Refrigerant adjustment device, refrigerant recovery equipment, and control method of refrigerant recovery equipment

By designing a refrigerant adjustment device and using the combined control of multiple valves and compressors to achieve precise transfer and recovery of refrigerant, the problem of refrigerant waste and leakage in refrigeration equipment is solved, and production efficiency and resource utilization are improved.

CN113007932BActive Publication Date: 2024-10-22GREE ELECTRIC APPLIANCE INC OF ZHUHAI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110291892.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-03-18
Publication Date
2024-10-22
Estimated Expiration
2041-03-18

AI Technical Summary

Technical Problem

During the production, inspection and maintenance of refrigeration equipment, refrigerant waste and leakage are serious problems, especially in the after-sales maintenance of household air conditioners and the position of the compressor of special air conditioners. The refrigerant filling amount is difficult to accurately control, resulting in waste of resources and production efficiency. low.

Method used

A refrigerant adjustment device is designed, including a suction pipeline, an exhaust pipeline and a compression pipeline. By setting up multiple valves and compressors, the precise transfer and recovery of refrigerant is achieved to ensure no waste and no leakage. The vacuum pipe is used circuit and gas-liquid separator for regulating and recovering refrigerant.

Benefits of technology

It achieves precise transfer and recovery of refrigerant, reduces resource waste, improves production efficiency, ensures the consistency of the amount of refrigerant in the refrigeration equipment, avoids refrigerant leakage, and reduces production costs and time waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113007932B_ABST
    Figure CN113007932B_ABST
Patent Text Reader

Abstract

The present application provides a refrigerant adjustment device, a refrigerant recovery device and a control method for the refrigerant recovery device. The refrigerant adjustment device includes an intake pipeline, an exhaust pipeline and a compression pipeline. The first end of the compression pipeline is connected to the intake pipeline, and the second end is connected to the exhaust pipeline. The exhaust pipeline includes a first interface and a second interface. The intake pipeline includes a third interface and a fourth interface. A first compressor is arranged on the compression pipeline. A valve A is arranged between the first compressor and the exhaust pipeline. The compression pipeline and the exhaust pipeline form a first node at the connection position. A valve B is arranged on the exhaust pipeline between the first node and the second interface. A valve C is arranged on the compression pipeline between the first compressor and the intake pipeline. The refrigerant adjustment device also includes a vacuum pipeline, and a valve E is arranged on the vacuum pipeline. According to the refrigerant adjustment device of the present application, the original refrigerant in the refrigeration equipment can be accurately transferred during production inspection to ensure no waste or leakage.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of refrigerant recovery, and in particular to a refrigerant adjustment device, a refrigerant recovery device, and a control method for the refrigerant recovery device. Background Art

[0002] The emission of Freon gas will damage the atmosphere, cause the greenhouse effect and lead to a series of environmental problems such as global temperature rise. Refrigeration equipment using Freon refrigerants is used in all walks of life. From source production detection to user use, after-sales maintenance and scrapping, there may be leakage of Freon refrigerants in each link, and even human private emission. As the supervision of Freon refrigerants becomes more and more stringent, it is necessary to strictly monitor, recycle and reuse the Freon refrigerants in the above-mentioned process links. In particular, during the testing and maintenance process, it is often necessary to move the refrigerant in the refrigeration equipment, and it is necessary to ensure that the refrigerant will not leak into the atmosphere when the connecting pipe is disconnected.

[0003] After-sales maintenance is difficult to supervise, and it is even rarer to use refrigerant recovery equipment for after-sales maintenance. In particular, there are a lot of refrigerant leaks and refrigerant recharges in the after-sales maintenance of household air conditioners. On the other hand, the compressors of some special air conditioners, especially those in computer rooms, are placed on the low-pressure indoor unit side. The refrigerant used for pressure-maintaining leak detection during the production test is different from the rated refrigerant filled in the unit. The frequent connection test process makes it difficult to accurately control the refrigerant filling amount in the unit when it leaves the factory. Basically, the refrigerant can only be refilled by vacuuming. This process is very wasteful of refrigerant and results in high production costs; vacuuming, maintaining pressure, and refilling refrigerant also wastes production time and results in low production efficiency.

