A rainwater seepage prevention structure from the side ditch to the slope foot area of ​​the filled and excavated square section road

By setting up a combination of C-type precast concrete blocks, permeable concrete, geomembrane, fill layer and anti-seepage lime soil layer from the road side ditch to the slope foot area, the problem of softening of the subgrade soil caused by rainfall infiltration is solved and waterproofing is achieved The effect is to enhance the protective performance of road ditches.

CN111188237BActive Publication Date: 2024-10-15CHANGAN UNIV +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010113325.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-02-24
Publication Date
2024-10-15
Estimated Expiration
2040-02-24

AI Technical Summary

Technical Problem

The area from the road ditch to the foot of the slope is prone to problems such as softening, settlement, and uneven settlement of the roadbed soil and inclination and cracking of the road shoulder retaining wall under the action of rainfall, which threatens the safety of road engineering operations.

Method used

A combined structure of multiple C-shaped precast concrete blocks, precast permeable concrete, geomembrane, soil filling layer, vegetation layer, vertical anti-seepage lime soil layer and sand filter layer is used to form an anti-seepage system to prevent rainwater from infiltrating and guiding it. Rainwater flows into roadside ditches.

Benefits of technology

It effectively prevents rainwater from infiltrating, avoids softening of roadbed soil, prevents soil loss, improves the waterproof performance of road side ditches, and has an ecological beautification effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111188237B_ABST
    Figure CN111188237B_ABST
Patent Text Reader

Abstract

The present invention provides a rainfall anti-seepage structure from the side ditch to the foot of the slope of a cut-and-fill section road. The anti-seepage structure comprises a vertical anti-seepage ash soil layer, a geomembrane, a fill layer and a vegetation layer which are sequentially arranged above the in-situ soil in the foot of the slope. A plurality of adjacently distributed C-shaped precast concrete blocks are longitudinally arranged on one side of the foot of the slope close to the side ditch. The top surface of the C-shaped precast concrete block is higher than the top surface of the vegetation layer. The C-shaped precast concrete block is filled with precast permeable concrete, which is used to prevent the softening of the roadbed soil due to rainfall, thereby inducing settlement, uneven settlement and cracks in the road surface, as well as inclination and cracking of the shoulder retaining wall of the cut-and-fill section and many other defects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of roadbed drainage in road engineering, and in particular relates to a rainfall seepage prevention structure from a side ditch to a slope foot area of ​​a filled and excavated square section road. Background Art

[0002] When road projects are carried out in mountainous and hilly areas with undulating terrain, it is common to encounter roadbed sections formed by excavating low-lying soil with poor surface properties and backfilling with soil with good properties. In such cut-and-fill sections, one side of the road ditch is often the toe of the slope, and there is an area from the road ditch to the toe line without special treatment. Under the action of atmospheric rainfall, the area from the road ditch to the toe of the slope in the cut-and-fill section without special treatment is often affected by rainfall infiltration, resulting in softening of the roadbed soil, which in turn induces many diseases such as settlement, uneven settlement and cracks of the road surface, and tilting and cracking of the shoulder retaining wall of the cut-and-fill section, which seriously threatens the normal operation safety of the road project. Summary of the invention

[0003] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a rainfall anti-seepage structure from the side ditch to the slope foot area of ​​the fill-cut section road, so as to solve the problems of the prior art that the roadbed soil is softened due to the influence of rainfall infiltration, thereby inducing settlement, uneven settlement and cracks of the road surface, as well as tilting and cracking of the shoulder retaining wall of the fill-cut section and many other defects.

[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions to achieve the above problems:

[0005] A rainfall anti-seepage structure from a road ditch to a slope foot area in a filled and cut section, the anti-seepage structure comprising a plurality of C-shaped precast concrete blocks longitudinally arranged in sequence on the side walls of the road ditch, the C-shaped precast concrete blocks and the side walls of the road ditch enclosing a through hole, the through hole being provided with precast permeable concrete, and a geomembrane being provided on the side of the C-shaped precast concrete block close to the slope foot area.

