A method and device for generating engineering price list based on engineering quantity bill

By automatically extracting and filling the bill of quantities data and calculating the quota project cost, it solves the problem of low efficiency of manual checklist and quota setting in the existing technology, and realizes the efficient and accurate generation of project price list.

CN112861500BActive Publication Date: 2024-10-29FOSHAN RAIL TRANSIT DESIGN & RES INST CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202110046237.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-01-14
Publication Date
2024-10-29
Estimated Expiration
2041-01-14

AI Technical Summary

Technical Problem

When the existing project pricing software generates the project pricing table, it is necessary to manually check the list and set the quota, resulting in low tabulation efficiency and error-prone.

Method used

By obtaining the bill of quantities, extract the data line by line and fill it into the preset project price list template. Determine the data type. If it is a fixed-rate project, match the fixed unit price and calculate the cost. Automatically calculate the cost of each project and sub-project and generate the initial price. surface.

Benefits of technology

It greatly improves the efficiency of generating project price lists, reduces manual operation errors, and improves the accuracy of price lists.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112861500B_ABST
    Figure CN112861500B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and device for generating a project price list based on a bill of quantities. The method extracts data from the bill of quantities one by one and fills them into a preset project price list template according to a pre-set bill of quantities to generate an initial price list. When filling, if the extracted data is the data of a quota item, the quota number of the quota item is extracted, and then the corresponding quota unit price is matched in a preset quota database according to the quota number, and then the quota item price of each quota item is calculated according to the quota unit price and the price-calculated engineering quantity of the quota item, and then the quota item price calculated is filled into the project price list template; after the initial price list is generated, the price of each list item, the price of each sub-item and the overall price of the project to be priced are automatically calculated, and then they are filled into the initial price list, and finally the project price list of the project to be priced is generated. By implementing the present invention, the generation efficiency of the project price list can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of engineering pricing, and in particular to an engineering pricing method and device based on a bill of quantities. Background Art

[0002] The emergence of engineering cost accounting software has played an important role in reducing the labor intensity of practitioners in the engineering cost accounting industry, improving work efficiency and document preparation quality. Since the engineering cost accounting software was developed and put into use in the 1990s, the main mode used for preparing the budget (hereinafter referred to as the traditional mode) is roughly as follows: the cost accounting personnel set up the fee collection program in the cost accounting software - refer to the EXCEL bill of quantities - check the bill of quantities item by item - input the engineering quantity - modify the information price of labor, materials and machinery - automatically summarize the total price.

[0003] When the above method is used for pricing, cost practitioners need to manually perform operations such as checking the list, applying the quota, and inputting the engineering quantity to finally generate the engineering price table. The table making efficiency is low and prone to errors. Summary of the invention

[0004] The embodiment of the present invention provides a method and device for a project price list based on a bill of quantities, which can improve the drawing efficiency and accuracy of the project price list.

[0005] An embodiment of the present invention provides a method for generating a project price table based on a bill of quantities, comprising: obtaining a bill of quantities; wherein the bill of quantities comprises: a plurality of data rows, each data row comprising a project level sequence number, a project type, a project number, a project name, a pricing unit and a pricing project quantity of a corresponding project; the project comprises: a project to be priced, each sub-project of the project to be priced, each list item under the sub-project and each quota item under the list item; the project number of the quota item is a quota number;

[0006] Extract each data row of the bill of quantities line by line, and fill each extracted data row into a preset engineering price table template line by line to generate an initial price table; wherein, filling the extracted data row into the preset engineering price table template specifically includes: judging whether the extracted data row is a data row of a quota item according to the project type of the extracted data row, and if not, directly filling all the data of the extracted data row into the filling area of ​​the corresponding level in the preset engineering price table template; if so, matching the corresponding quota unit price in the preset quota database according to the quota number of the extracted data row, calculating the quota item cost of the quota item according to the quota unit price and the priced engineering quantity of the extracted data row, and then filling all the data of the extracted data row and the quota item cost into the engineering price table template;

[0007] Calculate the sum of all quota item costs under each of the list items to obtain the list item cost of each of the list items, and fill the list item cost of each of the list items into the initial pricing table;

[0008] Calculate the sum of the costs of all the list items under each of the sub-projects to generate the sub-project cost of each of the sub-projects, fill the cost of each of the sub-projects into the initial pricing table, and then generate the total cost of the project to be priced based on the cost of each of the sub-projects, fill the total cost of the project to be priced into the initial pricing table to generate the project pricing table for the project to be priced.

[0009] Furthermore, the project number of the list item is the list number, and the project number of the sub-item is the sub-item number; wherein each of the sub-item numbers corresponds to a number of list numbers, and each of the list numbers corresponds to a number of the quota numbers.

