Segmental assembled building translation track and translation method

Through the combination of flexible sealing materials and tension prestressing, the problems of resource waste and track connection breakage in traditional building translation technology are solved, and safe and reliable segment-prefabricated translation tracks under uneven road conditions are achieved, reducing resource waste and construction periods have improved economic and social benefits.

CN110939292BActive Publication Date: 2024-12-03HENAN WENBO CONSTR ENG CO LTD +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN201911386920.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-12-29
Publication Date
2024-12-03
Estimated Expiration
2039-12-29

AI Technical Summary

Technical Problem

In traditional architectural translation technology, the rail under reinforced concrete can only be used once, resulting in waste of resources and emission of construction waste. The pins connecting the two unit tracks under uneven road conditions are prone to breaking, causing the rail seat to be misaligned.

Method used

Combination pads made of flexible sealing materials and tensioned prestressed steel strands connect the track units through shear keyways and reserved holes to form reusable segment-mounted translation tracks to ensure safety under uneven road conditions Reliably assemble and disassemble.

Benefits of technology

It has achieved safety performance and stress effects under uneven road conditions, reduced resource waste and construction waste emissions, shortened construction periods, and improved economic and social benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110939292B_ABST
    Figure CN110939292B_ABST
Patent Text Reader

Abstract

The present invention provides a segmented assembled building translation track and a translation method, comprising at least two track units that can be assembled and separated, wherein the two end faces of the track unit are respectively provided with corresponding shear key grooves, and shear keys that bear shear force are provided in the shear key grooves where the two spliced ​​track units are connected. The beneficial effects of the present invention are as follows: for projects with long-distance translation, it is not necessary to make a whole translation track, and only two groups of segmented assembled tracks can be made, and the translation can be performed by dismantling the track and then replacing the track. The reusable segmented prefabricated assembled lower track is used in the overall translation of the building, so as to reduce the emission of construction waste, save costs, and shorten the construction period. It is more environmentally friendly than traditional methods and can obtain better economic and social benefits.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of building construction, and in particular relates to a segment assembled building translation track and a translation method. Background Art

[0002] In order to meet the needs of road widening and reconstruction in the main urban area, a large number of normally used street-facing buildings are facing demolition. The overall translation technology of buildings allows these buildings to be retained and avoided demolition, which not only meets the needs of urban road upgrading and reconstruction, but also prolongs the service life of buildings, reduces resource waste and construction waste emissions. In addition, in the protection process of key cultural relics and important historical buildings, protection measures such as relocation and translation are often adopted. Traditional building translation technology mostly uses reinforced concrete lower tracks set on the building translation route, and the building is moved to the new site on the translation track. The reinforced concrete lower track can only be used once, and the translated building is demolished immediately after arriving at the new site, resulting in considerable resource waste and construction waste emissions.

[0003] Patent CN106760619B discloses a building translation device and a construction method thereof, which uses a split assembly displacement track to improve the lower track into a reusable segment prefabricated assembly lower track. A tenon is provided at the front end of the track unit, and a groove that matches the tenon is provided at the rear end. A connecting hole is provided at the tenon and the groove, and a pin passes through the connecting hole to connect the track unit. This construction method reduces the discharge of construction waste, saves costs, and shortens the construction period. It is more environmentally friendly than traditional methods and can achieve the best economic and social benefits. However, the connection method of the two unit tracks adopts staggered connection and pin connection. The bearing capacity of the pin is limited, especially the shear force. Due to different road conditions, the pins connecting the two unit tracks will be subjected to large shear forces, tensile forces, etc., and it is easy to break and cause the rail seat to be dislocated. A translation track and a translation method that are suitable for uneven road conditions, have good safety performance, good force effect, and are easy to assemble and disassemble are needed. Summary of the invention

[0004] The invention provides a segment assembled building translation track and a translation method which are suitable for uneven road conditions, have good safety performance, good force effect, and are easy to assemble and disassemble.

[0005] The objective of the present invention is achieved in the following manner: a segmented assembled building translation track comprises at least two track units that can be assembled and separated, shear key grooves corresponding to the positions are arranged on the two end faces of the track units, and shear keys for bearing shear force are arranged in the shear key grooves where the two spliced ​​track units are connected.

[0006] The shear key is a bonding pad, which is a flexible sealing material. The bonding pad includes a slurry bag and a connecting tube. The shape of the slurry bag corresponds to the shape of the shear key groove. A grouting hole is provided at one end of the bonding pad and an overflow hole is provided at the other end. The shear key is formed after the slurry in the bonding pad solidifies.

[0007] Adjacent shear key grooves are connected by connecting grooves and are called a shear key group; the shape of the connecting groove corresponds to the shape of the connecting pipe of the bonding pad.

