A structure and construction technology of a fully prestressed concrete composite box girder bridge

Through the full-section prestressed concrete combination box girder bridge structure and bowl-buckle bracket setting technology, the problems of large basement area, large amount of earth and limited prestressing during the construction of the existing box girder bridge are solved, and the structure is stable and construction safety is achieved It will not affect the effect from surrounding facilities.

CN111501519BActive Publication Date: 2024-11-15JIANGSU ZHONGTAI CONSTR & DEV GRP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202010411979.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-05-15
Publication Date
2024-11-15
Estimated Expiration
2040-05-15

AI Technical Summary

Technical Problem

The existing box girder bridge construction has problems such as large basement area, large amount of earthwork, complex construction terrain, resulting in facilities impact, difficulty in applying prestress, limited prestress, structural safety hazards and impact on surrounding facilities.

Method used

The full-section prestressed concrete combined box girder bridge structure is adopted, including the main bridge, C ramp bridge and I ramp bridge. Through bowl-buckle bracket erection and graded pre-pressing technology, combined with drilled pile foundation, it ensures the stability of the structure and construction safety.

Benefits of technology

A box girder bridge with reasonable structure, convenient construction, convenient access and good safety performance has been realized, which reduces the impact on surrounding facilities, enhances the stability and safety of the bridge body, and reduces construction risks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111501519B_ABST
    Figure CN111501519B_ABST
Patent Text Reader

Abstract

The invention relates to a full-section prestressed concrete composite box girder bridge structure, comprising a main bridge, a C ramp bridge and an I ramp bridge, wherein the main bridge is connected with the C ramp bridge and the I ramp bridge, and a bowl-hook type bracket is adopted as the whole structure, and the construction process comprises the following steps: foundation treatment - bracket erection - bracket pre-pressing - side form installation - steel bar binding - concrete pouring, with reasonable structure, reasonable material distribution and high utilization efficiency; the structure has large rigidity, enhanced negative prestress, bracket pre-pressing, through foundation treatment and bracket erection: bowl-hook bracket, template design scheme, the cast-in-place box girder adopts the full-chamber bowl-hook bracket form, which ensures the force bearing area of ​​the pedestal, is easy to maintain and has good durability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to a field of building construction technology, and in particular to a full-section prestressed concrete composite box girder bridge structure and construction technology with two directional ramps, a right-turn ramp I connecting a main line viaduct and a C ramp connecting a ground auxiliary road and the main line viaduct. Background Art

[0002] At present, the existing box girder has a large basement area and requires a large amount of earth excavation. In addition, due to the complex terrain of the construction site, there are ponds or villages, and the traditional method will affect local facilities. In addition, it is difficult to apply prestressing on the top plate using the existing model and process, and the prestressing force is limited. The box girder construction of this project has a certain safety impact on the surrounding buildings (structures), and also affects the surrounding public facilities such as communications and roads. There are some safety hazards in the structure, and the enclosure and bridge body are not firm and reliable. Summary of the invention

[0003] The technical problem to be solved by the present invention is to provide a full-section prestressed concrete composite box girder bridge structure with reasonable structure, convenient and simple construction, easy maintenance, convenient traffic and good safety performance.

[0004] In order to solve the above technical problems, the present invention provides a construction process for a full-section prestressed concrete composite box girder bridge structure, wherein the full-section prestressed concrete composite box girder bridge structure includes a main bridge, a C ramp bridge and an I ramp bridge, wherein the main bridge is connected by the C ramp bridge and the I ramp bridge, and the whole adopts a bowl-hook type bracket erection system; the C ramp bridge is arranged on one side of the I ramp bridge, the C ramp bridge is arranged as at least four standard sections, the C ramp bridge is arranged in the median strip of the ground auxiliary road, and is connected to the pile group foundation of the pedestal below, the first standard section of the C ramp is arranged with a width of 7m-9m, and the box girder height is 1m-1.6m, the first standard section of the C ramp is composed of an upper cast-in-place box girder bridge deck, a lower abutment, a pier body and a support frame, the pier body adopts a "vase" shaped pier, the third standard section of the C ramp is arranged with a width of 7m-9m, and the box girder height is 1.9m-2.2m, and the fourth standard section of the C ramp is arranged with a width of 7m -9m, box beam height is 1.6m-1.8m;

