A wind grille assembly for a rapid cooling section of a tempered glass processing equipment and its installation method
By designing air grating components in tempered glass processing equipment, using structures such as air nozzle sheet metal, side sealing plate and air guide sheet metal, the problem of difficulty in accurately adjusting the flatness and spacing of air grating in the quench section is improved, and the tempered glass is Pass rate and stability.
Patent Information
- Application Number
- CN202011026423.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-09-25
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2040-09-25
AI Technical Summary
The flatness and air nozzle spacing of the quench section of traditional tempered glass processing equipment are difficult to accurately adjust, resulting in a low pass rate of tempered glass.
Design a wind grid assembly including air nozzle sheet metal, side sealing plate, air guide sheet metal and suspension mounting plate. The combined structure of installation grooves, pads, tension rods and sealant ensures air grid plane and air Consistency and accuracy of mouth spacing.
The pass rate of tempered glass is improved, the number of post-adjustment and maintenance is reduced, and the stability of the wind grille is enhanced.
Smart Images

Figure CN112028464B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of tempered glass processing equipment, and in particular relates to a quenching section wind grid component of tempered glass processing equipment and an installation method thereof. Background Art
[0002] In the process of implementing the present invention, the inventors found that the prior art has at least the following problems:
[0003] The most critical workstation for making tempered glass is the quenching section. The flatness of the bottom surface of the upper and lower air grilles in the quenching section, the spacing between the upper and lower air nozzles, and the concentricity of the upper and lower air outlets are very important. Traditional air grilles are mainly welded by sheet metal, and the manufacturing process is similar. Such a manufacturing process cannot accurately make the above-mentioned key points no matter how easy the structure is to adjust. The welding deformation of the sheet metal means that the subsequent installation adjustment cannot meet the requirements of dimensional accuracy, so it is difficult to break through the qualified rate of tempered glass. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a quenching section blast grille assembly of tempered glass processing equipment and an installation method thereof, which can ensure the flatness of the blast grille and the distance between two blast nozzles and improve the qualified rate of tempered glass.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a wind grid assembly of the rapid cooling section of a tempered glass processing equipment, comprising:
[0006] A first component, the first component comprises two air nozzle sheet metals and two side sealing plates, the two air nozzle sheet metals are connected by a first cushion block; the two side sealing plates respectively seal two sides of the air nozzle sheet metal connector; the lower end of the air nozzle sheet metal connector is the air nozzle;
[0007] An assembly tool, on which a series of mounting grooves are provided, the lower end of the first component is adapted to the mounting grooves, and the air nozzle of the first component is fitted to the bottom surface of the mounting grooves;
[0008] A second cushion block, adjacent first components are connected by the second cushion block;
[0009] End plates, arranged at both ends of the first component, the ends connecting a series of ends of the first components;
[0010] a top plate connecting the upper portions of the series of first assemblies;
[0011] The wind barrel is installed on the top plate.
[0012] It also has an air guide sheet metal, the cross-section of which is "V" shaped. The air guide sheet metal is arranged between adjacent first components. The air guide sheet metal is located at the upper end of the first component, and the two sides of the air guide sheet metal respectively guide the wind to the air inlet at the upper end of the first components on both sides.
[0013] Ten first pads are evenly arranged between the two air nozzle sheet metals, and both sides of the air nozzle sheet metal connector are connected to the side sealing plates by screws, and no screws are arranged on the upper and lower ends of the air nozzle sheet metal connector.
[0014] The top plate is provided with a series of notches which cooperate with the top of the first component.
[0015] The second cushion block is provided with a tension rod, which passes through the second cushion block and locks the adjacent first component.
[0016] A windshield sheet metal is also provided, wherein the windshield sheet metal is arranged between adjacent first components and connected to the upper ends of the sides of the adjacent first components.
[0017] A suspension mounting plate is also provided, the suspension mounting plate is installed on the top plate, and a suspension bracket is provided and installed on the suspension mounting plate.
[0018] The upper end of the side sealing plate is provided with an air guiding angle.
[0019] A method for installing the wind grille assembly of the quenching section of the tempered glass processing equipment mentioned above includes the following corrections:
[0020] 1) Attach the first pad to the nozzle sheet metal, then take another nozzle sheet metal and connect it to the nozzle sheet metal, tighten the two nozzle sheet metals with screws, and do not use screws on the lower part of the nozzle sheet metal to ensure that the spacing is consistent with the inner width of the nozzle;
[0021] 2) Lock the two side sealing plates on the installed nozzle sheet metal, and adjust and calibrate the flatness of both sides of the nozzle sheet metal and the side sealing plates, as well as the verticality of the end face and the top;
[0022] 3) Place the seven groups of first components into the installation slots of the processed assembly tooling in sequence, with the bottom surface of the nozzle close to the assembly plane of the tooling to ensure the overall flatness and the consistency of the spacing between adjacent first components; place the second pad between adjacent first components, and use a tension rod to penetrate the whole and then lock it to prevent the first components from being tilted during installation;
[0023] 4) The two side end plates are glued and locked on the two side sealing plates. After this process, the 7 groups of first components form an integral component; then the top plate is embedded in the top of the integral component, the flatness is calibrated and the fit is ensured, and the top plate and the integral component are welded and sealed;
[0024] 5) Finally, install the suspension mounting plate, wind guide sheet metal, wind barrel, suspension bracket, and wind shield sheet metal in sequence.
