A pile foundation test loading device

By designing a pile foundation test loading device including a limiting support round block, a second limiting round plate and a hydraulic cylinder, the problems of inconvenient installation and disassembly, poor versatility and insufficient stability of the existing device are solved, and the installation of the device is realized Easy to disassemble, versatile and portable.

CN112229731BActive Publication Date: 2024-10-15CHINA NAT CHEM ENG NO 7 CONSTR
View PDF 17 Cites 0 Cited by

Patent Information

Application Number
CN202011071840.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-10-09
Publication Date
2024-10-15
Estimated Expiration
2040-10-09

AI Technical Summary

Technical Problem

The existing pile foundation test loading device is inconvenient to install and disassemble, has poor versatility, is unstable, and is inconvenient to carry.

Method used

A device including a limit support round block, a second limit round plate, a limit card holder, a limit block, a hydraulic cylinder and a pressure sensor is designed. The height and expansion degree of the support rod are adjusted through the hydraulic cylinder, and the fastening is used to adjust the height and expansion of the support rod. Knobs and hinged structures enable installation, disassembly, adjustment and fixation, adapting to pile foundations of different sizes and ground conditions.

Benefits of technology

The device is easy to install and disassemble, has strong versatility, high stability and is easy to carry, adapts to different pile foundations and ground conditions, and improves use efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112229731B_ABST
    Figure CN112229731B_ABST
Patent Text Reader

Abstract

The invention discloses a pile foundation test loading device, comprising a limit support circular block and a second limit circular plate, three first limit sockets are arranged on the limit support circular block along the circumferential direction; the three first limit sockets are respectively clamped with the first limit blocks; the first limit block is connected to the limit support rod through the first fastening knob; the limit support rod is connected to the adjusting support rod through the adjusting limit block; the second limit block is arranged at the connection between the lower end of the limit support rod and the adjusting support rod; the second limit socket is fixed to the inner wall of the second limit block; the second fastening knob is arranged on the adjusting limit block; the lower end of the adjusting support rod is fixed with a bottom limit block; the bottom limit block is connected with a hinged joint, the pile foundation test loading device is easy to install and disassemble, has strong versatility, is stable and easy to carry.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pile foundations, in particular to a pile foundation test loading device. Background Art

[0002] With the construction of high-rise buildings, bridges, towers and other buildings (structures), the combined loads on single piles from above are increasingly valued in engineering practice. Therefore, it is necessary to perform pressure tests on pile foundations, and therefore a pile foundation test loading device is needed.

[0003] However, the current pile foundation test loading device still has the problems of inconvenient installation and disassembly, poor versatility, instability and inconvenient carrying. Therefore, it is necessary to design a pile foundation test loading device that is easy to install and disassemble, has strong versatility, is stable and easy to carry. Summary of the invention

[0004] The purpose of the invention is to provide a pile foundation test loading device to solve the problems raised in the above background technology.

[0005] To achieve the above-mentioned purpose, the invention provides a pile foundation test loading device, including a limit support circular block and a second limit circular plate, three first limit clamps are arranged on the limit support circular block along the circumferential direction; the three first limit clamps are respectively clamped with the first limit blocks; the first limit block is connected to the limit support rod through a first tightening knob; the limit support rod is connected to the adjusting support rod through an adjusting limit block; a second limit block is arranged at the connection between the lower end of the limit support rod and the adjusting support rod; a second limit clamp is fixed on the inner wall of the second limit block; a second tightening knob is arranged on the adjusting limit block; a bottom limit block is fixed on the lower end of the adjusting support rod; an articulated joint is connected to the bottom limit block; a pressurized hydraulic cylinder is fixed on the limit support circular block; a limit ring sleeve is slidably connected to the pressurized hydraulic cylinder; three third limit clamps are fixed on the limit ring sleeve along the circumferential direction; the third The limit card seat is hinged to the first hinge block; a fourth tightening knob is fixed on a third limit card seat; the fourth tightening knob is threadedly connected to the limit ring sleeve; the first hinge block is connected to the telescopic end of the adjusting hydraulic cylinder; the second hinge block is fixed to the non-telescopic end of the adjusting hydraulic cylinder; the third tightening knob is arranged on the second hinge block; the second hinge block is hinged to the second limit card seat; the telescopic end of the pressurized hydraulic cylinder is connected with a threaded connector; the threaded connector is threadedly connected to the threaded connecting sleeve; the first limit circular plate is fixed with a plurality of limit sockets along the circumferential direction; the second limit circular plate is fixed with a plurality of limit guide posts; the limit guide posts pass through the limit sockets and are threadedly connected to the tightening nuts; a buffer spring is installed on the limit guide posts relative to the first limit circular plate and the second limit circular plate; a pressure sensor is arranged on the second limit circular plate.