[0004] Therefore, it is necessary to develop a refrigerant recovery and adjustment device to accurately transfer the original refrigerant in the refrigeration equipment during production inspection to ensure no waste or leakage. Summary of the invention

[0005] Therefore, the technical problem to be solved by the present application is to provide a refrigerant adjustment device, a refrigerant recovery equipment and a control method for the refrigerant recovery equipment, which can accurately transfer the original refrigerant in the refrigeration equipment during production inspection to ensure no waste or leakage.

[0006] In order to solve the above problems, the present application provides a refrigerant adjustment device, including an intake pipeline, an exhaust pipeline and a compression pipeline, the first end of the compression pipeline is connected to the intake pipeline, the second end of the compression pipeline is connected to the exhaust pipeline, the first end of the exhaust pipeline includes a first interface, the second end includes a second interface, the first end of the intake pipeline includes a third interface, the second end includes a fourth interface, a first compressor is arranged on the compression pipeline, a valve A is arranged between the first compressor and the exhaust pipeline, the compression pipeline and the exhaust pipeline form a first node at a connection position, a valve B is arranged on the exhaust pipeline between the first node and the second interface, a valve C is arranged on the compression pipeline between the first compressor and the intake pipeline, the refrigerant adjustment device also includes a vacuum pipeline, a valve E is arranged on the vacuum pipeline, and the vacuum pipeline is configured to vacuum the refrigerant adjustment device.

[0007] Preferably, a first pressure sensor is provided at the exhaust port of the first compressor, and a second pressure sensor is provided on the intake pipe.

[0008] Preferably, a gas-liquid separator is also provided on the compression pipeline, and the air intake port of the first compressor is connected to the outlet of the gas-liquid separator.

[0009] Preferably, the refrigerant adjustment device also includes a recovery pipeline, the first end of the recovery pipeline is connected to the suction pipeline, a second compressor and a valve D are provided on the recovery pipeline, the valve D is located at the end where the suction port of the second compressor is located, and the exhaust port of the second compressor is connected to the inlet of the gas-liquid separator.

[0010] Preferably, a vacuum pump is also provided on the vacuum pumping pipeline, the valve E is provided at the suction end of the vacuum pump, and the vacuum pumping pipeline is connected to the suction pipeline or the exhaust pipeline.

[0011] Preferably, a connecting pipe is connected between the second interface and the third interface, the first interface is connected to an exhaust pipe, the fourth interface is connected to an intake pipe, an opening and closing handle is provided at the end of the exhaust pipe away from the first interface, and an opening and closing handle is provided at the end of the intake pipe away from the fourth interface.

[0012] According to one aspect of the present application, a refrigerant recovery device is provided, including a refrigeration unit, the refrigeration unit including an indoor unit and an outdoor unit, and the refrigerant recovery device also includes the above-mentioned refrigerant adjustment device.

[0013] Preferably, the first interface is connected to the inlet of the indoor unit, the second interface is connected to the outlet of the outdoor unit, the third interface is connected to the inlet of the outdoor unit, and the fourth interface is connected to the outlet of the indoor unit.

[0014] Preferably, the indoor unit also includes a unit compressor and an indoor heat exchanger, the unit compressor is arranged between the indoor heat exchanger and the outlet of the indoor unit, an air valve is arranged on the pipeline between the unit compressor and the outlet of the indoor unit, and a liquid valve is arranged on the pipeline between the indoor heat exchanger and the inlet of the indoor unit.

[0015] According to one aspect of the present application, a refrigerant recovery device is provided, including a refrigeration unit, the refrigeration unit including an indoor unit and an outdoor unit, and the refrigerant recovery device also includes the above-mentioned refrigerant adjustment device.

[0016] Preferably, the indoor unit also includes a unit compressor and an indoor heat exchanger, the unit compressor is arranged between the indoor heat exchanger and the outlet of the indoor unit, a fluorine injection device is arranged on the pipeline between the unit compressor and the indoor heat exchanger, an air valve is arranged on the pipeline between the unit compressor and the outlet of the indoor unit, a liquid valve is arranged on the pipeline between the indoor heat exchanger and the inlet of the indoor unit, the exhaust pipe is connected to the air valve, and the intake pipe is connected to the fluorine injection device.

