A DC / DC converter test device and a power supply test system
Through the combination of tooling DC/DC converter and compensation power supply, an internal circulation of electric energy is formed, which solves the problems of electric energy waste and grid disturbance during DC/DC converter detection, and achieves efficient electric energy utilization and space saving.
Patent Information
- Application Number
- CN201910994844.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-10-18
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2039-10-18
AI Technical Summary
Existing DC/DC converter detection technology wastes power or causes grid disturbance.
The tooling DC/DC converter is used to cooperate with the compensation power supply to form an internal circulation of electric energy. The compensation power supply is used to compensate for the energy loss after the test cycle, avoiding electric energy feedback to the power grid, reducing the number of equipment and saving space.
It realizes the self-circulation of electric energy, saves electric energy, avoids interference to the power grid, eliminates the need to add grid isolation equipment, and improves test efficiency.
Smart Images

Figure CN110673055B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of power supply testing, and in particular to a testing device for a DC / DC converter and a power supply testing system. Background Art
[0002] One of the key technologies needed for the development of new energy electric vehicles is the design of battery power. Since the voltage generated by hydrogen fuel cells is not stable or does not match the driving voltage requirements of the back end, a DC / DC converter is needed to convert the voltage to make it stable and match the driving requirements. Therefore, testing DC / DC converters has become one of the key technologies in this field.
[0003] However, the main means used in the prior art for testing DC / DC converters is to use a power supply in front and connect a consumption-type electronic load in the back, or to connect a feedback-type electronic load in the back and connect to the power grid. Both methods require the preparation of a power supply at the front end, and the use of equipment such as a resistive electronic load or a feedback-type electronic load, so more space is needed for layout. Moreover, the former will waste a lot of test power due to the consumption-type load, and the latter will cause disturbances to the power grid due to the feedback of power to the power grid, and additional power grid isolation equipment is required when necessary. Therefore, it is necessary to propose a new DC / DC converter test device that can save power and not cause power grid disturbances. Summary of the invention
[0004] In view of the problem that the prior art DC / DC converter detection technology wastes electric energy or causes grid interference, a DC / DC converter test device and a power supply test system of the present invention are proposed to overcome the above problems.
[0005] In order to achieve the above object, the present invention adopts the following technical solutions:
[0006] According to one aspect of the present invention, a test device for a DC / DC converter is provided, the test device comprising: a host computer, a tooling DC / DC converter and a compensation power supply;
[0007] The host computer is used to connect to the DC / DC converter to be tested and detect the electrical performance of the DC / DC converter to be tested;
[0008] The input end of the tooling DC / DC converter is connected to the output end of the DC / DC converter to be tested, and the output end of the tooling DC / DC converter is connected to the input end of the DC / DC converter to be tested. The tooling DC / DC converter is used to transform the voltage output by the DC / DC converter to be tested and return it to the DC / DC converter to be tested, so that an internal circulation of electric energy is formed in the test device;
[0009] The compensation power supply is connected to the input end of the tooling DC / DC converter and is used to convert the alternating current of the power grid into direct current to supplement the power energy for the testing device.
[0010] Optionally, the testing device further comprises: a power analyzer; the power analyzer is used to measure the input circuit power and the output circuit power of the DC / DC converter to be tested.
[0011] Optionally, the testing device further comprises: a Hall sensor; the Hall sensor is arranged on a connection line between the tooling DC / DC converter and the DC / DC converter to be tested, and is used to detect line current and / or voltage.
[0012] Optionally, the testing device further comprises: an inductor; the inductor is used to be connected in series between the output end of the tooling DC / DC converter and the input end of the DC / DC converter to be tested.
[0013] Optionally, the test device further comprises: a constant voltage electronic load; the constant voltage electronic load is used to be connected in series between the input end of the tooling DC / DC converter and the output end of the DC / DC converter to be tested.
[0014] Optionally, the constant voltage electronic load is provided with an independent auxiliary power supply.
[0015] Optionally, the testing device further comprises: a cooling device, wherein the cooling device is used to reduce the temperature of the testing device and the DC / DC converter to be tested.
[0016] Optionally, the cooling device is a cold water circulation system.
[0017] According to another aspect of the present invention, a power supply testing system is provided, wherein the power supply comprises a battery and a DC / DC converter, and the power supply testing system comprises a testing device for the DC / DC converter as described in any one of the above items.
[0018] Optionally, the battery is a hydrogen fuel cell.