[0025] One of the above technical solutions has the following advantages or beneficial effects: it can ensure the flatness of the wind grille and the distance between each wind nozzle; and improve the qualified rate of tempered glass. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a structural schematic diagram of the wind grille assembly of the rapid cooling section of the tempered glass processing equipment provided in an embodiment of the present invention;
[0027] Figure 2 for Figure 1 A schematic diagram of the structure of the wind grid assembly of the quenching section of the tempered glass processing equipment;
[0028] Figure 3 for Figure 1 A schematic structural diagram of a side sealing plate of a quenching section air grille assembly of a tempered glass processing equipment;
[0029] The marks in the above figures are: 1. Side sealing plate, 2. Wind barrel, 3. Suspension bracket, 4. Suspension mounting plate, 5. Top plate, 6. Wind nozzle sheet metal, 7. Wind shield sheet metal, 8. Wind nozzle, 9. Assembly tooling, 10. End plate, 11. First cushion block, 12. Second cushion block, 13. Tension rod, 14. Wind guide sheet metal. DETAILED DESCRIPTION
[0030] In order to make the objectives, technical solutions and advantages of the present invention more clear, the embodiments of the present invention will be further described in detail below with reference to the accompanying drawings.
[0031] See also Figure 1-3 , a wind grille assembly of a quenching section of a tempered glass processing equipment, comprising:
[0032] The first component includes two air nozzle sheet metals and two side sealing plates, the two air nozzle sheet metals are connected by a first cushion block; the two side sealing plates respectively seal the two sides of the air nozzle sheet metal connector; the lower end of the air nozzle sheet metal connector is the air nozzle;
[0033] An assembly tool is provided with a series of mounting grooves, the lower end of the first component is adapted to the mounting groove, and the air nozzle of the first component is fitted to the bottom surface of the mounting groove;
[0034] A second cushion block, adjacent first components are connected by the second cushion block;
[0035] End plates, arranged at both ends of the first component, with ends connected to ends of a series of first components;
[0036] a top plate connecting the upper portions of the series of first assemblies;
[0037] Wind barrel, installed on the top plate.
[0038] It also has an air guide sheet metal, the cross-section of which is "V" shaped. The air guide sheet metal is arranged between adjacent first components, the air guide sheet metal is located at the upper end of the first component, and the two sides of the air guide sheet metal respectively guide the wind to the air inlet at the upper end of the first components on both sides.
[0039] Ten first pads are evenly arranged between the two air nozzle sheet metals. Both sides of the air nozzle sheet metal connector are connected to the side sealing plates through screws, and no screws are arranged on the upper and lower ends of the air nozzle sheet metal connector.
[0040] The top plate is provided with a series of notches which cooperate with the top of the first component.
[0041] A tension rod is provided on the second cushion block, and the tension rod passes through the second cushion block and locks the adjacent first component.
[0042] The invention also comprises a windshield sheet metal, which is arranged between adjacent first components and connected to the upper end of the side edge of the adjacent first components. The invention also comprises a suspension mounting plate, which is mounted on the top plate and is provided with a suspension bracket mounted on the suspension mounting plate. The upper end of the side sealing plate is provided with a wind guide angle.
[0043] The sealing plates on both sides are important components. The precision of their processing determines the various precision indicators of the formed wind grille. We first take a piece of material and grind it to the expected thickness, then cut it into shape by wire cutting, and finally process the remaining processes in the machining center. In this way, the flatness, installation hole position and verticality of the sealing plates on both sides are very accurate, and the head bevel plays a role in guiding the wind (such as Figure 3 As shown). Use super glue to adhere the processed equal-thickness first pad to the nozzle sheet metal, align the holes, a total of 10 pieces, then take another nozzle sheet metal and install it with the nozzle using blind rivets to form component a, tighten the two nozzle sheet metals with screws, and do not use screws for the two holes in the middle of the lower part to ensure that the spacing is consistent with the inner width of the nozzle; lock the two side sealing plates on the installed component a, here it is necessary to adjust and calibrate the flatness of both sides and the verticality of the end face and the top to form component b; then put the 7 groups of components b into the processed specific assembly tooling slots in turn, with the bottom surface of the nozzle close to the tooling plane to ensure the overall flatness and the verticality of the two components To ensure the consistency of spacing, two second pads are placed between the middle positions of the lower parts of each two groups of components, and the tension rods are used to penetrate the whole and then locked to prevent the components from being tilted during installation; the end plates on both sides are glued and locked on the sealing plates on both sides. After this process, 7 groups of components b form an integral component c; then the top plate is embedded in the top of component c, the surface is calibrated and the fit is ensured, and 7 notches are processed on the top plate; to prevent the hidden danger of air leakage, the top plate and component C are welded and sealed, because welding only at the top of the air nozzle sheet metal will not cause welding deformation to the whole, and finally the suspension installation plate, air guide sheet metal, air barrel, suspension bracket, and wind shield sheet metal are installed in sequence. The wind shield sheet metal is installed on both sides to form a V shape, which not only guides the hot air blown out but also discharges broken glass; the air guide sheet metal is to avoid the wind resistance formed by the wind blown into the air barrel blowing onto the top plate, so that the wind can be completely blown into the air nozzle; all connection installation places are sealed with glue before installation.