[0010] Furthermore, the cost of the list item is generated by calculating the sum of the costs of all the quota items under the list item in the following manner: matching several matched quota numbers corresponding to the list item according to the list number of the list item; extracting the matched quota cost corresponding to each of the matched quota numbers, calculating the sum of all the matched quota costs, and generating the list item cost.

[0011] Furthermore, the sum of the costs of all the list items under the sub-project is calculated in the following way to generate the sub-project cost of the sub-project: match several matched list numbers corresponding to the sub-project number of the sub-project; extract the matched list item cost corresponding to each of the matched list numbers, calculate the sum of all the matched list item costs, and generate the sub-project cost.

[0012] Based on the above method embodiment, the present invention provides a corresponding device embodiment;

[0013] Another embodiment of the present invention provides a device for generating a project price list based on a project list, comprising a project quantity list acquisition module, an initial price list generation module, a list item cost filling module, and a project price list generation module;

[0014] The bill of quantities acquisition module is used to acquire the bill of quantities; wherein the bill of quantities includes: a plurality of data rows, each of which includes the project level number, project type, project number, project name, pricing unit and pricing quantity of the corresponding engineering project; the engineering project includes: the engineering project to be priced, each sub-project of the engineering project to be priced, each list item under the sub-project and each quota item under the list item; the project number of the quota item is the quota number;

[0015] The initial price table generation module is used to extract each data row of the bill of quantities line by line, and fill each extracted data row into the preset engineering price table template line by line to generate an initial price table; wherein, filling the extracted data row into the preset engineering price table template specifically includes: judging whether the extracted data row is a data row of a quota item according to the project type of the extracted data row, if not, directly filling all the data of the extracted data row into the filling area of ​​the corresponding level in the preset engineering price table template; if so, matching the corresponding quota unit price in the preset quota database according to the quota number of the extracted data row, calculating the quota item cost of the quota item according to the quota unit price and the priced engineering quantity of the extracted data row, and then filling all the data of the extracted data row and the quota item cost into the engineering price table template;

[0016] The list item cost filling module is used to calculate the sum of all quota item costs under each list item, obtain the list item cost of each list item, and fill the cost of each list item into the initial pricing table;

[0017] The engineering price table generation module is used to calculate the sum of the costs of all list items under each of the sub-projects, generate the sub-project cost of each of the sub-projects, fill the cost of each of the sub-projects into the initial price table, and then generate the total cost of the engineering project to be priced based on the cost of each of the sub-projects, fill the total cost of the engineering project to be priced into the initial price table to generate the engineering price table of the engineering project to be priced.

[0018] The above implementation of the present invention has the following beneficial effects:

[0019] The embodiment of the present invention provides a method and device for generating a project price list based on a project list. The method extracts data in the project quantity list one by one and fills them into a preset project price template according to a pre-set project quantity list to generate an initial price list. When filling, if the extracted data is the data of the quota project, the quota number of the quota project is extracted, and then the corresponding quota unit price is matched in the preset quota database according to the quota number, and then the quota project cost of each quota project is calculated according to the quota unit price and the price engineering quantity of the quota project, and then the calculated quota project cost is filled into the project price template; after the initial price list is generated, the cost of each list item, the cost of each sub-item and the overall cost of the project to be priced are automatically calculated, and then filled into the initial price list, and finally the project price list of the project to be priced is generated. Compared with the prior art, the scheme of the present invention does not require cost practitioners to manually check the list and apply the quota. The generation efficiency of the project price list is greatly improved and it is not easy to make mistakes. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 The present invention is a flowchart of a method for generating a project price list based on a bill of quantities provided in accordance with an embodiment of the present invention.

[0021] Figure 2 It is a schematic diagram of a bill of quantities provided by an embodiment of the present invention.

[0022] Figure 3 It is a schematic diagram of a preset engineering price list template provided in one embodiment of the present invention.

[0023] Figure 4 It is a schematic diagram of an initial pricing table provided in one embodiment of the present invention.

[0024] Figure 5 The present invention is a schematic diagram of a device for generating a project price list based on a bill of quantities according to an embodiment of the present invention. DETAILED DESCRIPTION

[0025] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0026] like Figure 1 As shown, an embodiment of the present invention provides a method for generating a project price list of a bill of quantities, comprising:

[0027] Step S101: Obtain a bill of quantities; wherein the bill of quantities includes: a number of data rows, each data row containing the project level serial number, project type, project number, project name, pricing unit and pricing quantity of the corresponding engineering project; the engineering projects include: engineering projects to be priced, sub-projects of the engineering projects to be priced, list items under the sub-projects and quota items under the list items; the project number of the quota item is the quota number.

