Reinforced concrete wall footing node reinforcement structure and its construction method
By arranging prefabricated reinforced concrete components and connectors between the outer tank wall of the LNG storage tank and the cap to form a space to be poured, the load is dispersed and the steel structure and concrete are combined to solve the problem of poor stress at the wall foot joints and improve the bearing capacity. and construction efficiency.
Patent Information
- Application Number
- CN202011277962.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2020-10-22
- Filing Date
- 2020-11-16
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2040-11-16
AI Technical Summary
The external tank wall foot joints of large LNG storage tanks bear huge loads, which are prone to stress concentration and pose safety risks.
Prefabricated reinforced concrete components are used, and the angle design of the wall and base connectors is used to form a space to be poured to disperse the load. The combination of the steel structure and concrete improves the stress state of the wall foot nodes.
It effectively strengthens the bearing capacity of wall foot nodes, reduces stress concentration, improves structural reliability and construction efficiency, and reduces construction difficulty.
Smart Images

Figure CN112227535B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a reinforced concrete wall foot node reinforcement structure and a construction method thereof, belonging to the technical field of reinforced concrete structures. Background Art
[0002] At present, for general large-scale LNG storage tanks, especially LNG concrete storage tanks of 300,000 tons and above, the total load borne at the foot node of the outer tank wall is relatively large due to the high pressure inside the tank during use and the outer tank is easily affected by wind and bears a large wind load. At the same time, since the outer tank wall and the pedestal are at right angles, stress concentration is easily generated at the foot node of the outer tank wall at the lower end, which leads to damage at the foot node of the outer tank wall, posing a safety hazard. Summary of the invention
[0003] The purpose of the present invention is to provide a reinforced concrete wall foot node reinforcement structure and a construction method thereof, so as to solve the technical problems in the related art that the reinforced concrete wall foot node is in a poor stress state and is easily damaged.
[0004] The reinforced concrete wall foot node reinforcement structure provided by the present invention is arranged between the wall and the base, and comprises:
[0005] A prefabricated reinforced concrete component, comprising a first connection surface and a second connection surface, wherein an angle is formed between a first end of the first connection surface and a first end of the second connection surface, and the angle is the same as an angle between the wall and the base;
[0006] At least one group of wall connectors, wherein there is a spacing between the wall connectors in a group; one side of the wall connector is pre-embedded and connected to the first connection surface of the prefabricated reinforced concrete component, and the other side of the wall connector is connected to the wall embedded part;
[0007] At least one group of wall embedded parts is connected to the wall connecting parts in a one-to-one correspondence; one side of the wall embedded parts is embedded and connected to the wall, and the other side of the wall embedded parts is connected to the wall connecting parts;
[0008] At least one group of base connectors, wherein there is a spacing between the base connectors in one group, and the spacing is the same as the spacing between the wall connectors in one group; one side of the base connector is pre-embedded and connected to the second connection surface of the prefabricated reinforced concrete component, and the other side of the base connector is connected to the base embedded part;
[0009] At least one group of base embedded parts connected to the base connecting parts in a one-to-one correspondence; one side of the base embedded parts is embedded and connected to the base, and the other side of the base embedded parts is connected to the base connecting parts;
[0010] A group of the wall connecting parts, a group of the wall embedded parts, a group of the base connecting parts, a group of the base embedded parts, the wall, the base, the first connecting surface and the second connecting surface of the prefabricated reinforced concrete components together enclose a space to be poured, and the space to be poured is used for pouring concrete.
[0011] Furthermore, an inclined transition surface is provided between the second end of the first connecting surface and the second end of the second connecting surface.
[0012] Furthermore, the angle between the first connecting surface and the second connecting surface is a right angle.
[0013] Furthermore, a plurality of the prefabricated reinforced concrete components are spaced apart between the wall and the base. Since the outer tank wall of the LNG storage tank is circular and is subjected to the same forces in all directions, a plurality of prefabricated reinforced concrete components can be distributed at equal intervals along the outer tank wall of the LNG storage tank. In order to save costs and construction time as much as possible while ensuring that the foot nodes of the outer tank wall of the LNG storage tank are effectively strengthened, it is recommended that 12 to 16 groups of prefabricated reinforced concrete components be arranged in a single tank.
