A chain-type new ballast dump car for railways and its construction method
By designing a new rail-type ballast dump truck for railways, using the combination of a concave-bottom flat truck and a ballast transfer working device, the transfer problem between the stone ballast funnel truck and the material transport truck is solved, and efficient ballast dumping is achieved , meet the needs of railway construction.
Patent Information
- Application Number
- CN201910838118.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-09-05
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2039-09-05
AI Technical Summary
At the railway construction site, the space at the unloading entrance of the stone ball funnel truck is limited, and it is impossible to directly transport the stone ball to the inlet entrance of the material transport truck, resulting in difficulty in transferring the stone ball.
A new rail-type ballast dump truck was designed, including a concave bottom flat truck and a transfer ball working device. The ballast working device is installed on the concave bottom flat truck as an independent whole, equipped with a conveyor belt, a tie-cut excavation mechanism and Plastic styling mechanism, the transfer and plastic surgery of stone balls are achieved through excavation and conveyor belts.
It effectively solved the problem of transferring stone balls from stone ball funnel trucks to material transport trucks, lowered the center of gravity of the whole vehicle, and met the limit requirements of railway lines, achieving efficient stone ball dumping operations.
Smart Images

Figure CN112441429B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of railway maintenance using large-scale track maintenance machinery, and in particular to a chain-pulling new ballast dumping vehicle for railways and a construction method thereof. Background Art
[0002] Many construction operations at my country's railway construction sites require the coupling of material transport vehicles loaded with new ballast.
[0003] my country's new railway ballast is mainly transported from the quarry to the construction site by ballast hopper cars. The ballast hopper cars can only unload ballast from the bottom and the ballast unloading port is close to the track surface, while the ballast inlet of the material transport vehicle is higher and located on the top of the vehicle. Due to the limited space at the ballast unloading port of the ballast hopper car, the corresponding equipment cannot be installed here, and the ballast cannot be directly transported from the ballast unloading port at the bottom of the ballast hopper car to the ballast inlet at the top of the material transport vehicle. How to transfer the ballast in the ballast hopper car to the material transport vehicle has always been a practical problem that is difficult to solve at railway construction sites. Summary of the invention
[0004] In order to solve the problem of transferring ballast from a ballast hopper car to a material transport car at a railway construction site, the purpose of the present invention is to provide a railway chain-type new ballast dump car and a construction method to solve the problem of transferring and storing new ballast from a ballast hopper car to a material transport car during railway on-site construction. The ballast transfer working device of the new ballast dump car is an independent whole, with a concave-bottom flat car as a working platform, and the ballast transfer working device is installed on the concave-bottom flat car according to the railway cargo loading and reinforcement rules.
[0005] In order to achieve the above-mentioned design objectives, the scheme adopted by the present invention is as follows:
[0006] The first aspect of the present invention provides a chain-type new ballast dump car for railways, comprising a concave-bottom flat car and a ballast transfer device, wherein the concave-bottom flat car provides a working platform for the ballast transfer device; the ballast transfer device is integrated on a mounting base, and the ballast transfer device is integrally mounted on the concave-bottom flat car and can be separated from the concave-bottom flat car as a whole; a conveyor belt, a left conveyor belt and a right conveyor belt are provided at the front end of the concave-bottom flat car; a left chain-type digging mechanism and a right chain-type digging mechanism are provided on both sides of the concave-bottom flat car; a driver's cab, a power room and a ballast transfer shaping mechanism are provided at the rear end of the concave-bottom flat car. The ballast transfer device of the new ballast dump car of the present invention is an independent entity, with the concave-bottom flat car as the working platform, and the ballast transfer device is installed on the concave-bottom flat car according to the railway cargo loading and reinforcement rules.
[0007] The concave bottom flat car is a transport vehicle with high ends and a concave middle part, and the concave part is parallel to the horizontal plane.
[0008] Preferably, the front end of the left chain digging mechanism is connected to the left conveyor belt; the front end of the right chain digging mechanism is connected to the right conveyor belt.
[0009] The left conveyor belt can rotate along the rotation center, and the right conveyor belt can rotate along the rotation center to meet the different requirements of the two states of operation and collection.