[0005] The I ramp bridge is set to have at least 14 standard sections. The upper part of the I ramp bridge is a cast-in-place box girder. The main pier of the lower structure adopts a "vase" type pier, and the secondary pier adopts a pile-connected cap beam pier. The width of the first ramp bridge of I ramp is 7m-9m, and the box girder height is 1.2-1.6m. The width of the second ramp bridge of I ramp is 7m-9m, and the box girder height is 2.0m-2.2m. The width of the third ramp bridge of I ramp is 7m-9m, and the box girder height is 1.6m-1.8m. The width of the fourth ramp bridge of I ramp is 11.007m -4.75m, and the box girder height is 1.4m-1.6m.

[0006] Preferably, it also includes a double-sided widened small bridge, the upper part of the double-sided widened small bridge is prefabricated with a hollow slab beam, the lower part adopts a pile-connected cap beam type pier, and all pile foundations are bored cast-in-place piles.

[0007] Preferably, the main bridge uses C50 concrete, which is mixed centrally.

[0008] Preferably, the C ramp bridge and the I ramp bridge are made of a mixture of concrete, steel bars and steel strands.

[0009] The present invention also provides a construction process thereof, which comprises the following steps: 1) foundation treatment: determining the coordinates, elevations, and structural dimensions of the entire bridge for the construction of the cast-in-place box girder superstructure, as well as confirming the steel bar, concrete engineering quantity, and construction sequence of each component; treating the foundation with the support as a unit, with the width of the cross-bridge section extending 50 cm beyond the support, and the width of the cross-bridge section extending 100 cm beyond the support, and performing foundation treatment along the bridge; firstly, performing foundation treatment at the pedestal, filling in layers with plain soil, with each layer having a virtual thickness of 30-40 cm, and compacting each layer of plain soil with a compaction device after leveling, with a compaction degree of 70-90% until 20-30 cm below the original ground; after the plain soil is filled, filling in the plain soil with a thickness of 5% gray soil, using a roller for compaction, with a compaction degree of not less than 93%, and pouring 15 cm C20 on the 5% gray soil after compaction. Concrete foundation; secondly, mud pool treatment is carried out, the original mud is excavated to the original soil, and the plain soil is backfilled in layers. The thickness of each layer is 25-40cm. After each layer of plain soil is leveled, it is compacted with compaction equipment with a compaction degree of 80-90%, until 30cm below the original ground. After the plain soil is filled, 30cm thick 5% gray soil is filled on it, compacted by a roller, and the compaction degree is not less than 93%. After the 5% gray soil is compacted, a 15cmC20 concrete foundation is poured on it. The concrete foundation is set with a 0.5% transverse and longitudinal slope. In addition, the foundation treatment across the river and pond is carried out, and the silt in the river and pond is backfilled. The plain soil backfill needs to be rolled in layers, and a 20-ton roller is used for rolling. The compaction degree of each layer is 83-93%, the layer thickness is 30-40cm, and the backfill width exceeds the positive projection surface of the box beam support by 3m. The slope uses C20 concrete cover with a thickness of 5cm and backfills to 50cm above the water surface. Then, 30cm thick 5% lime soil is compacted and poured with 5-20cm C20 concrete. The concrete foundation is set with 0.5% transverse and longitudinal slopes. The third ramp of I is used to support the bracket part of the bridge deck of the flange plate. Finally, foundation drainage: a drainage ditch is excavated outside the bracket foundation.