[0014] Furthermore, each set of the wall connectors comprises a pair of connecting steel plates of the same shape and arranged opposite to each other, and the distance between the two connecting steel plates is usually 1 / 4 to 1 / 3 of the length of the connecting steel plates;
[0015] The length of the wall connector is preferably not less than the height of the first connecting surface, and the width is preferably set to 30-60 cm, of which about 10 cm is preferably embedded in the prefabricated reinforced concrete component, and the thickness is preferably set to 3-6 cm.
[0016] Furthermore, each group of the wall embedded parts includes a pair of connecting steel plates of the same shape and arranged relatively to each other; the length of the wall embedded parts is not less than the length of the wall connecting parts, and is adjusted according to the length of the wall connecting parts and the situation of the base embedded parts; the width is preferably set to 30 to 60 cm, of which about 10 cm is embedded in the prefabricated reinforced concrete components; the thickness is the same as the thickness of the wall connecting parts.
[0017] Furthermore, each group of the base connectors includes a pair of connecting steel plates of the same shape and arranged relatively to each other; the length of the base connector is preferably not less than the length of the second connecting surface; the width and thickness are the same as those of the wall connector, and it is preferably embedded in the prefabricated reinforced concrete component by about 10 cm.
[0018] Furthermore, each group of the base embedded parts includes a pair of connecting steel plates of the same shape and arranged relatively to each other; the length of the base embedded parts is not less than the length of the base connecting parts, and is adjusted according to the length of the base connecting parts and the situation of the wall embedded parts; the width and thickness are the same as those of the base connecting parts, and are preferably embedded in the LNG storage tank base for about 10 cm.
[0019] Furthermore, the connection between the wall connecting piece and the wall embedded piece, and the connection between the base connecting piece and the base embedded piece are both butt-jointed.
[0020] Furthermore, the connection between the wall connector and the wall embedded part is welding or connected via an intermediate connector, and the connection between the base connector and the base embedded part is welding or connected via an intermediate connector;
[0021] The intermediate connection piece is respectively welded, riveted or bolted to the wall connection piece and the wall embedded piece, so that the wall connection piece and the wall embedded piece are butted against each other;
[0022] The intermediate connecting member is respectively welded, riveted or bolted to the base connecting member and the base embedded member, so that the base connecting member and the base embedded member are butted against each other.
[0023] Furthermore, the connection between the wall connecting piece and the wall embedded piece, and the connection between the base connecting piece and the base embedded piece are both overlapped.
[0024] Furthermore, the connection between the wall connector and the wall embedded part is welding, riveting or bolting;
[0025] The connection between the base connector and the base embedded part is welding, riveting or bolting.
[0026] Furthermore, the correspondingly connected wall connectors and the wall embedded parts form an intersection at the junction of the wall and the base; the correspondingly connected base embedded parts and the base connectors form an intersection at the junction of the first connecting surface and the second connecting surface.
[0027] The present invention also provides a construction method of the reinforced concrete wall foot node reinforcement structure, comprising the following steps:
[0028] Pre-embed and connect one side of the wall connector to the first connection surface of the prefabricated reinforced concrete component;
[0029] Pre-embed and connect one side of the base connector to the second connection surface of the prefabricated reinforced concrete component;
[0030] Embed one side of the wall embedded part and connect it to the wall;
[0031] Embed one side of the base embedded part and connect it to the base;
[0032] Connecting the wall embedded parts to the wall connecting parts in a one-to-one correspondence;
[0033] Connecting the base embedded parts to the base connecting parts in a one-to-one correspondence;
[0034] Concrete is poured in situ in the space to be poured, and the space to be poured is surrounded by a group of wall connectors, a group of wall embedded parts, a group of base connectors, a group of base embedded parts, the wall, the base, the first connecting surface and the second connecting surface of the prefabricated reinforced concrete component.
[0035] The present invention has the following beneficial effects:
[0036] The reinforced concrete wall foot node reinforcement structure of the present invention disperses the load on the wall foot node by adding an additional supporting structure, and at the same time changes the shape of the wall foot to reduce the stress concentration at the wall foot node, so that the reinforced concrete wall foot node can be effectively strengthened. Moreover, the connection between the wall foot node reinforcement structure and the wall and the base adopts the form of combining steel structure with concrete, so it has better stress resistance, is not easy to be damaged, and has high reliability.