[0028] Step S102: extract each data row of the bill of quantities line by line, and fill each extracted data row into a preset engineering price table template line by line to generate an initial price table; wherein, filling the extracted data row into the preset engineering price table template specifically includes: judging whether the extracted data row is a data row of a quota item according to the project type of the extracted data row, and if not, directly filling all the data of the extracted data row into the preset engineering price table template; if so, matching the corresponding quota unit price in the preset quota database according to the quota number of the extracted data row, calculating the quota item cost of the quota item according to the quota unit price and the priced engineering quantity of the extracted data row, and then filling all the data of the extracted data row and the quota item cost into the engineering price table template.

[0029] Step S103: Calculate the sum of all quota item costs under each of the list items, obtain the list item cost of each of the list items, and fill the list item cost of each of the list items into the initial pricing table.

[0030] Step S104: Calculate the sum of the costs of all the list items under each of the sub-projects to generate a sub-project cost for each of the sub-projects, fill the cost of each of the sub-projects into the initial pricing table, and then generate the total cost of the project to be priced based on the cost of each of the sub-projects, fill the total cost of the project to be priced into the initial pricing table to generate a project pricing table for the project to be priced.

[0031] For step S101, firstly, the bill of quantities is described, such as Figure 2 As shown, in the present invention, the bill of quantities includes the following attributes: project level number, project type, project number, project name, pricing unit and pricing engineering quantity. In actual situations, a project often includes several levels of sub-projects, such as the attached figure of the present invention. Figure 2 The shield tunneling interval project based on the shield method shown in the figure takes the "shield method" as the engineering project to be priced, which includes the sub-item of "excavation and slag removal" and the sub-item of "segment splicing" (not shown in the figure), and there are several "list items" under the sub-items. For example, the sub-item of "excavation and slag removal" includes the list item of "shield lifting" and the list item of "shield lifting and dismantling", and the list item includes several "quota items". For example, the list item of "shield lifting and dismantling" includes the quota item of "shield lifting and dismantling as a whole" and the quota item of "frame dismantling". Each project has a project number. The project number of the quota item is defined as the quota number such as "M3-6-2" in the present invention. The project number of the list item is defined as the list number such as "80303001001" in the present invention. The project number of the sub-item is defined as the sub-item number in the present invention, such as "1".

[0032] For step S102, the preset engineering price calculation template is as follows: Figure 3 As shown in the figure, compared with the bill of quantities, the engineering price calculation template has an additional "project cost" attribute, which is used to fill in the cost of each project. The specific operations for generating the initial price calculation table based on the bill of quantities are as follows:

[0033] First, extract the data of the first row of the bill of quantities, and then determine whether it is a quota item based on the project type. If not, directly fill the extracted data into the engineering pricing template. If the attribute value of the project type is identified as "fixed", it means that the extracted row of data is the data of the quota item. At this time, extract the quota number, and then match the corresponding quota unit price in the preset quota database. Then multiply the quota unit price by the priced project quantity to obtain the quota cost of the extracted quota item, and then fill the quota cost and the extracted data into the engineering pricing template together. After the data of the first row of the bill of quantities is processed, extract the second row of data and fill them into the engineering pricing template one by one in the above manner until all the data of the bill of quantities is extracted and the initial pricing table is generated. The generated initial pricing table is as follows. Figure 4 shown.

[0034] It should be noted that the above-mentioned standard unit price is the sum of multiple standard costs, which include but are not limited to the following costs: direct labor costs, direct material costs, direct machinery consumption costs and management fees of the standard items.

[0035] For step S103, in a preferred embodiment, the sum of the costs of all the quota items under the list item is calculated in the following manner to generate the list item cost: match the list item with several matched quota numbers corresponding to it according to its list number; extract the matched quota cost corresponding to each of the matched quota numbers, calculate the sum of all the matched quota costs, and generate the list item cost.

[0036] Specifically, the initial pricing table already has the standard cost of each standard item. Then, the corresponding standard number is matched according to the list number of each list item, and then the standard costs of the matched standard items are summed up to get the cost of each list item. For example, the list number "80303001001" of the list item "shield lifting" corresponds to the standard numbers "M3-6-1" and "M3-6-2". So when calculating the list item cost of the list item "shield lifting", extract the standard cost "52265.26" of "M3-6-1" and the standard cost "42265.27" of "M3-6-2", calculate the sum of the two to get the list item "shield lifting", and the list cost of the remaining list items is deduced in the same way.