[0006] The anti-seepage structure also includes a fill layer and a vegetation layer sequentially arranged above the geomembrane and a vertical anti-seepage lime soil layer arranged below the geomembrane. The top surface of the C-shaped precast concrete block is higher than the top surface of the vegetation layer.

[0007] A plurality of sand and gravel filter layers are longitudinally arranged on one side of the fill layer close to the road ditch.

[0008] The vertical water-cutting lime soil layer is inclined toward the road ditch in a direction with an angle of 2° to 5° with the horizontal plane.

[0009] The sand and gravel filter layer is arranged corresponding to the through hole, and the height and width of the sand and gravel filter layer are respectively greater than the height and width of the through hole.

[0010] The C-shaped precast concrete block comprises a back section, a first overhanging section and T-shaped teeth, and the C-shaped precast concrete block is arranged on the side wall of the road ditch through the T-shaped teeth.

[0011] The geomembrane includes an upper geomembrane and a lower geomembrane, one end of the upper geomembrane is overlapped on one end of the lower geomembrane, and the lower geomembrane includes a second extending section, a third extending section and a flat section, the second extending section is arranged above the side wall of the road ditch, and the third extending section is arranged below the first extending section.

[0012] The anti-seepage structure also includes a longitudinal water-cutting lime-soil layer, which is arranged on the in-situ soil and is used to block the longitudinal flow of water.

[0013] The longitudinal water-cutting lime-soil layer abuts against the first extending section.

[0014] The top surface of the longitudinal water-cutting lime soil layer is flush with the top surface of the vegetation layer.

[0015] Compared with the prior art, the present invention has the following technical effects:

[0016] (I) The anti-seepage structure of the present invention can avoid the influence of rainfall infiltration on the roadbed soil by arranging a vertical anti-seepage gray soil layer, a geomembrane, a fill layer, a vegetation layer, a C-type prefabricated concrete block and prefabricated permeable concrete from the road ditch to the slope foot area.

[0017] (II) The vegetation layer of the present invention can absorb and utilize a part of the rainwater generated by rainfall and can produce the effect of ecological beautification.

[0018] (III) The fill layer of the present invention can effectively infiltrate rainwater that is not absorbed by the vegetation layer, and by providing a geomembrane and a vertical anti-seepage lime soil layer, it can effectively prevent rainwater from continuing to infiltrate and guide rainwater into the road ditch.

[0019] (IV) The sand and gravel filter layer of the present invention can effectively block the soil particles carried in the water flow entering the road ditch, thereby preventing the loss of soil. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the overall structure of the anti-seepage structure of the present invention;

[0021] Figure 2 It is a partial schematic diagram of the anti-seepage structure and the road ditch of the present invention;

[0022] Figure 3 It is a structural schematic diagram of a C-type prefabricated concrete block of the present invention;

[0023] Figure 4 It is a schematic structural diagram of the lower geomembrane of the present invention;

[0024] Figure 5 It is a schematic diagram of the arrangement of the lower geomembrane of the present invention on the side wall of the road ditch;

[0025] Figure 6 It is a schematic diagram of the longitudinal arrangement of the longitudinal water-cutting lime-soil layer of the present invention.

[0026] The meaning of each number in the figure is:

[0027] 1-slope foot area, 2-in-situ soil, 3-vertical anti-seepage lime soil layer, 4-geomembrane, 5-fill layer, 6-vegetation layer, 7-road ditch, 8-C-type precast concrete blocks, 9-precast permeable concrete, 10-sand and gravel filter layer, 11-vertical water interception lime soil layer;

[0028] 401-upper geomembrane, 402-lower geomembrane;

[0029] 4021-second extension section, 4022-third extension section, 4023-flat section;

[0030] 8-1- back section, 02- first extension section, 803- T-shaped teeth, 804- through hole.

[0031] The specific contents of the present invention are further explained in detail below in conjunction with embodiments. DETAILED DESCRIPTION

[0032] Specific embodiments of the present invention are given below. It should be noted that the present invention is not limited to the following specific embodiments, and all equivalent changes made on the basis of the technical solution of this application fall within the protection scope of the present invention.