[0037] The construction method of the reinforced concrete wall foot node reinforcement structure of the present invention has a simple structure of component elements, which are easy to manufacture, and adopts assembled installation, so that the splicing process of prefabricated reinforced concrete components with walls and bases is fast and simple. The reinforced concrete wall foot node reinforcement structure can be carried out simultaneously with the construction of walls and bases, without the need to support formwork and cast in batches. Therefore, the construction efficiency can be improved, the project period can be shortened, and the casting difficulty can be reduced under the premise of ensuring the connection quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 is a position diagram of the reinforced concrete wall foot node reinforcement structure of Example 1 of the present invention;
[0039] Figure 2 is a front view of a reinforced concrete wall foot node reinforcement structure according to Embodiment 1 of the present invention;
[0040] Figure 3 is a top view of a reinforced concrete wall foot node reinforcement structure according to Embodiment 1 of the present invention;
[0041] Figure 4 is a side view of a reinforced concrete wall foot node reinforcement structure according to Embodiment 1 of the present invention;
[0042] Figure 5 is a front view of a reinforced concrete wall foot node reinforcement structure according to Embodiment 2 of the present invention;
[0043] Figure 6 is a top view of a reinforced concrete wall foot node reinforcement structure according to Embodiment 2 of the present invention;
[0044] Figure 7 It is a side view of the reinforced concrete wall foot node reinforcement structure of Example 2 of the present invention.
[0045] The marks in the figure are as follows:
[0046] 1. Outer tank wall of LNG storage tank; 2. LNG storage tank pedestal; 3. Prefabricated reinforced concrete components; 4. Wall connectors; 5. Wall embedded parts; 6. Base connectors; 7. Base embedded parts; 8. Intermediate connectors; 9. Bolts; 10. Space to be poured. DETAILED DESCRIPTION
[0047] Unless otherwise specified, the experimental methods used in the following examples are conventional methods.
[0048] Unless otherwise specified, the materials and reagents used in the following examples can be obtained from commercial sources.
[0049] Embodiment 1,
[0050] like Figure 1 As shown, the reinforced concrete wall foot node reinforcement structure provided by the present invention is applied to the outer tank of the LNG storage tank and is arranged between the outer tank wall 1 of the LNG storage tank and the LNG storage tank base 2. It can improve the problems of poor stress state and easy damage at the wall foot node of the traditional LNG concrete storage tank, and the use of assembled installation can improve construction efficiency and reduce construction difficulty.
[0051] like Figures 2 to 4 As shown, a reinforced concrete wall foot node reinforcement structure provided by the present invention mainly includes a prefabricated reinforced concrete component 3, at least one group of wall connectors 4, at least one group of wall embedded parts 5, at least one group of base connectors 6, and at least one group of base embedded parts 7.
[0052] The prefabricated reinforced concrete component 3 is a prefabricated reinforced concrete structure in a polyhedral shape, comprising a first connecting surface and a second connecting surface, wherein the first connecting surface is used to be arranged opposite to the outer tank wall 1 of the LNG storage tank, and the second connecting surface is used to be arranged opposite to the LNG storage tank base 2. Since the angle between the outer tank wall 1 of the LNG storage tank and the LNG storage tank base 2 is a right angle, the angle between the first end of the first connecting surface and the first end of the second connecting surface is also correspondingly set to a right angle. The height of the first connecting surface is usually 1 / 8h to 1 / 4h, where h is the height of the outer tank wall 1 of the LNG storage tank; the length of the second connecting surface is usually 1 / 4 to 1 / 2 of the height of the first connecting surface, which can be adjusted according to the specific situation of the LNG storage tank base 2.
[0053] Multiple prefabricated reinforced concrete components 3 can be arranged at intervals. Since the outer tank wall 1 of the LNG storage tank is circular and subjected to the same forces in all directions, multiple prefabricated reinforced concrete components 3 can be distributed at equal intervals along the outer tank wall 1 of the LNG storage tank. In order to save costs and construction time as much as possible while ensuring that the wall foot nodes of the outer tank wall 1 of the LNG storage tank are effectively strengthened, it is recommended that 12 to 16 groups can be arranged in a single tank.
[0054] Each prefabricated reinforced concrete component 3 may be provided with one set of wall connectors 4 and one set of base connectors 6, or may be provided with multiple sets of wall connectors 4 and multiple sets of base connectors 6 of the same number.