[0017] Preferably, the indoor unit also includes a unit compressor and an indoor heat exchanger, the unit compressor is arranged between the indoor heat exchanger and the outlet of the indoor unit, a fluorine injection device is arranged on the pipeline between the unit compressor and the indoor heat exchanger, an air valve is arranged on the pipeline between the unit compressor and the outlet of the indoor unit, a liquid valve is arranged on the pipeline between the indoor heat exchanger and the inlet of the indoor unit, the exhaust pipe is connected to the fluorine injection device, and the intake pipe is connected to the air valve.

[0018] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided, comprising:

[0019] Check whether the vacuum pumping of the refrigerant adjustment device is qualified;

[0020] When the vacuum pumping of the refrigerant adjustment device is qualified, close the other valves of the refrigerant adjustment device, open the gas valve and liquid valve, open valve B, and test the refrigeration unit;

[0021] After the refrigeration unit is tested, the refrigerant in the outdoor unit and the refrigerant adjustment device is transported to the indoor unit by using the refrigerant adjustment device;

[0022] Close all valves of the refrigerant adjustment device, close the gas valve and the liquid valve, disconnect the first interface and the inlet of the indoor unit, disconnect the fourth interface and the outlet of the indoor unit, and complete the test of the refrigeration unit.

[0023] Preferably, the step of detecting whether the vacuuming of the refrigerant adjustment device is qualified comprises:

[0024] Keep the gas valve and liquid valve closed;

[0025] Open all valves of the refrigerant adjustment device and control the refrigerant adjustment device to start vacuuming;

[0026] Detect the pressure PH of the exhaust pipeline and the pressure PL of the suction pipeline, and stop vacuuming when the vacuum pressure meets the vacuum requirement;

[0027] Close valve E and hold for time t1 to check whether the vacuum degree of the refrigerant adjustment device meets the vacuum degree requirements. If so, the vacuuming is considered qualified.

[0028] Preferably, the step of using the refrigerant adjustment device to transport the refrigerant in the outdoor unit and the refrigerant adjustment device to the indoor unit includes:

[0029] Close the gas valve, valve B, valve D and valve E, and open the liquid valve, valve A and valve C;

[0030] Start the first compressor to press the refrigerant from the outdoor unit into the indoor unit.

[0031] Preferably, the step of using the refrigerant adjustment device to transport the refrigerant in the outdoor unit and the refrigerant adjustment device to the indoor unit further includes:

[0032] detecting a pressure ratio of the first compressor;

[0033] When the pressure ratio of the first compressor is n=PH / PL>n1, valve C is closed, valve D is opened, and the second compressor is started, where n1 is the set pressure ratio;

[0034] Check whether the pressure PL of the suction line reaches the set pressure;

[0035] When the pressure PL of the suction line reaches the set pressure, the current vacuum degree is maintained for t2 time, and then the first compressor and the second compressor are stopped.

[0036] Preferably, after closing all valves of the refrigerant adjustment device, the step of closing the gas valve and the liquid valve further includes:

[0037] Open valve B and valve D to start the second compressor;

[0038] Press the refrigerant into the gas-liquid separator;

[0039] When the pressure PL of the suction line reaches the set pressure, the current vacuum degree is maintained for t2 time, the second compressor is stopped, and valves B and D are closed.

[0040] Preferably, during the first vacuuming, the vacuum pump is directly connected to the atmosphere, and during subsequent vacuuming, the vacuum pump is connected to the recovery container.

[0041] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided, comprising:

[0042] Close valve A, valve C, valve D and valve E, open valve B, and test the refrigeration unit;

[0043] After the refrigeration unit has been tested,

[0044] Open valve D and start the second compressor to transfer the refrigerant to the gas-liquid separator; or open valve C to transfer the refrigerant to the gas-liquid separator.

[0045] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided, comprising:

[0046] Close the exhaust and suction pipes;

[0047] Open all valves of the refrigerant adjustment device and start the vacuum pump to evacuate;

[0048] After the vacuum is qualified, close all valves of the refrigerant adjustment device, close the gas valve and liquid valve, and open the exhaust and suction pipes;

[0049] Open valve A and valve C, start the first compressor to transfer the refrigerant of the indoor unit to the outdoor unit;

[0050] Close the exhaust pipe and the suction pipe and perform maintenance on the indoor unit;

[0051] When the maintenance of the indoor unit is completed, disconnect the suction pipe and the exhaust pipe from the refrigeration unit;

[0052] Open the gas valve and liquid valve of the refrigeration unit.