[0033] Example:

[0034] This embodiment provides a rainwater seepage prevention structure from the side ditch of a filled and cut section road to the slope foot area, such as Figure 1-6 As shown, the anti-seepage structure includes a plurality of C-shaped precast concrete blocks 8 longitudinally arranged in sequence on the side walls of the road ditch 7, wherein the C-shaped precast concrete blocks 8 and the side walls of the road ditch 7 enclose a through hole 804, wherein precast permeable concrete 9 is arranged in the through hole 804, and a geomembrane 4 is arranged on the side of the C-shaped precast concrete block 8 close to the slope foot area 1.

[0035] The anti-seepage structure provided by the present invention can be achieved by arranging vertical anti-seepage C-shaped precast concrete blocks 8 on the side walls of the road ditch 7. The C-shaped precast concrete blocks 8 can be enclosed with the side walls of the road ditch 7 to form a through hole 804, and by filling the through hole 804 with precast permeable concrete 9. When the rainfall is large, it can effectively prevent the softening of the roadbed soil and the loss of soil caused by the infiltration of rainwater from the road ditch to the foot of the slope in the filled and excavated section.

[0036] The prefabricated permeable concrete 9 is made of materials such as permeable concrete with good permeability, strength and durability. The length, width and height dimensions of the prefabricated permeable concrete block are 30cm*20cm*5cm.

[0037] As a preferred solution of this embodiment, the anti-seepage structure also includes a fill layer 5 and a vegetation layer 6 arranged in sequence above the geomembrane 4 and a vertical anti-seepage ash soil layer 3 arranged below the geomembrane 4, and the top surface of the C-type precast concrete block 8 is higher than the top surface of the vegetation layer 6.

[0038] Among them, the vegetation layer can make full use of a part of the rainwater generated by rainfall and can produce the effect of ecological beautification. The fill layer can effectively penetrate the rainwater that is not absorbed by the vegetation layer, and by setting up geomembrane and vertical anti-seepage gray soil layer, it can effectively prevent rainwater from continuing to infiltrate and guide rainwater into the road ditch.

[0039] As a preferred solution of this embodiment, a plurality of sand and gravel filter layers 10 are longitudinally provided on one side of the fill layer close to the road ditch.

[0040] The function of the sand and gravel filter layer 10 is to prevent soil particles from being carried away when rainwater flows out. The sand and gravel filter layer 10 has good water permeability and is composed of crushed stone and sand. The width is 15 cm to 20 cm and the length is the distance between adjacent longitudinal water-intercepting lime soil layers.

[0041] As a preferred solution of this embodiment, the vertical water-cutting lime-soil layer 3 is inclined toward the road ditch 7 at an angle of 2°~5° to the horizontal plane, so that rainwater in the fill layer 5 flows into the road ditch along the geomembrane on the vertical water-cutting lime-soil layer 3.

[0042] Among them, the vertical anti-seepage lime soil layer 3 has good anti-seepage ability, and the manufacturing material can be lime soil with a mass ratio of 2:8. The thickness of the vertical anti-seepage lime soil layer 3 is 15~20cm. During construction, the compaction degree is controlled to reach the maximum. The vertical anti-seepage lime soil layer 3 should extend horizontally to the slope foot area 1.

[0043] As a preferred solution of this embodiment, the sand and gravel filter layer 10 is arranged corresponding to the through hole 804, and the height and width of the sand and gravel filter layer 10 are respectively greater than the height and width of the through hole 804, in order to ensure that all rainwater passing through the prefabricated permeable concrete 9 can be filtered out of soil particles by the sand and gravel filter layer 10.

[0044] As a preferred solution of this embodiment, the C-shaped precast concrete block 8 includes a back section 801, a first extending section 802 and a T-shaped tooth 803, the two ends of the lower side of the back section 801 are respectively vertically connected to the first extending section 802, and the end of the first extending section 802 away from the back section 801 is connected to the T-shaped tooth 803, and the C-shaped precast concrete block 8 is arranged on the side wall of the road ditch 7 through the T-shaped tooth 803.

