A method and structure for vertical lifting in underwater tunnels suitable for hard ground

By building steel casing and replacement formations in hard strata, combined with shield method and steel structure reinforcement, safe and efficient vertical lifting in hard strata is achieved, solving the problems of high construction costs and long construction periods in traditional methods , improves the stability and construction safety of the tunnel.

CN112878375BActive Publication Date: 2024-12-06华能霞浦核电有限公司 +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110310738.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-03-23
Publication Date
2024-12-06
Estimated Expiration
2041-03-23

AI Technical Summary

Technical Problem

The existing technology cannot effectively implement the vertical lifting process in hard soil and rocks, which leads to high construction costs, long construction periods and great impact on the marine environment. Traditional methods require construction in weak soil layers, limiting the burial of tunnels. Depth and stability.

Method used

The steel casing is built using offshore construction platforms, drilling holes to replace the hard layer, and installing temporary covers for separation of the casing lower sections. The main tunnel is built through the shielding method and vertically lifting the riser sections. The vertical casing is reinforced by flushing pipes and steel structures. , forming a stable lifting structure.

Benefits of technology

It has achieved safe and efficient vertical lifting in hard strata, which has reduced engineering investment, shortened construction period, improved tunnel stability and construction safety, and reduced impact on the marine environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112878375B_ABST
    Figure CN112878375B_ABST
Patent Text Reader

Abstract

The invention discloses a method and structure for vertical lifting in an underwater tunnel suitable for hard strata. The implementation process is as follows: first, an offshore construction platform is built, and a steel casing is set up in the offshore platform to enter a hard and stable stratum; then, a hole is drilled under the protection of the casing to replace the hard stratum in the riser lifting area; the third step is to use the shield method to build the submarine main tunnel to the bottom of the lifting area; the fourth step is to vertically lift the riser to the sea area in sections through the replaced stratum in the main tunnel; the fifth step is to connect the steel casing with the upper steel structure diffusion structure; the sixth step is to fill the main tunnel with water, open the riser cover, and connect the sea area and the main tunnel to realize the function of taking / draining water. The invention can be well applied to geological conditions such as hard soil and rock formations, and its construction is convenient and safe, cost-effective, conducive to shortening the construction period, high facility stability, and safer and more reliable operation in the later stage of the project.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of submarine intake / drainage tunnel facility construction, and in particular to an implementation scheme for vertically lifting an underwater tunnel riser applicable to hard formations such as hard soil and rock. Background Art

[0002] At present, most nuclear power plants at home and abroad need to introduce seawater into the condenser for circulation and discharge to "cool down" the nuclear power plant. In order to reduce the impact on the marine environment, power plants built in recent years mostly use tunnels for water intake / drainage work, that is, tunnels are built under the seabed to connect the deep sea and the siphon wells on land. Considering the risks of underwater tunnel construction and to reduce the impact on the marine environment, water intake / drainage tunnels are mostly constructed using shield construction methods. After the water intake / drainage tunnel is excavated into the deep sea, it is connected to the deep sea through a vertical riser between the seabed and the tunnel. At present, the mainstream implementation plan for connecting risers in China is to push the risers out of the seabed surface section by section in the main tunnel through a cover after the construction of the main tunnel is completed, and finally add a head structure (cover) on the seabed surface. After the main tunnel is filled with water, the cover is removed to connect the main tunnel with seawater.

[0003] Since this method requires the riser to be buried in the main tunnel to the seabed surface, the burying needs to overcome the end resistance at the top of the riser and the side resistance on the side, and the lifting resistance is relatively large. Therefore, the vertical jacking method currently completed in China is only applicable to the working conditions where the upper part is a soft soil layer (standard penetration is less than 20 hits). At the same time, in order to facilitate the vertical jacking construction, the main tunnel at the riser position needs to be buried as shallowly as possible. Considering the construction safety and operation safety of the submarine main tunnel, the main tunnel should be buried as deep as possible and enter a better stratum. Therefore, for hard soil or rock formations with a large standard penetration number and a large burial depth of the main tunnel, the process of burying the riser in the tunnel cannot be used, and other methods such as artificial island excavation that have a greater impact on the sea area and require a larger investment need to be adopted.