[0019] In summary, the beneficial effects of the present invention are:
[0020] The present application uses a tooling DC / DC converter in conjunction with a compensation power supply to detect the DC / DC converter under test, thereby realizing self-circulation of electric energy within the test device. After each test cycle, the compensation power supply compensates for the lost energy, thereby saving electric energy and not causing interference to the power grid. There is no need to add power grid isolation equipment, thus saving space and being more efficient. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 A schematic diagram of the structure of a DC / DC converter test device provided by one embodiment of the present invention;
[0022] Figure 2 A schematic diagram of a testing device for a DC / DC converter provided in another embodiment of the present invention. DETAILED DESCRIPTION
[0023] In order to make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.
[0024] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0025] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0026] The technical concept of the present invention is: this application uses a tooling DC / DC converter in conjunction with a compensation power supply to detect the DC / DC converter to be tested, thereby realizing the self-circulation of electric energy in the test device. After each test cycle, the compensation power supply compensates for the lost energy, which not only saves electric energy but also does not cause interference to the power grid. There is no need to add power grid isolation equipment, which saves space and is more efficient.
[0027] Figure 1 A schematic diagram of a DC / DC converter test device according to an embodiment of the present invention. Figure 1 As shown, a test device for a DC / DC converter includes: a host computer, a tooling DC / DC converter and a compensation power supply.
[0028] The host computer is used to connect to the DC / DC converter to be tested and detect the electrical performance of the DC / DC converter to be tested. The electrical performance may include the input and output characteristics of the DC / DC converter to be tested. For example, the input voltage and current and the output voltage and current may be made into a curve with a corresponding relationship to measure the voltage regulation performance of the DC / DC converter to be tested under different input states.
[0029] The input end of the tooling DC / DC converter is connected to the output end of the DC / DC converter to be tested, and the output end of the tooling DC / DC converter is connected to the input end of the DC / DC converter to be tested. Based on such a connection relationship, the tooling DC / DC converter is used to transform the voltage output by the DC / DC converter to be tested and return it to the DC / DC converter to be tested, so that an internal circulation of electric energy is formed in the test device. Thus, the electric energy after detection is reused, which improves the efficiency of electric energy, and does not need to be fed back to the power grid, which will not cause power grid disturbance, and there is no need to add isolation equipment.
[0030] The compensation power supply is connected to the input end of the tooling DC / DC converter, and is used to convert the AC power of the power grid into DC power to supplement the power for the test device. Since some power will be lost after each test, the compensation power supply is connected to the input end of the tooling DC / DC converter to replenish the power loss in time. Compared with the test device using the feedback type electronic load in the prior art, this embodiment only needs to connect the compensation power supply to the power grid, and there is no need to connect the electronic load to the power grid again at the back end for feedback, so less equipment is required, space is saved, and no disturbance is caused to the power grid.
[0031] In summary, this embodiment saves electric energy and does not cause interference to the power grid. There is no need to add power grid isolation equipment, which saves space and is more efficient.
[0032] Figure 2 A schematic diagram of a DC / DC converter test device is provided for another embodiment of the present invention, wherein the input end of the tooling DC / DC converter is a high-voltage end, which is used to receive the voltage output by the DC / DC converter to be tested, and the parallel compensation power supply to obtain electric energy supplement, and the tooling DC / DC converter steps down the voltage and returns it to the DC / DC converter to be tested.
[0033] like Figure 2 As shown, the test device also includes: a power analyzer; the power analyzer is used to measure the input circuit power and the output circuit power of the DC / DC converter to be tested, so as to further enrich the content of detecting the DC / DC converter to be tested.
[0034] In one embodiment of the present invention, the testing device further comprises: a Hall sensor. The Hall sensor is a sensor made based on the Hall effect. Figure 2 As shown, in this embodiment, the Hall sensor is arranged on the connection line between the tool DC / DC converter and the DC / DC converter to be tested, so as to detect the line current and / or voltage. Of course, it is also possible to use other types of sensors to detect and record the line voltage and / or current, which will not be described in detail here.
[0035] In one embodiment of the present invention, the testing device further comprises: an inductor, see Figure 2 As shown, the inductor is used to be connected in series between the output end of the tooling DC / DC converter and the input end of the DC / DC converter to be tested. The inductor connected in series at the input end can filter the low-frequency disturbance, increase the inductive reactance of the input end, reduce the input current ripple, and achieve stable and accurate detection.
[0036] In one embodiment of the present invention, the testing device further comprises: a constant voltage electronic load. Figure 2 As shown, the constant voltage electronic load is used to be connected in series between the input end of the tooling DC / DC converter and the output end of the DC / DC converter to be tested. The constant voltage electronic load is connected in series at the high voltage end to increase the loop impedance. At the same time, it also has a certain filtering effect, which can absorb pulses and filter out high-frequency waves.