[0045] Among them, the manufacturing material of the C-type precast concrete block 8 is selected from concrete with a certain anti-seepage function. The inner side of the T-shaped tooth 803 of the C-type precast concrete block 8 is constructed close to the side wall of the road ditch and is bonded by applying cement mortar. The length, width and height dimensions of the C-type precast concrete block 8 are 50cm*20cm*20cm.

[0046] As a preferred solution of this embodiment, the geomembrane 4 includes an upper geomembrane 401 and a lower geomembrane 402, one end of the upper geomembrane 401 is overlapped at one end of the lower geomembrane 402, and the overlap length is not less than 25 cm, the lower geomembrane 402 includes a second extension section 4021, a third extension section 4022 and a flat section 4023, the second extension section 4021 is connected to the flat section 4023 in the same plane, the third extension section 4022 is located on both sides of the second extension section 4021, and is vertically connected to the flat section 4023, the second extension section 4021 is arranged above the side wall of the road ditch 7, and the third extension section 4022 is arranged on the side of the first extension section 802 close to the slope foot area;

[0047] Among them, the geomembrane 4 adopts geotechnical materials with anti-seepage ability, and there is an overlap section of not less than 25 cm in length at the connection between the upper geomembrane 401 and the lower geomembrane 402, and the contact surface of the overlap section remains smooth; the upper geomembrane 401 is arranged near the foot of the slope, and the lower geomembrane 402 is arranged near the road ditch; the upper geomembrane 401 is a whole piece, and the length of the second overhanging section 4021 is the same as the side wall thickness of the road ditch 7. In order to better combine the lower geomembrane 402 with the road ditch 7, the length of the third overhanging section 4022 is the same as the height of the C-type precast concrete block 8. In order to better combine the lower geomembrane 402 with the road ditch 7, the second overhanging section 4021 of the lower geomembrane 402 is neatly placed on the top surface of the side wall of the road ditch 7 during construction, and the upper geomembrane 401 extends horizontally to the foot of the slope 1.

[0048] In this embodiment, the permeability coefficient of the geomembrane and the permeability coefficient of the in-situ soil without the geomembrane are respectively given, as shown in Table 1, which are 6 groups of permeability coefficients obtained by conducting permeability tests of the geomembrane and silt using 6 geomembranes and 6 silt soil samples.

[0049] Table 1

[0050]

[0051] According to the above comparative test data, the permeability of geomembranes is on the order of 10 -11 cm / s, and the average permeability coefficient is 2.4×10 -11 cm / s; the permeability coefficient of silt is on the order of 10 -5 cm / s, and the average permeability coefficient is 3.2×10 -5 cm / s.

[0052] In summary, according to the geomembrane permeability coefficient and silt permeability coefficient obtained from the comparative test, it can be seen that from the order of magnitude of the permeability coefficient alone, the silt permeability coefficient is 100,000 times that of the geomembrane. This shows that the solution of this embodiment can increase the permeability resistance of the in-situ soil by 100,000 times, so that it is difficult for rainfall from the road ditch to the slope foot area to penetrate into the in-situ soil, thereby softening the roadbed soil.

[0053] As a preferred solution of this embodiment, it is characterized in that the anti-seepage structure also includes a longitudinal water-cutting lime-soil layer 11, and the longitudinal water-cutting lime-soil layer 11 is arranged on the in-situ soil 2 to block the longitudinal flow of rainwater.

[0054] Among them, the longitudinal water-cutting lime-soil layer 11 has good anti-seepage ability, and the manufacturing material can be lime-soil with a mass ratio of 2:8; the construction position of the longitudinal water-cutting lime-soil layer 11 is located at the first extended section of the C-type precast concrete block 8, and the thickness of the longitudinal water-cutting lime-soil layer 11 is recommended to be 15 cm ~ 20 cm. The longitudinal water-cutting lime-soil layer 11 should extend horizontally to the slope foot area 1, and the longitudinal water-cutting lime-soil layer 11 can be set at intervals of 8m ~ 10m.