[0006] Preferably, the second hinge block is hinged to the second limiting clamping seat via a second hinge shaft.

[0007] Preferably, a first limiting hole for the second hinge shaft to pass through is formed on the second hinge block; a second limiting hole for the second hinge shaft to pass through is formed on the second limiting socket; and the first limiting hole corresponds to the second limiting hole one by one.

[0008] Preferably, the limiting guide column is provided with an external thread which is threadably connected to the fastening nut.

[0009] Preferably, the pressure sensor is connected to the computer via electrical signals.

[0010] Preferably, the pressurized hydraulic cylinder is adapted to the limiting ring sleeve; and the threaded connector is adapted to the threaded connector sleeve.

[0011] Preferably, the inner wall of the second limiting block is fixedly connected with a second limiting socket by means of screws.

[0012] Preferably, a threaded hole is provided on the limiting ring sleeve; a fastening stud is provided on the fourth fastening knob; and the limiting ring sleeve is threadedly connected to the fourth fastening knob via the threaded hole and the fastening stud.

[0013] Preferably, a plurality of mounting holes are provided on the mounting base for fixing to the ground.

[0014] Preferably, the articulated joint is hinged to the mounting base via a first articulated axis.

[0015] Compared with the prior art, the invention has the following beneficial effects:

[0016] 1. The pile foundation test loading device comprises a second limit holder fixed on the inner wall of the second limit block; the second hinge block is hinged to the second limit holder through the second hinge axis, and the second hinge block is provided with a third tightening knob; a fourth tightening knob is fixed to a third limit holder; a threaded hole is provided on the limit ring sleeve; a tightening stud is provided on the fourth tightening knob; the limit ring sleeve is threadedly connected with the fourth tightening knob through the threaded hole and the tightening stud; a second tightening knob is provided on the adjustment limit block; the threaded connector is threadedly connected with the threaded connector sleeve; the limit guide column passes through the limit jack and is threadedly connected with the tightening nut; loosen the third tightening knob, the fourth tightening knob and the second tightening knob The button is then pressed downwardly, and at the same time, the adjusting hydraulic cylinder is started to extend and retract the telescopic end of the adjusting hydraulic cylinder, thereby causing the second limit block to slide up and down, thereby adjusting the height and expansion degree of the three adjusting support rods, and then tightening the third tightening knob, the second tightening knob and the first tightening knob to complete the expansion of the adjusting support rod and the adjustment of the height of the adjusting support rod, and then use bolts to fix the mounting base to the ground, and then install the buffer spring on the limit guide column, and then make the limit guide column pass through the limit jack and threadedly connect it with the fastening nut; then thread the threaded connector and the threaded connector sleeve, and the device is installed, which is easy to install and disassemble.

