Automatic AC Feed Control (AFC) with zero voltage / current switching
Through automatic AC feed control technology, the relay switch is switched at a precise time at the zero-voltage crossover point of the second input power supply, which solves the problem of sparks and stress during power switching and improves the stability and reliability of the equipment.
Patent Information
- Application Number
- CN202010090181.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2019-03-01
- Filing Date
- 2020-02-13
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2040-02-13
AI Technical Summary
Relay switches can experience sparks and component stress when switching from a first power source to a second power source, causing undesirable mechanical switching problems.
Using automatic AC feed control (AFC) technology, through relay switching circuits and control circuit systems, the amplitude and phase values of the input power are used for precise timing switching to ensure switching at the zero-voltage crossover point of the second input power supply, thereby minimizing to reduce sparks and stress on relay switches.
It achieves zero-voltage switching during power switching, reduces sparks and stress on relay switches, and improves the stability and reliability of the equipment.
Smart Images

Figure CN111641256B_ABST
Abstract
Description
[0001] CROSS-REFERENCE TO RELATED APPLICATIONS
[0002] This patent application claims priority under 35 U.S.C. 119(e) to co-pending U.S. provisional patent application serial number 62 / 812,564, filed on March 1, 2019, and entitled “Automatic AC Feed Control (AFC) with Zero Voltage / Current Switching,” which is incorporated herein by reference in its entirety. Technical Field
[0003] The present invention generally relates to power converters with relay switches. More particularly, the present invention relates to automatic AC feed control (AFC) with zero voltage / current switching in power converters with relay switches. Background Art
[0004] Multiple power supplies are used in many power-demanding applications such as data centers with multiple servers. For example, a first power supply is actively connected to a load while a second power supply used as a backup is disconnected from the load. Both power supplies are powered whether connected or disconnected. In the event that the first power supply is interrupted, the first power supply is disconnected from the load and the second power supply is actively connected to the load. Typically, a relay switch is used to physically switch the load from the first power supply to the second power supply.
[0005] Problems arise when switching from a first power source to a second power source. A relay switch used to switch from a first power source to a second power source is a mechanical switch using a switch arm that moves from a first terminal to a second terminal. If current provided by the second power source is present at the relay switch when switching, sparks may occur. This can also cause component stress, both of which are undesirable. Summary of the invention
[0006] Embodiments relate to a power converter with AFC (Automatic AC Feed Control) for implementing zero voltage switching when switching from a first input power source to a second input power source. The power converter with AFC includes a relay switching circuit and a control circuit system for selectively providing power to a connected power converter. The control circuit system uses sensed amplitude values and phase values of the two input power sources to determine when the first input power source is lost, and selectively connects the second input power source according to precise timing control to minimize component stress.
[0007] In one aspect, a power supply and power converter system is disclosed. The system includes a first input AC power supply, a second input AC power supply, a relay switching circuit, a power conversion circuit, a voltage sensing circuit, and a control circuit. The relay switching circuit is coupled to the first input AC power supply and the second input AC power supply. Under normal operating conditions, the relay switching circuit is configured to enable connection with the first input AC power supply and disable connection with the second input AC power supply. The power conversion circuit is coupled to the relay switching circuit. The voltage sensing circuit is coupled to the first input AC power supply and the second input AC power supply. The control circuit is coupled to the voltage sensing circuit, the relay switching circuit, and the power conversion circuit. The control circuit is configured to: receive the sensed voltage levels of the first input AC power supply and the second input AC power supply to determine whether the first input AC power supply is interrupted and whether it is necessary to switch to the second input AC power supply; and control the switching of the relay switching circuit to disable the connection with the first input AC power supply and enable the connection with the second input AC power supply at the zero voltage crossing point of the sensed voltage level of the second input AC power supply. In some embodiments, the power conversion circuit includes a main switch, and the control circuit is configured to transmit a control signal to the main switch so that the main switch is disconnected at the zero voltage crossing point. In some embodiments, the power conversion circuit includes a power factor correction (PFC) power converter. In some embodiments, the power conversion circuit further includes a DC to DC converter coupled to the output of the PFC power converter. In some embodiments, the PFC power converter is a boost converter. In some embodiments, the control circuit includes a first control circuit for providing a control signal to the relay switching circuit, and a second control circuit for providing a control signal to the PFC power converter, wherein the system further includes an isolation barrier between the first control circuit and the second control circuit. In some embodiments, the first control circuit is configured to provide a control signal to the second control circuit through the isolation barrier. In some embodiments, the control circuit is configured to determine whether it is necessary to switch to the second input AC power source by determining whether the sensed voltage value of the first input AC power source is zero within a predetermined waiting period of time. In some embodiments, the control circuit is configured to control the switching of the relay switching circuit by calculating the next zero voltage crossing point time of the second input AC power source immediately after the predetermined waiting period, and then transmitting a control signal to the relay switching circuit at a time equal to the calculated next zero voltage crossing point time minus the predetermined switching delay period.In some embodiments, the control circuit is further configured to transmit a second control signal to the main switch of the power conversion circuit before the next zero voltage crossing point time, wherein the second control signal causes the main switch to be disconnected so that the main switch is disconnected when the relay switching circuit switches.
