on the pedal, and a gutter bottom formwork is supported by the steel pipe support frame to serve as a bottom formwork when the gutter is cast in situ, and a side of the gutter bottom formwork away from the prefabricated shear wall is connected to a gutter side formwork. The gutter construction structure is implemented in combination with a relatively mature external protective frame, the external protective frame is connected to the middle of the outer side surface of the prefabricated shear wall on the top floor as a load-bearing support for the formwork, which reduces the construction difficulty and is safe and reliable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of formwork for buildings, and in particular relates to a top floor gutter construction structure and a construction method for an assembled building. Background Art

[0002] During the construction of prefabricated buildings, the top floor columns, eaves gutters, parapets and other structures are not easy to prefabricate due to the different top floor designs of various buildings. Currently, they are mostly constructed in the form of cast-in-place. Figure 1 As shown, the construction and formwork of the gutter 102 requires the construction of a load-bearing foundation through a cantilevered I-beam 103 that passes through the wall, and a large number of scaffolding and steel pipe support frames 4 to form a strength connection and support the formwork of the cast-in-place gutter. The construction is relatively complicated and the safety is poor, and further optimization and improvement are needed. Summary of the invention

[0003] In view of the above-mentioned deficiencies in the prior art, the technical problem to be solved by the present invention is to provide a construction structure and a construction method for the top eaves gutter of an assembled building, so as to achieve the effect of simpler and more convenient construction and higher safety.

[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions:

[0005] A structure for constructing a top eaves gutter of an assembled building, comprising a vertical prefabricated shear wall on the top floor of the building; vertically, an external protective frame is connected to the middle part of the outer side surface of the prefabricated shear wall, and the external protective frame comprises a horizontal pedal, and the upper surface of the pedal is connected to a vertical front guard plate, and the front guard plate is flush with a side of the pedal away from the prefabricated shear wall; a plurality of vertical embedded steel bars extend from the upper surface of the prefabricated shear wall, and the vertical embedded steel bars are connected to one end of a gutter steel cage, and the other end of the gutter steel cage extends toward the front guard plate, a steel pipe support frame is provided on the pedal, and an eaves gutter bottom formwork is supported by the steel pipe support frame to serve as a bottom formwork when the eaves gutter is cast in place, and a side of the eaves gutter bottom formwork away from the prefabricated shear wall is connected to an eaves gutter side formwork to serve as a side formwork when the eaves gutter is cast in place, and the eaves gutter side formwork abuts against the inner side surface of the front guard plate to facilitate the force when pouring concrete slurry.

[0006] To further improve the above technical solution, at least two tripods are connected to the lower surface of the pedal, and each tripod is arranged at intervals along the length direction of the pedal. The tripod includes a vertical channel steel and a horizontal channel steel connected in an inverted L shape. The web of the horizontal channel steel is connected to the lower surface of the pedal, and the web of the vertical channel steel is flush with the side of the pedal close to the prefabricated shear wall and abuts against the outer side of the prefabricated shear wall. The web of the vertical channel steel is vertically spaced with two through holes, and through-wall holes are prefabricated on the prefabricated shear wall corresponding to the through holes. The vertical channel steel is bolted to the outside of the prefabricated shear wall by passing through the through-wall bolts and the through holes in sequence and threadedly connecting nuts. A flexible rope is also provided on the vertical channel steel, and the flexible rope is connected to the nut to prevent the nut from falling off after disassembly.

[0007] Furthermore, the nut includes a nut body, and a flange is provided around one end face of the nut body. The flange has a square shape, and the side length of the square corresponds to the distance between the inner sides of the two wing plates of the vertical channel steel to cooperate and play a role in preventing rotation.

[0008] Furthermore, the through hole is a vertical waist-shaped groove so as to fine-tune the connection position with the prefabricated shear wall in the vertical direction.

[0009] Furthermore, the flexible rope is an iron chain.

