A control method for intelligent grab crane control system based on material imaging
Through material imaging technology and intelligent control system, the material stack data is automatically identified and processed, and automatic loading and unloading is realized, solving the problems of low efficiency and safety hazards of traditional grab cranes, and improving the intelligence of unmanned loading and unloading and management.
Patent Information
- Application Number
- CN202010680310.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-07-15
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The traditional grab crane loading and unloading process is low, the labor intensity of manual operation is high, and there are safety hazards, making it difficult to achieve unmanned loading and unloading and automated management.
Using an intelligent grab crane control system based on material imaging, the image data is obtained in real time through the imaging device of the stacking bin and the unloading bin, the coordinate system is established, the boundaries are set, the coordinates of the stack vertices and peaks are extracted, the vertices and peaks of the stack are processed in layers, and the selection is selected. Operate mode, calculate the movement path according to the mode, and control the grab to automatically grab and release materials.
Automatic identification, automatic positioning, automatic loading and unloading are realized, which improves work efficiency and safety, reduces manpower and energy consumption, and improves the intelligence of material field management.
Abstract
Description
Technical Field
[0001] The invention relates to the field of granular material processing, and in particular to a control method of an intelligent grab crane control system based on material imaging. Background Art
[0002] With the rapid development of the economy, a large amount of garbage, scrap steel, nuclear waste, biomass and other bulk particles need to be treated harmlessly or reused. During the treatment process, they need to be loaded and unloaded into the processing equipment by grab cranes. At present, the traditional loading and unloading process mode is generally adopted, that is, the mode of manual direct observation of materials and manual control of grab cranes. However, the traditional loading and unloading mode has low work efficiency, high labor intensity of manual operation, and long-term work is prone to safety accidents. In order to change the traditional loading and unloading process mode, improve the degree of intelligence, loading and unloading efficiency and safety reliability, and reduce the labor intensity of workers, many research institutions and manufacturers at home and abroad are paying more and more attention to the research and development of intelligent grab cranes.
[0003] Research and development of intelligent grab cranes requires the use of computational image processing technology, which is organically combined with grab cranes through the control of the central control room. Its goal is to realize unmanned loading and unloading processes in bulk material yards, and on this basis, to realize the integration of material yard management, central control, and unmanned control of stackers and reclaimers. In order to ensure that the grab can operate well, it is necessary to design a system and method that can reliably obtain three-dimensional dynamic material pile images. The intelligent grab crane control system processes data and automatically generates a reasonable operation route to achieve automatic identification, automatic positioning, automatic loading and unloading, automatic grabbing, and automatic feeding (or stacking). It provides intelligent lifting machinery for application fields such as waste incineration power plants, nuclear waste treatment, and unmanned chemical plants, and is conducive to improving working conditions, reducing manpower, saving labor costs and energy, and improving work efficiency and production safety. Summary of the invention
[0004] The purpose of the present invention is to solve the problems in the background technology and to provide a control method for an intelligent grab crane control system based on material imaging.
[0005] The above technical objectives of the present invention are achieved through the following technical solutions:
[0006] A control system for an intelligent grab crane based on material imaging, comprising: a material stacking bin, a material discharge bin, an intelligent grab, an imaging device and a control center; a feed channel and a material discharge gate are arranged above the material stacking bin, a plurality of vertically arranged height baselines are arranged on the side of the material stacking bin, wherein the topmost height baseline is the top line of the material stacking bin, and the feed channel and the material discharge gate are arranged above the top line of the material stacking bin; the intelligent grab comprises a trolley (power P1, speed V1) for controlling the lateral movement of the grab, a trolley (power P2, speed V2) for controlling the longitudinal movement of the grab, a crane for controlling the lifting of the grab and a material stack imaging; the intelligent grab obtains image data of the material stacking bin and the material discharge bin in real time through the imaging device, and moves under the moving path given by the control center; the imaging device comprises a height line identifier and a laser scanning device.