[0010] During operation, the left and right chain excavation mechanisms are extended outwards first. After being extended to the right position, the chain excavation mechanisms are lowered until the required excavation depth is reached, and then the left and right conveyor belts are rotated to the ballast outlet of the chain excavation mechanisms to realize the new ballast dumping operation; when the vehicle is closed, the left and right conveyor belts are first rotated to the closed state, and then the chain excavation mechanisms are lifted, and finally the chain excavation mechanisms are retracted horizontally to meet the limit requirements of the railway line.
[0011] In any of the above schemes, it is preferred that the left-chain digging mechanism is supported by a transverse support column A and a transverse support column B and is installed on a left-chain support.
[0012] In any of the above schemes, it is preferred that one side of the left chain digging mechanism is connected to a left horizontal cylinder, and can be horizontally extended and retracted under the action of the left horizontal cylinder.
[0013] In any of the above schemes, it is preferred that a left lifting cylinder is provided on the left chain digging mechanism, and the left chain digging mechanism rotates along the center line of the A horizontal support column under the action of the left lifting cylinder, thereby adjusting the left excavation depth.
[0014] In any of the above solutions, preferably, the left lifting cylinder is fixed on the left lifting cylinder seat.
[0015] In any of the above schemes, it is preferred that the right pick chain excavation mechanism is supported by a C transverse support column and a D transverse support column and is installed on a right pick chain support.
[0016] In any of the above schemes, it is preferred that a right horizontal oil cylinder is provided on one side of the right chain digging mechanism, and the right chain digging mechanism can be horizontally extended and retracted under the action of the right horizontal oil cylinder.
[0017] In any of the above schemes, it is preferred that the right chain digging mechanism is provided with a right lifting cylinder, and the right chain digging mechanism can rotate along the center line of the C transverse support column under the action of the right lifting cylinder, so as to adjust the right digging depth.
[0018] In any of the above solutions, preferably, the right lifting cylinder is fixed on the right lifting cylinder seat.
[0019] In any of the above schemes, it is preferred that a left lifting cylinder seat is provided on the A transverse support column and the B transverse support column.
[0020] In any of the above schemes, it is preferred that the left chain digging mechanism and the right chain digging mechanism are both provided with digging teeth, digging chains, ballast inlet and ballast outlet.
[0021] A second aspect of the present invention provides a construction method for a railway chain-type new ballast dump car, which comprises the following steps:
[0022] Step 1: Operation preparation: put the chain-type new ballast dump truck, material transport truck and ballast hopper truck on the same railway line. The chain-type new ballast dump truck and material transport truck are connected and located at one end of the line, and the ballast hopper truck is located at the other end of the line. The distance between the two is the sum of the trench length for storing new ballast and the 20-meter safety distance.
[0023] Step 2: Use a material transport vehicle or other vehicle to pull a chain-type new ballast dump vehicle, dig trenches on both sides of the railway line with the chain-type new ballast dump vehicle (the length and depth of the trench depend on the length of the station line and the amount of new ballast dump), transport the dug old ballast to the material transport vehicle, and finally transport it to the designated place by the material transport vehicle;
[0024] Step 3: The material transport vehicle and the chain-type new ballast dump vehicle are returned, and the ballast hopper vehicle is moved to the new trench dug in the second step. The ballast unloading port of the ballast hopper vehicle that needs to unload ballast is opened, and the new ballast is unloaded into the trench dug in the second step until the trenches on both sides of the line are filled;
[0025] Step 4: The ballast hopper car is returned, and the material transport car is used to pull the chain-type new ballast dump car, and the chain-type new ballast dump car is used to dig up the new ballast unloaded in the ditch on both sides of the railway line in the third step, and transport it to the material transport car through the conveyor belt;
[0026] Step 5: Repeat steps 3 and 4 until all required material transport vehicles are filled; after all material transport vehicles are filled, repeat step 3 again and unload the new ballast in the ballast hopper vehicle into the trench dug in step 4;
[0027] Step 6: Use the ballast-scraping and shaping mechanism to level the new ballast unloaded into the ditch in the fifth step, completing the new ballast dumping work.
[0028] Compared with the prior art, the railway chain-type new ballast dump car of the present invention has the following advantages and effects:
[0029] 1. The concave-bottom flat car used in the chain-type new ballast dump car for railways of the present invention has a low working surface, which can effectively reduce the center of gravity of the whole car.
[0030] 2. The ballast transfer device of the new ballast transfer car is an independent whole, with a concave-bottom flat car as the working platform. The ballast transfer device is installed on the concave-bottom flat car according to the railway cargo loading and reinforcement rules.
