A kind of assembled foundation of container module building and installation method thereof
By using steel structure foundation connecting beams to bolt nodes in container module buildings, combined with the cross structure of standard short columns and flexible tie rods, the problem of poor stress performance of existing foundations is solved, and the resistance to horizontal bearing capacity and assembly efficiency are improved. Suitable for areas with frequent earthquakes.
Patent Information
- Application Number
- CN202010451698.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-25
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2040-05-25
AI Technical Summary
The foundation stress performance of existing container module buildings is poor, especially the horizontal bearing capacity is insufficient, and it is not suitable for areas with frequent earthquakes. The traditional welding connection method leads to low assembly efficiency.
The steel structure foundation connecting beam is connected to the bolt nodes, and an intersection structure is formed through standard short columns, short beams and flexible pull rods to improve the horizontal bearing capacity, and adjustable node plates and short beams are used to adapt to spiral piles of different spacings.
It improves the standardization degree and horizontal bearing capacity of the prefabricated foundation, is suitable for areas with frequent earthquakes, and simplifies the installation and disassembly process, reducing on-site workload.
Smart Images

Figure CN111519756B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of container module buildings, and in particular to an assembled foundation of a container module building and an installation method thereof. Background Art
[0002] Modular steel structure buildings are an advanced stage of the development of building industrialization. They are highly integrated prefabricated buildings. The construction speed of modular buildings has unparalleled advantages over traditional buildings. Modular buildings usually use factory-prefabricated containers to achieve mass production. However, the foundation of existing container modular buildings often uses traditional cast-in-place foundations, which have a long maintenance period.
[0003] In order to speed up the foundation construction, steel structure spiral pile foundation has gradually been adopted in recent years. However, in the application process, due to the non-standard structural system adopted by the steel structure spiral pile foundation, the degree of standardization is low, and the connection nodes are mostly fixed and welded, resulting in poor stress performance of the entire container module prefabricated foundation, especially weak horizontal bearing capacity, which is not suitable for areas prone to earthquakes. Summary of the invention
[0004] The purpose of the present invention is to overcome the defects of the above-mentioned prior art and to provide a prefabricated foundation of a container modular building and an installation method thereof, so as to improve the structural force transmission system of the prefabricated foundation and enhance its horizontal bearing capacity.
[0005] The objective of the present invention can be achieved through the following technical scheme: an assembled foundation of a container module building, comprising a steel structure foundation connecting beam, the top of the steel structure foundation connecting beam is connected to the bottom beam of the container module through a bolt node, the bottom of the steel structure foundation connecting beam is connected to a plurality of vertical steel structure spiral piles through standard short columns, the standard short columns are connected by short beams, and two cross-shaped tie rods are installed between the standard short columns.
[0006] Furthermore, one end of the standard short column is connected to the bottom of the steel structure foundation connecting beam through a first node plate, and the other end of the standard short column is connected to the steel structure spiral pile through a second node plate and a third node plate in sequence.
[0007] Furthermore, a fourth node plate is provided at the position where the standard short column is connected to the short beam, and fifth node plates are provided at both ends of the short beam respectively, and the fourth node plate and the fifth node plate are connected to each other.
[0008] Furthermore, a sixth node plate is provided between the standard short column and the first node plate, a seventh node plate is provided between the standard short column and the fourth node plate, and a tie rod is connected between the sixth node plate of the standard short column and the seventh node plate of the adjacent standard short column.
[0009] Furthermore, the sixth node plate and the seventh node plate are arranged symmetrically to each other.
[0010] Further, the span distance between the sixth node plate and the seventh node plate is adjustable.
[0011] Furthermore, the sixth node plate and the seventh node plate are both provided with mounting holes for connecting the pull rods.
[0012] Furthermore, both ends of the sixth node plate and both ends of the seventh node plate are provided with mounting holes.
[0013] Furthermore, the short beam is a short beam with adjustable length so as to be suitable for steel structure screw piles with different spacings.
[0014] Furthermore, the pull rod is a flexible pull rod.