[0007] Preferably, the height baseline is provided with a reflective surface, and the top line of the silo protrudes inward from the side of the silo to form a top line boss.
[0008] An intelligent grab crane control method based on material imaging adopts the above control system and includes the following implementation steps:
[0009] S1. Establish a coordinate system and set a grabbing boundary and a stacking boundary. The grabbing boundary is the stacking area of the stacking bin, and the stacking boundary is the stacking area of the unloading bin;
[0010] S2. Material stacking bin imaging: After the material is discharged from the feeding channel and behind the discharge gate, the grid graphic data of the material stack in the material stacking bin is obtained by scanning with an imaging device. The coordinates (x, y, z) are recorded for each grid point, where x is the horizontal axis distance, y is the vertical axis distance, and z is the height data;
[0011] S3, extract the top and peak coordinates of the pile: extract the position coordinates (xd, yd, zd) of the pile vertex D according to the grid data, where zd is the height data of the pile vertex; select the coordinates (xfi, yfi, zfi) of several pile peak points Fi according to the grid data and the vertex height, where 0.9*zd≤zfi≤zd, and i is a natural number;
[0012] S4. Material pile stratification: stratify from bottom to top in the depth direction of the material pile bin, the bottom layer is the material pile layer, the middle layer is the energy-saving cleaning layer, and the top layer is the high-speed cleaning layer;
[0013] S5, mode selection: select the operation mode according to the command of the control center, the operation modes include: stop mode, energy-saving mode and high-speed mode. In the stop mode, the trolley, car and crane are not working, and the imaging device scans and refreshes the image of the stacking bin at a set interval; in the energy-saving mode and high-speed mode, the trolley, car and crane move along the calculated path under the control of the control center, and the imaging device scans and refreshes the image of the stacking bin after each grabbing operation, and the imaging device scans and refreshes the image of the unloading bin after each stacking operation;
[0014] S6, calculating the path: according to the mode selected in step S5, using different algorithms to calculate the path;
[0015] S7. After the path calculation is completed, the grab bucket is controlled to move and release the material according to the calculation results.
[0016] Preferably, the specific steps of imaging in step S2 include: 1. Image forming: using a laser scanning device to obtain a top curved surface image of a pile containing a top line image of a silo, and obtaining height data of the top curved surface of the pile through a height line identifier; 2. Data gridding: removing images outside the boundary at a data processing center, gridding the remaining top curved surface images of the pile, recording position coordinate data for each grid, and obtaining basic pile grid data A; 3. After a period of time T, repeating steps S3-S4 to obtain verification pile grid data B, and gridding the basic pile grid data A. The basic material pile grid data A is compared with the verification material pile grid data B to calculate the similarity P; 4. If the similarity P is greater than or equal to the set value Px, the verification is successful; if the similarity P is less than the set value Px, the verification fails, the basic material pile grid data A is deleted, and the verification material pile grid data B is written into the basic material pile grid data A, and step S5 is repeated to obtain new verification material pile grid data B, and compare again until the verification is successful; 5. After the verification is successful, the basic material pile grid data A and the verification material pile grid data B are superimposed to obtain the final grid data C.
[0017] Preferably, the specific steps of the image gridding are: ① the X-axis and the Y-axis are equally divided by a distance L to form a plurality of grids, each grid recording data (xi, yi, zi), wherein (xi, yi) represents the grid position of the X-axis and the Y-axis, and zi represents the height of the pile in the grid; ② the height line identifier identifies a height baseline parallel line group graphic with the top as the silo top line; the top surface image of the pile obtained by scanning with the laser scanning device includes the silo top line image; the two groups of pictures are fitted with the silo top line as the reference to obtain a grid map; ③ the height baseline spacing is a known constant, so the height data zi corresponding to each (xi, yi) coordinate is calculated by the surface graphic with the height baseline (31) as the ruler, and written into the grid recording data (xi, yi, zi).