[0010] Furthermore, a perforation is prefabricated in the lower portion of the prefabricated shear wall, the perforation is perpendicular to the prefabricated shear wall, a horizontal steel pipe is passed through the perforation, one end of the horizontal steel pipe extending out of the prefabricated shear wall is connected to an inclined support steel pipe, one end of the inclined support steel pipe is connected to the horizontal steel pipe, and the other end is supported and abutted against the lower surface of the pedal.

[0011] Furthermore, a PVC plastic pipe is pre-buried in the prefabricated shear wall, and the inner hole of the PVC plastic pipe is formed as the perforation.

[0012] Furthermore, an angle of 45° to 60° is formed between the inclined support steel pipe and the prefabricated shear wall.

[0013] The present invention also relates to a method for constructing a top floor gutter of an assembled building. The method comprises constructing the above-mentioned top floor gutter construction structure of the assembled building, comprising the following steps:

[0014] 1) Hoist and connect the external protection frame to the middle of the outer side of the prefabricated shear wall on the top floor;

[0015] 2) Build a steel pipe support frame on the pedal of the outer protection frame;

[0016] 3) Lay the eaves gutter bottom formwork and eaves gutter side formwork on the steel pipe support frame;

[0017] 4) Lay the eaves gutter steel cage on the eaves gutter bottom formwork, and fix the eaves gutter steel cage to the vertical embedded steel bars extending from the upper surface of the prefabricated shear wall;

[0018] 5) Pour concrete slurry to form eaves gutters;

[0019] The method also includes the following removal steps:

[0020] 6) After the concrete slurry meets the design strength, remove the steel pipe support frame;

[0021] 7) Remove the bottom formwork and side formwork of the eaves gutter;

[0022] 8) Remove the outer protective frame.

[0023] To further improve the above method, step 1) further includes inserting a horizontal steel pipe into the perforation at the lower part of the prefabricated shear wall, connecting an oblique support steel pipe to the end of the horizontal steel pipe extending outside the prefabricated shear wall, and the oblique support steel pipe is supported against the lower surface of the pedal; an angle of 45° to 60° is formed between the oblique support steel pipe and the prefabricated shear wall;

[0024] Step 8) Before removing the outer protective frame, remove the diagonal support steel pipes and horizontal steel pipes first.

[0025] Compared with the prior art, the present invention has the following beneficial effects:

[0026] 1. The eaves gutter construction structure of the present invention is implemented in combination with a relatively mature external protective frame. The external protective frame is connected to the middle of the outer side surface of the prefabricated shear wall on the top floor and used as a load-bearing support for the formwork, which can reduce the difficulty of construction and has a reliable structure. During the demolding process, the construction personnel first remove the steel pipe support frame, and then remove the eaves gutter bottom formwork and eaves gutter side formwork. During the demolding process, the external protective frame provides protection for the construction safety of the personnel and prevents the formwork from falling from a high altitude, which is safer.

[0027] 2. The functional design of the present invention is more perfect. During the assembly and disassembly of the external protective frame, after the through-wall bolts and nuts are disengaged from the threaded connection, the nuts are restricted by flexible ropes and always remain connected to the vertical channel steel. The nuts are not independent, which avoids the problem of nuts falling off or being lost after disassembly of the bolting. When reused, the nuts are connected to the vertical channel steel by flexible ropes, and there is no need to re-equip or search for the nuts, which brings convenience to reuse and construction, and also eliminates the potential safety hazard of personal injury caused by the falling of nuts during disassembly, thereby improving safety.

[0028] 3. When the outer protective frame of the present invention is connected to the wall, it is only necessary to rotate the through-wall bolt on one side, while the nut does not need to be rotated on the other side (during the connection and disassembly process), which simplifies the operation process and improves construction efficiency; and the manufacturing is simple, the materials are easily available, and the production cost is low. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 - A schematic diagram of the building top floor gutter construction structure of the background technology;

[0030] Figure 2 - A structural diagram of a top eaves gutter construction structure of an assembled building in a specific embodiment;

[0031] Figure 3-Figure 2 Left side view (in order to facilitate the illustration of the nut 9, the oblique support ribs 73 and the horizontal connecting ribs 74 are hidden);