[0008] On the other hand, a method for switching power of a power converter is disclosed. The method includes coupling a first input AC power source and a second input AC power source to a relay switching circuit, wherein, under normal operating conditions, the relay switching circuit is configured to enable the connection of the first input AC power source to the power conversion circuit and disable the connection of the second input AC power source to the power conversion circuit. The method further includes sensing the voltage levels of the first input AC power source and the second input AC power source. The method further includes determining whether the first input AC power source is interrupted and whether it is necessary to switch to the second input AC power source. The method further includes controlling the switching of the relay switching circuit to disable the connection with the first input AC power source and enable the connection with the second input AC power source at the zero voltage crossing point of the sensed voltage level of the second input AC power source. In some embodiments, the power conversion circuit includes a main switch, and the method further includes transmitting a control signal to the main switch so that the main switch is disconnected at the zero voltage crossing point. In some embodiments, determining whether it is necessary to switch to the second input AC power source includes determining whether the sensed voltage value of the first input AC power source is zero within a predetermined waiting period of time. In some embodiments, controlling the switching of the relay switching circuit includes: calculating the next zero voltage crossing point time of the second input AC power source immediately after the predetermined waiting period, and then transmitting a control signal to the relay switching circuit at a time equal to the calculated next zero voltage crossing point time minus the predetermined switching delay period. In some embodiments, the method further includes transmitting a second control signal to the main switch of the power conversion circuit before the next zero voltage crossing point time, wherein the second control signal causes the main switch to be turned off so that the main switch is turned off when the relay switching circuit switches. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] Several example embodiments are described with reference to the accompanying drawings, wherein the same reference numerals are used to provide the same components. The example embodiments are intended to illustrate rather than limit the present invention. These drawings include the following figures:
[0010] Figure 1 A functional block diagram of a power converter with AFC according to some embodiments is shown.
[0011] Figure 2 A schematic block diagram of a power converter with AFC according to some embodiments is shown.
[0012] Figure 3 An exemplary control timing diagram for implementing switching according to some embodiments is shown.
[0013] Figure 4 An exemplary calibration circuit for determining a relay switching delay period is presented in accordance with some embodiments.
[0014] Figure 5 An exemplary relationship between the inductor coil voltage and the relay switching time T4 is shown. DETAILED DESCRIPTION
[0015] Embodiments of the present application relate to relay switching control. Those of ordinary skill in the art will recognize that the following detailed description of relay switching control is illustrative only and is not intended to be limiting in any way. For those skilled in the art who benefit from this disclosure, they will easily think of other embodiments of relay switching control.
[0016] Reference will now be made in detail to the embodiments of the relay switching control as shown in the accompanying drawings. The same reference numeral designators will be used throughout the drawings and the following detailed description to refer to the same or similar parts. For the sake of clarity, all conventional features of the embodiments described herein are not shown and described. Of course, it should be appreciated that when developing any such actual embodiments, in order to achieve the specific goals of the developer, many implementation-specific decisions must be made, such as, following application- and business-related constraints, and these specific goals will vary with the implementation and the developer. In addition, it will be appreciated that such development efforts may be complex and time-consuming, but for those of ordinary skill in the art who benefit from this disclosure this will be no more than a routine work of engineering.
