Construction device and construction method of cantilever roof

By designing the cantilever roof construction device and using drive parts and connecting rods to drive the operation platform to move, the problems of long construction period, high cost and low efficiency of metal aluminum plate edge decoration on the roof of high-rise buildings are solved, and the construction period is short and low cost is achieved , high efficiency effect.

CN111663760BActive Publication Date: 2025-02-11MCC URBAN INVESTMENT HLDG CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202010634523.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-07-02
Publication Date
2025-02-11
Estimated Expiration
2040-07-02

AI Technical Summary

Technical Problem

When the roof of the top floor of high-rise buildings is decorated with metal aluminum plate edges, the existing technology has problems such as long construction period, high cost and low construction efficiency.

Method used

A construction device for cantilever roof is designed, including an operating platform, a connecting rod and a driving member. The connecting rod is driven to move along the cross beam through the driving member, driving the operating platform to move along the cross beam, realizing the rapid installation of the metal aluminum edge.

Benefits of technology

This construction device and method can significantly shorten the construction period, reduce costs, improve construction efficiency, and be simple to operate and high safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111663760B_ABST
    Figure CN111663760B_ABST
Patent Text Reader

Abstract

The invention discloses a construction device and a construction method for a cantilever roof, which belongs to the technical field of cantilever roof construction, and is designed to solve the technical problems of long construction period, high cost, low construction efficiency, etc. for the entire frame. The construction device for the cantilever roof is arranged on a roof column, and there are multiple roof columns, and the multiple roof columns are distributed in a matrix. A crossbeam is arranged between two adjacent roof columns along a first direction of the multiple roof columns, and a longitudinal beam is arranged between two adjacent roof columns along a second direction. The construction device for the cantilever roof includes an operating platform, a connecting rod and a driving member, and the operating platform is detachably connected to the connecting rod, and the connecting rod is movably arranged on the crossbeam, and the connecting rod is detachably connected to the driving member, and the driving member is configured to drive the connecting rod to move along the length direction of the crossbeam so as to drive the operating platform to move along the length direction of the crossbeam. The construction device and the construction method for the cantilever roof have the advantages of short construction period, low cost, and high construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cantilever roof construction, and in particular to a cantilever roof construction device and a cantilever roof construction method. Background Art

[0002] At present, the top roofs of some high-rise buildings need to be decorated with metal aluminum plates. For example, the flower rack on the roof of a student dormitory building is cantilevered, and the outer circle of the flower rack is decorated with metal aluminum plates. At present, each roof flower rack is constructed with a cantilevered I-beam double-row scaffolding. However, the construction period of the entire frame is long and each building roof needs a cantilevered external frame, which is too costly and has low construction efficiency. Summary of the invention

[0003] The first purpose of the present invention is to provide a cantilever roof construction device, which solves the technical problems of long erection period, high cost and low construction efficiency.

[0004] The second purpose of the present invention is to provide a cantilever roof construction method, which solves the technical problems of long erection period of the entire frame, high cost and low construction efficiency.

[0005] To achieve the above-mentioned purpose, the present invention adopts the following technical solutions:

[0006] A construction device for a cantilever roof is arranged on a roof column, wherein there are multiple roof columns, and the multiple roof columns are distributed in a matrix. A crossbeam is arranged between two adjacent roof columns along a first direction, and a longitudinal beam is arranged between two adjacent roof columns along a second direction. The construction device for the cantilever roof comprises an operating platform, a connecting rod and a driving member, wherein the operating platform is detachably connected to the connecting rod, the connecting rod is movably arranged on the crossbeam, and the connecting rod is detachably connected to the driving member; wherein the driving member is configured to drive the connecting rod to move along the length direction of the crossbeam so as to drive the operating platform to move along the length direction of the crossbeam.

[0007] Optionally, the construction device of the cantilever roof further includes a guide assembly, the crossbeam is an I-beam, the guide assembly is connected to the connecting rod, and the guide assembly is located in a beam groove of the crossbeam.

[0008] Optionally, the guide assembly includes a pulley, a support member and an axle body, the support member is connected to the connecting rod, the axle body is arranged on the support member, the pulley is rotatably passed through the axle body, and the connecting rod can drive the pulley to move along the length direction of the beam.

[0009] Optionally, the driving member is an electric hoist, which is detachably fixed to the longitudinal beam and connected to the connecting rod via a connecting line.

[0010] Optionally, the construction device of the cantilever roof further includes a hoist, which is disposed on the connecting rod and is used to adjust the vertical distance between the operating platform and the crossbeam.

[0011] Optionally, the connecting rod is an I-beam rod.

[0012] Optionally, the operating platform is a hanging basket.

[0013] Optionally, the construction device for the cantilever roof further includes an anti-falling safety lock, and the anti-falling safety lock is arranged between the connecting rod and the operating platform.