[0008] A through hole arranged on the track unit and parallel to the length direction of the track unit is called a reserved hole. A steel strand with prestressed tension is arranged in the reserved hole, and the steel strand passes through the spliced ​​track units.

[0009] The reserved hole is located at the end surface of the track unit to set a positioning hole, and a sleeve for the steel strand to pass through is set in the connected positioning holes of two adjacent track units.

[0010] A positioning hole is arranged on the end surface of the track unit, and a positioning pin is arranged in the connected positioning holes of two adjacent track units.

[0011] The method comprises the following steps: (1) prefabricating a track unit; the two end surfaces of the track unit are pre-set with positioning holes, pre-set holes, and shear key slots; prefabricating a bonding pad, which is made of a flexible sealing material, including a grout bag and a connecting pipe, and the two ends of the bonding pad are respectively provided with grouting holes and overflow holes, and the shape of the grout bag corresponds to the shape of the shear key slot; (2) placing two prefabricated track units on a concrete cushion layer to prepare for docking, placing positioning pins in the positioning holes, and placing sleeves in the positioning holes at the positions of the pre-set holes; placing the inflated bonding pad into the shear key slot and making it engage with the shear key slot; (3) Insert the steel hinge wire into the reserved hole, tension and anchor the steel hinge wire, open the grouting hole of the combination pad to release air, and then grout the slurry bag with pressure from the grouting hole of the combination pad until the slurry without bubbles emerges from the overflow hole. Keep the grouting pressure to seal the overflow hole, and then seal the grouting hole; (4) After the slurry in the slurry bag of the combination pad solidifies and reaches the required strength, a shear bond is formed between the two track units; (5) The translation building slides on the track unit, and the track unit that passes by can be disassembled and reassembled in front of the moving direction of the translation building.

[0012] The translation building is supported by a supporting beam, and a jacking jack and a jacking support are installed at the rear end of the supporting beam. The jacking support is fixed to the track unit by a tension plate. There is a slider at the bottom of the supporting beam. Under the action of the jacking jack, the translation building moves.

[0013] The process of disassembling the track unit is as follows: release the stress of the steel hinge wire in the track unit, remove the steel hinge wire and its anchor, and remove the bonding pads between the track units.

[0014] The beneficial effects of the present invention are as follows: the present invention abandons the cast-in-place concrete lower track of the traditional building translation, and connects two pieces of segmented assembled tracks through a slurry bag bonding pad. Due to the isolation effect of the bonding pad, the slurry does not contact the end face of the segmented assembled track. After the translation is completed, the two pieces of segmented assembled tracks are naturally separated, and the end face does not need to be cleaned, thereby avoiding damage to the segmented assembled track during the cleaning process. When reused again, only a new slurry bag needs to be replaced to assemble a new track. In addition, for long-distance translation projects, it is not necessary to make an entire translation track. Only two sets of segmented assembled tracks can be made, and the translation is carried out by alternating forward by dismantling and then repairing. The reusable segmented prefabricated assembled lower track is used in the overall translation of the building, which can reduce the emission of construction waste, save costs, and shorten the construction period. It is more environmentally friendly than traditional methods and can obtain better economic and social benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a layout diagram of the building translation track of the present invention.

[0016] Figure 2 This is a structural diagram of the end face of the track unit.

[0017] Figure 3 It is the track unit bonding pad.

[0018] Figure 4 yes Figure 3 Section view.

[0019] Figure 5 This is a schematic diagram of the pre-assembly of the track unit.

[0020] Figure 6 This is a schematic diagram of the track unit after splicing.

[0021] Among them, 1 is the track unit, 2 is the concrete cushion, 3 is the translation building, 4 is the support beam, 5 is the push jack, 6 is the push support, 7 is the tie plate, 8 is the slider, 9 is the lifting ring, 10 is the positioning hole, 11 is the reserved hole, 12 is the shear key groove, 13 is the connecting groove, 14 is the combining pad, 16 is the slurry bag, 17 is the connecting pipe, 18 is the grouting hole, 20 is the overflow hole, 22 is the positioning pin, 23 is the sleeve, and 24 is the steel strand. DETAILED DESCRIPTION

[0022] like Figure 1-6As shown, a segmented assembled building translation track includes at least two track units 1 that can be assembled and separated. The two end faces of the track unit 1 are respectively provided with corresponding shear key grooves 12, and the shear key that bears the shear force is provided in the shear key grooves 12 where the two spliced ​​track units 1 are connected. In the existing assembly structure of the building translation track, there is no structure that specifically bears the shear force on the plane perpendicular to the forward direction. Because the ground cannot be guaranteed to be absolutely flat during the construction process, the connection between the two track units 1 will certainly bear a large shear force, which is easy to be damaged, resulting in a connection rupture, uneven track, and affecting the smooth progress of the translation process. The shear key can be a commonly used rigid structure such as a pin or shaft, and multiple are arranged side by side. It can also be made of a material with variable stiffness. Each unit track 1 has a length of L, and a translation track is composed of several track units 1, which are placed on a concrete cushion 2 to form a complete translation track. The translation building 3 is pushed by a jack to slide on the translation track. The specific structure can refer to the patent documents of the background technology.