[0017] Figure 1A functional block diagram of a power converter with AFC according to some embodiments is shown. The power converter 2 with AFC includes a first input power 4 and a second input power 6. The first input power 4 and the second input power 6 can be any conventional power sources, such as a main power grid and a backup generator, respectively. Each of the first input power 4 and the second input power 6 is coupled to a relay switching circuit 12. The relay switching circuit 12 is configured to selectively connect the first input power 4 or the second input power 6 to the rest of the power converter. In normal operation, the first input power 4 is connected to the rest of the power converter. A line filter 14 is coupled to the relay switching circuit 12. The line filter 14 can be any conventional filtering circuit, such as a circuit for filtering EMI (electromagnetic interference). The line filter 14 is coupled to a PFC (power factor correction) power converter 18, which is coupled to a DC to DC converter 22. The output of the DC to DC converter 22 provides an output voltage V of the power converter 2 with AFC. 输出 . The voltage sensing circuit 8 is coupled to the first input power 4 and the second input power 6. The voltage sensing circuit 8 is configured to sense the voltage level of the first input power 4 and the voltage level of the second input power 6, and output the sensed voltage level to the AFC control circuit 10. The AFC control circuit 10 is configured to control the relay switching circuit 12 to selectively connect the first input power 4 or the second input power 6 to the rest of the power converter. The PFC control circuit 20 is coupled to the PFC power converter 18. The PFC control circuit 20 is configured to control the PFC power converter 18. The AFC control circuit 10 and the PFC control circuit 20 are coupled to provide control signaling across the isolation barrier 16. The AFC control circuit 10 and the PFC control circuit 20 are separated by the isolation barrier 16 so that the voltage sensing circuit 8 can be grounded separately. The isolation barrier 16 can be a transformer, a capacitor, or other type of conventional isolation barrier. In some embodiments, an optical coupler is used to transmit control signaling across the isolation barrier 16. It should be understood that any alternative conventional signaling device capable of transmitting control signaling across the isolation barrier can be used.
[0018] refer to Figure 2 The exemplary embodiment of FIG. 1 describes the operation of the power converter 2 with AFC in more detail. Figure 2 A schematic block diagram of a power converter with AFC according to some embodiments is shown. Figure 2 The power converter with AFC shown is conceptually similar to Figure 1 The power converter with AFC is the same. Figure 2The power converter with AFC is shown Figure 1 An exemplary embodiment of a power converter with AFC includes a schematic diagram of selected functional blocks. The system includes two input power sources, which provide an input voltage V corresponding to a first input power 4 输入A and an input voltage V corresponding to the second input power 6 输入B In an exemplary embodiment, the first input power is an AC voltage source operating in the voltage range of 180VAC to 264VAC and the frequency range of 47Hz to 63Hz. Although the system shown and described involves two power supplies, it should be understood that additional power supplies may also be included. The input power is switched through the relay circuit 12 ( Figure 2 ) is connected to a power converter. In some embodiments, the relay switching circuit 12 includes two relay switches - relay switch 32 and relay switch 34. It should be understood that additional relay switches can be used and these additional relay switches can be configured to accommodate alternative input power supply configurations and input power supplies greater than the two shown and described. In some embodiments, each input power supply is connected to a corresponding relay switch via a fuse and a smoothing capacitor. Figure 2 In the exemplary configuration shown, the fuse 24 and the smoothing capacitor 26 are coupled between the first input power 4 and the relay switch 32 , and the fuse 28 and the smoothing capacitor 30 are coupled between the second input power 6 and the relay switch 34 .