[0055] A set of wall connectors 4 includes a pair of connecting steel plates of the same shape and arranged oppositely, and the spacing between the two connecting steel plates is usually 1 / 4 to 1 / 3 of the length of the connecting steel plates. One side of the wall connector 4 is welded and fixed to the steel bars of the precast reinforced concrete component 3, and is partially cast in the first connecting surface of the reinforced concrete component 3 when the reinforced concrete component 3 is precast; the other side of the wall connector 4 is used to connect with the wall embedded parts 5 in a one-to-one correspondence. The length of the wall connector 4 is preferably not less than the height of the first connecting surface; the width is preferably set to 30 to 60 cm, of which about 10 cm is embedded in the precast reinforced concrete component 3; the thickness is preferably set to 3 to 6 cm.
[0056] A set of wall embedded parts 5 includes a pair of connecting steel plates of the same shape and arranged oppositely, and the spacing between the two connecting steel plates is the same as the spacing between the two connecting steel plates of the wall connector 4. One side of the wall embedded part 5 is welded and fixed to the steel bars of the outer tank wall 1 of the LNG storage tank, and is cast on site so that its part is embedded in the part of the outer tank wall 1 of the LNG storage tank relative to the first connection surface; the other side of the wall embedded part 5 is used to connect with the wall connector 4 in a one-to-one correspondence. The length of the wall embedded part 5 is not less than the length of the wall connector 4, and is adjusted according to the length of the wall connector 4 and the situation of the base embedded part 7; the width is preferably set to 30 to 60 cm, of which about 10 cm is embedded in the prefabricated reinforced concrete component 3; the thickness is the same as the thickness of the wall connector 4.
[0057] A set of base connectors 6 includes a pair of connecting steel plates of the same shape and arranged oppositely, and the spacing between the two connecting steel plates is the same as the spacing between the two connecting steel plates of the wall connector 4. The base connector 6 is welded and fixed to the steel bars of the precast reinforced concrete component 3, and is partially cast in the second connecting surface of the reinforced concrete component 3 when the reinforced concrete component 3 is precast; the other side of the base connector 6 is used to connect with the base embedded parts 7 in a one-to-one correspondence. The length of the base connector 6 is preferably not less than the length of the second connecting surface; the width and thickness are the same as those of the wall connector 4, and it is embedded in the precast reinforced concrete component 3 for about 10 cm.
[0058] A group of base embedded parts 7 includes a pair of connecting steel plates of the same shape and arranged oppositely, and the spacing between the two connecting steel plates is the same as the spacing between the two connecting steel plates of the base connector 6. One side of the base embedded part 7 is welded and fixed to the steel bars of the LNG storage tank base 2, and is cast on site so that it is partially embedded in the part of the LNG storage tank base 2 relative to the second connection surface; the other side of the base embedded part 7 is used to connect with the base connector 6 in a one-to-one correspondence. The length of the base embedded part 7 is not less than the length of the base connector 6, and is adjusted according to the length of the base connector 6 and the situation of the wall embedded part 5; the width and thickness are the same as the base connector 6, and it is embedded in the LNG storage tank base 2 for about 10 cm.
[0059] At this point, the wall connectors 4, wall embedded parts 5, base connectors 6, base embedded parts 7, as well as the LNG storage tank outer tank wall 1, the LNG storage tank base 2, and the first connection surfaces and the second connection surfaces of the prefabricated reinforced concrete components 3 of the same group together form a space to be poured 10 with an L-shaped cross-section, and the space to be poured 10 is used for pouring concrete.
[0060] Through the above-mentioned reinforcement structure, the load on the wall foot node is dispersed to the entire reinforcement structure, thereby improving the stress condition at the wall foot node and increasing the bearing capacity limit at the wall foot node. At the same time, the shape of the wall foot is changed by the above-mentioned reinforcement structure, the stress concentration at the wall foot node is reduced, and the reinforced concrete wall foot node can be effectively strengthened. Moreover, the connection between the wall foot node reinforcement structure and the wall adopts the form of a combination of steel structure and concrete, which is easy to connect, is not easily damaged by force after connection, and has high reliability.