[0010] 2) Scaffolding installation: Bowl-hook bracket and formwork design scheme. The cast-in-place box girder adopts a full-height bowl-hook bracket. The bracket width is the top width of the box girder plus the working width on both sides. The maximum height of the bridge bracket is 16.4m. The box girder structure has end beams, middle beams, bottom plates, webs, flange plates and top plates. The mid-span is a general section. The bottom plate, webs and top plates are gradually thickened near the beams. The base and top support are set on the top surface of the treated concrete foundation. The adjustable base is placed at longitudinal and transverse intervals. The steel plate thickness of the bottom plate is 6mm. The top of the bracket is set with an adjustable height U-shaped top support with a steel plate thickness of 5mm. The engagement length of the base and top support with the vertical pole adjustment nut is 6 buckles, and the length inserted into the vertical pole is 150mm;

[0011] Among them, the construction of the bowl-hook bracket: the bracket position is laid out, and the line is drawn according to the row spacing after the laying out. Then the sweeping rod is placed, and the vertical rods are fastened to the sweeping rods one by one. The first step crossbar is installed and fastened to each vertical rod. The second step crossbar is installed, and temporary diagonal braces are added to install the third and fourth step crossbars. In addition, scissor braces and reinforcement fasteners are added, and channel steel, wooden squares, and bottom molds are laid;

[0012] 3) Pre-stressing of the support: Pre-stress the support. When the support is fully stable and pre-stressed for 7 days, unload it symmetrically in stages, and then pour the box girder. In the order of pouring concrete, load it in stages according to 60%→80%→100%→120%, first the bottom plate, web plate, then the top plate and wing plate; load it to 20% of the deadweight of the box girder, and adjust the bottom formwork;

[0013] 4) Install the side formwork: The box beams are all made of bamboo plywood, and the bottom formwork is directly laid on the longitudinal wood. When laying the bottom formwork, the joints along the wood direction are spliced ​​on the wood, and the board seams are taped. The elevation of the template is measured with a level, and the adjustable screw rod on the top of the bracket is used for correction; a water outlet is set at the bottom formwork position at the lowest point of each span;

[0014] The side formwork of the box beam is supported on the bottom formwork, with small wooden beams and large vertical steel pipe beams as the backing. Each diagonal supporting steel pipe is connected to the support poles respectively. A counter-tension rod is set at the position where the diagonal support rod is connected on each row of poles. The length of the counter-tension rod is at least from the outermost pole to the second pole under the bottom plate. Each tension rod has no less than 3 fasteners. The bottom formwork is erected first, and then the side formwork. After the bottom plate reinforcement is tied, the inner formwork is installed;

[0015] 5) Tie up the steel bars, install and position the prestressed pipes: The order of steel bar installation is to install and tie up the steel bars of the bottom plate of the box beam, the steel bar skeleton and steel bars of the web plate; the steel bar skeleton and steel bars of the diaphragm plate, and install and tie up the upper steel bars and chamfered steel bars of the bottom plate of the box beam; after the second installation of the inner formwork of the box chamber, install and tie up the upper and lower steel bars of the top plate, chamfered steel bars, guardrails, expansion joints and other embedded parts; then install the inner formwork side plates;

[0016] 6) Concrete pouring: The box girder concrete is poured in two times, and the time interval between the two pourings shall not exceed 9 days; the bottom plate and web plate are poured in the first time, and the dividing point between the two pourings is set at the junction of the top plate and the web plate, and a 2cm thick wooden strip is set at the junction of the wing plate and the wing plate; after the secondary curing of the concrete, the inner formwork side plates are removed and the inner formwork top plate is installed; prestressing grouting is carried out, sealing and laying, and finally the bracket is removed.

[0017] The concrete pouring process is: pouring in layers from low to high and from one end to the other. A box girder is poured longitudinally at one time, and the vertical pouring is done in the order of bottom plate, web plate, and top plate.

[0018] The bending angle of the curved hook portion is 30-45 degrees.