[0019] Each relay switch 32, 34 is a mechanical switch including a first terminal and a second terminal and also including a switch arm. In a first position, the switch arm is connected to the first terminal. In a second position, the switch arm is connected to the second terminal. The first position is considered to be a static state or home position. In some embodiments, each relay switch 32, 34 is a magnetic relay switch that uses a magnet to move the switch arm from the first position to the second position. The magnetic relay switch also includes an inductor coil. When current is provided through the inductor coil, a magnetic field is induced that moves the magnet, which in turn moves the switch arm from the first position to the second position. When the current is removed from the inductor coil, the magnetic field no longer exists, so the magnet returns to its stable position, and the switch arm returns to the first position, such as by a spring. In this embodiment, the magnetic relay switch is controlled by the AFC control circuit 10 by controlling the current flowing through the inductor coil of each relay switch. When there is current flowing through the inductor coil, the switch arm of the relay switch is connected to the second terminal. When there is no current, the switch arm is connected to the first terminal. It should be understood that other types of relay switches that can be controlled by the AFC control circuit 10 can be used. Such as Figure 2As shown, each of the relay switches 32, 34 is in a static state, wherein the switch arm is positioned against the first terminal. During normal operation of the power converter with AFC, the relay switches 32, 34 are each in a static state, which enables connection to the first input power 4.
[0020] The top terminal of the first input power 4 is connected to the first terminal of the relay switch 32, and the top terminal of the second input power 6 is connected to the second terminal of the relay switch 32. The bottom terminal of the first input power 4 is connected to the first terminal of the relay switch 34, and the bottom terminal of the second input power 6 is connected to the second terminal of the relay switch 34. In order to connect the first input power 4 to the power converter, the relay switch 32 is connected to the first terminal of the relay switch 32, and the relay switch 34 is connected to the first terminal of the relay switch 34, as shown in FIG. Figure 2 To connect the second input power 6 to the power converter, the switch arm of the relay switch 32 is connected to the second terminal of the relay switch 32 , and the switch arm of the relay switch 34 is connected to the terminal 2 of the relay switch 34 .
[0021] The exemplary PFC power converter 18 is configured as a boost converter and includes a boost inductor 36, a main switch 38, a diode 40, an auxiliary switch 44, a surge resistor 46, a bulk capacitor 48, and a bypass circuit path including a diode 42. The output voltage of the PFC power converter 18 is the voltage across the bulk capacitor 48. In order for the boost converter to operate properly, the output voltage must be higher than the input voltage. However, there is a zero output voltage during power-on, so the output voltage is less than the input voltage at this time. Whenever the input voltage is greater than the output voltage, the bypass circuit path is automatically enabled because, under this condition, the diode 42 is forward biased. Whenever the output voltage is greater than the input voltage, the bypass circuit path is automatically disabled because, under this condition, the diode 42 is reverse biased. Before enabling the main circuit path, the bypass circuit path is used to charge the bulk capacitor 48 (output voltage). Once bulk capacitor 48 is charged to a point where the output voltage is greater than the input voltage, diode 42 in the bypass circuit path becomes reverse biased and current stops flowing through the bypass circuit path, and the main circuit path is enabled by closing and opening main switch 38 . Figure 2 The circuit diagram of the PFC power converter 18 shown is for exemplary purposes only. It should be understood that other circuit configurations may be used. It should also be understood that the power converter may generally be of an alternative type other than a boost converter.
[0022] Although not in Figure 2 As shown, the DC to DC converter 22 includes an isolation barrier to provide a voltage difference between the PFC power converter 18 and the output voltage V输出 In some embodiments, the isolation barrier includes a transformer having a primary winding coupled to the PFC power converter 18 and a primary winding coupled to the circuit output V 输出 of the secondary winding.
[0023] There are three current paths through the power converter 2 with AFC. The first current path includes current flowing through the relay switches 32, 34 and the line filter 14. The second current path is on the secondary side of the isolation barrier and includes current flowing through a bypass circuit path having a diode 42. The third current path includes current flowing through the boost inductor 36 and the main switch 38 or the diode 40 (depending on whether the main switch 38 is closed or open). The third current path is the main current path through the PFC power converter 18. After power-on, current flows through the third current path to charge the boost inductor 36. The current flows through the third current path according to the control of the main switch 38 by the PFC control circuit 20. When the main switch 38 is closed (ON), current flows through the boost inductor 36 and the main switch 38 (which charges the boost inductor 36), while the output voltage V is provided by the charge already stored in the bulk capacitor 48. 输出 When the main switch is OFF, current flows through the boost inductor 36 and the diode 40 and is provided to both the bulk capacitor 48 and the DC to DC converter 22 to provide an output voltage V 输出 .