[0018] Preferably, the similarity P calculation steps are as follows: ① calculate the difference between ziA and ziB at the same position point of each (xi, yi) coordinate in the basic material pile grid data A and the verification material pile grid data B; ② record the number of grids n whose difference is less than or equal to a, and record the number of grids m whose difference is greater than a, where a is the set accuracy parameter; ③ Similarity P=n / (n+m).
[0019] Preferably, the data of each grid point of the final grid data C is (xi, yi, ziC), and the data superposition processing algorithm is ziC=(ziA+ziB) / 2, where ziA and ziB are the height values of the stockpile at the same position with the coordinates (xi, yi) in the basic stockpile grid data A and the verification stockpile grid data B.
[0020] As a preferred method, the path calculation method of the energy-saving mode is as follows: 1. Determine the stacking point: according to the size of the hopper and the size of the unloading bin, preset the coordinates of several stacking points (Xt1, Yt1, Zt1) ~ (Xtn, Ytn, Ztn) and sort them, and determine the coordinates of the current stacking point as (Xtj, Ytj, Ztj), j (1≤j≤n) is the number of current stacking; 2. Grab point selection: select from the vertex D of the pile and the peak point Fi of the pile, and calculate the energy consumption :Wd=│xd-Xtj│×P1 / V1+│yd-Ytj│×P2 / V2, WFi=│xfi-Xtj│×P1 / V1+│yfi-Ytj│×P2 / V2, compare Wd with all WFi, and select the coordinates of the minimum pile vertex D or the pile peak point Fi as the grabbing point; 3. Generate a motion path: The motion path is the moving trajectory from the grabbing point in step 2 to the stacking point in step 1.
[0021] Preferably, the path calculation method of the high-speed mode is as follows: 1. Determine the stacking point: according to the size of the hopper and the size of the unloading bin, preset the coordinates of several stacking points (Xt1, Yt1, Zt1)~(Xtn, Ytn, Ztn) and sort them, determine the coordinates of the first stacking point as (Xtj, Ytj, Ztj), j (1≤j≤n) is the number of current stacking; 2. Grab point selection: select from the pile vertex D and the pile peak point Fi, calculate the time: Td=│xd-Xtj│ / V1+│yd-Ytj│ / V2, TFi=│xfi-Xtj│ / V1+│yfi-Ytj│ / V2, compare Td with the size of all TFi, select the coordinates of the pile vertex D or the pile peak point Fi with the minimum value as the grab point; 3. Generate a motion path: the motion path is the moving trajectory from the grab point in step 2 to the stacking point in step 1.
[0022] Since the height difference between the top and the peak of the pile is within 10%, and the position of each stacking point is the same, the speed and power consumption of the longitudinal crane can be ignored in the calculation, thereby reducing the computing load of the control center and improving work efficiency.
[0023] Preferably, the mode selection includes automatic selection and manual selection; wherein the automatic selection logic is: when the zd height is less than the stockpile layer height, the shutdown mode is selected; when the zd height is within the energy-saving cleaning layer height range, the energy-saving mode is selected; when the zd height is within the high-speed cleaning layer height range, the high-speed mode is selected.
[0024] Preferably, the stacking layer height is H / 5, the energy-saving cleaning layer height is 7H / 15, the high-speed cleaning layer height is H / 3, and H is the maximum stacking height of the stacking bin.
[0025] In summary, the present invention compares the two imaging results through multiple scanning and imaging, and determines whether the material pile is in a stable state by comparing the similarity, until finally obtaining an accurate grid map of the material pile in a stable state. Compared with ordinary scanning systems, the coordinates are directly modeled and calculated after the scan is completed. The data obtained by this solution is more reliable and can better reflect the true state of the material pile. On this basis, different vertices and peak points of the material pile are measured in different ways under different working modes to obtain the running route that conforms to the current mode, realizing the function of intelligently switching modes according to the usage scenario. DETAILED DESCRIPTION
[0026] The following specific embodiments are merely explanations of the present invention and are not limitations of the present invention. After reading this specification, those skilled in the art may make modifications to the embodiments without any creative contribution as needed. However, such modifications are protected by the patent law as long as they are within the scope of the claims of the present invention.