[0019] Compared with the prior art, the present invention has the following advantages: This application involves ramps in two directions, east to north and south to east. A right-turn ramp (I ramp) connects the main line viaduct and Changjiang Avenue. An upper ramp (C ramp) is set to connect the ground auxiliary road and the main line viaduct. The upper construction power supply cable is attached to the outer bracket bridge through a PVC pipe and connected to each distribution box on the cast-in-place box girder. Clean river water is used for construction and maintenance. The box girder construction has no safety impact on surrounding buildings (structures) and does not affect surrounding public facilities such as communications and roads. The construction site is reasonably located, the structure is safe, the enclosure and enclosure are firm and reliable, and there are no safety hazards. The I ramp of this project crosses the rural cement road, strengthens the safety maintenance of the intersection, and makes good signs and signs and arranges personnel to direct and guide the construction vehicles in and out to prevent accidents. At present, the above-ground and underground pipelines are being relocated, and there are no above-ground and underground pipelines during the construction of the cast-in-place box girder. I The 11th to 14th ramps are connected to the avenue by widening. Before the construction of the bridge substructure, the elevation of the old bridge is re-measured to ensure smooth connection between the new and old ramps.

[0020] The structure has large rigidity, enhanced negative prestress, and prestressed brackets: prestress the brackets. When the brackets are fully stable and prestressed for 7 days, unload them symmetrically in stages, cast the box girder, tie the steel bars, install and position the prestressed pipes: the order of steel bar installation, install and tie the box girder bottom plate steel bars, web steel bar skeleton and steel bars; diaphragm steel bar skeleton and steel bars, install and tie the upper and lower steel bars and chamfered steel bars of the box girder bottom plate; after the second box room inner formwork is installed, install and tie the upper and lower steel bars, chamfered steel bars and guardrails, expansion joints and other embedded parts of the top plate; then install the inner formwork side plates to enhance the stability of the bridge body; the structure is reasonable, the material distribution is reasonable, and the utilization efficiency is high; through foundation treatment and bracket erection: bowl-hook bracket, formwork design scheme, the cast-in-place box girder adopts a full-height bowl-hook bracket form, which ensures the force-bearing area of ​​the pedestal, is easy to maintain, and has good durability. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1The present invention is a flow chart of the construction process of the full-section prestressed concrete composite box girder bridge structure.

[0022] Figure 2 It is a layout diagram of the full-section prestressed concrete composite box girder bridge structure of the present invention.

[0023] Figure 3 It is a schematic diagram of the C ramp bridge structure in the full-section prestressed concrete composite box girder bridge structure of the present invention.

[0024] Figure 4 It is a schematic diagram of the structure of ramp bridge I in the full-section prestressed concrete composite box girder bridge structure of the present invention. DETAILED DESCRIPTION

[0025] The present invention is further described below in conjunction with embodiments, but the protection scope of the present invention is not limited thereto: Figure 2-4 As shown, a full-section prestressed concrete composite box girder bridge structure includes a main bridge 1, a C ramp bridge 2 and an I ramp bridge 3. The main bridge 1 is connected by the C ramp bridge 2 and the I ramp bridge 3, and the whole adopts a bowl-hook type bracket structure;

[0026] The C ramp bridge 2 is arranged on one side of the I ramp bridge 3, and the C ramp bridge 2 is arranged to have at least four standard sections. The C ramp bridge 2C ramp bridge 2 is arranged in the middle strip of the ground auxiliary road, and is connected to the pile group foundation of the platform. The width of the first standard section 11 of the C ramp is set to

[0027] 7m-9m, the box beam height is 1m -1.6m, the first standard section of C ramp 11 consists of the upper cast-in-place box beam deck 112 and the lower abutment

[0028] 113, the pier body 114 and the support frame 115, the pier body 114 is a "vase" pier, the third standard section 12 of the C ramp is set to have a width of 7m-9m, the box beam height is 1.9m-2.2m, and the fourth standard section 13 of the C ramp is set to have a width of 7m-9m.

[0029] 9m, box girder height is 1.6m-1.8m;

[0030] The I ramp bridge 3 is set to be at least 14 standard sections, the upper part of the I ramp bridge 3 is a cast-in-place box girder, the main pier of the lower structure adopts a "vase" type pier, and the secondary pier adopts a pile-connected cap beam pier. The width of the I ramp first ramp bridge 31 is 7m-9m, and the box girder height is 1.2-1.6m, the width of the I ramp second ramp bridge 32 is 7m-9m, and the box girder height is 2.0m-2.2m, the width of the I ramp third ramp bridge 33 is 7m-9m, and the box girder height is 1.6m-1.8m, and the width of the I ramp fourth ramp bridge 34 is 11.007m-4.75m, and the box girder height is 1.4m-1.6m;

[0031] It also includes a double-sided widened small bridge 4, the upper part of the double-sided widened small bridge 4 is prefabricated with a hollow slab beam, the lower part adopts a pile-connected cap beam type pier, and all pile foundations are bored cast-in-place piles.