[0014] Optionally, the connecting line is a steel wire rope.

[0015] The construction device for cantilevered roofs of the present invention has the following beneficial effects compared to the prior art: since the driving member is configured to drive the connecting rod to move along the length direction of the cross beam, thereby driving the operating platform to move along the length direction of the cross beam, it is convenient for the operator on the operating platform to sequentially install the metal aluminum edges along the length direction of the cross beam. In addition, since the operating platform is detachably connected to the connecting rod, and the connecting rod is detachably connected to the driving member, it can effectively solve the problem of the intersection of the cross beam and the longitudinal beam hindering the continued movement of the operating platform, and the operating platform and the connecting rod can be reinstalled on other cross beams to continue to install the metal aluminum edges. In summary, the construction device for cantilevered roofs has a short construction period, low construction cost and high construction efficiency.

[0016] A cantilever roof construction method, the cantilever roof construction method adopts the cantilever roof construction device, comprising the following steps:

[0017] S1: The driving member is fixed to one of the longitudinal beams, the two ends of the connecting rod are stopped on two of the cross beams, the two ends of the connecting rod are respectively connected to the operating platform through the hoist, the guide assembly is placed in the beam groove of the cross beam and connected to the connecting rod, and the connecting line is connected between the driving member and the connecting rod;

[0018] S2: starting the driving member to pull the connecting line to move along the length direction of the beam, thereby driving the operating platform to move along the length direction of the beam until it moves to the longitudinal beam;

[0019] S3: The driving member is removed from the longitudinal beam and reinstalled on another of the longitudinal beams. The hoist pays out the operating platform in a direction away from the cross beam until the operating platform is placed on the roof panel. The tower crane lifts the connecting rod and the guide assembly and places them on the other two cross beams, moves the operating platform to the bottom of the cross beam, and connects the operating platform to the connecting rod again.

[0020] The construction method of the cantilever roof of the present invention has the following beneficial effects compared with the prior art: through the combination of the operating platform, the connecting rod and the driving member, and the detachable installation method, the cantilever roof can be effectively installed with a split-span metal aluminum edge without the need to build a scaffolding, which greatly reduces the construction cost and construction period and improves the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a structural schematic diagram of a cantilever roof construction device provided in a specific embodiment of the present invention;

[0022] Figure 2 It is a structural schematic diagram of an operating platform provided by a specific embodiment of the present invention.

[0023] Reference numerals:

[0024] 100, roof column; 200, cross beam; 300, longitudinal beam; 1, operating platform; 2, connecting rod; 3, driving part; 4, guide assembly; 5, connecting line. DETAILED DESCRIPTION

[0025] In order to make the technical problem solved by the present invention, the technical solution adopted and the technical effect achieved more clearly, the technical solution of the present invention is further explained below with reference to the accompanying drawings and through specific implementation methods.

[0026] Reference below Figure 1-Figure 2 The specific structure of the construction device for the cantilever roof according to the embodiment of the present invention is described.

[0027] It should be noted in advance that the intersection of the cross beam 200 and the longitudinal beam 300 on the cantilevered roof will hinder the operating platform 1 from continuously moving along the length direction of the cross beam 200 .

[0028] like Figure 1As shown, the present embodiment provides a construction device for a cantilever roof, which is arranged on a roof column 100. There are multiple roof columns 100, and the multiple roof columns 100 are distributed in a matrix. A crossbeam 200 is arranged between two adjacent roof columns 100 along a first direction of the multiple roof columns 100, and a longitudinal beam 300 is arranged between two adjacent roof columns 100 along a second direction. The construction device for the cantilever roof includes an operating platform 1, a connecting rod 2 and a driving member 3. The operating platform 1 is detachably connected to the connecting rod 2, and the connecting rod 2 is movably arranged on the cross beam 200, and the connecting rod 2 is detachably connected to the driving member 3; wherein the driving member 3 is configured to drive the connecting rod 2 to move along the length direction of the cross beam 200, thereby driving the operating platform 1 to move along the length direction of the cross beam 200.

[0029] It is understandable that, since the driving member 3 is configured to drive the connecting rod 2 to move along the length direction of the beam 200, thereby driving the operating platform 1 to move along the length direction of the beam 200, it is convenient for the operator on the operating platform 1 to sequentially install the metal aluminum edges along the length direction of the beam 200. In addition, since the operating platform 1 is detachably connected to the connecting rod 2, and the connecting rod 2 is detachably connected to the driving member 3, it can effectively solve the problem that the intersection of the beam 200 and the longitudinal beam 300 hinders the continued movement of the operating platform 1. The operating platform 1 and the connecting rod 2 can be reinstalled on other beams 200 to continue to install the metal aluminum edges. In summary, the construction device of the cantilever roof has a short construction period, low construction cost, high construction efficiency, simple operation and high safety.