[0027] The present invention is described in detail below in conjunction with embodiments. Embodiment 1:
[0028] A control system for an intelligent grab crane based on material imaging comprises: a material stacking bin, a material discharge bin, an intelligent grab, an imaging device and a control center; a feed channel and a material discharge gate are arranged above the material stacking bin, a plurality of vertically arranged height baselines are arranged on the side of the material stacking bin, wherein the topmost height baseline is the top line of the material stacking bin, the feed channel and the material discharge gate are arranged above the top line of the material stacking bin, the height baseline is provided with a reflective surface, and the top line of the material stacking bin protrudes inward from the side of the material stacking bin to form a top line boss; the intelligent grab comprises a large vehicle (power P1, speed V1) for controlling the lateral movement of the grab, a small vehicle (power P2, speed V2) for controlling the longitudinal movement of the grab, a crane for controlling the lifting of the grab and a material stack imaging; the intelligent grab obtains image data of the material stacking bin and the material discharge bin in real time through the imaging device, and moves under the moving path given by the control center; the imaging device comprises a height line identifier and a laser scanning device.
[0029] An intelligent grab crane control method based on material imaging adopts the above control system and includes the following implementation steps:
[0030] S1. Establish a coordinate system and set a grabbing boundary and a stacking boundary. The grabbing boundary is the stacking area of the stacking bin, and the stacking boundary is the stacking area of the unloading bin;
[0031] S2. Material stacking bin imaging: After the material is discharged from the feeding channel and behind the discharge gate, the grid graphic data of the material stack in the material stacking bin is obtained by scanning with an imaging device. The coordinates (x, y, z) are recorded for each grid point, where x is the horizontal axis distance, y is the vertical axis distance, and z is the height data;
[0032] The specific steps of imaging include: 1. Image forming: Use a laser scanning device to obtain the top surface image of the pile containing the top line image of the silo, and obtain the height data of the top surface of the pile through the height line identifier; 2. Data gridding: In the data processing center, remove the image outside the boundary, grid the remaining top surface image of the pile, record the position coordinate data for each grid, and obtain the basic pile grid data A. The specific steps of image gridding are: ① Divide the X-axis and Y-axis by a distance L to form several grids, and each grid records the data (xi, yi, zi), where (xi, yi) represents the grid position of the X-axis and Y-axis, and zi represents the grid ① The height of the pile within; ② The height line identifier identifies the height baseline parallel line group graphic with the top of the silo top line; The surface image of the top of the pile scanned by the laser scanning device contains the silo top line image; The two groups of pictures are fitted by taking the silo top line as the reference to obtain a grid map; ③ The height baseline spacing is a known constant value, so the height data zi corresponding to each (xi, yi) coordinate is calculated through the surface graphic with the height baseline as the ruler, and written into the grid record data (xi, yi, zi); 3. After a period of time T (0.05s≤T≤1s), repeat steps S3-S4 to obtain the verification pile grid data B, and compare the basic pile grid data A with Verify the stockpile grid data B for comparison and calculate the similarity P. The similarity P calculation steps are as follows: ① Calculate the difference between ziA and ziB at the same position point (xi, yi) in the basic stockpile grid data A and the verification stockpile grid data B; ② Record the number of grids n whose difference is less than or equal to a, and record the number of grids m whose difference is greater than a, where a is the set accuracy parameter (0.1cm≤a≤50cm); ③ Similarity P=n / (n+m); 4. If the similarity P is greater than or equal to the set value Px (70%≤Px≤100%), the verification is passed; if the similarity P is less than the set value Px, the verification fails and the basic stockpile grid data is deleted. The basic material pile grid data A is obtained, and the verification material pile grid data B is written into the basic material pile grid data A, and step S5 is repeated to obtain new verification material pile grid data B, and then the comparison is performed again until the verification is passed; 5. After the verification is passed, the basic material pile grid data A and the verification material pile grid data B are superimposed to obtain the final grid data C. The data of each grid point of the final grid data C is (xi, yi, ziC), and the data superposition processing algorithm is ziC=(ziA+ziB) / 2, where ziA and ziB are the height values of the material pile at the same position of the (xi, yi) coordinates in the basic material pile grid data A and the verification material pile grid data B.