[0032] The main bridge 1 uses C50 concrete, which is mixed centrally.

[0033] C ramp bridge 2 and I ramp bridge 3 are made of a mixture of concrete, steel bars and steel strands.

[0034] like Figure 1 As shown in the figure, the construction process of the full-section prestressed concrete composite box girder bridge structure includes the following steps: 1) Foundation treatment: determine the coordinates, elevation, and structural dimensions of the entire bridge for the construction of the cast-in-place box girder superstructure, as well as the steel bar, concrete engineering quantity and construction sequence of each component. Through the support foundation treatment, take each unit as a unit, the cross-bridge width of the section is 50cm outside the support, and the cross-bridge width of the river crossing section is 100cm outside the support. The foundation treatment is carried out along the bridge; first, the foundation treatment is carried out at the pedestal, and the soil is filled in layers with plain soil. The thickness of each layer is 30-40cm. After each layer of plain soil is leveled, it is compacted with a compaction equipment with a compaction degree of 70-90% until 20-30cm below the original ground. After the plain soil is filled, it is filled with plain soil with a thickness of 5% gray soil, which is compacted by a roller with a compaction degree of not less than 93%. After the 5% gray soil is compacted, 15cmC20 Concrete foundation; secondly, mud pool treatment, excavation of the original mud to the original soil, backfilling with plain soil in layers, each layer of virtual paving thickness 25-

[0035] 40cm, each layer of plain soil is compacted with compaction equipment after leveling, with a compaction degree of 80-90%, until 30cm below the original ground. After the plain soil is filled, 30cm thick 5% gray soil is filled on it, and compacted by roller, with a compaction degree of not less than 93%. After the 5% gray soil is compacted, 15cm C20 concrete foundation is poured on it. The concrete foundation is set with 0.5% transverse and longitudinal slopes. In addition, the foundation treatment across the river and pond is carried out, and the silt in the river and pond is backfilled. The plain soil backfill needs to be rolled in layers, and a 20-ton roller is used for rolling. The compaction degree of each layer is 83-93%, the layer thickness is 30-40cm, and the backfill width exceeds the positive projection surface of the box beam support by 3m. The slope uses C20 concrete cover with a concrete cover thickness of 5cm. After backfilling to 50cm above the water surface, 30cm thick 5% gray soil is compacted and then poured with 5-20cm C20 Concrete, concrete foundation is set with 0.5% transverse and longitudinal slope; the third ramp of I is used to support the bracket part of the bridge deck of the flange plate. Finally, foundation drainage: drainage ditches are excavated outside the bracket foundation;

[0036] 2) Scaffolding installation: Bowl-hook bracket and formwork design scheme. The cast-in-place box girder adopts a full-height bowl-hook bracket. The bracket width is the top width of the box girder plus the working width on both sides. The maximum height of the bridge bracket is 16.4m. The box girder structure has end beams, middle beams, bottom plates, webs, flange plates and top plates. The mid-span is a general section. The bottom plate, webs and top plates are gradually thickened near the beams. The base and top support are set on the top surface of the treated concrete foundation. The adjustable base is placed at longitudinal and transverse intervals. The steel plate thickness of the bottom plate is 6mm. The top of the bracket is set with an adjustable height U-shaped top support with a steel plate thickness of 5mm. The engagement length of the base and top support with the vertical pole adjustment nut is 6 buckles, and the length inserted into the vertical pole is 150mm;