[0017] 2. The pile foundation test loading device has three first limit clamps arranged on the limit support circular block along the circumferential direction; the three first limit clamps are respectively clamped with the first limit blocks; the first limit block is connected to the limit support rod through the first fastening knob; the limit support rod is connected to the adjustment support rod through the adjustment limit block; a second limit block is arranged at the connection between the lower end of the limit support rod and the adjustment support rod; a second limit clamp is fixed on the inner wall of the second limit block; a second fastening knob is arranged on the adjustment limit block; the first hinge block is connected to the telescopic end of the adjustment hydraulic cylinder; the non-telescopic end of the adjustment hydraulic cylinder is fixed with the second hinge block; the second hinge block is arranged The third tightening knob; according to the size of the pile foundation and the conditions of the ground, adjust the height and expansion degree of the three adjustment support rods. First, loosen the third tightening knob, the fourth tightening knob and the second tightening knob, and then press down the limit ring sleeve. At the same time, start the adjusting hydraulic cylinder to make the telescopic end of the adjusting hydraulic cylinder extend and retract, so that the second limit block slides up and down, and then adjust the height and expansion degree of the three adjustment support rods. Then tighten the third tightening knob, the second tightening knob and the first tightening knob to complete the expansion of the adjustment support rod and the adjustment of the height of the adjustment support rod. It can adapt to pile foundations of different sizes and different bottom surfaces, and has strong versatility.

[0018] 3. The pile foundation test loading device is provided with a third tightening knob on the second hinge block; a fourth tightening knob is fixed on a third limit holder; the first limit block is connected to the limit support rod through the first tightening knob; three first limit holders are provided along the circumferential direction on the limit support circular block; the three first limit holders are respectively clamped with the first limit blocks; the second tightening knob is provided on the adjustment limit block; then the third tightening knob is tightened to fix the adjustment hydraulic cylinder, the second tightening knob is used to limit and fix the adjustment limit block, the first tightening knob is used to limit and fix the limit support rod, and the mounting base is fixed to the ground with bolts, so that the device is relatively stable.

[0019] 4. The pile foundation test loading device has three first limit sockets arranged along the circumferential direction on the limit support circular block; the three first limit sockets are respectively clamped with the first limit blocks; the first limit block is connected to the limit support rod through the first tightening knob; the limit support rod is connected to the adjusting support rod through the adjusting limit block; a second limit block is arranged at the connection between the lower end of the limit support rod and the adjusting support rod; a second limit socket is fixed on the inner wall of the second limit block; a second tightening knob is arranged on the adjusting limit block; the first hinge block is connected to the telescopic end of the adjusting hydraulic cylinder; a second hinge block is fixed on the non-telescopic end of the adjusting hydraulic cylinder; and a third tightening knob is arranged on the second hinge block; when the use of this device is completed, the third tightening knob, the fourth tightening knob, the second tightening knob and the first tightening knob are loosened, and then the three adjusting support rods are moved closer to the pressurized hydraulic cylinder, and the stable support leg is stored and folded for easy carrying.

[0020] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 A schematic diagram of the structure of a pile foundation test loading device invented Figure 1 ;

[0022] Figure 2 for Figure 1 A schematic diagram of the enlarged structure at A in the middle;

[0023] Figure 3 for Figure 1 A schematic diagram of the enlarged structure at B in the middle;

[0024] Figure 4 for Figure 1 Schematic diagram of the enlarged structure at C in the middle;

[0025] Figure 5 A schematic diagram of the structure of a pile foundation test loading device invented Figure 2 ;

[0026] Figure 6 A schematic diagram of the structure of a pile foundation test loading device invented Figure 3 ;

[0027] Figure 7 A schematic diagram of the structure of a pile foundation test loading device invented Figure 4 .

[0028] The markings in the attached drawings are as follows: 1-limit support round block; 2-first limit card seat; 3-first limit block; 4-first tightening knob; 5-limit support rod; 6-second limit block; 7-adjustment limit block; 8-second tightening knob; 9-adjustment support rod; 10-bottom limit block; 11-hinged joint; 12-first hinge axis; 13-mounting base; 14-mounting hole; 15-second limit card seat; 16-second hinge axis; 17-first Three tightening knobs; 18-pressurized hydraulic cylinder; 19-limiting ring sleeve; 20-third limiting socket; 21-fourth tightening knob; 22-first hinge block; 23-adjusting hydraulic cylinder; 24-threaded connector; 25-threaded connector sleeve; 26-first limiting circular plate; 27-second limiting circular plate; 28-limiting guide column; 29-buffer spring; 30-fastening nut; 31-pressure sensor; 32-second hinge block; 33-limiting socket. DETAILED DESCRIPTION