[0033] S3, extract the top and peak coordinates of the pile: extract the position coordinates (xd, yd, zd) of the pile vertex D according to the grid data, where zd is the height data of the pile vertex; select the coordinates (xfi, yfi, zfi) of several pile peak points Fi according to the grid data and the vertex height, where 0.9*zd≤zfi≤zd, and i is a natural number;
[0034] S4. Material pile stratification: stratify from bottom to top in the depth direction of the material pile bin, the bottom layer is the material pile layer, the middle layer is the energy-saving cleaning layer, and the top layer is the high-speed cleaning layer. The height of the material pile layer is H / 5, the height of the energy-saving cleaning layer is 7H / 15, and the high-speed cleaning layer is H / 3. H is the maximum material pile height of the material pile bin.
[0035] S5. Mode selection: select the operation mode according to the command of the control center. The operation modes include: shutdown mode, energy-saving mode and high-speed mode. In the shutdown mode, the trolley, car and crane are not working, and the imaging device scans and refreshes the image of the stockpile bin at a set interval; in the energy-saving mode and high-speed mode, the trolley, car and crane move along the calculated path under the control of the control center, and the imaging device scans and refreshes the image of the stockpile bin after each grabbing operation, and the imaging device scans and refreshes the image of the unloading bin after each stacking operation.
[0036] Mode selection includes automatic selection and manual selection; the automatic selection logic is: when the height is less than the stockpile layer height, select the shutdown mode; when the height is in the energy-saving cleaning layer height range, select the energy-saving mode; when the height is in the high-speed cleaning layer height range, select the high-speed mode.
[0037] S6, calculating the path: according to the mode selected in step S5, using different algorithms to calculate the path;
[0038] The path calculation method of the energy-saving mode is as follows: 1. Determine the stacking point: according to the size of the hopper and the size of the unloading bin, preset the coordinates of several stacking points (Xt1, Yt1, Zt1)~(Xtn, Ytn, Ztn) and sort them, determine the coordinates of the first stacking point as (Xtj, Ytj, Ztj), j (1≤j≤n) is the number of current stacking; 2. Grab point selection: select from the material pile vertex D and the material pile peak point Fi, calculate the energy consumption: Wd=│xd-Xtj│×P1 / V1+│yd-Ytj│×P2 / V2, WFi=│xfi-Xtj│×P1 / V1+│yfi-Ytj│×P2 / V2, compare Wd with the size of all WFi, and select the coordinates of the material pile vertex D or the material pile peak point Fi with the minimum value as the grab point; 3. Generate a motion path: The motion path is the moving trajectory from the grab point in step 2 to the stacking point in step 1.
[0039] The path calculation method of the high-speed mode is as follows: 1. Determine the stacking point: according to the size of the hopper and the size of the unloading bin, preset the coordinates of several stacking points (Xt1, Yt1, Zt1)~(Xtn, Ytn, Ztn) and sort them, determine the coordinates of the first stacking point as (Xtj, Ytj, Ztj), j (1≤j≤n) is the number of current stacking; 2. Grab point selection: select from the material pile vertex D and the material pile peak point Fi, calculate the time: Td=│xd-Xtj│ / V1+│yd-Ytj│ / V2, TFi=│xfi-Xtj│ / V1+│yfi-Ytj│ / V2, compare Td with the size of all TFi, select the coordinates of the material pile vertex D or the material pile peak point Fi with the minimum value as the grab point; 3. Generate a motion path: the motion path is the moving trajectory from the grab point in the above step 2 to the stacking point in step 1.
[0040] S7. After the path calculation is completed, the grab bucket is controlled to move and release the material according to the calculation results.