[0037] Among them, the construction of the bowl-hook bracket: the bracket position is laid out, and the line is drawn according to the row spacing after the laying out. Then the sweeping rod is placed, and the vertical rods are fastened to the sweeping rods one by one. The first step crossbar is installed and fastened to each vertical rod. The second step crossbar is installed, and temporary diagonal braces are added to install the third and fourth step crossbars. In addition, scissor braces and reinforcement fasteners are added, and channel steel, wooden squares, and bottom molds are laid;

[0038] 3) Pre-stressing of the support: Pre-stress the support. When the support is fully stable and pre-stressed for 7 days, unload it symmetrically in stages, and then pour the box girder. In the order of pouring concrete, load it in stages according to 60%→80%→100%→120%, first the bottom plate, web plate, then the top plate and wing plate; load it to 20% of the deadweight of the box girder, and adjust the bottom formwork;

[0039] 4) Install the side formwork: The box beams are all made of bamboo plywood, and the bottom formwork is directly laid on the longitudinal wood. When laying the bottom formwork, the joints along the wood direction are spliced ​​on the wood, and the board seams are taped. The elevation of the template is measured with a level, and the adjustable screw rod on the top of the bracket is used for correction; a water outlet is set at the bottom formwork position at the lowest point of each span;

[0040] The side formwork of the box beam is supported on the bottom formwork, with small wooden beams and large vertical steel pipe beams as the backing. Each diagonal supporting steel pipe is connected to the support poles respectively. A counter-tension rod is set at the position where the diagonal support rod is connected on each row of poles. The length of the counter-tension rod is at least from the outermost pole to the second pole under the bottom plate. Each tension rod has no less than 3 fasteners. The bottom formwork is erected first, and then the side formwork. After the bottom plate reinforcement is tied, the inner formwork is installed;

[0041] 5) Tie up the steel bars, install and position the prestressed pipes: The order of steel bar installation is to install and tie up the steel bars of the bottom plate of the box beam, the steel bar skeleton and steel bars of the web plate; the steel bar skeleton and steel bars of the diaphragm plate, and install and tie up the upper steel bars and chamfered steel bars of the bottom plate of the box beam; after the second installation of the inner formwork of the box chamber, install and tie up the upper and lower steel bars of the top plate, chamfered steel bars, guardrails, expansion joints and other embedded parts; then install the inner formwork side plates;

[0042] 6) Concrete pouring: The box girder concrete is poured in two times, and the time interval between the two pourings shall not exceed 9 days; the bottom plate and web plate are poured in the first time, and the dividing point between the two pourings is set at the junction of the top plate and the web plate, and 2cm thick wooden strips are set at the junction of the wing plate and the wing plate; after the secondary curing of the concrete, the inner formwork side plates are removed and the inner formwork top plate is installed; prestressing grouting is carried out, sealing and laying, and finally the bracket is removed.

[0043] The concrete pouring process is: pouring in layers from low to high and from one end to the other. A box girder is poured longitudinally at one time, and the vertical pouring is done in the order of bottom plate, web plate, and top plate.

[0044] The specific embodiments described herein are merely examples of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in similar ways, but they will not deviate from the spirit of the present invention or exceed the scope defined by the appended claims.