[0061] Since the space 10 to be poured is a closed space, it should be ensured that the poured concrete will not overflow. Therefore, in actual design, the corresponding wall connectors 4 and wall embedded parts 5 are connected at the junction of the outer tank wall 1 of the LNG storage tank and the LNG storage tank base 2, and the corresponding base connectors 6 and base embedded parts 7 are also connected at the junction of the first connection surface and the second connection surface of the precast reinforced concrete component 3. In this embodiment, the two intersection lines extend obliquely from the junction of the first connection surface and the second connection surface of the precast reinforced concrete component 3 to the junction of the outer tank wall 1 of the LNG storage tank and the LNG storage tank base 2, and the wall connectors 4, the wall embedded parts 5, the base connectors 6, and the base embedded parts 7 are all prefabricated and processed into trapezoidal steel plates.
[0062] As an optional implementation, the connection between the wall connector 4 and the wall embedded part 5, and the connection between the base connector 6 and the base embedded part 7 are connected together by docking. The docking here means that the wall connector 4 and the wall embedded part 5 are in contact with the end face of the connection side (parallel to the outer tank wall 1 of the LNG storage tank), and the wall connector 4 and the wall embedded part 5 do not overlap each other; the base connector 6 and the base embedded part 7 are in contact with the end face of the connection side (parallel to the LNG storage tank base 2), and the base connector 6 and the base embedded part 7 do not overlap each other. Under the condition of the same size, the docking method provides a larger pouring space, and the concrete has a slightly stronger load-bearing capacity after pouring.
[0063] Specifically, this embodiment and its accompanying drawings provide examples of using several intermediate connectors 8 to connect the wall connector 4 with the wall embedded part 5, and to connect the base connector 6 with the base embedded part 7. Among them, taking the intermediate connector 8 connecting the wall connector 4 with the wall embedded part 5 as an example, the following is described in detail: the intermediate connector 8 can be set as a rectangular plate, located outside the wall connector 4 and the wall embedded part 5, and the intermediate connector 8 is connected to the wall connector 4 and the wall embedded part 5 respectively, so that the wall connector 4 and the wall embedded part 5 form a connection. The plate thickness of the intermediate connector 8 can be the same as that of the wall connector 4, the plate length can be 20 to 50 cm, and the plate width can be 1 / 2 to 3 / 4 of the plate length; the maximum distance between two adjacent groups of intermediate connecting plates 8 is generally 80 cm, and the number is determined by the specific project situation. There are many ways to connect the intermediate connector 8 to the wall connector 4 and the wall embedded part 5, such as welding, riveting or bolt connection, etc., as long as the intermediate connector 8 can be firmly fixed to the wall connector 4 and the wall embedded part 5, the specific connection method and the number of components should be calculated according to the actual situation of the project. Among them, the connection by bolts 9 can be matched with the preset through holes on the wall connector 4, the wall embedded part 5 and the intermediate connector 8, which is a fast and easy installation method. On this basis, the situation of the intermediate connector 8 docking the base connector 6 and the base embedded part 7 is the same as the above content, and will not be repeated here.
[0064] In addition, when the connection between the wall connector 4 and the wall embedded part 5, and the connection between the base connector 6 and the base embedded part 7 are both connected by docking, the wall connector 4 and the wall embedded part 5, and the base connector 6 and the base embedded part 7 can also be connected by welding respectively.
[0065] The construction method of the reinforced concrete wall foot node reinforcement structure of the present invention comprises the following operations:
[0066] During the process of pouring the outer tank of the LNG storage tank on site, the wall embedded parts 5 and the base embedded parts 7 are connected, and the wall embedded parts 5 and the base embedded parts 7 are respectively welded and fixed to the steel mesh of the LNG storage tank outer tank wall 1 and the LNG storage tank base 2 and poured with concrete, so that the wall embedded parts 5 are embedded and fixed in the LNG storage tank outer tank wall 1, and the base embedded parts 7 are embedded and fixed in the LNG storage tank base 2.
[0067] During the process of prefabricating the reinforced concrete component 3, the wall connector 4 and the base connector 6 are connected, and the wall connector 4 and the base connector 6 are respectively welded and fixed to the steel mesh of the first connection surface and the second connection surface of the prefabricated reinforced concrete component 3 and poured with concrete, so that the wall connector 4 is pre-embedded and fixed in the first connection surface of the prefabricated reinforced concrete component 3, and the base connector 6 is pre-embedded and fixed in the second connection surface of the prefabricated reinforced concrete component 3.