[0029] The following is further described in detail through specific implementation methods:

[0030] like Figure 1-7 The pile foundation test loading device shown in the figure comprises a limit support round block 1 and a second limit circular plate 27, three first limit clamping seats 2 are arranged on the limit support round block 1 along the circumferential direction; the three first limit clamping seats 2 are respectively clamped with first limit blocks 3; the first limit blocks 3 are connected to the limit support rod 5 through the first fastening knob 4; the limit support rod 5 is connected to the adjustment support rod 9 through the adjustment limit block 7; the second limit block 6 is arranged at the connection between the lower end of the limit support rod 5 and the adjustment support rod 9; A second limit holder 15 is fixed to the inner wall of the second limit block 6; a second tightening knob 8 is provided on the adjustment limit block 7; a bottom limit block 10 is fixed to the lower end of the adjustment support rod 9; an articulated joint 11 is connected to the bottom limit block 10; a pressurized hydraulic cylinder 18 is fixed to the limit support circular block 1; a limit ring sleeve 19 is slidably connected to the pressurized hydraulic cylinder 18; three third limit holders 20 are fixed to the limit ring sleeve 19 along the circumferential direction; the third limit holder 20 is hinged to the first articulated block 22; a A fourth fastening knob 21 is fixed to the third limit holder 20; the fourth fastening knob 21 is threadedly connected to the limit ring sleeve 19; the first hinge block 22 is connected to the telescopic end of the adjusting hydraulic cylinder 23; the non-telescopic end of the adjusting hydraulic cylinder 23 is fixed with a second hinge block 32; the second hinge block 32 is provided with a third fastening knob 17; the second hinge block 32 is hinged to the second limit holder 15; the telescopic end of the pressurizing hydraulic cylinder 18 is connected to a threaded connector 24; the threaded connector 24 is connected to the threaded connector The connecting sleeve 25 is threadedly connected; a first limiting circular plate 26 is fixed on the threaded connecting sleeve 25; a plurality of limiting holes 33 are opened in the circumferential direction of the first limiting circular plate 26; a plurality of limiting guide posts 28 are fixed on the second limiting circular plate 27; the limiting guide posts 28 pass through the limiting holes 33 and are threadedly connected with the fastening nuts 30; a buffer spring 29 is installed on the limiting guide posts 28 relative to the first limiting circular plate 26 and the second limiting circular plate 27; a pressure sensor 31 is arranged on the second limiting circular plate 27.

[0031] In this embodiment, the second hinge block 32 is hinged to the second position limiting holder 15 via the second hinge shaft 16 .

[0032] In this embodiment, a first limiting hole for the second hinge shaft 16 to pass through is formed on the second hinge block 32; a second limiting hole for the second hinge shaft 16 to pass through is formed on the second limiting socket 15; the first limiting hole corresponds to the second limiting hole one by one.

[0033] In this embodiment, the limiting guide column 28 is provided with an external thread which is threadedly connected to the fastening nut 30 .

[0034] In this embodiment, the pressure sensor 31 is connected to the computer via electrical signals.

[0035] In this embodiment, the pressurized hydraulic cylinder 18 is adapted to the limiting ring sleeve 19 ; the threaded connector 24 is adapted to the threaded connector sleeve 25 .

[0036] In this embodiment, the inner wall of the second limiting block 6 is fixedly connected with a second limiting socket 15 by screws.

[0037] In this embodiment, a threaded hole is provided on the limiting ring sleeve 19; a fastening stud is provided on the fourth fastening knob 21; the limiting ring sleeve 19 is threadedly connected to the fourth fastening knob 21 through the threaded hole and the fastening stud.