Claims

1. A construction process for a full-section prestressed concrete composite box girder bridge structure, characterized in that: A full-section prestressed concrete composite box girder bridge structure comprises a main bridge (1), a C ramp bridge (2) and an I ramp bridge (3), wherein the main bridge (1) is connected via the C ramp bridge (2) and the I ramp bridge (3), and the whole structure adopts a cup-hook type bracket structure; The C ramp bridge (2) is arranged on one side of the I ramp bridge (3), and the C ramp bridge (2) is arranged to have at least four standard sections. The C ramp bridge (2) is arranged in the median strip of the ground auxiliary road and is connected to the pile group foundation of the pedestal below. The first standard section (11) of the C ramp is arranged to have a width of 7m-9m and a box beam height of 1m-1.6m. The first standard section (11) of the C ramp is composed of an upper cast-in-place box beam bridge deck (112), a lower abutment (113), a pier body (114) and a support frame (115). The pier body (114) is a "vase" shaped pier. The third standard section (12) of the C ramp is arranged to have a width of 7m-9m and a box beam height of 1.9m-2.2m. The fourth standard section (13) of the C ramp is arranged to have a width of 7m-9m and a box beam height of 1.6m-1.8m. The ramp bridge (3) is set to have at least 14 standard sections. The upper part of the ramp bridge (3) is a cast-in-place box girder. The main pier of the lower structure adopts a "vase" type pier, and the secondary pier adopts a pile-connected cap beam pier. The width of the first ramp bridge (31) is 7m-9m, and the box girder height is 1.2-1.6m. The width of the second ramp bridge (32) is 7m-9m, and the box girder height is 2.0m-2.2m. The width of the third ramp bridge (33) is 7m-9m, and the box girder height is 1.6m-1.8m. The width of the fourth ramp bridge (34) is 11.007m-4.75m, and the box girder height is 1.4m-1.6m. The construction process of the full-section prestressed concrete composite box girder bridge structure includes the following steps: 1) Foundation treatment: Determine the coordinates, elevation, and structural dimensions of the entire bridge for the construction of the cast-in-place box girder superstructure, as well as the steel bar, concrete engineering quantity, and construction sequence of each component. Through the support foundation treatment, take each unit as a unit, and the width of the cross-bridge section is 50cm outside the support, and the width of the cross-bridge section across the river is 100cm outside the support. The foundation treatment is carried out along the bridge; first, the foundation treatment is carried out at the pedestal, and the soil is filled in layers. The thickness of each layer is 30-40cm. After each layer of soil is leveled, it is compacted with a compaction equipment, and the compaction degree is 70-90% until 20-30cm below the original ground. After the soil is filled, fill it with 5% gray soil, compact it with a roller, and the compaction degree is not less than 93%. After the 5% gray soil is compacted, a 15cmC20 concrete foundation is poured on it; Secondly, the mud pool is treated, the original mud is excavated to the original soil, and the plain soil is backfilled in layers. The thickness of each layer is 25-40cm. After each layer of plain soil is leveled, it is compacted with a compaction equipment with a compaction degree of 80-90%, until 30cm below the original ground. After the plain soil is filled, 30cm thick 5% gray soil is filled on it, and compacted with a roller with a compaction degree of not less than 93%. After the 5% gray soil is compacted, a 15cmC20 concrete foundation is poured on it. The concrete foundation is set with a 0.5% transverse and longitudinal slope. In addition, the foundation treatment across the river and pond is carried out, and the silt in the river and pond is backfilled. The plain soil backfill needs to be rolled in layers, and a 20-ton roller is used for rolling. The compaction degree of each layer is 83-93%, the layer thickness is 30-40cm, and the backfill width exceeds the positive projection surface of the box beam support by 3m. The slope uses C20 concrete cover with a thickness of 5cm and backfills to 50cm above the water surface. Then, 30cm thick 5% lime soil is compacted and poured with 5-20cm C20 concrete. The concrete foundation is set with 0.5% transverse and longitudinal slopes. The third ramp of I is used to support the bracket part of the flange plate on the bridge deck. Finally, foundation drainage: a drainage ditch is excavated outside the bracket foundation. 2) Bracket erection: Bowl-hook bracket and formwork design scheme. The cast-in-place box girder adopts a full-height bowl-hook bracket. The bracket width is the top width of the box girder plus the working width on both sides. The maximum height of the bridge bracket is 16.4m. The box girder structure has end beams, middle beams, bottom plates, webs, flange plates and top plates. The mid-span is a general section. The bottom plate, webs and top plates are gradually thickened near the beams. The base and top support are set on the top surface of the treated concrete foundation. The adjustable base is placed at longitudinal and transverse intervals. The steel plate thickness of the bottom plate is 6mm. The top of the bracket is set with an adjustable height U-shaped top support with a steel plate thickness of 5mm. The engagement length of the base and top support with the vertical pole adjustment nut is 6 buckles, and the length inserted into the vertical pole is 150mm. Among them, the construction of the bowl-hook bracket: the bracket position is laid out, and the line is drawn according to the row spacing after the laying out. Then the sweeping rod is placed, and the vertical rods are fastened to the sweeping rods one by one. The first step crossbar is installed and fastened to each vertical rod. The second step crossbar is installed, and temporary diagonal braces are added to install the third and fourth step crossbars. In addition, scissor braces and reinforcement fasteners are added, and then channel steel, wooden squares, and bottom molds are laid; 3) Pre-stressing of the support: Pre-stress the support. When the support is fully stable and pre-stressed for 7 days, unload it symmetrically in stages, and then pour the box girder. In the order of pouring concrete, load it in stages according to 60%→80%→100%→120%, first the bottom plate, web plate, then the top plate and wing plate; load it to 20% of the deadweight of the box girder, and adjust the bottom formwork; 4) Install the side formwork: The box beams are all made of bamboo plywood, and the bottom formwork is directly laid on the longitudinal wood. When laying the bottom formwork, the joints along the wood direction are spliced ​​on the wood, and the board seams are taped. The elevation of the template is measured with a level, and the adjustable screw rod on the top of the bracket is used for correction; a water outlet is set at the bottom formwork position at the lowest point of each span; The side formwork of the box beam is supported on the bottom formwork, with small wooden beams and large vertical steel pipe beams as the backing. Each diagonal supporting steel pipe is connected to the support poles respectively. A counter-tension rod is set at the position where the diagonal support rod is connected on each row of poles. The length of the counter-tension rod is at least from the outermost pole to the second pole under the bottom plate. Each tension rod has no less than 3 fasteners. The bottom formwork is erected first, and then the side formwork. After the bottom plate reinforcement is tied, the inner formwork is installed; 5) Tie up the steel bars, install and position the prestressed pipes: The order of steel bar installation is to install and tie up the steel bars of the bottom plate of the box beam, the steel bar skeleton and steel bars of the web plate; the steel bar skeleton and steel bars of the diaphragm plate, and install and tie up the upper steel bars and chamfered steel bars of the bottom plate of the box beam; after the second installation of the inner formwork of the box chamber, install and tie up the upper and lower steel bars of the top plate, chamfered steel bars, guardrails, expansion joints and other embedded parts; then install the inner formwork side plates; 6) Concrete pouring: The box girder concrete is poured in two times, and the time interval between the two pourings shall not exceed 9 days; the bottom plate and web plate are poured in the first time, and the dividing point between the two pourings is set at the junction of the top plate and the web plate, and 2cm thick wooden strips are set at the junction of the wing plate and the wing plate; after the secondary curing of the concrete, the inner formwork side plates are removed and the inner formwork top plate is installed; prestressing grouting is carried out, sealing and laying, and finally the bracket is removed.