[0068] After the concrete strength of the outer tank concrete and the prefabricated reinforced concrete component 3 meets the construction standard, a lifting machine is used on site to lift the prefabricated reinforced concrete component 3 to the preset node position, so that the connection ends of the wall connector 4 and the wall embedded component 5, and the connection ends of the base connector 6 and the base embedded component 7 are in contact. The prefabricated reinforced concrete component 3 is fixed at the node position using supporting equipment such as a jack.
[0069] Each intermediate connector 8 is closely attached to the outer side of the connection between the wall connector 4 and the wall embedded part 5, the base connector 6 and the base embedded part 7, and the preset through holes on the intermediate connectors 8 are aligned with the preset through holes on the wall connector 4, the wall embedded part 5, the platform connector 6 and the platform embedded part 7. Bolts 9 are passed through the preset through holes of the intermediate connector 8 and the wall connector 4, the wall embedded part 5, the platform connector 6 and the platform embedded part 7 to fix them.
[0070] When the wall connector 4 and the wall embedded part 5, the base connector 6 and the base embedded part 7 are connected in other ways, the above operations are changed accordingly, which are all conventional technical means and will not be described in detail.
[0071] Concrete is poured into the space 10 to be poured on site. After the strength of the poured concrete meets the requirements, the jack of the supporting equipment can be removed, and the installation construction of the reinforced concrete wall foot node reinforcement structure is completed.
[0072] Through the above construction method, prefabricated installation can be adopted to make the splicing process of the reinforced structure quick and easy. The reinforced concrete wall foot node reinforcement structure can be carried out simultaneously with the construction of the LNG storage tank outer tank wall 1 and the LNG storage tank base 2, without the need to support formwork and pour in batches, ultimately improving construction efficiency, shortening the project period, and reducing the difficulty of pouring while ensuring the quality of the connection.
[0073] It should be noted that the application scenario of this embodiment is the outer tank of the LNG storage tank, and the wall embedded parts 5 and the base embedded parts 7 are respectively connected to the outer tank wall 1 of the LNG storage tank and the LNG storage tank base 2. The outer tank wall 1 of the LNG storage tank belongs to the wall, and the LNG storage tank base 2 belongs to the base; for example, the wall and the base can also be the retaining wall and the heel plate. Obviously, the reinforced concrete wall foot node reinforcement structure of this embodiment can be set between the wall and the base, which will improve the problem of poor stress state and easy damage at the foot node of the traditional reinforced concrete wall, and improve the construction efficiency and reduce the construction difficulty. In the application scenario of non-circular walls, in addition to arranging multiple prefabricated reinforced concrete components 3 at intervals, it can also be arranged as a whole with a single prefabricated reinforced concrete component 3 corresponding to each wall. At this time, each prefabricated reinforced concrete component 3 is provided with multiple groups of wall connectors 4 and multiple groups of base connectors 6 of the same number.
[0074] Moreover, the reinforced concrete wall foot node reinforcement structure of this embodiment can be set on the inside or outside of the wall in the application scenarios of other walls and bases. It can be reasonably selected according to the actual structural stress conditions without affecting the essential technical effect of this embodiment.
[0075] In addition, the angle between the first end of the first connecting surface of the precast reinforced concrete component 3 and the first end of the second connecting surface is the same as the angle between the wall and the base. In most cases, the angle between the first end of the first connecting surface of the precast reinforced concrete component 3 and the first end of the second connecting surface is a right angle.
[0076] As a preferred embodiment, there is an inclined transition surface between the second end of the first connecting surface and the second end of the second connecting surface. This shape conforms to the structural characteristic that the force is small at the top and large at the bottom, while avoiding stress concentration at right angles. It can also minimize the use of steel bars and concrete and reduce construction costs.
[0077] Embodiment 2,
[0078] like Figures 5 to 7 As shown, this embodiment shows some structural forms different from embodiment 1:
[0079] In this embodiment, as an optional implementation, the connection between the wall connector 4 and the wall embedded part 5, and the connection between the base connector 6 and the base embedded part 7 are both connected together in an overlapping manner. Overlapping here means that the wall connector 4 and the wall embedded part 5 are in contact with the surface perpendicular to the outer tank wall 1 of the LNG storage tank, and the wall connector 4 and the wall embedded part 5 are partially or completely overlapped; the base connector 6 and the base embedded part 7 are in contact with the surface perpendicular to the LNG storage tank base 2, and the base connector 6 and the base embedded part 7 are partially or completely overlapped. The overlapping method can avoid the use of intermediate connectors 8, reduce the number of components, and thus reduce processing time.