[0037] For step S104, in a preferred embodiment, the sum of the costs of all the list items under the sub-project is calculated in the following manner to generate the sub-project cost of the sub-project: match several matched list numbers corresponding to the sub-project number of the sub-project; extract the matched list item cost corresponding to each of the matched list numbers, calculate the sum of all the matched list item costs, and generate the sub-project cost.

[0038] Specifically, consistent with the principle of step S103, the list item number corresponding to each sub-item number is searched, and then the sum of the list item costs of the matched list items is calculated to obtain the sub-item cost of each sub-item. After obtaining the cost of each sub-item, the sum of the costs of all sub-items of the project to be priced is calculated to obtain the final cost of the project to be priced, and then filled in the initial pricing table to generate the final project pricing table of the project to be priced.

[0039] The above solution eliminates the need for cost practitioners to manually check lists and apply quotas, greatly improving the efficiency of generating engineering price lists and making them less prone to errors.

[0040] Based on the above method embodiment, the present invention provides a corresponding device embodiment:

[0041] like Figure 5 As shown, another embodiment of the present invention provides a device for generating a project price list based on a project list, including a project quantity list acquisition module, an initial price list generation module, a list item cost filling module, and a project price list generation module;

[0042] The bill of quantities acquisition module is used to acquire the bill of quantities; wherein the bill of quantities includes: a plurality of data rows, each of which includes the project level number, project type, project number, project name, pricing unit and pricing quantity of the corresponding engineering project; the engineering project includes: the engineering project to be priced, each sub-project of the engineering project to be priced, each list item under the sub-project and each quota item under the list item; the project number of the quota item is the quota number;

[0043] The initial price table generation module is used to extract each data row of the bill of quantities line by line, and fill each extracted data row into the preset engineering price table template line by line to generate an initial price table; wherein, filling the extracted data row into the preset engineering price table template specifically includes: judging whether the extracted data row is a data row of a quota item according to the project type of the extracted data row, if not, directly filling all the data of the extracted data row into the preset engineering price table template; if so, matching the corresponding quota unit price in the preset quota database according to the quota number of the extracted data row, calculating the quota item cost of the quota item according to the quota unit price and the priced engineering quantity of the extracted data row, and then filling all the data of the extracted data row and the quota item cost into the engineering price table template;

[0044] The list item cost filling module is used to calculate the sum of all quota item costs under each list item, obtain the list item cost of each list item, and fill the cost of each list item into the initial pricing table;

[0045] The engineering price table generation module is used to calculate the sum of the costs of all list items under each of the sub-projects, generate the sub-project cost of each of the sub-projects, fill the cost of each of the sub-projects into the initial price table, and then generate the total cost of the engineering project to be priced based on the cost of each of the sub-projects, fill the total cost of the engineering project to be priced into the initial price table to generate the engineering price table of the engineering project to be priced.

[0046] In a preferred embodiment, the item number of the list item is the list number, and the item number of the sub-item is the sub-item number; wherein each of the sub-item numbers corresponds to a number of list numbers, and each of the list numbers corresponds to a number of the quota numbers.

[0047] In a preferred embodiment, the list item cost filling module calculates the sum of the costs of all the quota items under the list item in the following manner to generate the list item cost: match the list item with a number of matched quota numbers corresponding to it according to the list number of the list item; extract the matched quota cost corresponding to each of the matched quota numbers, calculate the sum of all the matched quota costs, and generate the list item cost

[0048] In a preferred embodiment, the engineering cost estimate sheet generation module calculates the sum of the costs of all the list items under the sub-project in the following manner to generate the sub-project cost of the sub-project: matching several matched list numbers corresponding to the sub-project number of the sub-project; extracting the matched list item cost corresponding to each of the matched list numbers, calculating the sum of all the matched list item costs, and generating the sub-project cost.

[0049] It should be noted that the device embodiments described above are merely schematic, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. In addition, in the accompanying drawings of the device embodiments provided by the present invention, the connection relationship between the modules indicates that there is a communication connection between them, which may be specifically implemented as one or more communication buses or signal lines. A person of ordinary skill in the art may understand and implement it without paying any creative effort.

[0050] The above is a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several improvements and modifications without departing from the principle of the present invention. These improvements and modifications are also considered to be within the scope of protection of the present invention.