[0024] During operation, if the first input power 4 is interrupted or lost, the load is still connected to the output of the power converter. In this case, the load draws current from the charged bulk capacitor 48, which causes the voltage across the bulk capacitor 48 (which is also the voltage output from the PFC power converter 18) to drop. When the power source switches to the second input power 6, depending on the instantaneous AC voltage level of the second input power 6 when the relay is switched, the voltage at the input of the PFC power converter 18 may be greater than the voltage pulled down across the bulk capacitor 48, in which case the bypass diode 42 is forward biased, thereby automatically enabling the bypass circuit path (second current path).
[0025] The purpose of a power converter with AFC is to establish zero current through the power converter and perform switching of the relay switch during the zero current condition, which can be achieved by precisely timing the relay switch switching at the zero voltage crossing point of the second input power. The timing of the zero voltage of the second input power and the timing of the zero voltage switching of the relay switch are determined and implemented to minimize (if not eliminate) the spark at the relay switch. The smaller the amount of spark, the less stress on the relay switch. In a conventional configuration, the relay switch switches from the first input power source to the second input power source without regard to the value of the current through the power converter or the zero voltage switching with respect to the second input power.
[0026] In order to establish a zero current through the power converter 2 with AFC, the current through each of the three current paths during relay switching must be zero. With respect to the first current path, there is no active control in the line filter 14 because the line filter 14 only includes passive components such as inductors and capacitors. In order to control the current in the first current path, zero voltage switching with respect to the second input power 6 is implemented. If the input voltage is zero, the input current is zero, which results in the current through the first current path being zero. With respect to the second current path, switching is implemented at the zero voltage crossing point of the second input power 6. If switching occurs at such a zero voltage crossing point, then at this time the buck voltage (the output of the PFC power converter 18) is higher than the voltage input to the PFC power converter 18, which means that the diode 42 is reverse biased and no current flows through the second current path. Therefore, zero current through the first current path and the second current path can be achieved by ensuring that the relay switching occurs at the zero voltage crossing point of the second input power 6. With respect to the third current path, this can be controlled by disconnecting the main switch 38 by the PFC control circuit 20. Before the AFC control circuit 10 initiates switching of the relay switch, the AFC control circuit 10 sends a signal to the PFC control circuit 20 to turn off the main switch 38 in the PFC power converter 18 .
[0027] In operation, the power converter 2 with AFC is configured to determine when it is necessary to switch an interruption of the first input power 4 to the second input power 6, and to determine and implement the precise timing and control of the switching. Figure 3An exemplary control timing diagram for implementing switching according to some embodiments is shown. Voltage curve 56 shows the sensed voltage level from the first input power 4, and voltage curve 58 shows the sensed voltage level from the second input power 6. Under normal operating conditions, the relay switches 32, 34 are connected to the first input power 4. The voltage sensing circuit 8 and the AFC control circuit 10 are configured to sense and detect the amplitude and phase of both the first input power 4 and the second input power 6. When the sensed voltage level of the first input power 4 is lost (for example, the sensed voltage level is zero for a certain period of time), it is determined that an interruption of the first input power has occurred. Time t0 indicates when the first input power 4 as sensed and detected by the voltage sensing circuit 8 and the AFC control circuit 10 is lost. Time period T ac_失去 (T2) is a waiting period for determining whether the first input power 4 is truly lost or is only temporarily interrupted, such as due to noise or other reasons. The period T2 is called a trigger delay. If the first input power is not restored after the period T2, it is determined that switching is to be performed. The period T2 is a known value determined in advance. The AFC control circuit 10 implements a zero voltage switching algorithm to determine when to send a control signal to the relay switch to perform switching.
[0028] The time period T1 is a time period between zero voltage crossing points of the second input power 6. The time period T1 is calculated by the AFC control circuit 10 and is determined based on the second input power 6 that has been previously sensed. zvs_等待 (T3) is the time to wait for the correct phase of the second input power 6 (i.e., wait for the next zero voltage crossing point of the second input power 6). Since the second input power 6 is being sensed and detected, the most recent zero voltage crossing point of the second input power 6 is known, and the subsequent zero voltage crossing point can be calculated by the AFC control circuit 10 based on T1.