[0053] Preferably, the step of starting the first compressor to transfer the refrigerant of the indoor unit to the outdoor unit further includes:

[0054] detecting a pressure ratio of the first compressor;

[0055] When the pressure ratio of the first compressor is n=PH / PL>n1, valve C is closed, valve D is opened, and the second compressor is started, where n1 is the set pressure ratio;

[0056] Check whether the pressure PL of the suction line reaches the set pressure;

[0057] When the pressure PL of the suction line reaches the set pressure, the current vacuum degree is maintained for t2 time, and then the first compressor and the second compressor are stopped;

[0058] Close the intake and exhaust ports.

[0059] Preferably, after the maintenance of the indoor unit is completed, before the step of disconnecting the suction pipe and the exhaust pipe from the refrigeration unit, the step further includes:

[0060] Open the air intake pipe to connect the refrigerant adjustment device to the indoor unit;

[0061] Open valve E and turn on the vacuum pump to evacuate the indoor unit until the vacuum degree meets the requirements;

[0062] Close valve E, vacuum pump and suction pipe in sequence.

[0063] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided, comprising:

[0064] Close all valves of the refrigerant adjustment device;

[0065] Open the exhaust pipe;

[0066] Open valve B;

[0067] Open valve D and start the second compressor to transfer the refrigerant to the gas-liquid separator; or open valve C to transfer the refrigerant to the gas-liquid separator.

[0068] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided, comprising:

[0069] Close the exhaust and suction pipes;

[0070] Open all valves of the refrigerant adjustment device and start the vacuum pump to evacuate;

[0071] After the vacuum is qualified, close all valves of the refrigerant adjustment device, close the gas valve and liquid valve, and open the exhaust and suction pipes;

[0072] Open valve A and valve C, start the first compressor to transfer the refrigerant of the outdoor unit to the indoor unit;

[0073] Close the exhaust pipe and the suction pipe and perform maintenance on the outdoor unit;

[0074] After the maintenance of the outdoor unit is completed, disconnect the suction pipe and the exhaust pipe from the refrigeration unit;

[0075] Open the gas valve and liquid valve of the refrigeration unit.

[0076] Preferably, the step of starting the first compressor to transfer the refrigerant of the outdoor unit to the indoor unit further includes:

[0077] detecting a pressure ratio of the first compressor;

[0078] When the pressure ratio of the first compressor is n=PH / PL>n1, valve C is closed, valve D is opened, and the second compressor is started, where n1 is the set pressure ratio;

[0079] Check whether the pressure PL of the suction line reaches the set pressure;

[0080] When the pressure PL of the suction line reaches the set pressure, the current vacuum degree is maintained for t2 time, and then the first compressor and the second compressor are stopped;

[0081] Close the intake and exhaust ports.

[0082] Preferably, after the maintenance of the outdoor unit is completed, before the step of disconnecting the suction pipe and the exhaust pipe from the refrigeration unit, the step further includes:

[0083] Open the air suction pipe to connect the refrigerant adjustment device with the outdoor unit;

[0084] Open valve E and turn on the vacuum pump to evacuate the outdoor unit until the vacuum degree meets the requirements;

[0085] Close valve E, vacuum pump and suction pipe in sequence.

[0086] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided, comprising:

[0087] Close all valves of the refrigerant adjustment device;

[0088] Open the suction pipe;

[0089] Open valve D and start the second compressor to transfer the refrigerant to the gas-liquid separator; or open valve C to transfer the refrigerant to the gas-liquid separator.

[0090] According to one aspect of the present application, a control method for the above-mentioned refrigerant recovery equipment is provided. When the refrigerant recovery equipment includes a gas-liquid separator, the control method includes:

[0091] When it is necessary to add refrigerant to the refrigeration unit, the first compressor is turned on and valve A is opened to inject the refrigerant in the gas-liquid separator into the refrigeration unit;

[0092] Calculate the refrigerant mass remaining in the gas-liquid separator and obtain the refrigerant mass adjustment data in the refrigeration unit;

[0093] After the refrigerant quality in the refrigeration unit is adjusted to the target quality, valve A is closed to turn off the first compressor.