[0015] A method for installing an assembled foundation of a container modular building comprises the following steps:
[0016] S1. Drive the steel structure screw piles into the site;
[0017] S2. Connect the top of the steel structure screw pile to the bottom of the standard short column with bolts through the second node plate and the third node plate;
[0018] S3, bolting the fourth node plate and the fifth node plate to each other to install the short beam between the standard short columns;
[0019] S5. Install a tie rod between the sixth node plate and the seventh node plate of two adjacent standard short columns by bolt connection, so that two tie rods in a cross shape are connected between the two adjacent standard short columns;
[0020] S6. Connect the top of the standard short column to the bottom of the steel structure foundation connecting beam through the first node plate bolts;
[0021] S7. Connect the top of the steel structure foundation connecting beam to the bottom beam of the container module through a bolt node to complete the installation of the assembled foundation of the container module building.
[0022] Compared with the prior art, the present invention has the following advantages:
[0023] 1. The present invention adopts a steel structure foundation connecting beam to replace the traditional concrete foundation, which is beneficial to environmental protection. The present invention adopts a bolt node and a plurality of node plates to form a full bolt connection for the entire assembled foundation. Compared with the fixed welding method, the assembly rate of the foundation is greatly improved, which is beneficial to installation and disassembly and reduces on-site workload.
[0024] 2. The present invention forms a standard component by setting a standard short column and installing a plurality of node plates for connection on the standard short column; and forms another standard component by setting a short beam and installing node plates at both ends of the short beam, thereby improving the standardization degree of the prefabricated foundation of the present invention.
[0025] 3. The present invention can effectively improve the horizontal bearing capacity of the assembled foundation by installing cross-type flexible tie rods between standard short columns, so that the present invention can be applied to areas prone to earthquakes.
[0026] Fourth, the present invention utilizes short beams with adjustable lengths to accommodate steel structure spiral piles of different spacings; utilizing the sixth node plate and the seventh node plate with adjustable span distances on the standard short columns, the crossing angle of the flexible tie rods can be flexibly changed, thereby enhancing the structural flexibility of the present invention and being beneficial to practical applications. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the installation effect of the embodiment;
[0028] Figure 2 It is a schematic diagram of a standard short column member;
[0029] Figure 3 is a schematic diagram of a short beam member;
[0030] Explanation of markings in the figure: 1. Container module, 2. Steel structure screw pile, 3. Container module bottom beam, 4. Steel structure foundation connecting beam, 5. Bolt node, 6. Standard short column, 7. Second node plate, 8. Tie rod, 9. Third node plate, 10. Short beam, 11. Sixth node plate, 12. Seventh node plate, 13. Fourth node plate, 14. First node plate, 15. Fifth node plate. DETAILED DESCRIPTION
[0031] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0032] Example
[0033] Figure 1 The figure shows a schematic diagram of the installation effect of the prefabricated foundation in the embodiment, wherein the bottom of the container module 1 is the container module bottom beam 3, the bottom of the container module bottom beam 3 is connected to the top of the steel structure foundation connecting beam 4 through a bolt node 5, and the bottom of the steel structure foundation connecting beam 4 is connected to a plurality of vertical steel structure spiral piles 2 through standard short columns 6, the standard short columns 6 are connected to each other through short beams 10, and two cross-shaped tie rods 8 are installed between the standard short columns 6.
[0034] like Figure 2 and Figure 3As shown, one end of the standard short column 6 is connected to the bottom of the steel structure foundation connecting beam 4 through the first node plate 14, and the other end of the standard short column 6 is connected to the steel structure spiral pile 2 through the second node plate 7 and the third node plate 9 in sequence. A fourth node plate 13 is provided at the position where the standard short column 6 is connected to the short beam 10, and fifth node plates 15 are provided at both ends of the short beam 10 respectively. The fourth node plate 13 and the fifth node plate 15 are connected to each other, so that the short beam 10 connects two standard short columns 6.
[0035] In addition, a sixth node plate 11 is provided between the standard short column 6 and the first node plate 14, and a seventh node plate 12 is provided between the standard short column 6 and the fourth node plate 13. Both the sixth node plate 11 and the seventh node plate 12 are provided with mounting holes for connecting the tie rods. One end of the tie rod 8 is connected to the sixth node plate 11, and the other end of the tie rod 8 is connected to the seventh node plate 12 of the adjacent standard short column 6.
[0036] In this embodiment, in order to improve the structural flexibility, the tie rod 8 is a flexible tie rod, the span distance between the sixth node plate 11 and the seventh node plate 12 is adjustable, and the short beam 10 is a short beam with adjustable length to adapt to steel structure screw piles 2 with different spacings.