[0080] When the connection between the wall connector 4 and the wall embedded part 5, and the connection between the base connector 6 and the base embedded part 7 are both overlapped, the connection between the wall connector 4 and the wall embedded part 5 can be welded, riveted or bolted; the connection between the base connector 6 and the base embedded part 7 can also be welded, riveted or bolted.
[0081] In this embodiment, the intersection line between the wall connector 4 and the wall embedded part 5, and the intersection line between the base connector 6 and the base embedded part 7 are longitudinally extended from the intersection of the first connection surface and the second connection surface of the precast reinforced concrete component 3 rather than obliquely extended, and the wall connector 4, the wall embedded part 5, the base connector 6, and the base embedded part 7 are all prefabricated and processed into rectangular steel plates. It can be seen that as long as the correspondingly connected wall connector 4 and the wall embedded part 5 form an intersection at the intersection of the outer tank wall 1 of the LNG storage tank and the LNG storage tank base 2, and the correspondingly connected base connector 6 and the base embedded part 7 also form an intersection at the intersection of the first connection surface and the second connection surface of the precast reinforced concrete component 3, so that the space 10 to be poured is formed into a closed space where concrete can be poured, there is no strict requirement for the specific form of the two intersection lines.
[0082] From the above description, it can be seen that the above two embodiments of the present invention can achieve the following technical effects: the structure is simple and reasonable, which is easy to process and manufacture; the prefabricated reinforced concrete component 3 can be constructed simultaneously with the wall and the base, which reduces the construction time; the prefabricated reinforced concrete component 3 is fast and easy to splice and cast with the existing structure, which improves the construction efficiency and reduces the construction difficulty. At the same time, the prefabricated reinforced concrete component 3 can well strengthen the wall foot node, improve the stress condition of the wall foot node on the outer side or inner side of the reinforced concrete structure, and the connection is well stressed, not easy to be damaged, and has high reliability.
[0083] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0084] In addition, it should be noted that the use of terms such as "first" and "second" to limit components is only for the convenience of distinguishing the corresponding components. Unless otherwise stated, the above terms have no special meaning and therefore cannot be understood as limiting the scope of protection of this application.
[0085] Unless otherwise specifically stated, the relative arrangement, numerical expressions and numerical values of the parts and steps set forth in these embodiments do not limit the scope of the present application. At the same time, it should be understood that, for ease of description, the sizes of the various parts shown in the accompanying drawings are not drawn according to the actual proportional relationship. The technology, method and equipment known to those of ordinary skill in the relevant field may not be discussed in detail, but in appropriate cases, the technology, method and equipment should be considered as a part of the authorization specification. In all examples shown and discussed here, any specific value should be interpreted as being merely exemplary, rather than as a limitation. Therefore, other examples of exemplary embodiments may have different values. It should be noted that similar reference numerals and letters represent similar items in the following drawings, so that once a certain item is defined in an accompanying drawing, it does not need to be further discussed in subsequent drawings.
[0086] In the description of the present application, it should be understood that the directions or positional relationships indicated by directional words such as "front, back, up, down, left, right", "lateral, vertical, perpendicular, horizontal" and "top, bottom" are usually based on the directions or positional relationships shown in the drawings, and are only for the convenience of describing the present application and simplifying the description. Unless otherwise specified, these directional words do not indicate or imply that the device or element referred to must have a specific direction or be constructed and operated in a specific direction, and therefore cannot be understood as limiting the scope of protection of the present application; the directional words "inside and outside" refer to the inside and outside relative to the contours of each component itself.
[0087] For ease of description, spatially relative terms such as "above", "above", "on the upper surface of", "above", etc. may be used here to describe the spatial positional relationship between a device or feature and other devices or features as shown in the figure. It should be understood that spatially relative terms are intended to include different orientations of the device in use or operation in addition to the orientation described in the figure. For example, if the device in the accompanying drawings is inverted, the device described as "above other devices or structures" or "above other devices or structures" will be positioned as "below other devices or structures" or "below other devices or structures". Thus, the exemplary term "above" can include both "above" and "below". The device can also be positioned in other different ways (rotated 90 degrees or in other orientations), and the spatially relative descriptions used here are interpreted accordingly.