[0023] The shear key can be a bonding pad 14, which is a flexible sealing material. The bonding pad 14 includes a slurry bag 16 and a connecting tube 17. The shape of the slurry bag 16 corresponds to the shape of the shear key groove 12; a grouting hole 18 is provided at one end of the bonding pad 14, and an overflow hole 20 is provided at the other end; a shear key is formed after the slurry in the bonding pad 14 solidifies. Pressure grouting is required for the bonding pad 14, and the slurry is a non-shrinking gel material. After the slurry in the slurry bag 16 of the bonding pad 14 solidifies and reaches the required strength, a shear key that transmits shear force between the two track units 1 is formed. Before use, the bonding pad 14 should be filled with air to check the air tightness and kept in an inflated state for standby use.

[0024] Adjacent shear key grooves 12 are connected by connecting grooves 13 and are called a shear key group; the shape of the connecting groove 13 corresponds to the shape of the connecting tube 17 of the bonding pad 14. Two shear key groups are symmetrically arranged in the middle position of the end face of the track unit 1, and one shear key group is arranged at both sides. Of course, it can also be arranged in other places according to needs and the cross-sectional shape of the track unit 1. The size and movement of shear key groups at different positions are not necessarily the same.

[0025] The through hole parallel to the length direction of the track unit 1 is called a reserved hole 11. The reserved hole 11 is provided with a steel strand 24 with prestressed tension, and the steel strand 24 passes through the spliced ​​track unit 1. The length direction of the track unit 1 here refers to the direction of building translation and the length direction of track splicing. The steel strand 24 can withstand tension.

[0026] The reserved hole 11 is located at the end surface of the track unit 1 and a positioning hole 10 is provided. A sleeve 23 is provided in the connected positioning holes 10 of two adjacent track units 1 for passing the steel strand 24. The sleeve 23 also bears shear force.

[0027] The end face of the track unit 1 is provided with a positioning hole 10, and the positioning pins 22 are provided in the connected positioning holes 10 of two adjacent track units 1. The positioning pins 22 and sleeves 23 are both made of rigid materials. In addition, the track unit 1 is equipped with a lifting ring 9 for easy installation, transportation and disassembly. The positioning pins 22 and sleeves 23 can also transmit a certain shear force. At the same time, under the joint action of the prestressing force of the steel hinge wire 24, the track unit 1 forms an overall force system.

[0028] A translation method for a segmented assembled building translation track, characterized in that it comprises the following steps: (1) prefabricating a track unit 1; the two end surfaces of the track unit 1 are pre-set with positioning holes 10 and pre-set holes 11, and a shear key slot 12; prefabricating a bonding pad 14, the bonding pad 14 is made of a flexible sealing material, comprises a slurry bag 16 and a connecting pipe 17, and grouting holes 18 and overflow holes 20 are respectively arranged at both ends of the bonding pad 14, and the shape of the slurry bag 16 corresponds to the shape of the shear key slot 12; (2) placing two prefabricated track units 1 on a concrete cushion layer 2 for docking, placing a positioning pin 22 in the positioning hole 10, and placing a sleeve 23 in the positioning hole 10 at the position of the pre-set hole 11; placing the inflated bonding pad 14 (3) Insert the steel hinge wire 24 into the reserved hole 11, tension and anchor the steel hinge wire 24, open the grouting hole 18 of the bonding pad 14 to release air, and then pressure grout the slurry bag 16 from the grouting hole 18 of the bonding pad 14 until the slurry without bubbles emerges from the overflow hole 20, keep the grouting pressure to seal the overflow hole 20, and then seal the grouting hole 18; (4) After the slurry in the slurry bag 16 of the bonding pad 14 solidifies and reaches the required strength, a shear key is formed between the two track units 1; (5) The translation building 3 slides on the track unit 1, and the track unit 1 that passes by can be disassembled and reassembled in front of the moving direction of the translation building 3.