[0037] The above-mentioned prefabricated foundation is applied in practice. The specific installation process includes:
[0038] S1, driving the steel structure screw pile 2 into the site;
[0039] S2, connecting the top of the steel structure screw pile 2 to the bottom of the standard short column 6 by bolts through the second node plate 7 and the third node plate 9;
[0040] S3, bolting the fourth node plate 13 and the fifth node plate 15 to each other, so as to install the short beam 10 between the standard short columns 6;
[0041] S5, installing the tie rod 8 between the sixth node plate 11 and the seventh node plate 12 of two adjacent standard short columns 6 by bolt connection, so that two tie rods 8 in a cross shape are connected between the two adjacent standard short columns 6;
[0042] S6, connecting the top of the standard short column 6 to the bottom of the steel structure foundation connecting beam 4 through the first node plate 14 bolts;
[0043] S7. Connect the top of the steel structure foundation connecting beam 4 to the bottom beam 3 of the container module through the bolt node 5 to complete the installation of the assembled foundation of the container module building.
Claims
1. A method for installing an assembled foundation of a container modular building, It is characterized in that The assembled foundation of the container module building comprises a steel structure foundation connecting beam (4), the top of the steel structure foundation connecting beam (4) is connected to the bottom beam (3) of the container module via a bolt node (5), the bottom of the steel structure foundation connecting beam (4) is connected to a plurality of vertical steel structure spiral piles (2) via standard short columns (6), the standard short columns (6) are connected via short beams (10), and two cross-shaped tie rods (8) are installed between the standard short columns (6); One end of the standard short column (6) is connected to the bottom of the steel structure foundation connecting beam (4) through a first node plate (14), and the other end of the standard short column (6) is connected to the steel structure screw pile (2) through a second node plate (7) and a third node plate (9) in sequence; A fourth node plate (13) is provided at a position where the standard short column (6) is connected to the short beam (10), and fifth node plates (15) are provided at both ends of the short beam (10), and the fourth node plate (13) and the fifth node plate (15) are connected to each other; A sixth node plate (11) is provided between the standard short column (6) and the first node plate (14), a seventh node plate (12) is provided between the standard short column (6) and the fourth node plate (13), and a tie rod (8) is connected between the sixth node plate (11) of the standard short column (6) and the seventh node plate (12) of the adjacent standard short column (6); The installation method comprises the following steps: S1, driving the steel structure screw pile (2) into the site; S2, connecting the top of the steel structure screw pile (2) to the bottom of the standard short column (6) by bolts through the second node plate (7) and the third node plate (9); S3, bolting the fourth node plate (13) and the fifth node plate (15) to each other, so as to install the short beam (10) between the standard short columns (6); S5. Installing a tie rod (8) between the sixth node plate (11) and the seventh node plate (12) of two adjacent standard short columns (6) by bolt connection, so that two tie rods (8) in a cross shape are connected between the two adjacent standard short columns (6); S6. Connecting the top of the standard short column (6) to the bottom of the steel structure foundation connecting beam (4) through the first node plate (14) bolts; S7. Connect the top of the steel structure foundation connecting beam (4) to the bottom beam (3) of the container module via a bolt node (5) to complete the installation of the assembled foundation of the container module building.
2. The method for installing the assembled foundation of a container modular building according to claim 1, It is characterized in that The sixth node plate (11) and the seventh node plate (12) are arranged symmetrically to each other.
3. The method for installing the assembled foundation of a container modular building according to claim 2, It is characterized in that The span distance between the sixth node plate (11) and the seventh node plate (12) is adjustable.
4. The method for installing the assembled foundation of a container modular building according to claim 2, It is characterized in that Both ends of the sixth node plate (11) and both ends of the seventh node plate (12) are provided with mounting holes for connecting the pull rods (8).
5. The method for installing the assembled foundation of a container modular building according to claim 1, It is characterized in that The short beam (10) is a short beam with adjustable length, so as to be suitable for steel structure screw piles (2) with different spacings.
6. The method for installing the assembled foundation of a container modular building according to claim 1, It is characterized in that The pull rod (8) is a flexible pull rod.
Citation Information
Patent Citations
Modular building
CN104755678A
Special-shaped column hinged steel frame door-shaped support structure of assembled low-rise building
CN106245768A
Quakeproof stabilizing device applied to container building foundation
CN109629897A
Fabricated foundation of container module building
CN212427499U