[0032] Figure 4 - Schematic diagram of a single vertical channel steel and related connection structure in a specific embodiment;

[0033] Figure 5-Figure 4 A top view of

[0034] Figure 6-Figure 4 Rear view of

[0035] Among them, there are prefabricated shear wall 1, vertical embedded steel bars 11, PVC plastic pipe 12, external protective frame 2, pedal 21, front guard plate 22, eaves gutter steel cage 3, steel pipe support frame 4, eaves gutter bottom formwork 5, eaves gutter side formwork 6, tripod 7, vertical channel steel 71, horizontal channel steel 72, oblique supporting ribs 73, horizontal connecting ribs 74, through holes 75, through-wall bolts 8, nuts 9, nut body 91, flange 92, flexible rope 93, horizontal steel pipe 100, oblique supporting steel pipe 101, eaves gutter 102, and cantilever I-beam 103. DETAILED DESCRIPTION

[0036] The specific implementation modes of the present invention will be further described in detail below in conjunction with the accompanying drawings.

[0037] See also Figure 2-3A specific embodiment of an assembled building top eaves gutter construction structure includes a vertical prefabricated shear wall 1 on the top floor of the building; in the vertical direction, an external protective frame 2 is connected to the middle of the outer side surface of the prefabricated shear wall 1, and the external protective frame 2 includes a pedal 21 horizontally connected to a tripod 7, and the tripod 7 is connected to the lower surface of the pedal 21 for connecting the prefabricated shear wall 1, and a vertical positive guard plate 22 is connected to the upper surface of the pedal 21, and the positive guard plate 22 is flush with a side of the pedal 21 away from the prefabricated shear wall 1 to protect the construction personnel on the pedal 21; a plurality of vertical embedded steel bars 11 extend from the upper surface of the prefabricated shear wall 1, and the vertical embedded steel bars 11 are connected to the eaves One end of the eaves gutter steel cage 3 is tied and connected, and the other end of the eaves gutter steel cage 3 extends toward the front guard plate 22. A steel pipe support frame 4 is provided on the pedal 21, and a gutter bottom formwork 5 is supported by the steel pipe support frame 4 to serve as a bottom formwork for cast-in-place eaves. To ensure sealing, the width of the eaves gutter bottom formwork 5 corresponds to the distance from the front guard plate 22 to the outer side of the precast shear wall 1. The upper surface of the eaves gutter bottom formwork 5 is connected with a vertical eaves gutter side formwork 6 to serve as a side formwork for cast-in-place eaves. The eaves gutter side formwork 6 is flush with a side of the eaves gutter bottom formwork 5 away from the precast shear wall 1, and the eaves gutter side formwork 6 is in contact with the inner side of the front guard plate 22 so as to be reliably stressed when pouring concrete slurry.