[0030] It is particularly noted that the first direction is perpendicular to the second direction.

[0031] Alternatively, if Figure 2 As shown, the construction device for the cantilever roof also includes a guide assembly 4 , the cross beam 200 is an I-beam beam, the guide assembly 4 is connected to the connecting rod 2 , and the guide assembly 4 is located in the beam groove of the cross beam 200 .

[0032] It should be noted that the guide assembly 4 serves to guide the connecting rod 2 along the length direction of the cross beam 200 and to limit the position of the connecting rod 2 to prevent it from shaking left and right during movement, thereby affecting the quality of the metal aluminum edge installation by the operator. In addition, the I-beam structure of the cross beam 200 is fully utilized, and the beam groove on the I-beam serves as a slide rail, and the guide assembly 4 can move in the beam groove, which is ingeniously designed and saves construction costs.

[0033] Optionally, the guide assembly 4 includes a pulley, a support member and an axle body, the support member is connected to the connecting rod 2, the axle body is arranged on the support member, the pulley is rotatably passed through the axle body, and the connecting rod 2 can drive the pulley to move along the length direction of the beam 200.

[0034] It is understandable that if Figure 1As shown, the driving member 3 drives the connecting rod 2 to move along the length direction of the beam 200. Since the connecting rod 2 is connected to the support member, the pulley is rotatably provided on the shaft body on the support member. Therefore, when the connecting rod 2 moves along the length direction of the beam 200, the pulley continuously rolls in the beam groove, thereby playing a role in guiding the connecting rod 2.

[0035] Optionally, the driving member 3 is an electric hoist, which is detachably fixed to the longitudinal beam 300 and connected to the connecting rod 2 via a connecting wire 5. It is understandable that the electric hoist as the driving member 3 can effectively pull the connecting wire 5, thereby driving the connecting rod 2 to move along the length direction of the crossbeam 200. In other embodiments of the present invention, the driving member 3 can also be selected in other ways according to actual conditions, and is not limited to an electric hoist.

[0036] Optionally, the construction device of the cantilever roof further includes a hoist, which is arranged on the connecting rod 2 and is used to adjust the vertical distance between the operating platform 1 and the cross beam 200. It should be noted that after the operator installs the metal aluminum edge between the two longitudinal beams 300, the operating platform 1 needs to be disassembled. Since the hoist can adjust the vertical distance between the operating platform 1 and the cross beam 200, it is convenient to place the operating platform 1 on the roof panel and reinstall it on the next roof column 100 where the metal aluminum edge needs to be installed.

[0037] Optionally, the connecting rod 2 is an I-beam rod, which has high structural strength and low cost, and can directly use the I-beam rods at the construction site. Of course, in other embodiments of the present invention, the connecting rod 2 can be made of other materials according to actual conditions, and is not limited to the I-beam rod.

[0038] Optionally, the operating platform 1 is a hanging basket having a guardrail to protect the personal safety of the operator. The hanging basket has a large space for convenient placement of the metal aluminum edge to be installed.

[0039] Optionally, the construction device of the cantilever roof also includes an anti-fall safety lock, which is arranged between the connecting rod 2 and the operating platform 1, further providing personal safety for the operator and preventing falling.

[0040] Optionally, the connecting line 5 is a steel wire rope, which has high strength, corrosion resistance, and is not easy to break. Of course, in other embodiments of the present invention, the connecting line 5 can be made of other materials with excellent performance according to actual needs.

[0041] A cantilever roof construction method, the cantilever roof construction method using a cantilever roof construction device, comprising the following steps:

[0042] S1: The driving member 3 is fixed on one of the longitudinal beams 300, the two ends of the connecting rod 2 are stopped on two of the cross beams 200, the two ends of the connecting rod 2 are respectively connected to the operating platform 1 through a hoist, the guide assembly 4 is placed in the beam groove of the cross beam 200 and connected to the connecting rod 2, and a connecting line 5 is connected between the driving member 3 and the connecting rod 2;

[0043] S2: Start the driving member 3 to pull the connecting wire 5 to move along the length direction of the beam 200, thereby driving the operating platform 1 to move along the length direction of the beam 200, and the operator on the operating platform 1 installs the metal aluminum edge on the cantilever roof until it moves to the longitudinal beam 300;

[0044] S3: Remove the driving part 3 from the longitudinal beam 300 and reinstall it on another longitudinal beam 300. The hoist will lay out the operating platform 1 in the direction away from the cross beam 200 until the operating platform 1 is placed on the roof panel. The tower crane will lift the connecting rod 2 and the guide assembly 4 and place them on the other two cross beams 200, and move the operating platform 1 to the bottom of the cross beam 200. The operating platform 1 will be connected to the connecting rod 2 again, and the operator on the operating platform 1 will install the metal aluminum edge again.