[0038] In this embodiment, a plurality of mounting holes 14 are provided on the mounting base 13 for fixing to the ground.

[0039] In this embodiment, the articulated joint 11 is articulated to the mounting base 13 via a first articulated shaft 12 .

[0040] When the pile foundation test loading device is working, first adjust the height and expansion degree of the three adjustment support rods 9 according to the size of the pile foundation and the ground conditions. First, loosen the third tightening knob 17, the fourth tightening knob 21 and the second tightening knob 8, and then press the limit ring sleeve 19 downward. At the same time, start the adjusting hydraulic cylinder 23 to make the telescopic end of the adjusting hydraulic cylinder 23 extend and retract, so that the second limit block 6 slides up and down, and then adjust the height and expansion degree of the three adjustment support rods 9. Then tighten the third tightening knob 17, the second tightening knob 8 and the first tightening knob 4 to complete the expansion of the adjustment support rod 9 and the adjustment of the height of the adjustment support rod 9. Then use bolts to fix the mounting base 13 to the ground, and then use the buffer spring 29 Install it on the limit guide column 28, then make the limit guide column 28 pass through the limit socket 33 and threadedly connect with the fastening nut 30; then thread the threaded connector 24 and the threaded connector sleeve 25, and the installation of the device is completed, and then start the pressurized hydraulic cylinder 18 to extend the telescopic end of the pressurized hydraulic cylinder 18, so that the pressure sensor 31 tightly supports the pile foundation, and the pile foundation is pressure tested. The pressure measured by the pressure sensor 31 is transmitted to the computer so that people can intuitively see that when the device is used, loosen the third fastening knob 17, the fourth fastening knob 21, the second fastening knob 8 and the first fastening knob 4, and then move the three adjustment support rods 9 closer to the pressurized hydraulic cylinder 18 to store and fold the stable support leg.

[0041] The pile foundation test loading device comprises a second limit holder 15 fixed to the inner wall of the second limit block 6; a second hinge block 32 is hinged to the second limit holder 15 through a second hinge shaft 16, and a third fastening knob 17 is arranged on the second hinge block 32; a fourth fastening knob 21 is fixed to a third limit holder 20; a threaded hole is arranged on the limit ring sleeve 19; a fastening stud is arranged on the fourth fastening knob 21; the limit ring sleeve 19 is threadedly connected with the fourth fastening knob 21 through the threaded hole and the fastening stud; a second fastening knob 8 is arranged on the adjustment limit block 7; a threaded connector 24 is threadedly connected with the threaded connector sleeve 25; a limit guide column 28 passes through a limit socket 33 and is threadedly connected with a fastening nut 30; loosen the third fastening knob 17, the fourth fastening knob 21 and the first The second tightening knob 8 is used, and then the limiting ring sleeve 19 is pressed downward. At the same time, the adjusting hydraulic cylinder 23 is started to extend and retract the telescopic end of the adjusting hydraulic cylinder 23, so that the second limiting block 6 slides up and down, and then the height and expansion degree of the three adjusting support rods 9 are adjusted. Then the third tightening knob 17, the second tightening knob 8 and the first tightening knob 4 are tightened to complete the expansion of the adjusting support rod 9 and the adjustment of the height of the adjusting support rod 9. Then the mounting base 13 is fixed to the ground with bolts, and then the buffer spring 29 is installed on the limiting guide column 28, and then the limiting guide column 28 is threadedly connected to the fastening nut 30 through the limiting socket 33; then the threaded connector 24 is threadedly connected to the threaded connector sleeve 25, and the installation of the device is completed, and it is easy to install and disassemble.