[0029] Time period T 继电器 (T4) is the mechanical delay of the relay switches 32, 34, i.e., the time delay for the switch arm to physically switch terminals after receiving the switching control signal from the AFC control circuit 10. Since the relay switches 32, 34 are mechanical, there is a delay between sending a signal to notify the relay switch to switch and the actual mechanical switching of the switch arm from one terminal to the other terminal. When the switch arm changes from one terminal to the other terminal, the switch arm will physically swing or vibrate against the other terminal before it stabilizes in contact with the other terminal. The time period T4 takes into account the time period that the switch arm vibrates before it stabilizes on the terminal. The time period T4 is a predetermined known value.
[0030] In this way, the timing of transmitting the control signal by the AFC control circuit 10 to the relay switches 32, 34 is established by determining when the next zero voltage crossing point of the second input power 6 is, and then transmitting the control signal at time t2 (which is a time period T4 before the expected timing of the next zero voltage crossing point of the second input power 6 at time t3). Before time t3, the AFC control circuit 10 transmits a control signal to the PFC control circuit 20 indicating that the main switch 38 in the PFC power converter 18 is to be disconnected. In turn, the PFC control circuit 20 transmits a control signal to the main switch 38 to disconnect so that the current in the third current path is zero at time t3 (switching time). It should be understood that Figure 3 The voltage waveforms, absolute time periods, and relative durations of the time periods shown are for exemplary purposes only, and the specific values are application specific.
[0031] As previously described, time period T4 (T 继电器 ) is a predetermined value. In the case of magnetic relay switches, each relay switch depends on the current passing through the inductor coil. The larger the current, the larger the induced magnetic field and the faster the switch arm switches from the first terminal to the second terminal. Thus, the time period T 继电器 The value of is a function of the voltage level applied to the relay switch. Figure 4 The calibration circuit 50 shown can be used to predetermine the time period T for a given applied voltage. 继电器 The given applied voltage will be used to control the relay switches 32, 34 ( Figure 2 ). Usually, the time period T 继电器 is predetermined for a given voltage applied to the relay switch for switching. 继电器 This may be determined during a calibration step, such as during production, using calibration circuit 50 .
[0032] Typical timing examples are provided below. The AC loss detection time (T2) can be achieved in less than 4ms. The zero voltage switching wait time (T3) for the next zero voltage crossing point depends on when the first input power 4 is lost relative to the most recent previous zero voltage crossing point of the second input power 6 from the time the first input power 4 is lost. The worst case is that the zero voltage switching wait time T3 is equal to the time period T1 which is the time period between the zero voltage crossing points of the second input power 6. When a high voltage is applied, the relay switching time (T4) can be achieved in less than 4ms. For example, a relay switching time T4 of 3.3ms can be achieved using an inductor coil voltage of 35V. Figure 5An exemplary relationship between the inductor coil voltage and the relay switching time T4 is shown in FIG. It should be understood that different relay switches may behave differently and have different relationships of the inductor coil voltage to the relay switching time T4.
[0033] Typical power converters have a 20ms hold-up time, which means that if input power is lost for 20ms or less, the output voltage V 输出 will not be adversely affected (due to the charge stored in the bulk capacitor 48) and operation will not be affected. In this case, the zero voltage switching wait time T3 is at most 12ms before the operation of the power converter is affected. If the example second input power has a range of 180VAC to 264VAC and a frequency of 47Hz to 63Hz, the worst case for the entire cycle of the second input power is 21ms, and since the time period T1 is half of the entire cycle, the worst case for the time period T1 is 10.5ms. Therefore, in the worst case scenario of T3, the total time (T2+T3+T4) to implement the AFC control timing for switching is 4ms+10.5ms+4ms=18.5ms, which is less than the maximum delay of 20ms to maintain the operation of the power converter in the event of a loss of the first input power 4.
[0034] The present application has been described with respect to specific embodiments in conjunction with details in order to facilitate an understanding of the principles of construction and operation of relay switching control. Many of the components shown and described in the various figures may be interchanged to achieve the necessary results, and this specification should also be understood to cover such interchanges. Thus, references herein to specific embodiments and details thereof are not intended to limit the scope of the appended claims. It will be clear to those skilled in the art that modifications may be made to the embodiments selected for illustration without departing from the spirit and scope of the present application.