[0004] In addition, for drainage tunnels, in order to prevent the pressurized water in the riser from directly rushing out of the water surface and forming a "spring" that affects the marine environment, it is necessary to add a cover structure to the head of the drainage riser in engineering practice. In places where the submarine currents are strong, in order to prevent the head structure from being washed away by the sea water, it is necessary to make a relatively large and bulky head structure and place it above the riser. In order to provide a stable foundation for the bulky head structure, it is necessary to first use a water dredger to clean up the silt, dump gravel, etc. This not only requires more engineering investment, but also increases the construction period. Summary of the invention

[0005] The technical problem to be solved by the present invention is to provide a method and structure for vertical jacking in underwater tunnels in hard strata, which is convenient and safe in construction, economical in cost, conducive to shortening the construction period, and safer and more reliable in the later operation of the project, in view of the defects of the prior art.

[0006] In order to solve the above technical problems, the present invention adopts the following technical solution: a method for vertical lifting in an underwater tunnel suitable for hard ground, characterized in that: the method is carried out according to the following steps:

[0007] The first step is to build an offshore construction platform, drive a casing into the stable stratum inside the construction platform, and make the top of the casing exposed above the sea surface;

[0008] The second step is to drill and replace the hard formation in the riser jacking area under the protection of the casing;

[0009] The third step is to separate the upper section of the casing from the lower section of the casing, so that the top of the lower section of the casing is submerged below the sea surface, and a temporary cover is installed on the top of the lower section of the casing;

[0010] The fourth step is to use the shield method to build the main submarine tunnel, which is connected to the bottom of the lower section of the casing;

[0011] The fifth step is to vertically lift the riser section by section through the replaced strata in the main tunnel to the sea area, and make the top of the riser submerge below the sea surface; inject cement slurry through the pre-buried flushing pipes around the riser to reinforce the surrounding replaced strata to strengthen the fixation of the riser;

[0012] Step 6: Connect the lower section of the casing to the upper steel diffusion structure and cover the riser inside;

[0013] The seventh step is to fill the main tunnel with water and open the lifting cover on the top of the riser to connect the main tunnel with the sea to realize the water intake / discharge function.

[0014] Furthermore, the casing is made of steel, and includes an independent upper casing section and a lower casing section, which are connected and fixed by a connecting flange, and the connecting flange is located 0.8-1.2m above the original mud surface; in the third step, the connecting flange is opened underwater, and then the upper casing section is hoisted out; the inner diameter of the casing is 0.4-0.6m larger than the later borehole diameter to reserve drilling operation space; the casing is driven to a depth embedded in a stable hard stratum, and the bottom end of the lower casing section is not less than 1 meter from the top of the main tunnel.

[0015] Furthermore, when replacing the hard strata in the second step, the replacement diameter is 0.8-1.2m larger than the outer diameter of the riser to reserve errors during the shield main tunnel and jacking construction; the replacement depth is 0.8-1.2m within the excavation range of the main tunnel arch to achieve complete engagement with the main tunnel; during replacement, non-toxic and harmless materials with a standard penetration number of less than 10 are filled to form a replacement layer, and the replacement materials include fine sand, soft soil, etc.

[0016] Furthermore, when replacing the hard formation in the second step, several flushing pipes are pre-buried in the casing near the inner wall of the lower section of the casing, so as to perform flushing to reduce resistance when excessive resistance is encountered during the later riser jacking process; the outer wall of the replacement layer is close to the inner wall of the lower section of the casing, and 6 to 10 flushing pipes are buried at equal intervals along the circumference of the replacement layer; the flushing pipes are PVC pipes with a diameter of 40 to 60 mm, and plum blossom-shaped flushing holes are provided at intervals of 0.8 to 1.2 m along the radial direction at the position where the flushing pipes are inserted into the replacement layer.

[0017] Furthermore, the temporary cover is made of a steel structure, which is connected and fixed to the lower section of the casing through a connecting flange to prevent the risk of breakdown and pressure relief during the construction of the underwater main tunnel.

[0018] Furthermore, the upper steel structure diffusion structure is a head cover, whose outer diameter is 20mm smaller than the inner diameter of the casing, is made of circular steel plate and sealed with ribs, and has water inlet and outlet windows on the side; anti-corrosion treatment is performed on the head cover according to the use environment and life span.

[0019] Furthermore, the head cover is initially connected to the lower section of the casing through a limit card reserved thereon, and then locked and fixed to the lower section of the casing using 12 M30 high-strength bolts.

[0020] Furthermore, after the main tunnel is constructed, steel pipe segments are installed at the bottom and dome of the main tunnel in alignment with the casing; and a reinforcement support portion is formed under the steel pipe segment at the bottom of the main tunnel by grouting, and a jacking reaction frame is erected in alignment with the reinforcement support portion to support the riser.