[0094] The refrigerant adjustment device provided in the present application includes an intake pipeline, an exhaust pipeline and a compression pipeline. The first end of the compression pipeline is connected to the intake pipeline, and the second end of the compression pipeline is connected to the exhaust pipeline. The first end of the exhaust pipeline includes a first interface, and the second end includes a second interface. The first end of the intake pipeline includes a third interface, and the second end includes a fourth interface. A first compressor is arranged on the compression pipeline, and a valve A is arranged between the first compressor and the exhaust pipeline. The compression pipeline and the exhaust pipeline form a first node at a connection position, a valve B is arranged on the exhaust pipeline between the first node and the second interface, and a valve C is arranged on the compression pipeline between the first compressor and the intake pipeline. The refrigerant adjustment device also includes a vacuum pipeline, and a valve E is arranged on the vacuum pipeline. The vacuum pipeline is configured to vacuum the refrigerant adjustment device. The refrigerant adjusting device is provided with a plurality of valves and a first compressor, and a vacuum extraction pipeline at the same time. When the refrigeration unit is subjected to production testing, different valve opening and closing combinations and compressor operation control can be utilized, so that the compressor in the refrigerant adjusting device can replace the compressor in the refrigeration unit, and adjustment actions such as refrigerant migration can be realized. The consistency of the refrigerant amount in the refrigerant adjusting device is utilized to ensure the consistency of the refrigerant amount in the refrigeration unit. After the test is completed, the refrigerant in the refrigeration unit can be smoothly returned to the indoor unit on the low-pressure side. During production testing, the original refrigerant in the refrigeration equipment can be accurately transferred to ensure that there is no waste or leakage. BRIEF DESCRIPTION OF THE DRAWINGS

[0095] Figure 1 This is a structural principle diagram of a refrigerant recovery device according to one embodiment of the present application;

[0096] Figure 2 This is a structural schematic diagram of a refrigerant recovery device according to one embodiment of the present application;

[0097] Figure 3 This is a structural schematic diagram of a refrigerant recovery device according to an embodiment of the present application.

[0098] The reference numerals are as follows:

[0099] 1. Suction pipeline; 2. Exhaust pipeline; 3. Compression pipeline; 4. First interface; 5. Second interface; 6. Third interface; 7. Fourth interface; 8. First compressor; 9. Vacuum pipeline; 10. First pressure sensor; 11. Second pressure sensor; 12. Gas-liquid separator; 13. Recovery pipeline; 14. Second compressor; 15. Vacuum pump; 16. Connecting pipeline; 17. Exhaust pipe; 18. Suction pipe; 19. Unit compressor; 20. Indoor heat exchanger; 21. Gas valve; 22. Liquid valve; 23. Fluorine injection device; 24. Throttle valve; 25. Outdoor heat exchanger. DETAILED DESCRIPTION

[0100] See also Figure 1As shown, according to an embodiment of the present application, the refrigerant adjustment device includes an intake pipeline 1, an exhaust pipeline 2 and a compression pipeline 3, the first end of the compression pipeline 3 is connected to the intake pipeline 1, the second end of the compression pipeline 3 is connected to the exhaust pipeline 2, the first end of the exhaust pipeline 2 includes a first interface 4, and the second end includes a second interface 5, the first end of the intake pipeline 1 includes a third interface 6, and the second end includes a fourth interface 7, a first compressor 8 is arranged on the compression pipeline 3, a valve A is arranged between the first compressor 8 and the exhaust pipeline 2, the compression pipeline 3 and the exhaust pipeline 2 form a first node at the connection position, a valve B is arranged on the exhaust pipeline 2 between the first node and the second interface 5, a valve C is arranged on the compression pipeline 3 between the first compressor 8 and the intake pipeline 1, the refrigerant adjustment device also includes a vacuum pipeline 9, a valve E is arranged on the vacuum pipeline 9, and the vacuum pipeline 9 is configured to vacuum the refrigerant adjustment device.