[0038] The eaves gutter construction structure of the embodiment is implemented in combination with the relatively mature external protective frame 2. The existing prefabricated shear wall 1 is generally prefabricated with a hole connected to the external protective frame 2 at the upper part, so that the wall and floor of the upper layer can be constructed after the external protective frame 2 is connected to ensure the safety of the construction workers. The present invention connects the external protective frame 2 to the middle of the outer side surface of the prefabricated shear wall 1 on the top floor, and uses it as a load-bearing support for the formwork, which can reduce the difficulty of construction and is safe and reliable. The external protective frame 2 is a mature product, which is involved in the existing technologies such as CN206376507U, CN108756196A, CN207110421U, CN106677509A, CN108868096A, etc., and will not be repeated here. During implementation, the external protective frame 2 is first hoisted and connected to the middle of the outer side surface of the prefabricated shear wall 1 on the top floor, and bolted and fixed. Specifically, the external protective frame 2 can be connected end to end with a corresponding number of ends outside a circle of outer walls of the corresponding building. In a circle, a steel pipe support frame 4 is built on the pedal 21 of the outer protective frame 2. The steel pipe support frame 4 is a plurality of steel pipes staggered and connected by fasteners. It is a prior art. The steel pipe support frame 4 is then used as an intermediate support. The eaves gutter bottom formwork 5 and the eaves gutter side formwork 6 are laid on the steel pipe support frame 4. Then, the eaves gutter steel cage 3 is laid and tied on site, or the formed eaves gutter steel cage 3 is hoisted onto the eaves gutter bottom formwork 5, and the eaves gutter steel cage 3 is connected to the vertical embedded steel bars extending from the upper surface of the top prefabricated shear wall 1. 11 are tied and fixed, or welded; cast-in-place construction can be carried out, wherein, according to the shape of the eaves gutter to be formed, the templates to be set in other positions of the eaves gutter are the same as the existing method, and the present invention does not make specific restrictions. It can be selected to set the relevant upper mold and other side molds on the floor layer that has been built on the prefabricated shear wall 1 according to the existing means, or it can be connected through the positive guard plate; after the cast-in-place structure meets the strength requirements, the demoulding process is that the construction personnel first enter and remove the steel pipe support frame 4, and then remove the eaves gutter bottom template 5 and the eaves gutter side template 6. The construction personnel enter and carry out the demoulding from the hollow part of the prefabricated shear wall 1, such as the window position. During the demoulding process, the external protective frame 2 provides protection for the construction safety of the personnel and prevents the template from falling from a high altitude, and the safety is better. At the same time, this is also the reason why the external protective frame 2 cannot be used directly to support the eaves gutter bottom template 5. In that case, the external protective frame 2 needs to be removed first, which naturally brings the problem that the eaves gutter template may fall and cause safety hazards. In the present invention, the external protective frame 2 is removed at the end of the demolition project.

[0039] The eaves gutter construction structure of the embodiment is implemented in combination with the relatively mature external protective frame 2. The existing prefabricated shear wall 1 is generally prefabricated with a hole connected to the external protective frame 2 at the upper part, so that the construction of the wall and floor of the upper layer can be carried out after the external protective frame 2 is connected to ensure the safety of the construction workers. The present invention connects the external protective frame 2 to the middle of the outer side surface of the prefabricated shear wall 1 on the top floor, and uses it as a load-bearing support for the formwork, which can reduce the difficulty of construction and is safe and reliable. The outer protective frame 2 is a mature product, which is involved in the prior arts such as CN206376507U, CN108756196A, CN207110421U, CN106677509A, and CN108868096A, and will not be described in detail. During implementation, the outer protective frame 2 is first hoisted and connected to the middle of the outer side surface of the prefabricated shear wall 1 on the top floor, and bolted and fixed. Specifically, the outer protective frame 2 can be connected to a circle with a corresponding number of ends outside a circle of the outer wall of the corresponding building, and then a steel pipe support frame 4 is built on the pedal 21 of the outer protective frame 2. The steel pipe support frame 4 is a plurality of steel pipes staggeredly connected by fasteners, which is a prior art. Then, the steel pipe support frame 4 is used as an intermediate support, and the eaves bottom formwork 5 and the eaves side formwork 6 are laid on the steel pipe support frame 4. Then, the eaves gutter steel cage 3 is laid and tied on site, or the already formed eaves gutter steel cage 3 is laid. After being hoisted onto the eaves gutter bottom formwork 5, the eaves gutter steel cage 3 is tied and fixed to the vertical embedded steel bars 11 extending from the upper surface of the top prefabricated shear wall 1, and cast-in-place construction can be carried out. According to the shape of the eaves gutter to be formed, the formworks to be set at other positions of the eaves gutter are the same as the existing method, and the present invention does not make specific restrictions. After the cast-in-place structure meets the strength requirements, the demolding process is that the construction personnel first enter and remove the steel pipe support frame 4, and then remove the eaves gutter bottom formwork 5 and the eaves gutter side formwork 6. During the demolding process, the external protective frame 2 provides protection for the construction safety of the personnel and prevents the formwork from falling from a high altitude, and the safety is better. At the same time, this is also the reason why the external protective frame 2 cannot be used directly to support the eaves gutter bottom formwork 5. In that case, the external protective frame 2 needs to be removed first, which naturally brings about the problem that the eaves gutter formwork may fall and cause safety hazards. In the present invention, the external protective frame 2 is removed at the end of the demolition project.