[0021] A vertical lifting implementation structure suitable for underwater tunnels in hard strata includes a main tunnel and a riser, and is characterized in that: the main tunnel is built in the hard stratum on the seabed, a casing is drilled above the main tunnel, the upper end of the casing is submerged below the sea surface, and there is a gap between the lower end of the casing and the main tunnel; the interior of the casing is a displacement layer formed by drilling and filling non-toxic and harmless materials with a standard penetration number of less than 10, and the riser is vertically lifted upward from the main tunnel so that the upper end of the riser passes through the displacement layer and extends into the seawater; a head cover with a through hole is fixed to the upper end of the casing, and the riser is covered inside the casing by the head cover.

[0022] The present invention has the following beneficial effects: First, it solves the problem that the vertical jacking method cannot be applied in hard soil, rock and other strata with a large standard penetration number. The vertical jacking method has low cost, good construction safety, and high construction efficiency. It is a commonly used method for connecting the intake / drainage tunnel with seawater. However, the traditional vertical jacking method has high requirements for the stratum conditions at the jacking position and can only be implemented in soft soil layers with a low standard penetration number. In recent years, with the large-scale construction and development of nuclear power plants at home and abroad, the stratum conditions encountered during the construction process are also different. After adopting the present invention, the vertical jacking method is no longer restricted by stratum conditions, especially in hard soil, rock strata and other sections. Compared with the traditional open-cut method for island construction, it can reduce project investment, shorten construction period, and reduce the impact on the marine environment.

[0023] Second, the new type of drainage head steel cover combined with the steel casing can greatly reduce the engineering cost of the drainage head cover, improve production efficiency, and shorten the construction period. In order to prevent the pressurized water of the drainage riser from directly rushing out of the water surface and forming a "spring eye" phenomenon, the top of the drainage riser needs to be covered with a diffusion cover. The head diffusion cover needs to maintain stability under the impact of the upward pressurized water in the riser and the impact of the horizontal ocean current on the seabed. The traditional practice usually designs the cover into a reinforced concrete structure weighing hundreds of tons. In order to place the head structure weighing hundreds of tons, it is necessary to first use the sea dredger to dredge the seabed to remove the upper soft silt layer, and then replace the cushion layer such as gravel as the foundation. After adopting the present invention, the head diffusion cover can be replaced with a light steel structure. At the same time, the present invention forms a "pile-cap" structure with the casing as a "pile" and the head steel cover as a cap by connecting the light steel structure cover with the steel casing used during the stratum replacement. It has sufficient stability in use, which can not only prevent the high-pressure water in the riser from rushing directly to the sea surface, but also form all-round permanent protection for the riser.

[0024] Third, the burial depth of the underwater main tunnel can be increased, which improves the safety of the main tunnel construction and operation. When designing traditional intake / drainage tunnels, in order to enable the later riser to be jacked up from the tunnel for construction, the tunnel axis at the riser position needs to be lifted as much as possible, and the top of the tunnel needs to be buried in a soft stratum, and the burial depth cannot be too large to avoid difficulty in jacking up due to excessive lateral resistance or end resistance of the stratum. However, the placement of the tunnel vault in a soft stratum and the shallow burial depth bring two important problems: one is the risk of breaking through the covering layer during shield construction, which is not conducive to construction safety; the other is that during operation, due to the thin covering layer, it may be subject to risks such as anchoring and shipwreck. After adopting the present invention, the main tunnel can be buried deep into a hard and stable stratum, and by replacing the original stratum, the resistance during jacking can be reduced to smoothly realize vertical jacking operations.

[0025] Fourth, the stability of the intake / drainage riser can be increased. In the traditional vertical jacking process, the risers need to be set in soft strata due to construction needs, which is not conducive to the risers' later wave resistance and earthquake resistance. After applying the present invention, the risers can be set in relatively stable hard soil and rock formations, greatly improving the stability of the risers during operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a schematic diagram of an offshore construction platform and a drilling steel casing;

[0027] Figure 2 Schematic diagram of using fine sand to replace the original stratum and adding a temporary cover;

[0028] Figure 3 The schematic diagram is for lifting the riser section by section out of the mud surface in the main tunnel;

[0029] Figure 4 A flange is used to connect the casing and the drainage cover.