[0042] The pile foundation test loading device comprises three first limit clamping seats 2 arranged along the circumferential direction on the limit support circular block 1; the three first limit clamping seats 2 are respectively clamped with the first limit blocks 3; the first limit block 3 is connected to the limit support rod 5 through the first fastening knob 4; the limit support rod 5 is connected to the adjustment support rod 9 through the adjustment limit block 7; a second limit block 6 is arranged at the connection between the lower end of the limit support rod 5 and the adjustment support rod 9; a second limit clamping seat 15 is fixed to the inner wall of the second limit block 6; a second fastening knob 8 is arranged on the adjustment limit block 7; a first hinge block 22 is connected to the telescopic end of the adjustment hydraulic cylinder 23; a second hinge block 32 is fixed to the non-telescopic end of the adjustment hydraulic cylinder 23; a second hinge block 32 is arranged on the second hinge block 32 A third tightening knob 17 is provided; according to the size of the pile foundation and the ground conditions, the height and expansion degree of the three adjustment support rods 9 are adjusted. First, the third tightening knob 17, the fourth tightening knob 21 and the second tightening knob 8 are loosened, and then the limit ring sleeve 19 is pressed downward. At the same time, the adjusting hydraulic cylinder 23 is started to extend and retract the telescopic end of the adjusting hydraulic cylinder 23, so that the second limit block 6 slides up and down, and then the height and expansion degree of the three adjustment support rods 9 are adjusted. Then, the third tightening knob 17, the second tightening knob 8 and the first tightening knob 4 are tightened to complete the expansion of the adjustment support rod 9 and the adjustment of the height of the adjustment support rod 9. It is suitable for pile foundations of different sizes and different bottom surfaces, and has strong versatility.

[0043] The pile foundation test loading device is characterized in that a third tightening knob 17 is arranged on the second hinge block 32; a fourth tightening knob 21 is fixed on a third limit holder 20; the first limit block 3 is connected to the limit support rod 5 through the first tightening knob 4; three first limit holders 2 are arranged along the circumferential direction on the limit support circular block 1; the three first limit holders 2 are respectively clamped with the first limit blocks 3; a second tightening knob 8 is arranged on the adjustment limit block 7; then the third tightening knob 17 is tightened to fix the adjustment hydraulic cylinder 23, the second tightening knob 8 is used to limit and fix the adjustment limit block 7, the first tightening knob 4 is used to limit and fix the limit support rod 5, and the mounting base 13 is fixed to the ground with bolts, so that the device is relatively stable.

[0044] The pile foundation test loading device comprises three first limit clamping seats 2 arranged on the limit support circular block 1 along the circumferential direction; the three first limit clamping seats 2 are respectively clamped with the first limit blocks 3; the first limit blocks 3 are connected to the limit support rod 5 through the first fastening knob 4; the limit support rod 5 is connected to the adjustment support rod 9 through the adjustment limit block 7; a second limit block 6 is arranged at the connection between the lower end of the limit support rod 5 and the adjustment support rod 9; a second limit clamping seat 15 is fixed on the inner wall of the second limit block 6; a limit block 7 is arranged on the adjustment limit block 7. There is a second fastening knob 8; the first hinge block 22 is connected to the telescopic end of the adjusting hydraulic cylinder 23; the non-telescopic end of the adjusting hydraulic cylinder 23 is fixed with a second hinge block 32; the second hinge block 32 is provided with a third fastening knob 17; when the use of the device is completed, the third fastening knob 17, the fourth fastening knob 21, the second fastening knob 8 and the first fastening knob 4 are loosened, and then the three adjusting support rods 9 are moved closer to the pressurized hydraulic cylinder 18, and the stable outrigger is stored and folded, which is convenient to carry and has good practicality.

[0045] The above is only an embodiment of the present invention, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several modifications and improvements can be made without departing from the structure of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the present invention.