[0044] In this way, a total of 8 groups of components are installed, which are then spliced on the upper and lower suspension beams to form upper and lower air grille components, which are installed on the frame as a whole. The air outlets of the upper and lower air grilles are adjusted to correspond to each other through the designed three-way adjustment structure, and the flatness of the upper and lower air grilles and the distance between the two air nozzles can be guaranteed; the overall quenching section structure is not described here. The newly designed air grille structure increases the stability and qualification rate of tempered glass and reduces the number of subsequent adjustments and maintenance.
[0045] By adopting the above structure, the flatness of the wind grid and the distance between two wind nozzles can be guaranteed, and the qualified rate of tempered glass can be improved.
[0046] The present invention is described above by way of example in conjunction with the accompanying drawings. It is obvious that the specific implementation of the present invention is not limited to the above-mentioned method. As long as various non-substantial improvements are made using the method concept and technical solution of the present invention, or the concept and technical solution of the present invention are directly applied to other occasions without improvement, they are all within the protection scope of the present invention.
Claims
1. A method for installing a wind grille assembly of a quenching section of a tempered glass processing equipment, characterized in that: The quench section air grille assembly has: A first component, the first component comprises two air nozzle sheet metals and two side sealing plates, the two air nozzle sheet metals are connected by a first cushion block; the two side sealing plates respectively seal two sides of the air nozzle sheet metal connector; the lower end of the air nozzle sheet metal connector is the air nozzle; An assembly tool, on which a series of mounting grooves are provided, the lower end of the first component is adapted to the mounting grooves, and the air nozzle of the first component is fitted to the bottom surface of the mounting grooves; A second cushion block, adjacent first components are connected by the second cushion block; End plates, arranged at both ends of the first components, the end plates connecting ends of a series of first components; a top plate connecting the upper portions of the series of first assemblies; A wind barrel, mounted on the top plate; Ten first cushion blocks are evenly arranged between the two air nozzle sheet metals, and both sides of the air nozzle sheet metal connector are connected to the side sealing plates by screws, and no screws are arranged on the upper and lower ends of the air nozzle sheet metal connector; The top plate is provided with a series of notches, the notches cooperating with the top of the first component; It also has an air guide sheet metal, the cross section of which is "V" shaped, and the air guide sheet metal is arranged between adjacent first components, the air guide sheet metal is located at the upper end of the first component, and the two sides of the air guide sheet metal respectively guide the wind to the air inlets at the upper ends of the first components on both sides; The second cushion block is provided with a tension rod, which passes through the second cushion block and locks the adjacent first component; A windshield sheet metal is also provided, wherein the windshield sheet metal is arranged between adjacent first components and connected to the upper ends of the sides of the adjacent first components; The installation method of the quench section air grille assembly includes the following steps: Glue the first gasket to the nozzle sheet metal, then take another nozzle sheet metal and connect it to the nozzle sheet metal, tighten the two nozzle sheet metals with screws, and do not use screws on the lower part of the nozzle sheet metal to ensure that the spacing is consistent with the inner width of the nozzle; Lock the two side sealing plates onto the installed nozzle sheet metal, and adjust and calibrate the flatness of both sides of the nozzle sheet metal and the side sealing plates, as well as the verticality of the end face and the top; Place the seven groups of first components into the installation slots of the processed assembly tooling in sequence, with the bottom surface of the air nozzle close to the assembly plane of the assembly tooling to ensure the overall flatness and the consistency of the spacing between adjacent first components; place the second pad between adjacent first components, and use a tension rod to penetrate the whole and then lock it to prevent the first components from being tilted during installation; The end plates on both sides are glued and locked on the sealing plates on both sides. After this process, the 7 groups of first components form an integral component. Then the top plate is embedded in the top of the integral component, the flatness is calibrated and the fit is ensured, and the top plate and the integral component are welded and sealed. Finally, install the suspension mounting plate, wind guide sheet metal, wind barrel, suspension bracket, and wind shield sheet metal in sequence.
2. The method for installing the wind grille assembly of the quenching section of the tempered glass processing equipment according to claim 1, characterized in that: A suspension mounting plate is also provided, the suspension mounting plate is installed on the top plate, and a suspension bracket is provided and installed on the suspension mounting plate.
3. The method for installing the wind grille assembly of the quenching section of the tempered glass processing equipment according to claim 2, characterized in that: The upper end of the side sealing plate is provided with an air guiding angle.