[0030] In the figure, 11 is the upper section of the casing, 12 is the lower section of the casing, 2 is the riser, 3 is the steel pipe segment, 4 is the jacking cover, 5 is the flushing pipe, 6 is the reinforcement support part, 7 is the head cover, 8 is the connecting flange, 9 is the temporary cover, 10 is the construction platform, and 13 is the platform support. DETAILED DESCRIPTION

[0031] The present invention will be further described below by means of specific embodiments in conjunction with the accompanying drawings:

[0032] This embodiment is carried out according to the following steps:

[0033] 1. As attached Figure 1 As shown, a construction platform 10 is set up offshore and a steel casing is installed. The specific steps are:

[0034] Step 1: Combine the design drawings and offshore surveying technology to accurately locate the coordinates of each outlet in the sea area, and set up an offshore construction platform 10 near the drainage riser according to the design drawings. The bottom of the platform needs to be about 1m higher than the sea level during the temporary construction period (considering the wave height). The platform support 13 of the construction platform 10 needs to be driven into the stable formation to ensure the stability of the construction platform 10 during the drilling replacement period.

[0035] Step 2: Prefabricate the steel casing in the factory. The inner diameter of the casing should be about 0.5m larger than the borehole diameter. The wall thickness of the steel casing needs to be determined based on the stability during the construction period and the degree of seawater corrosion combined with the service life. The steel casing is composed of two sections, the upper and lower sections, which are connected and fixed by connecting flanges 8. The lower section 12 of the casing is buried underground in the seabed and is treated with relevant anti-corrosion treatment as a permanent structure.

[0036] Step 3: Drive a steel casing to the designed elevation through the offshore construction platform 10. The lower section 12 of the casing shall not enter the shield tunneling range and should be 1m above the shield arch.

[0037] 2. As attached Figure 2 As shown, the original stratum is replaced and a temporary cover 9 is added. The specific steps are:

[0038] Step 1: Use the construction platform 10 to replace the original soil layer in the jacking range with an impact drill or a rotary drill. The drilling range needs to be larger than the jacking range, with a diameter of about 1m and a drilling depth of 1m below the main tunnel arch.

[0039] The second step: Use the drilling mud with a large proportion to return the original stratum. After the original stratum is cleaned, adjust the mud density and fill the borehole with fine sand and other materials that are conducive to jacking to form a replacement layer.

[0040] Step 3: After the replacement is completed, the flange interface reserved in the middle of the steel casing is disassembled and the upper section 11 of the casing is lifted out.

[0041] Step 4: bury 8 φ50PVC flushing pipes 5 in advance to reserve conditions for later flushing resistance reduction and grouting reinforcement.

[0042] Step 5: In order to prevent the risk of pressure relief that may be caused during the subsequent shield tunneling, a temporary cover (steel material) is fixedly connected to the top of the lower section 12 of the casing by a flange.

[0043] Step 6: The main tunnel is constructed by the shield method. The shield machine's precise navigation system is used to excavate the tunnel with the replacement point as the target. Special steel segments 3 are arranged in the jacking range. A jacking cover 4 is reserved on the top of the steel segment 3. The jacking cover 4 and the steel segment 3 are connected by bolts.

[0044] 3. As attached Figure 3 As shown, the riser 2 is lifted out of the mud surface section by section in the main tunnel. The specific steps are as follows:

[0045] Step 1: In order to prevent insufficient reaction force of the stratum at the bottom of the main tunnel during jacking, grouting reinforcement is performed on the bottom of the tunnel to form a reinforced support portion 6.

[0046] Step 2: Remove the temporary cover 9 at the top of the lower section 12 of the casing.

[0047] Step 3: Set up a jacking reaction frame on the reinforced support part 6 in the main tunnel and install a vertical jacking sealing water-stopping system.

[0048] Step 4: Connect the first section of riser 2 to the jacking cover 4 on the steel pipe segment 3, perform trial jacking according to the calculated jacking force, and check the waterproof device, etc.

[0049] Step 5: Push out the riser 2 section by section. If the lifting resistance is too large during the lifting process, high-pressure flushing can be performed through the reserved flushing holes 5 to reduce the resistance.

[0050] Step 6: After the riser 2 is lifted, in order to increase the stability of the riser 2, cement slurry is injected through the pre-buried flushing pipe 5 around the riser 2 to reinforce the surrounding replacement strata.

[0051] 4. As attached Figure 4 As shown in the figure, connect the steel casing and the head cover, the specific steps are as follows:

[0052] The first step: prefabricate the head cover 7 of the steel structure in the factory. The head cover 7 is a permanent structure and needs to be treated for corrosion. It is advisable to use an anti-corrosion paint + sacrificial anode protection block solution for protection.