[0045] The construction method of the cantilever roof of the present invention has the following beneficial effects compared with the prior art: through the combination of the operating platform 1, the connecting rod 2 and the driving member 3, and the detachable installation method, the cantilever roof can be effectively installed with a split-span metal aluminum edge, and steps S1 and S2 can be repeated without building a scaffold, which greatly reduces the construction cost and construction period and improves the construction efficiency.

[0046] In the description of this specification, the description with reference to the terms "some embodiments", "other embodiments", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0047] In addition, it should be understood that the orientations or positional relationships indicated by terms such as "upper", "lower", "inside", "outside", "vertical", and "horizontal" are based on the orientations or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0048] In the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", "installed", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above-mentioned terms in the present invention can be understood according to specific circumstances.

[0049] In addition, features defined as "first" or "second" may explicitly or implicitly include one or more of the features, and are used to distinguish and describe features, without distinction of order or importance. In the description of the present invention, unless otherwise specified, "plurality" means two or more.

[0050] The above contents are only preferred embodiments of the present invention. For ordinary technicians in this field, according to the concept of the present invention, there will be changes in the specific implementation methods and application scopes. The content of this specification should not be understood as limiting the present invention.

Claims

1. A construction method for a cantilever roof, characterized in that: A cantilever roof construction device is used for construction, wherein the cantilever roof construction device is arranged on a roof column (100), wherein the roof column (100) is multiple, and the multiple roof columns (100) are distributed in a matrix, and a cross beam (200) is arranged between two adjacent roof columns (100) along a first direction of the multiple roof columns (100), and a longitudinal beam (300) is arranged between two adjacent roof columns (100) along a second direction, and the cantilever roof construction device comprises an operating plane The operating platform (1) comprises a connecting rod (2) and a driving member (3), wherein the operating platform (1) is detachably connected to the connecting rod (2), the connecting rod (2) is movably arranged on the crossbeam (200), and the connecting rod (2) is detachably connected to the driving member (3); wherein the driving member (3) is configured to drive the connecting rod (2) to move along the length direction of the crossbeam (200) so as to drive the operating platform (1) to move along the length direction of the crossbeam (200); The cantilever roof construction device further comprises a guide assembly (4), the cross beam (200) is an I-beam, the guide assembly (4) is connected to the connecting rod (2), and the guide assembly (4) is located in a beam groove of the cross beam (200); The driving member (3) is an electric hoist, which is detachably fixed to the longitudinal beam (300) and connected to the connecting rod (2) via a connecting line (5); It also includes a hoist, which is arranged on the connecting rod (2) and is used to adjust the vertical distance between the operating platform (1) and the crossbeam (200); The construction method of the cantilever roof comprises the following steps: S1: The driving member (3) is fixed to one of the longitudinal beams (300), the two ends of the connecting rod (2) are stopped on two of the cross beams (200), the two ends of the connecting rod (2) are respectively connected to the operating platform (1) through the hoist, the guide assembly (4) is placed in the beam groove of the cross beam (200) and connected to the connecting rod (2), and the connecting line (5) is connected between the driving member (3) and the connecting rod (2); S2: starting the driving member (3) to pull the connecting line (5) to move along the length direction of the crossbeam (200), thereby driving the operating platform (1) to move along the length direction of the crossbeam (200) until it moves to the longitudinal beam (300); S3: The driving member (3) is removed from the longitudinal beam (300) and reinstalled on another longitudinal beam (300). The hoisting machine arranges the operating platform (1) in a direction away from the cross beam (200) until the operating platform (1) is placed on the roof panel. The tower crane lifts the connecting rod (2) and the guide assembly (4) and places them on the other two cross beams (200), moves the operating platform (1) to the bottom of the cross beam (200), and connects the operating platform (1) to the connecting rod (2) again.

2. The construction method of the cantilever roof according to claim 1, characterized in that: The guide assembly (4) comprises a pulley, a support member and an axle body, wherein the support member is connected to the connecting rod (2), the axle body is arranged on the support member, the pulley is rotatably passed through the axle body, and the connecting rod (2) can drive the pulley to move along the length direction of the beam (200).

3. The construction method of the cantilever roof according to claim 1, characterized in that: The connecting rod (2) is an I-beam rod.

4. The construction method of the cantilever roof according to claim 1, characterized in that: The operating platform (1) is a hanging basket.

5. The construction method of the cantilever roof according to claim 1, characterized in that: It also comprises an anti-falling safety lock, which is arranged between the connecting rod (2) and the operating platform (1).

6. The construction method of the cantilever roof according to claim 1, characterized in that: The connecting line (5) is a steel wire rope.

Citation Information

Patent Citations

  • Walking hanging basket and installing method of walking hanging basket

    CN104989094A

  • Can stride across landing girder's aerial working platform

    CN207194419U

  • Construction device of cantilever roof

    CN212359072U