[0040] See also Figure 2-6, wherein two tripods 7 are connected to the lower surface of the pedal 21, and the two tripods 7 are arranged at intervals along the length direction of the pedal 21, and the tripod 7 includes a vertical channel steel 71 and a horizontal channel steel 72 connected in an inverted L shape, and the web of the horizontal channel steel 72 is connected to the lower surface of the pedal 21 and is perpendicular to the length direction of the pedal 21, and the web of the vertical channel steel 71 is flush with a side of the pedal 21 close to the prefabricated shear wall 1 and abuts against the outer side of the prefabricated shear wall 1, and the web of the vertical channel steel 71 is vertically spaced with two through holes 75, and a through-wall hole is prefabricated on the prefabricated shear wall 1 corresponding to the through hole 75, and the vertical channel steel 71 is bolted to the outer side of the prefabricated shear wall 1 by the through-wall bolt 8 passing through the through-wall hole and the through hole 75 in turn and threading the nut 9 to bolt the vertical channel steel 71 to the outer side of the prefabricated shear wall 1, that is, the outer protective frame 2 is fixed to the outer side of the prefabricated shear wall 1, and a flexible rope 93 is also provided on the vertical channel steel 71, and the flexible rope 93 is connected to the nut 9 to prevent the nut 9 from falling off after disassembly. The nut 9 includes a nut body 91, and a flange 92 is provided around one end surface of the nut body 91. The flange 92 is square in shape, and the side length of the square corresponds to the distance between the inner sides of the two wing plates of the vertical channel steel 71 to cooperate and play a role in preventing rotation.

[0041] In this way, because the outer protective frame 2 is reusable, during the use of the through-wall bolt 8 and the nut 9, both the connection and the disassembly need to be constructed manually from both sides of the wall, with the bolt being rotated on one side and the nut 9 being turned on the other side. The operation process is relatively troublesome, especially after disassembly, the nut 9 used in conjunction with the through-wall bolt 8 is in an independent state, which is easy to fall or lose, causing inconvenience when used again, and there is also a safety hazard of falling and causing injury. After the vertical channel steel 71 and the nut 9 are connected to each other by a flexible rope 93 in this embodiment, when disassembling, after the through-wall bolt 8 and the nut 9 are disconnected from the threaded connection, the nut 9 is restricted by the flexible rope 93 and always maintains a connection state with the vertical channel steel 71. The nut 9 is not an independent monomer form, which avoids the problem of the nut 9 being easy to fall or lose after the bolt connection is disassembled. When reused, the nut 9 is connected to the vertical channel steel 71 by the flexible rope 93, and there is no need to re-equip or find the nut 9, which brings convenience to reuse and construction, and also eliminates the safety hazard of personnel injury caused by the nut 9 falling during disassembly, thereby improving safety. The nut 9 is provided with a flange 92 and used in conjunction with the wing plate, so that the nut 9 does not need to be rotated (during the connection and removal process), which simplifies the operation process and improves the construction efficiency. During implementation, the flange 92 can be made of a steel plate, and a hole for connecting with the nut body 91 is processed on the flange 92 so that it can be sleeved on the outside of the nut body 91 and fixedly connected by welding.

[0042] Among them, the through hole 75 is a vertical waist-shaped groove (also called waist-shaped hole) so as to fine-tune the connection position with the prefabricated shear wall 1 in the vertical direction. The waist-shaped groove is for the position of the through-wall hole on the prefabricated shear wall 1. The position of the outer protective frame 2 can be fine-tuned to meet the construction size requirements. This is also the reason why the nut 9 is not directly fixed on the vertical channel steel 71. In addition, the use of a flexible rope 93 to connect the nut 9 also facilitates the replacement of the nut 9 after the internal thread of the nut 9 is slipped. The method of directly welding the nut 9 to the vertical channel steel 71 will inevitably cause the inconvenience of replacing the nut 9. During implementation, the slot width of the waist-shaped groove formed as the through hole 75 should correspond to or be slightly larger than the major diameter of the screw section of the through-wall bolt 8.