[0031] 3. The left transverse conveyor belt rotates along the rotation center under the action of the oil cylinder, and the right transverse conveyor belt rotates along the rotation center under the action of the oil cylinder to meet the different requirements of the two states of operation and collection. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 The present invention is a schematic structural diagram of a preferred embodiment of a chain-type new ballast dump car for railways.
[0033] Figure 2 For the railway chain-type new ballast dumping vehicle according to the present invention Figure 1 A top view of the preferred embodiment is shown. DETAILED DESCRIPTION
[0034] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the prior art descriptions. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other embodiments can be obtained based on these drawings without creative work.
[0035] like Figure 1-Figure 2 As shown, a schematic structural diagram of a preferred embodiment of a chain-type new ballast dump car for railways according to the present invention is shown. The chain-type new ballast dump car includes a concave-bottom flat car 1 and a ballast working device. The concave-bottom flat car 1 provides a working platform for the ballast working device. The ballast working device is integrated on the mounting base 3 and is integrally mounted on the concave-bottom flat car 1. It can be separated from the concave-bottom flat car 1 as a whole, so as to facilitate the inspection and maintenance of the concave-bottom flat car 1. The working device is equipped with a driver's cab 10, in which a ballast working device control unit is installed. The operator can operate the working device in the driver's cab. The power room 11 provides the required power for all power components of the ballast working device. The ballast-scraping and shaping mechanism 13 is used to flatten the new ballast unloaded from the ballast hopper car to comply with relevant regulations of the railway line.
[0036] The railway chain-type new ballast dump car of the present invention comprises a concave-bottom flat car 1 and a ballast-transferring device, wherein the concave-bottom flat car 1 provides a working platform for the ballast-transferring device; the ballast-transferring device is integrated on a mounting base 3, and the ballast-transferring device is integrally mounted on the concave-bottom flat car 1 and can be integrally separated from the concave-bottom flat car 1; a conveyor belt 2, a left conveyor belt 15 and a right conveyor belt 21 are provided at the front end of the concave-bottom flat car 1; a left chain-transferring digging mechanism 4 and a right chain-transferring digging mechanism 5 are provided on both sides of the concave-bottom flat car 1; a driver's cab 10, a power room 11 and a ballast-transferring shaping mechanism 13 are provided at the rear end of the concave-bottom flat car 1. The ballast-transferring device of the new ballast dump car of the present invention is an independent whole, with the concave-bottom flat car as the working platform, and the ballast-transferring device is installed on the concave-bottom flat car according to the railway cargo loading and reinforcement rules.
[0037] In this embodiment, the front end of the left chain digging mechanism 4 is connected to the left conveyor belt 15 ; the front end of the right chain digging mechanism 5 is connected to the right conveyor belt 21 .
[0038] The left conveyor belt 15 can rotate along the rotation center 14, and the right conveyor belt 21 can rotate along the rotation center 20, so as to meet the different requirements of the two states of operation and collection.
[0039] During operation, the left and right chain excavation mechanisms 4 and 5 are extended outwards first, and after being extended to the right position, the chain excavation mechanisms are lowered until the required excavation depth is reached, and then the left and right conveyor belts 15 and 21 are rotated to the ballast outlet of the chain excavation mechanisms to realize the new ballast dumping operation; when the vehicle is closed, the left and right conveyor belts 15 and 21 are first rotated to the closed state, and then the chain excavation mechanisms are lifted, and finally the chain excavation mechanisms are horizontally retracted to meet the limit requirements of the railway line.
[0040] The working principle of the railway chain-type new ballast dump car of the present invention is as follows: when viewed from the vehicle's forward direction 12 (such as Figure 1 As shown in the figure, during operation, the concave-bottom flat car 1 (one side of the conveyor belt 2) is connected to the required number of material transport vehicles, the conveyor belt 2 extends to the material transport vehicle silo, the left pick chain excavation mechanism 4 and the right pick chain excavation mechanism 5 are lowered, the left conveyor belt 15 and the right conveyor belt 21 are rotated to the ballast outlet of the corresponding pick chain excavation mechanism, and the concave-bottom flat car 1 moves in direction 12 under the traction of the material transport vehicle or other vehicles. The two sets of pick chain excavation mechanisms dig up the new ballast placed in the ditch on both sides of the railway line in advance, and the moving pick teeth pick the ballast to the left conveyor belt 15 and the right conveyor belt 21, transport it to the conveyor belt 2, pass through the conveyor belt 2, and finally transport it to the material transport vehicle.