Claims
1. A control method for an intelligent grab crane control system based on material imaging, characterized in that: An intelligent grab crane control system based on material imaging is adopted, and the control system includes: a stacking bin, a discharge bin, an intelligent grab, an imaging device and a control center; a feed channel and a discharge gate are arranged above the stacking bin, and a plurality of vertically arranged height baselines are arranged on the side of the stacking bin, wherein the topmost height baseline is the bin top line, and the height baseline is provided with a reflective surface, and the bin top line protrudes inward from the side of the stacking bin to form a top line boss, and the feed channel and the discharge gate are arranged above the bin top line; the intelligent grab includes a large car for controlling the horizontal movement of the grab, a small car for controlling the longitudinal movement of the grab, a crane for controlling the lifting of the grab, and a material pile imaging; the intelligent grab obtains the image data of the stacking bin and the discharge bin in real time through the imaging device, and moves under the moving path given by the control center; the imaging device includes a height line identifier and a laser scanning device; the specific implementation steps include: S1. Establish a coordinate system and set a grab boundary and a stacking boundary. The grab boundary is the stacking area of the stacking bin, and the stacking boundary is the stacking area of the unloading bin; S2. Material stacking bin imaging: After the material is discharged from the feeding channel and behind the discharge gate, the grid graphic data of the material stack in the material stacking bin is obtained by scanning with an imaging device. The coordinates (x, y, z) are recorded for each grid point, where x is the horizontal axis distance, y is the vertical axis distance, and z is the height data; S3, extract the top and peak coordinates of the pile: extract the position coordinates (xd, yd, zd) of the pile vertex D according to the grid data, where zd is the height data of the pile vertex; select the coordinates (xfi, yfi, zfi) of several pile peak points Fi according to the grid data and the vertex height, where 0.9*zd≤zfi≤zd, and i is a natural number; S4. Material pile stratification: stratify from bottom to top in the depth direction of the material pile bin, the bottom layer is the material pile layer, the middle layer is the energy-saving cleaning layer, and the top layer is the high-speed cleaning layer; S5, mode selection: select the operation mode according to the command of the control center, the operation modes include: stop mode, energy-saving mode and high-speed mode. In the stop mode, the trolley, car and crane are not working, and the imaging device scans and refreshes the image of the stacking bin at a set interval; in the energy-saving mode and high-speed mode, the trolley, car and crane move along the calculated path under the control of the control center, and the imaging device scans and refreshes the image of the stacking bin after each grabbing operation, and the imaging device scans and refreshes the image of the unloading bin after each stacking operation; S6, calculating the path: according to the mode selected in step S5, using different algorithms to calculate the path; S7. After the path calculation is completed, the grab is controlled to move and release the material according to the calculation results.
2. The control method of the intelligent grab crane control system based on material imaging according to claim 1 is characterized in that: The specific steps of imaging in step S2 include:
1. Image forming: using a laser scanning device to obtain a material pile top curved surface image including a silo top line image, and obtaining height data of the material pile top curved surface through a height line identifier; 2. Data gridding: in a data processing center, images outside the boundary are eliminated, and the remaining material pile top curved surface images are gridded, and position coordinate data is recorded for each grid to obtain basic material pile grid data A; 3. After a period of time T, repeating steps S3-S4 to obtain verification material pile grid data B, comparing the basic material pile grid data A with the verification material pile grid data B, and calculating the similarity P; 4. If the similarity P is greater than or equal to a set value Px, the verification is passed; if the similarity P is less than the set value Px, the verification fails, the basic material pile grid data A is deleted, and the verification material pile grid data B is written into the basic material pile grid data A, and step S5 is repeated to obtain new verification material pile grid data B, and compare again until the verification is passed; 5. After the verification is passed, the basic material pile grid data A and the verification material pile grid data B are superimposed to obtain the final grid data C.