[0043] The flexible rope 93 is an iron chain, and its two ends are respectively welded to the web of the vertical channel steel 71 and the flange 92, and the flange 92 can be selected to face the side of the nut body 91. In this way, the use effect is guaranteed, the service life of the flexible rope 93 is guaranteed, and the connection is simple and reliable.

[0044] The lower part of the prefabricated shear wall 1 is prefabricated with a perforation, which is perpendicular to the prefabricated shear wall 1. A horizontal steel pipe 100 is inserted into the perforation. One end of the horizontal steel pipe 100 extending outside the prefabricated shear wall 1 is connected to an inclined support steel pipe 101. One end of the inclined support steel pipe 101 is connected to the horizontal steel pipe 100 through a fastener (not shown in the figure), and the other end is supported against the lower surface of the pedal 21. In this way, the strength of the outer protective frame 2 as a formwork support can be further improved to ensure construction safety, especially when the outer protective frame 2 near the corner or the column has a higher load-bearing requirement.

[0045] The prefabricated shear wall 1 is pre-buried with a PVC plastic pipe 12, and the inner hole of the PVC plastic pipe 12 is formed as the perforation. This can reduce the damage to the prefabricated shear wall 1 caused by the horizontal steel pipe 100 due to overcoming the tilt, and also facilitate the prefabrication of the perforation.

[0046] The inclined support steel pipe 101 and the prefabricated shear wall 1 preferably form an angle of 45° to 60°, and the angle shown in the figure is 60°, so as to better support the external protection frame 2.

[0047] During implementation, the pedal 21 and the front guard plate 22 can be made of hot-rolled steel plates, and the connection method can be welding or detachable connection, or steel mesh can be selected. Corresponding to the steel mesh, there must be a steel skeleton (steel frame) welded with longitudinal and transverse steel bars (which can also be square steel or angle steel), and the steel mesh is connected to the steel skeleton for use; the vertical channel steel 71 and the horizontal channel steel 72 of the tripod 7 are respectively opened with a 45° bevel at the end, so as to be welded and connected into an L shape, and the web of the horizontal channel steel 72 is connected to the lower surface of the pedal 21, which can be welded or bolted. An oblique support rib 73 is also connected between the vertical channel steel 71 and the horizontal channel steel 72, and a horizontal connecting rib 74 can also be connected between the middle part of the oblique support rib 73 and the vertical channel steel 71 to form a more stable tripod 7.

[0048] The present invention also provides a method for constructing a top floor gutter of an assembled building, the method comprising constructing the above-mentioned top floor gutter construction structure of an assembled building, comprising the following steps:

[0049] 1) The outer protective frame 2 is hoisted and connected to the middle of the outer side surface of the prefabricated shear wall 1 on the top floor; the outer protective frame 2 is fixedly connected to the outer side of the prefabricated shear wall 1 by passing the through-wall bolts 8 through the prefabricated through-wall holes on the prefabricated shear wall 1 and the through-holes 75 on the outer protective frame 2 in sequence and bolting nuts 9;

[0050] A horizontal steel pipe 100 is inserted into the prefabricated perforation at the lower part of the prefabricated shear wall 1, and the end of the horizontal steel pipe 100 extending outside the prefabricated shear wall 1 is connected to the oblique support steel pipe 101 through a fastener so that the angle can be adjusted, and the oblique support steel pipe 101 is supported and abutted against the lower surface of the pedal 21; the connection length and angle between the oblique support steel pipe 101 and the horizontal steel pipe 100 are adjusted through the fastener, so that an angle of 45° to 60° is formed between the oblique support steel pipe 101 and the prefabricated shear wall 1;

[0051] During implementation, the outer protective frame 2 can be connected end to end to form a circle outside a circle of outer walls (prefabricated shear walls 1) of the corresponding building according to the corresponding number;