[0029] The translation building 3 is supported by a supporting beam 4, and a jacking jack 5 and a jacking support 6 are installed at the rear end of the supporting beam 4. The jacking support 6 is fixed to the track unit 1 by a tension plate 7. A slider 8 is provided at the bottom of the supporting beam 4. Under the action of the jacking jack 5, the translation building 3 moves.

[0030] The process of disassembling the track unit 1 is as follows: release the stress of the steel hinge wire 24 in the track unit 1, remove the steel hinge wire 24 and its anchor, and remove the bonding pad 14 between the track units 1. Since the slurry is enclosed in the slurry bag 16, the slurry bag 16 plays an isolating role, and the slurry in the slurry bag 16 does not directly contact the end face of the track unit 1, and the two track units 1 are not bonded together by the slurry, so after the translation is completed, the two pieces of track units 1 are naturally separated, and no slurry will remain on the end face of the track unit 1. The end face does not need to be cleaned, avoiding damage to the track unit 1 during the cleaning process and ensuring the integrity of the end face. The dismantled track unit 1 is hoisted and transported back to the yard for storage in pieces for reuse next time.

[0031] The technical features of the above-described embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

Claims

1. A segmented assembled building translation track, comprising at least two track units that can be assembled and separated, Features: The two end surfaces of the track unit are respectively provided with corresponding shear key grooves, and shear keys for bearing shear force are provided in the shear key grooves where the two spliced ​​track units are connected; The shear key is a bonding pad, which is a flexible sealing material. The bonding pad includes a slurry bag and a connecting tube. The shape of the slurry bag corresponds to the shape of the shear key groove. A grouting hole is provided at one end of the bonding pad and an overflow hole is provided at the other end. The shear key is formed after the slurry in the bonding pad solidifies.

2. According to claim 1, a segmented assembled building translation track, Features: Adjacent shear key grooves are connected by connecting grooves and are called a shear key group; the shape of the connecting groove corresponds to the shape of the connecting pipe of the bonding pad.

3. According to claim 2, a segmented assembled building translation track, Features: The through hole parallel to the length direction of the track unit is arranged on the track unit, which is called a reserved hole. A steel strand with prestressed tension is arranged in the reserved hole, and the steel strand passes through the spliced ​​track units.

4. According to claim 3, a segmented assembled building translation track, Features: The reserved hole is located at the end surface of the track unit to set a positioning hole, and a sleeve for the steel strand to pass through is set in the connected positioning holes of two adjacent track units.

5. According to claim 2, a segmented assembled building translation track, Features: The end surface of the track unit is provided with a positioning hole, and the connecting positioning holes of two adjacent track units are provided with a positioning pin.

6. A translation method for a segmented assembled building translation track, Features: The following steps are involved: (1) Prefabricated track unit; The two end surfaces of the track unit are reserved with positioning holes, reserved holes, and shear key slots; the prefabricated bonding pad is made of flexible sealing material, including a grout bag and a connecting pipe. Grouting holes and overflow holes are respectively set at both ends of the bonding pad. The shape of the grout bag corresponds to the shape of the shear key slot; (2) Place the two prefabricated track units on the concrete cushion layer to prepare for docking, place positioning pins in the positioning holes, and place sleeves in the positioning holes at the reserved hole positions; put the inflated bonding pad into the shear key slot and make it tightly engage with the shear key slot; (3) Prefabricated Insert the steel hinge wire into the hole, tension and anchor the steel hinge wire, open the grouting hole of the bonding pad to release air, and then pressure grout the slurry bag from the grouting hole of the bonding pad until slurry without bubbles emerges from the overflow hole. Keep the grouting pressure to seal the overflow hole, and then seal the grouting hole; (4) After the slurry in the slurry bag of the bonding pad solidifies and reaches the required strength, a shear bond is formed between the two track units; (5) The translation building slides on the track unit, and the track unit that passes by can be disassembled and reassembled in front of the moving direction of the translation building.

7. The translation method of the segmented assembled building translation track according to claim 6, Features: The translation building is supported by a supporting beam, a jacking jack and a jacking support are installed at the rear end of the supporting beam, the jacking support is fixed on the track unit by a tension plate, and a slider is provided at the bottom of the supporting beam. Under the action of the jacking jack, the translation building moves.

8. The translation method of the segmented assembled building translation track according to claim 6, Features: The process of disassembling the track unit is as follows: release the stress of the steel hinge wire in the track unit, remove the steel hinge wire and its anchor, and remove the bonding pads between the track units.

Citation Information

Patent Citations

  • A building translation device and its construction method

    CN106760619B

  • Building translation device and building translation construction method

    CN106760619A

  • Track under push -and -pull device

    CN206681556U

  • Running target track that can splice

    CN206752215U

  • Segmental assembly type building translation track

    CN211548918U