[0041] In this embodiment, the left-chain excavating mechanism 4 is supported by an A transverse support column 17 and a B transverse support column 19 and is installed on the left-chain support 16 .
[0042] In this embodiment, one side of the left chain digging mechanism 4 is connected to the left horizontal cylinder 18, and under the action of the left horizontal cylinder 18, it can be horizontally extended and retracted.
[0043] In this embodiment, the left chain excavation mechanism 4 is provided with a left lifting cylinder 8. Under the action of the left lifting cylinder 8, the left chain excavation mechanism 4 rotates along the center line of the A transverse support column 17, thereby adjusting the left excavation depth.
[0044] In this embodiment, the left lifting cylinder 8 is fixed on the left lifting cylinder seat 6 .
[0045] In this embodiment, the right chain digging mechanism 5 is supported by a C transverse support column 23 and a D transverse support column 25 and is installed on the right chain support 22 .
[0046] In this embodiment, a right horizontal oil cylinder 24 is provided on one side of the right chain digging mechanism 5 , and the right chain digging mechanism 5 can be horizontally extended and retracted under the action of the right horizontal oil cylinder 24 .
[0047] In this embodiment, the right chain digging mechanism 5 is provided with a right lifting cylinder 9. Under the action of the right lifting cylinder 9, the right chain digging mechanism 5 can rotate along the center line of the C transverse support column 23, so as to adjust the right digging depth.
[0048] In this embodiment, the right lifting cylinder 9 is fixed on the right lifting cylinder seat 7 .
[0049] In this embodiment, the A transverse support column 17 and the B transverse support column 19 are installed on the left chain support 16 .
[0050] In this embodiment, the left chain excavation mechanism 4 and the right chain excavation mechanism 5 are both provided with excavation teeth, excavation chains, ballast inlet and ballast outlet.
[0051] A second aspect of the present invention provides a construction method for a railway chain-type new ballast dump car, which comprises the following steps:
[0052] Step 1: Operation preparation: put the chain-type new ballast dump truck, material transport truck and ballast hopper truck on the same railway line. The chain-type new ballast dump truck and material transport truck are connected and located at one end of the line, and the ballast hopper truck is located at the other end of the line. The distance between the two is the sum of the trench length for storing new ballast and the 20-meter safety distance.
[0053] Step 2: Use a material transport vehicle or other vehicle to pull a chain-type new ballast dump vehicle, dig trenches on both sides of the railway line with the chain-type new ballast dump vehicle (the length and depth of the trench depend on the length of the station line and the amount of new ballast dump), transport the dug old ballast to the material transport vehicle, and finally transport it to the designated place by the material transport vehicle;
[0054] Step 3: The material transport vehicle and the chain-type new ballast dump vehicle are returned, and the ballast hopper vehicle is moved to the new trench dug in the second step. The ballast unloading port of the ballast hopper vehicle that needs to unload ballast is opened, and the new ballast is unloaded into the trench dug in the second step until the trenches on both sides of the line are filled;
[0055] Step 4: The ballast hopper car is returned, and the material transport car is used to pull the chain-type new ballast dump car, and the chain-type new ballast dump car is used to dig up the new ballast unloaded in the ditch on both sides of the railway line in the third step, and transport it to the material transport car through the conveyor belt;
[0056] Step 5: Repeat steps 3 and 4 until all required material transport vehicles are filled; after all material transport vehicles are filled, repeat step 3 again and unload the new ballast in the ballast hopper vehicle into the trench dug in step 4;
[0057] Step 6: Use the ballast-scraping and shaping mechanism to level the new ballast unloaded into the ditch in the fifth step, completing the new ballast dumping work.
[0058] It is not difficult for a person skilled in the art to understand that the railway chain-type new ballast dump car and construction method of the present invention include any combination of the various parts in this specification. Due to space limitations and to make the specification concise, these combinations are not described in detail one by one here, but after reading this specification, the scope of the present invention consisting of any combination of the various parts constituting this specification is self-evident.