2. The construction process of the full-segment prestressed concrete composite box girder bridge structure according to claim 1 is characterized by: The full-section prestressed concrete composite box girder bridge structure also includes a double-sided widened small bridge (4), wherein the double-sided widened small bridge (4) has a prefabricated hollow slab beam at the upper portion and a pile-connected cap beam pier at the lower portion, and all pile foundations are bored cast-in-place piles.

3. The construction process of the full-segment prestressed concrete composite box girder bridge structure according to claim 1 is characterized in that: The main bridge (1) uses C50 concrete, which is mixed centrally.

4. The construction process of the full-segment prestressed concrete composite box girder bridge structure according to claim 1 is characterized in that: The C ramp bridge (2) and the I ramp bridge (3) are made of a mixture of concrete, steel bars and steel strands.

5. The construction process of the full-segment prestressed concrete composite box girder bridge structure according to claim 1 is characterized by: The concrete pouring process is: pouring in layers from low to high and from one end to the other. A box girder is poured longitudinally at one time, and the vertical pouring is in the order of bottom plate, web plate, and top plate.

Citation Information

Patent Citations

  • Arch-pylon involute curved surface stay cable main-ramp overpass

    CN105755946A

  • Cast-in-place prestressed concrete continuous box girder one-time pouring and forming construction method

    CN108951425A

  • Single-level versatile overpass

    WO2015055152A1

  • Double-track beam for magnetic-levitation rail-wrap-type rail transit

    WO2017101767A1