3. The control method of the intelligent grab crane control system based on material imaging according to claim 2 is characterized in that: The specific steps of the image gridding are as follows: ① the X-axis and the Y-axis are equally divided by a distance L to form a plurality of grids, each grid recording data (xi, yi, zi), wherein (xi, yi) represents the grid position of the X-axis and the Y-axis, and zi represents the height of the pile in the grid; ② the height line identifier identifies a height baseline parallel line group graphic with the top as the silo top line; the top surface image of the pile obtained by scanning with the laser scanning device includes the silo top line image; the two groups of images are fitted with the silo top line as the reference to obtain a grid map; ③ the height baseline spacing is a known constant, so the height data zi corresponding to each (xi, yi) coordinate is calculated by the surface graphic with the height baseline (31) as the ruler, and written into the grid recording data (xi, yi, zi).
4. The control method of the intelligent grab crane control system based on material imaging according to claim 3 is characterized in that: The steps for calculating the similarity P are as follows: ① Calculate the difference between ziA and ziB at the same position of each (xi, yi) coordinate in the basic stockpile grid data A and the verification stockpile grid data B; ② Record the number of grids n whose difference is less than or equal to a, and record the number of grids m whose difference is greater than a, where a is the set accuracy parameter; ③Similarity P=n / (n+m).
5. The control method of the intelligent grab crane control system based on material imaging according to claim 4 is characterized in that: The data of each grid point of the final grid data C is (xi, yi, ziC), and the data superposition processing algorithm is ziC=(ziA+ziB) / 2, where ziA and ziB are the height values of the stockpile at the same position with the coordinates (xi, yi) in the basic stockpile grid data A and the verification stockpile grid data B.
6. The control method of the intelligent grab crane control system based on material imaging according to claim 1 is characterized in that: The path calculation method of the energy-saving mode is as follows:
1. Determine the stacking point: according to the size of the hopper and the size of the unloading bin, preset the coordinates of several stacking points (Xt1, Yt1, Zt1)~(Xtn, Ytn, Ztn) and sort them, determine the coordinates of the first stacking point as (Xtj, Ytj, Ztj), j (1≤j≤n) is the number of current stacking; 2. Grab point selection: select from the material pile vertex D and the material pile peak point Fi, calculate the energy consumption: Wd=│xd-Xtj│×P1 / V1+│yd-Ytj│×P2 / V2, WFi=│xfi-Xtj│×P1 / V1+│yfi-Ytj│×P2 / V2, compare Wd with the size of all WFi, and select the coordinates of the material pile vertex D or the material pile peak point Fi with the minimum value as the grab point; 3. Generate a motion path: The motion path is the moving trajectory from the grab point in step 2 to the stacking point in step 1.
7. The control method of the intelligent grab crane control system based on material imaging according to claim 6 is characterized in that: The path calculation method of the high-speed mode is as follows:
1. Determine the stacking point: according to the size of the hopper and the size of the unloading bin, preset the coordinates of several stacking points (Xt1, Yt1, Zt1)~(Xtn, Ytn, Ztn) and sort them, determine the coordinates of the first stacking point as (Xtj, Ytj, Ztj), j (1≤j≤n) is the number of current stacking; 2. Grab point selection: select from the material pile vertex D and the material pile peak point Fi, calculate the time: Td=│xd-Xtj│ / V1+│yd-Ytj│ / V2, TFi=│xfi-Xtj│ / V1+│yfi-Ytj│ / V2, compare Td with the size of all TFi, select the coordinates of the material pile vertex D or the material pile peak point Fi with the minimum value as the grab point; 3. Generate a motion path: the motion path is the moving trajectory from the grab point in the above step 2 to the stacking point in step 1.
8. The control method of the intelligent grab crane control system based on material imaging according to claim 1 is characterized in that: Mode selection includes automatic selection and manual selection; the automatic selection logic is: when the height is less than the stockpile layer height, select the shutdown mode; when the height is in the energy-saving cleaning layer height range, select the energy-saving mode; when the height is in the high-speed cleaning layer height range, select the high-speed mode.