Claims

1. A method for generating a project price list based on a bill of quantities, characterized in that: include: Obtain a bill of quantities; wherein the bill of quantities includes: a plurality of data rows, each of which includes a project level number, a project type, a project number, a project name, a pricing unit, and a pricing quantity of the corresponding engineering project; the engineering project includes: an engineering project to be priced, each sub-project of the engineering project to be priced, each list item under the sub-project, and each quota item under the list item; the project number of the quota item is the quota number; wherein the project number of the list item is the list number, and the project number of the sub-project is the sub-project number; wherein each of the sub-project numbers corresponds to a plurality of list numbers, and each of the list numbers corresponds to a plurality of the quota numbers; Extracting each data row of the bill of quantities line by line, and filling each extracted data row into a preset engineering price table template line by line to generate an initial price table; wherein filling the extracted data row into the preset engineering price table template specifically comprises: judging whether the extracted data row is a data row of a quota item according to the item type of the extracted data row, and if not, directly filling all the data of the extracted data row into the preset engineering price table template; if so, matching the corresponding quota unit price in a preset quota database according to the quota number of the extracted data row, calculating the quota item cost of the quota item according to the quota unit price and the priced engineering quantity of the extracted data row, and then filling all the data of the extracted data row and the quota item cost into the engineering price table template; Matching a number of matched quota numbers corresponding to the list item according to the list number; extracting the matched quota cost corresponding to each of the matched quota numbers, calculating the sum of all the matched quota costs, and generating the list item cost; filling the cost of each list item into the initial pricing table; Calculate the sum of the costs of all the list items under each of the sub-projects to generate the sub-project cost of each of the sub-projects, fill the cost of each of the sub-projects into the initial pricing table, generate the total cost of the project to be priced based on the cost of each of the sub-projects, fill the total cost of the project to be priced into the initial pricing table to generate the project pricing table for the project to be priced.

2. The method for generating a project price list based on a bill of quantities as claimed in claim 1, characterized in that: The sub-project cost of the sub-project is generated by calculating the sum of the costs of all list items under the sub-project in the following way: Matching a number of matched list numbers corresponding to the sub-item number of the sub-item; The matched list item cost corresponding to each matched list number is extracted, the sum of all the matched list item costs is calculated, and the sub-item cost is generated.

3. A device for generating a project price list based on a project list, characterized in that: include: Module for obtaining the bill of quantities, module for generating the initial price list, module for filling the bill of quantities item cost and module for generating the project price list; The bill of quantities acquisition module is used to acquire the bill of quantities; wherein the bill of quantities includes: a plurality of data rows, each of which includes the project level number, project type, project number, project name, pricing unit and pricing engineering quantity of the corresponding engineering project; the engineering project includes: the engineering project to be priced, each sub-project of the engineering project to be priced, each list item under the sub-project and each quota item under the list item; the project number of the quota item is the quota number; wherein the project number of the list item is the list number, and the project number of the sub-project is the sub-project number; wherein each of the sub-project numbers corresponds to a plurality of list numbers, and each of the list numbers corresponds to a plurality of the quota numbers; The initial price table generation module is used to extract each data row of the bill of quantities line by line, and fill each extracted data row into the preset engineering price table template line by line to generate an initial price table; wherein, filling the extracted data row into the preset engineering price table template specifically includes: judging whether the extracted data row is a data row of a quota item according to the project type of the extracted data row, if not, directly filling all the data of the extracted data row into the preset engineering price table template; if so, matching the corresponding quota unit price in the preset quota database according to the quota number of the extracted data row, calculating the quota item cost of the quota item according to the quota unit price and the priced engineering quantity of the extracted data row, and then filling all the data of the extracted data row and the quota item cost into the engineering price table template; The bill item cost filling module is used to match a number of matched quota numbers corresponding to the bill item according to the bill item number; extract the matched quota cost corresponding to each matched quota number, calculate the sum of all the matched quota costs, and generate the bill item cost; fill the cost of each bill item into the initial pricing table; The engineering price table generation module is used to calculate the sum of the costs of all list items under each of the sub-projects, generate the sub-project cost of each of the sub-projects, fill the cost of each of the sub-projects into the initial price table, and then generate the total cost of the engineering project to be priced based on the cost of each of the sub-projects, fill the total cost of the engineering project to be priced into the initial price table to generate the engineering price table of the engineering project to be priced.

4. The device for generating a project price list based on a project list according to claim 3, characterized in that: The engineering price list generation module calculates the sum of the costs of all list items under the sub-project in the following way to generate the sub-project cost of the sub-project: Matching a number of matched list numbers corresponding to the sub-item number of the sub-item; The matched list item cost corresponding to each matched list number is extracted, the sum of all the matched list item costs is calculated, and the sub-item cost is generated.

Citation Information

Patent Citations

  • Automatic pricing method for electric power marketing project bidding and system thereof

    CN106447405A

  • List engineering quantity automatic generation method and system

    CN110443499A

  • Power transmission and transformation project cost calculation system and cost calculation method based on three-dimensional model