[0052] 2) Build a steel pipe support frame 4 on the pedal 21 of the outer protective frame 2; the construction personnel go up to the pedal 21, and the steel pipe support frame 4 is built by staggered connection of a number of steel pipes through fasteners;

[0053] 3) Lay the eaves gutter bottom formwork 5 and the eaves gutter side formwork 6 on the steel pipe support frame 4; in this step, the construction workers can stand on the floor layer that has been built on the prefabricated shear wall 1 by existing means, or stand on the pedal 21 of the adjacent external protection frame 2;

[0054] 4) Lay the eaves gutter steel cage 3 on the eaves gutter bottom formwork 5, and fix the eaves gutter steel cage 3 to the vertical embedded steel bars 11 extending from the upper surface of the prefabricated shear wall 1; the eaves gutter steel cage 3 can be laid and tied on site, or the prefabricated eaves gutter steel cage 3 can be hoisted onto the eaves gutter bottom formwork 5, and the eaves gutter steel cage 3 is tied and fixed to the vertical embedded steel bars 11 extending from the upper surface of the top prefabricated shear wall 1, or welded and fixed;

[0055] 5) pouring concrete slurry to form the eaves gutter; according to the shape of the eaves gutter to be formed, the templates to be set at other positions of the eaves gutter are the same as the existing method, and the present invention is not specifically limited. The relevant upper mold and other side molds can be set on the floor layer, and can also be connected through the front guard plate;

[0056] The method also includes the following removal steps:

[0057] 6) After the concrete slurry meets the design strength, the steel pipe support frame 4 is removed; the construction personnel enter from the hollow part of the prefabricated shear wall 1, such as the window position, and carry out the removal;

[0058] 7) Remove the eaves gutter bottom formwork 5 and the eaves gutter side formwork 6; remove the relevant removed steel pipes, eaves gutter bottom formwork 5, and eaves gutter side formwork 6 through the hollowed-out parts of the prefabricated shear wall 1, such as the window position;

[0059] 8) The oblique support steel pipe 101 and the horizontal steel pipe 100 are removed. The construction workers can stand on the outer protective frame of the next prefabricated shear wall to carry out the removal process and the connection process in step 1) (including the connection between the through-wall bolts 8 and the nuts 9);

[0060] Continue to dismantle the outer protective frame 2; use a tower crane to cooperate with the dismantling, and then lift it to the ground for reuse.

[0061] The beneficial effects of this method are the same as those described above and will not be described in detail.

[0062] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.