[0088] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A construction method for a reinforced concrete wall foot node reinforcement structure, characterized in that: The reinforced concrete wall foot node reinforcement structure is arranged between the wall and the base, and includes: A prefabricated reinforced concrete component, comprising a first connection surface and a second connection surface, wherein an angle is formed between a first end of the first connection surface and a first end of the second connection surface, and the angle is the same as an angle between the wall and the base; At least one group of wall connectors, wherein there is a spacing between the wall connectors in a group; one side of the wall connector is pre-embedded and connected to the first connection surface of the prefabricated reinforced concrete component, and the other side of the wall connector is connected to the wall embedded part; At least one group of wall embedded parts is connected to the wall connecting parts in a one-to-one correspondence; one side of the wall embedded parts is embedded and connected to the wall, and the other side of the wall embedded parts is connected to the wall connecting parts; At least one group of base connectors, wherein there is a spacing between the base connectors in one group, and the spacing is the same as the spacing between the wall connectors in one group; one side of the base connector is pre-embedded and connected to the second connection surface of the prefabricated reinforced concrete component, and the other side of the base connector is connected to the base embedded part; At least one group of base embedded parts is connected to the base connecting parts in a one-to-one correspondence; one side of the base embedded parts is embedded and connected to the base, and the other side of the base embedded parts is connected to the base connecting parts; A group of the wall connecting parts, a group of the wall embedded parts, a group of the base connecting parts, a group of the base embedded parts, the wall, the base, the first connecting surface and the second connecting surface of the prefabricated reinforced concrete component together enclose a space to be poured, and the space to be poured is used for pouring concrete; The construction method comprises the following steps: Pre-embed and connect one side of the wall connector to the first connection surface of the prefabricated reinforced concrete component; Pre-embed and connect one side of the base connector to the second connection surface of the prefabricated reinforced concrete component; Embed one side of the wall embedded part and connect it to the wall; Embed one side of the base embedded part and connect it to the base; Connecting the wall embedded parts to the wall connecting parts in a one-to-one correspondence; Connecting the base embedded parts to the base connecting parts in a one-to-one correspondence; Concrete is poured in situ in the space to be poured, and the space to be poured is surrounded by a group of wall connectors, a group of wall embedded parts, a group of base connectors, a group of base embedded parts, the wall, the base, the first connecting surface and the second connecting surface of the prefabricated reinforced concrete component.
2. The construction method according to claim 1, characterized in that: An inclined transition surface is provided between the second end of the first connecting surface and the second end of the second connecting surface.
3. The construction method according to claim 1 or 2, characterized in that: An angle between the first connecting surface and the second connecting surface is a right angle.
4. The construction method according to claim 1 or 2, characterized in that: A plurality of the prefabricated reinforced concrete components are arranged at intervals between the wall and the base.
5. The construction method according to claim 1 or 2, characterized in that: The connection between the wall connecting piece and the wall embedded piece, and the connection between the base connecting piece and the base embedded piece are both butt-jointed.
6. The construction method according to claim 5, characterized in that: The connection between the wall connector and the wall embedded part is welding or connected via an intermediate connector; the connection between the base connector and the base embedded part is welding or connected via an intermediate connector; The intermediate connection piece is respectively welded, riveted or bolted to the wall connection piece and the wall embedded piece, so that the wall connection piece and the wall embedded piece are butted against each other; The intermediate connecting member is respectively welded, riveted or bolted to the base connecting member and the base embedded member, so that the base connecting member and the base embedded member are butted against each other.
7. The construction method according to claim 1 or 2, characterized in that: The connection between the wall connecting piece and the wall embedded piece, and the connection between the base connecting piece and the base embedded piece are both overlapped.
8. The construction method according to claim 7, characterized in that: The connection between the wall connector and the embedded wall part is welding, riveting or bolting; The connection between the base connector and the base embedded part is welding, riveting or bolting.
9. The construction method according to claim 1 or 2, characterized in that: The correspondingly connected wall connectors and the wall embedded parts form an intersection at the junction of the wall and the base; The correspondingly connected base embedded parts and the base connecting parts form an intersection at the junction of the first connecting surface and the second connecting surface.