[0037] In one embodiment of the present invention, the constant voltage electronic load is composed of an IGBT switch, etc., and is provided with an independent auxiliary power supply. Of course, the auxiliary power supply is only used to control the opening and closing of the IGBT in the constant voltage electronic load, and there is no need to provide power to the test device, so there is no need to use a high voltage power supply.
[0038] In one embodiment of the present invention, the testing device further comprises: a cooling device, which is used to reduce the temperature of the testing device and the DC / DC converter to be tested.
[0039] like Figure 2 In the illustrated embodiment, the cooling device is a cold water circulation system.
[0040] The present application also discloses a power supply testing system, wherein the tested power supply includes a battery and a DC / DC converter, and the power supply testing system includes a testing device for the DC / DC converter as described in any one of the above items.
[0041] In one embodiment of the present invention, the battery of the power supply to be tested is a hydrogen fuel cell. The power supply test system can be applied to the new energy automobile industry to test the on-board hydrogen fuel power supply. Of course, other power supplies with DC / DC converters can also be tested by this application, which will not be repeated here.
[0042] In summary, the present application uses a tooling DC / DC converter in conjunction with a compensation power supply to detect the DC / DC converter to be tested, realizing the self-circulation of electric energy in the test device. After each test cycle, the compensation power supply compensates for the lost energy, which not only saves electric energy, but also does not interfere with the power grid. There is no need to add power grid isolation equipment, which saves space and is more efficient. In the preferred embodiment of the present application, it can also be combined with an inductor and a constant voltage electronic load to filter out low-frequency and high-frequency ripples and improve the accuracy of detection.
[0043] The above is only a specific embodiment of the present invention. Under the above teachings of the present invention, those skilled in the art can make other improvements or modifications on the basis of the above embodiments. Those skilled in the art should understand that the above specific description is only to better explain the purpose of the present invention, and the protection scope of the present invention shall be based on the protection scope of the claims.
Claims
1. A test device for a DC / DC converter, It is characterized in that The test device includes: a host computer, a tooling DC / DC converter and a compensation power supply; The host computer is used to connect to the DC / DC converter to be tested and detect the electrical performance of the DC / DC converter to be tested; the electrical performance includes the input and output characteristics of the DC / DC converter to be tested, so as to measure the voltage regulation performance of the DC / DC converter to be tested under different input states; The input end of the tooling DC / DC converter is connected to the output end of the DC / DC converter to be tested, and the output end of the tooling DC / DC converter is connected to the input end of the DC / DC converter to be tested. The tooling DC / DC converter is used to transform the voltage output by the DC / DC converter to be tested and return it to the DC / DC converter to be tested, so that an internal circulation of electric energy is formed in the test device; The compensation power supply is connected to the input end of the tooling DC / DC converter and is used to convert the AC power of the power grid into DC power to supplement the power energy for the test device; The test device further comprises: a Hall sensor; the Hall sensor is arranged on a connection line between the tooling DC / DC converter and the DC / DC converter to be tested, and is used to detect line current and / or voltage.
2. The test device for a DC / DC converter according to claim 1, It is characterized in that The test device also includes: a power analyzer; the power analyzer is used to measure the input circuit power and the output circuit power of the DC / DC converter to be tested.
3. The test device for a DC / DC converter according to claim 1, It is characterized in that The testing device also includes: an inductor; the inductor is used to be connected in series between the output end of the tooling DC / DC converter and the input end of the DC / DC converter to be tested.
4. The test device for a DC / DC converter according to claim 1, It is characterized in that The test device also includes: a constant voltage electronic load; the constant voltage electronic load is used to be connected in series between the input end of the tooling DC / DC converter and the output end of the DC / DC converter to be tested.
5. The test device for a DC / DC converter according to claim 4, It is characterized in that The constant voltage electronic load is provided with an independent auxiliary power supply.
6. The test device for a DC / DC converter according to claim 1, It is characterized in that The test device also includes: a cooling device, which is used to reduce the temperature of the test device and the DC / DC converter to be tested.
7. The test device for a DC / DC converter according to claim 6, It is characterized in that The cooling device is a cold water circulation system.
8. A power supply test system, wherein the power supply comprises a battery and a DC / DC converter, It is characterized in that The power supply testing system comprises a testing device for a DC / DC converter as claimed in any one of claims 1 to 7.
9. The power supply testing system according to claim 8, It is characterized in that The battery is a hydrogen fuel cell.