Claims

1. A method for constructing a top floor gutter of an assembled building, characterized in that: The method comprises constructing a prefabricated building top eaves gutter construction structure, the prefabricated building top eaves gutter construction structure comprising a vertical prefabricated shear wall (1) on the top of the building; vertically, an outer protective frame (2) is connected to the middle of the outer side surface of the prefabricated shear wall (1), the outer protective frame (2) comprises a horizontal pedal (21), the upper surface of the pedal (21) is connected to a vertical front guard plate (22), the front guard plate (22) is flush with a side of the pedal (21) away from the prefabricated shear wall 1; a plurality of vertical embedded steel bars (11) extend from the upper surface of the prefabricated shear wall (1), the vertical embedded steel bars (11) are aligned with the eaves gutter One end of the steel cage (3) is connected, and the other end of the eaves gutter steel cage (3) extends toward the front guard plate (22); a steel pipe support frame (4) is provided on the pedal (21) and a gutter bottom template (5) is supported by the steel pipe support frame (4) to serve as a bottom template when the eaves gutter is cast in situ; a side of the eaves gutter bottom template (5) away from the prefabricated shear wall (1) is connected to a gutter side template (6) to serve as a side template when the eaves gutter is cast in situ; the gutter side template (6) abuts against the inner side surface of the front guard plate (22) to receive force when pouring concrete slurry; the width of the eaves gutter bottom template (5) corresponds to the distance from the front guard plate (22) to the outer side surface of the prefabricated shear wall (1); At least two tripods (7) are connected to the lower surface of the pedal (21), and the tripods (7) are arranged at intervals along the length direction of the pedal (21). The tripod (7) comprises a vertical channel steel (71) and a horizontal channel steel (72) connected in an inverted L shape. The web of the horizontal channel steel (72) is connected to the lower surface of the pedal (21), and the web of the vertical channel steel (71) is flush with a side surface of the pedal (21) close to the prefabricated shear wall (1) and abuts against the outer side surface of the prefabricated shear wall (1). The web of the channel steel (71) is provided with two through holes (75) at intervals in the vertical direction. A through-hole is prefabricated on the prefabricated shear wall (1) corresponding to the through hole (75). Through-hole bolts (8) are passed through the through-hole and the through hole (75) in sequence and are threadedly connected with nuts (9) to bolt the vertical channel steel (71) to the outside of the prefabricated shear wall (1). A flexible rope (93) is also provided on the vertical channel steel (71). The flexible rope (93) is connected to the nut (9) to prevent the nut (9) from falling off after disassembly. A perforation is prefabricated at the lower part of the prefabricated shear wall (1), the perforation being perpendicular to the prefabricated shear wall (1), a horizontal steel pipe (100) being passed through the perforation, one end of the horizontal steel pipe (100) extending outside the prefabricated shear wall (1) being connected to an inclined support steel pipe (101), one end of the inclined support steel pipe (101) being connected to the horizontal steel pipe (100), and the other end being supported and abutted against the lower surface of the pedal (21); This method contains the following steps: 1) hoisting and connecting the outer protection frame (2) to the middle of the outer side surface of the prefabricated shear wall (1) on the top floor; the outer protection frame (2) is also connected end to end to form a circle outside the prefabricated shear wall (1) of the corresponding building in a circle according to the corresponding number; A horizontal steel pipe (100) is inserted into the through hole at the bottom of the prefabricated shear wall (1); an inclined support steel pipe (101) is connected to the end of the horizontal steel pipe (100) extending outside the prefabricated shear wall (1); the inclined support steel pipe (101) is supported and abutted against the lower surface of the pedal (21); an angle of 45° to 60° is formed between the inclined support steel pipe (101) and the prefabricated shear wall (1); 2) constructing a steel pipe support frame (4) on the pedal (21) of the outer protective frame (2); 3) Laying the eaves gutter bottom formwork (5) and the eaves gutter side formwork (6) on the steel pipe support frame (4); 4) laying the eaves gutter steel cage (3) on the eaves gutter bottom formwork (5), and fixing the eaves gutter steel cage (3) to the vertical embedded steel bars (11) extending from the upper surface of the prefabricated shear wall (1); 5) Pour concrete slurry to form eaves gutters; The method also includes the following removal steps: 6) After the concrete slurry meets the design strength, remove the steel pipe support frame (4); 7) Remove the gutter bottom formwork (5) and the gutter side formwork (6); 8) Remove the outer protective frame (2); Step 8) Before removing the outer protective frame (2), first remove the inclined support steel pipe (101) and the horizontal steel pipe (100).

2. A method for constructing a top floor gutter of an assembled building according to claim 1, characterized in that: The nut (9) comprises a nut body (91), and a flange (92) is provided around one end surface of the nut body (91). The flange (92) has a square shape, and the side length of the square corresponds to the distance between the inner sides of the two wing plates of the vertical channel steel (71) to cooperate and play a role in preventing rotation.

3. A method for constructing a top floor gutter of an assembled building according to claim 2, characterized in that: The through hole (75) is a vertical waist-shaped groove so as to fine-tune the connection position with the prefabricated shear wall (1) in the vertical direction.

4. A method for constructing a top floor gutter of an assembled building according to claim 3, characterized in that: The flexible rope (93) is an iron chain.

5. A method for constructing a top floor gutter of an assembled building according to claim 4, characterized in that: A PVC plastic pipe (12) is pre-buried in the prefabricated shear wall (1), and the inner hole of the PVC plastic pipe (12) is formed as the perforation.

6. A method for constructing a top floor gutter of an assembled building according to claim 5, characterized in that: An included angle of 45° to 60° is formed between the inclined support steel pipe (101) and the prefabricated shear wall (1).