[0055] As a preferred solution of this embodiment, it is characterized in that the longitudinal water-intercepting lime soil layer 11 is in contact with the first extending section 802, so as to effectively intercept the longitudinal flow of rainwater.

[0056] As a preferred solution of this embodiment, it is characterized in that the top surface of the longitudinal water-intercepting lime-soil layer 11 is flush with the top surface of the vegetation layer 6 .

[0057] The construction steps of the anti-seepage structure of this embodiment are: excavating a construction trench for a vegetation layer, a fill layer, and a vertical anti-seepage gray soil layer; setting a horizontal slope at the bottom of the trench and leveling the bottom surface of the construction trench; constructing a vertical anti-seepage gray soil layer; constructing C-type precast concrete blocks and precast permeable concrete blocks; constructing a longitudinal anti-seepage gray soil layer; laying a lower geomembrane; laying an upper geomembrane; constructing a sand and gravel filter layer and a fill layer; and constructing a vegetation layer.

Claims

1. A rainwater seepage prevention structure from the side ditch of a filled and excavated section of a road to the slope foot area. It is characterized in that The anti-seepage structure comprises a plurality of C-shaped precast concrete blocks (8) arranged longitudinally in sequence on the side walls of the road ditch (7), the C-shaped precast concrete blocks (8) and the side walls of the road ditch (7) enclosing a through hole (804), the through hole (804) being provided with precast permeable concrete (9), and a geomembrane (4) being provided on one side of the C-shaped precast concrete blocks (8) close to the slope foot area (1); The anti-seepage structure further comprises a fill layer (5) and a vegetation layer (6) sequentially arranged above the geomembrane (4), and a vertical anti-seepage lime soil layer (3) arranged below the geomembrane (4), and the top surface of the C-shaped prefabricated concrete block (8) is higher than the top surface of the vegetation layer (6); A plurality of sand and gravel filter layers (10) are longitudinally arranged on one side of the fill layer close to the road ditch; The vertical anti-seepage lime soil layer (3) is inclined toward the road ditch (7) in a direction with an angle of 2° to 5° with the horizontal plane; The sand and gravel filter layer (10) is arranged corresponding to the through hole (804), and the height and width of the sand and gravel filter layer (10) are respectively greater than the height and width of the through hole (804); The C-shaped precast concrete block (8) comprises a back section (801), a first overhanging section (802) and a T-shaped tooth (803); the two ends of a lower side of the back section (801) are respectively vertically connected to the first overhanging section (802); the end of the first overhanging section (802) away from the back section (801) is connected to the T-shaped tooth (803); the C-shaped precast concrete block (8) is arranged on the side wall of the road ditch (7) via the T-shaped tooth (803); The geomembrane (4) comprises an upper geomembrane (401) and a lower geomembrane (402), one end of the upper geomembrane (401) is overlapped on one end of the lower geomembrane (402), the lower geomembrane (402) comprises a second extending section (4021), a third extending section (4022) and a flat section (4023), the second extending section (4021) and the flat section (4023) are connected in the same plane, the third extending section (4022) is located on both sides of the second extending section (4021) and is vertically connected to the flat section (4023), the second extending section (4021) is arranged above the side wall of the road ditch (7), and the third extending section (4022) is arranged on the side of the first extending section (802) close to the slope foot area; The anti-seepage structure further comprises a longitudinal water-blocking lime soil layer (11), which is arranged on the in-situ soil (2) and is used to block the longitudinal flow of water. The in-situ soil (2) is located between the slope foot area (1) and the road ditch (7).

2. The anti-seepage structure according to claim 1, It is characterized in that The longitudinal water-intercepting lime-soil layer (11) is in contact with the first extending section (802).

3. The anti-seepage structure according to claim 1, It is characterized in that The top surface of the longitudinal water-cutting lime soil layer (11) is flush with the top surface of the vegetation layer (6).