[0053] Step 2: transport the head cover 7 to the drain outlet by sea, dock the head cover 7 with the lower section of the casing driven in earlier, and connect them with 12 M30 high-strength bolts.

[0054] Step 3: Fill the main tunnel with water. When the internal and external water pressures are basically balanced, remove the jacking cover at the top of the first section of the riser 2 to form a water intake / discharge circuit.

[0055] The present invention has been described in detail above. The above description is only a preferred embodiment of the present invention and should not limit the scope of implementation of the present application. That is, all equivalent changes and modifications made within the scope of the present application should still fall within the scope of the present invention.

Claims

1. A vertical jacking method for underwater tunnels in hard ground, characterized by: Follow the steps below, The first step is to build an offshore construction platform, drive a casing into the stable stratum inside the construction platform, and make the top of the casing exposed above the sea surface; The second step is to drill and replace the hard formation in the riser jacking area under the protection of the casing; The third step is to separate the upper section of the casing from the lower section of the casing, so that the top of the lower section of the casing is submerged below the sea surface, and a temporary cover is installed on the top of the lower section of the casing; The fourth step is to use the shield method to build the main submarine tunnel, which is connected to the bottom of the lower section of the casing; The fifth step is to vertically lift the riser section by section through the replaced strata in the main tunnel to the sea area, and submerge the top of the riser below the sea surface; Step 6: Connect the lower section of the casing to the upper steel diffusion structure and cover the riser inside; Step 7: Fill the main tunnel with water and open the top cover on the riser to connect the main tunnel with the sea area to realize the water intake / discharge function; When replacing the hard ground in the second step, the replacement diameter is 0.8-1.2m larger than the outer diameter of the riser to reserve the error during the shield main tunnel and jacking construction; the replacement depth is 0.8-1.2m within the excavation range of the main tunnel arch to achieve complete engagement with the main tunnel; during replacement, non-toxic and harmless materials with a standard penetration number of less than 10 are filled to form a replacement layer, and the replacement materials include fine sand and soft soil; When replacing the hard formation in the second step, several flushing pipes are pre-buried in the casing near the inner wall of the lower section of the casing to reduce resistance by flushing when excessive resistance is encountered during the later riser jacking process; the outer wall of the replacement layer is close to the inner wall of the lower section of the casing, and 6-10 flushing pipes are buried at equal intervals along the circumference of the replacement layer; the flushing pipes are PVC pipes with a diameter of 40-60mm, and plum blossom-shaped flushing holes are arranged at intervals of 0.8-1.2m along the radial direction at the position where the flushing pipes are inserted into the replacement layer.

2. The vertical jacking implementation method in an underwater tunnel suitable for hard ground according to claim 1, characterized in that: The casing is made of steel, and includes an independent upper section and a lower section, which are connected and fixed by a connecting flange. The connecting flange is located 0.8-1.2m above the original mud surface. In the third step, the connecting flange is opened underwater, and then the upper section of the casing is hoisted out. The inner diameter of the casing is 0.4-0.6m larger than the later borehole diameter to reserve space for drilling operations. The casing is set to a depth embedded in a stable hard stratum, and the bottom end of the lower section of the casing is not less than 1 meter from the top of the main tunnel.

3. The vertical jacking implementation method in an underwater tunnel suitable for hard ground according to claim 1, characterized in that: The temporary cover is made of steel structure, which is connected and fixed to the lower section of the casing through a connecting flange to prevent the risk of breakdown and pressure relief during the construction of the underwater main tunnel.

4. The vertical jacking implementation method in an underwater tunnel suitable for hard ground according to claim 1, characterized in that: The upper steel structure diffusion structure is a head cover, whose outer diameter is 20mm smaller than the inner diameter of the casing, made of circular steel plate and sealed with ribs, with water inlet and outlet windows on the side; anti-corrosion treatment is performed on the head cover according to the use environment and life span.

5. The vertical jacking implementation method in an underwater tunnel suitable for hard ground according to claim 4 is characterized in that: The head cover is initially connected to the lower section of the casing through the limit card reserved on it, and then locked and fixed to the lower section of the casing with 12 M30 high-strength bolts.

6. The vertical jacking implementation method in an underwater tunnel suitable for hard ground according to claim 1, characterized in that: After the main tunnel is built, steel segments are installed on the bottom and dome of the main tunnel in alignment with the casing; A reinforced support portion is formed under the steel pipe segment at the bottom of the main tunnel by grouting, and a jacking reaction frame is set up aligned with the reinforced support portion to support the riser.