Claims
1. A power supply and power converter system, the system include: a. First input AC power supply; b. Second input AC power supply; c. a relay switching circuit coupled to the first input AC power source and the second input AC power source, wherein, under normal operating conditions, the relay switching circuit is configured to enable connection with the first input AC power source and disable connection with the second input AC power source; d. a power conversion circuit coupled to the relay switching circuit; e. a voltage sensing circuit coupled to the first input AC power source and the second input AC power source; and f. a control circuit coupled to the voltage sensing circuit, the relay switching circuit and the power conversion circuit, wherein the control circuit is configured to: receive the sensed voltage levels of the first input AC power source and the second input AC power source to determine whether the first input AC power source is interrupted and whether switching to the second input AC power source is required by determining whether the sensed voltage value of the first input AC power source is zero within a predetermined waiting period; and control switching of the relay switching circuit to disable connection with the first input AC power source and enable connection with the second input AC power source at a zero voltage crossing point of the sensed voltage level of the second input AC power source, wherein the control circuit is configured to control switching of the relay switching circuit by calculating a next zero voltage crossing point time of the second input AC power source immediately after the predetermined waiting period, and then transmitting a control signal to the relay switching circuit at a time equal to the calculated next zero voltage crossing point time minus a predetermined switching delay period.
2. The system according to claim 1, in, The power conversion circuit includes a main switch, and the control circuit is configured to transmit a control signal to the main switch so that the main switch is open at the zero voltage crossing point.
3. The system according to claim 1, in, The power conversion circuit includes a power factor corrected power converter.
4. The system according to claim 3, in, The power conversion circuit further includes a DC to DC converter coupled to an output of the power factor correction power converter.
5. The system according to claim 3, in, The power factor corrected power converter is a boost converter.
6. The system according to claim 3, in, The control circuit includes a first control circuit for providing a control signal to the relay switching circuit, and a second control circuit for providing a control signal to the power factor correction power converter, wherein the system further includes an isolation barrier between the first control circuit and the second control circuit.
7. The system according to claim 6, in, The first control circuit is configured to provide a control signal to the second control circuit across the isolation barrier.
8. The system of claim 1, in, The control circuit is further configured to transmit a second control signal to the main switch of the power conversion circuit before the next zero voltage crossing point time, wherein the second control signal turns off the main switch so that the main switch is turned off when the relay switching circuit switches.
9. A method of switching power supply of a power converter, the method include: a. coupling a first input AC power source and a second input AC power source to a relay switching circuit, wherein, under normal operating conditions, the relay switching circuit is configured to enable connection of the first input AC power source to the power conversion circuit and disable connection of the second input AC power source to the power conversion circuit; b. sensing the voltage levels of the first input AC power source and the second input AC power source; c. determining whether the first input AC power supply is interrupted and whether it is necessary to switch to the second input AC power supply by determining whether the sensed voltage value of the first input AC power supply is zero within a predetermined waiting period of time; and d. controlling the switching of the relay switching circuit to disable the connection with the first input AC power source and enable the connection with the second input AC power source at a zero voltage crossing point of the sensed voltage level of the second input AC power source, wherein controlling the switching of the relay switching circuit includes: calculating the next zero voltage crossing point time of the second input AC power source immediately after the predetermined waiting period, and then transmitting a control signal to the relay switching circuit at a time equal to the calculated next zero voltage crossing point time minus a predetermined switching delay period.
10. The method according to claim 9, in, The power conversion circuit includes a main switch, and the method further includes transmitting a control signal to the main switch so that the main switch is open at the zero voltage crossing point.
11. The method according to claim 9, in, The method further includes transmitting a second control signal to a main switch of the power conversion circuit before the next zero voltage crossing point time, wherein the second control signal turns off the main switch so that the main switch is turned off when the relay switching circuit switches.
Citation Information
Patent Citations
Active inrush current control using a relay for AC to DC converters
CN101268597A
Relay control device and cooking machine
CN101596074A
Switching power converter for reducing emi from ring oscillation and its control method
CN102239628A
Selecting a single AC source for a switching power supply
CN102687361A
Power supply including zero-cross detection circuit, and image forming apparatus
CN103166484A