Claims
1. A chain-type new ballast dump car for railways, comprising a concave-bottom flat car (1) and a ballast transfer working device, wherein the concave-bottom flat car (1) provides a working platform for the ballast transfer working device; the ballast transfer working device is integrated on a mounting base (3), and is characterized in that: The ballast transfer device is integrally mounted on a concave-bottom flat car (1) and can be separated from the concave-bottom flat car (1); a conveyor belt (2), a left conveyor belt (15) and a right conveyor belt (21) are provided at the front end of the concave-bottom flat car (1); a left chain digging mechanism (4) and a right chain digging mechanism (5) are provided on both sides of the concave-bottom flat car (1); a driver's cab (10), a power room (11) and a ballast shaping mechanism (13) are provided at the rear end of the concave-bottom flat car (1); a right lifting cylinder (9) is provided on the right chain digging mechanism (5); and the right chain digging mechanism (5) can rotate along the center line of a C transverse support column (23) under the action of the right lifting cylinder (9).
2. The railway chain-type new ballast dumping vehicle according to claim 1, characterized in that: The front end of the left chain digging mechanism (4) is connected to the left conveyor belt (15); the front end of the right chain digging mechanism (5) is connected to the right conveyor belt (21).
3. The railway chain-type new ballast dumping vehicle according to claim 1 or 2, characterized in that: The left-hand chain excavation mechanism (4) is supported by a transverse support column A (17) and a transverse support column B (19), and is mounted on a left-hand chain support (16).
4. The railway chain-type new ballast dumping vehicle according to claim 1 or 2, characterized in that: One side of the left chain digging mechanism (4) is connected to the left horizontal oil cylinder (18) and can be horizontally extended and retracted under the action of the left horizontal oil cylinder (18).
5. The railway chain-type new ballast dumping vehicle according to claim 1 or 2, characterized in that: A left lifting cylinder (8) is provided on the left chain excavation mechanism (4). Under the action of the left lifting cylinder (8), the left chain excavation mechanism (4) rotates along the center line of the A transverse support column (17).
6. The railway chain-type new ballast dumping vehicle according to claim 5, characterized in that: The left lifting cylinder (8) is fixed on the left lifting cylinder seat (6).
7. The railway chain-type new ballast dumping vehicle according to claim 1, characterized in that: The right chain digging mechanism (5) is supported by a C transverse support column (23) and a D transverse support column (25) and is mounted on the right chain support (22).
8. The railway chain-type new ballast dumping vehicle according to claim 1 or 7, characterized in that: A right horizontal oil cylinder (24) is provided on one side of the right chain digging mechanism (5). Under the action of the right horizontal oil cylinder (24), the right chain digging mechanism (5) can be extended and retracted horizontally.
9. A construction method using the railway chain-type new ballast dump car according to claim 1, comprising the following steps: Step 1: Operation preparation: put the chain-type new ballast dump truck, material transport truck and ballast hopper truck on the same railway line. The chain-type new ballast dump truck and material transport truck are connected and located at one end of the line, and the ballast hopper truck is located at the other end of the line. The distance between the two is the sum of the trench length for storing new ballast and the 20-meter safety distance. Step 2: Use a material transport vehicle or other vehicle to pull a chain-type new ballast dump vehicle, and use the chain-type new ballast dump vehicle to dig trenches on both sides of the railway line. The length and depth of the trench depend on the length of the station line and the amount of new ballast dump. The excavated old ballast is transported to the material transport vehicle, and finally transported to the designated place by the material transport vehicle; Step 3: The material transport vehicle and the chain-type new ballast dump vehicle are returned, and the ballast hopper vehicle is moved to the new trench dug in the second step. The ballast unloading port of the ballast hopper vehicle that needs to unload ballast is opened, and the new ballast is unloaded into the trench dug in the second step until the trenches on both sides of the line are filled; Step 4: The ballast hopper car is returned, and the material transport car is used to pull the chain-type new ballast dump car, and the chain-type new ballast dump car is used to dig up the new ballast unloaded in the ditch on both sides of the railway line in the third step, and transport it to the material transport car through the conveyor belt; Step 5: Repeat steps 3 and 4 until all required material transport vehicles are filled; after all material transport vehicles are filled, repeat step 3 again and unload the new ballast in the ballast hopper vehicle into the trench dug in step 4; Step 6: Use the ballast-scraping and shaping mechanism to level the new ballast unloaded into the ditch in the fifth step, completing the new ballast dumping work.