Claims

1. A pile foundation test loading device, characterized in that: The invention comprises a limit support circular block (1) and a second limit circular plate (27); three first limit clamping seats (2) are arranged on the limit support circular block (1) along the circumferential direction; the three first limit clamping seats (2) are respectively clamped with a first limit block (3); the first limit block (3) is connected to the limit support rod (5) through a first tightening knob (4); the limit support rod (5) is connected to the adjustment support rod (9) through an adjustment limit block (7); a second limit block (6) is arranged at the connection between the lower end of the limit support rod (5) and the adjustment support rod (9); the second limit block (6) is provided inside the second limit block (6); A second limit card seat (15) is fixed to the wall; a second tightening knob (8) is arranged on the adjustment limit block (7); a bottom limit block (10) is fixed to the lower end of the adjustment support rod (9); a hinge joint (11) is connected to the bottom limit block (10); a pressurized hydraulic cylinder (18) is fixed to the limit support circular block (1); a limit ring sleeve (19) is slidably connected to the pressurized hydraulic cylinder (18); three third limit card seats (20) are fixed to the limit ring sleeve (19) along the circumferential direction; the third limit card seats (20) are hinged to the first hinge block (22); a third limit card seat (20) is hinged to the first hinge block (22); A fourth tightening knob (21) is fixed on the holder (20); the fourth tightening knob (21) is threadedly connected to the limiting ring sleeve (19); the first hinge block (22) is connected to the telescopic end of the adjusting hydraulic cylinder (23); the non-telescopic end of the adjusting hydraulic cylinder (23) is fixed with a second hinge block (32); the second hinge block (32) is provided with a third tightening knob (17); the second hinge block (32) is hingedly connected to the second limiting holder (15); the telescopic end of the pressurizing hydraulic cylinder (18) is connected to a threaded connector (24); the threaded connector (24) is connected to the threaded connector sleeve ( 25) threaded connection; a first limiting circular plate (26) is fixed on the threaded connection sleeve (25); a plurality of limiting plug holes (33) are opened on the first limiting circular plate (26) along the circumferential direction; a plurality of limiting guide pillars (28) are fixed on the second limiting circular plate (27); the limiting guide pillars (28) pass through the limiting plug holes (33) and are threadedly connected to the fastening nuts (30); a buffer spring (29) is installed on the limiting guide pillars (28) relative to the first limiting circular plate (26) and the second limiting circular plate (27); a pressure sensor (31) is arranged on the second limiting circular plate (27); The second hinge block (32) is hinged to the second limiting clamp (15) via the second hinge shaft (16); the second hinge block (32) is provided with a first limiting hole for the second hinge shaft (16) to pass through; the second limiting clamp (15) is provided with a second limiting hole for the second hinge shaft (16) to pass through; the first limiting hole corresponds to the second limiting hole one by one; the limiting ring sleeve (19) is provided with a threaded hole; the fourth tightening knob (21) is provided with a tightening stud; the limiting ring sleeve (19) is threadedly connected to the fourth tightening knob (21) via the threaded hole and the tightening stud.

2. A pile foundation test loading device according to claim 1, characterized in that: The limiting guide column (28) is provided with an external thread which is threadedly connected to the fastening nut (30).

3. A pile foundation test loading device according to claim 1, characterized in that: The pressure sensor (31) is connected to the computer via electrical signals.

4. A pile foundation test loading device according to claim 1, characterized in that: The pressurized hydraulic cylinder (18) is adapted to the limiting ring sleeve (19); and the threaded connector (24) is adapted to the threaded connector sleeve (25).

5. A pile foundation test loading device according to claim 1, characterized in that: The inner wall of the second limiting block (6) is fixedly connected to a second limiting clamping seat (15) via screws.

6. A pile foundation test loading device according to claim 1, characterized in that: A plurality of mounting holes (14) are provided on the mounting base (13) for fixing to the ground.

7. A pile foundation test loading device according to claim 1, characterized in that: The articulated joint (11) is articulated with the mounting base (13) via a first articulated shaft (12).

Citation Information

Patent Citations

  • Universal lamp bracket for mobile lighting

    CN101532651A

  • Highway road surface compressive capacity detection device

    CN207779825U

  • Cell -phone camera support

    CN208210055U

  • The invention discloses a radar support for efficiently monitoring traffic violation

    CN208871263U

  • Tripod with high surveying and mapping adaptability

    CN209100939U