[0101] The refrigerant adjusting device is provided with a plurality of valves and a first compressor 8, and a vacuum pipeline 9. When the refrigeration unit is subjected to production testing, different valve opening and closing combinations and compressor operation control can be used to enable the compressor in the refrigerant adjusting device to replace the compressor in the refrigeration unit, so as to achieve adjustment actions such as refrigerant migration. The consistency of the refrigerant amount in the refrigerant adjusting device is utilized to ensure the consistency of the refrigerant amount in the refrigeration unit. After the test, the refrigerant in the refrigeration unit can be smoothly returned to the indoor unit on the low-pressure side. During production testing, the original refrigerant in the refrigeration equipment can be accurately transferred to ensure that there is no waste or leakage.

[0102] The exhaust port of the first compressor 8 is provided with a first pressure sensor 10, and the suction pipe 1 is provided with a second pressure sensor 11. The first pressure sensor 10 is used as a high-pressure sensor to detect the pressure at the exhaust port of the first compressor 8, and the second pressure sensor 11 is used as a low-pressure sensor to detect the pressure at the suction port of the first compressor 8 or in the suction pipe 1. By measuring these two pressures, the vacuum degree in the refrigerant adjustment device can be calculated, thereby determining whether the vacuum degree in the refrigerant adjustment device meets the requirements, providing a reliable test basis for the implementation of other tests.

[0103] A gas-liquid separator 12 is also provided on the compression pipeline 3, and the air inlet of the first compressor 8 is connected to the outlet of the gas-liquid separator 12. The gas-liquid separator 12 can store the refrigerant, and when the amount of refrigerant in the refrigeration unit needs to be adjusted, the excess refrigerant in the refrigeration unit can be transferred to the gas-liquid separator 12 for storage, thereby facilitating the adjustment of the refrigerant amount of the refrigeration unit, so that the amount of refrigerant in the refrigeration unit can more accurately meet the operation requirements.

[0104] The refrigerant adjustment device also includes a recovery pipeline 13, a first end of which is connected to the suction pipeline 1, a second compressor 14 and a valve D are provided on the recovery pipeline 13, the valve D is located at the end where the suction port of the second compressor 14 is located, and the exhaust port of the second compressor 14 is connected to the inlet of the gas-liquid separator 12. The second compressor 14 is connected in series with the first compressor 8, and can realize multiple functions such as single compressor operation, dual compressor series operation, and compressor forced refrigerant recovery by adjusting the connection state of the first compressor 8 and the second compressor 14, thereby improving the application scope of the refrigerant adjustment device, enhancing the adjustment function of the refrigerant adjustment device, and meeting various needs of refrigerant adjustment.

[0105] A vacuum pump 15 is also provided on the vacuum pumping line 9, a valve E is provided at the suction end of the vacuum pump 15, and the vacuum pumping line 9 is connected to the suction line 1 or the exhaust line 2. In this embodiment, the outlet of the vacuum pump 15 is not shown to be connected to the recovery container. When the refrigerant adjustment device is used for the first time without refrigerant recovery, and the vacuum pump 15 sucks air, the outlet of the vacuum pump 15 can be directly connected to the atmosphere.

[0106] In one embodiment, the vacuum pump 15 may not be provided on the vacuum pumping pipeline 9. When vacuum pumping is required, the vacuum pumping pipeline 9 may be directly connected to an external vacuum pumping system to perform a vacuum pumping operation.

[0107] See also Figure 2 and Figure 3 In one embodiment, a connecting pipe 16 is connected between the second interface 5 and the third interface 6, the first interface 4 is connected to an exhaust pipe 17, and the fourth interface 7 is connected to an intake pipe 18. An opening and closing handle is provided at the end of the exhaust pipe 17 away from the first interface 4, and an opening and closing handle is provided at the end of the intake pipe 18 away from the fourth interface 7.

[0108] See also Figure 1 As shown, in one embodiment, the refrigerant recovery device includes a refrigeration unit, the refrigeration unit includes an indoor unit and an outdoor unit, and the refrigerant recovery device also includes the above-mentioned refrigerant adjustment device.

[0109] The first interface 4 is connected to the inlet of the indoor unit, the second interface 5 is connected to the outlet of the outdoor unit, the third interface 6 is connected to the inlet of the outdoor unit, and the fourth interface 7 is connected to the outlet of the indoor unit.

[0110] The indoor unit also includes a unit compressor 19 and an indoor heat exchanger 20. The unit compressor 19 is arranged between the indoor heat exchanger 20 and the outlet of the indoor unit. An air valve 21 is arranged on the pipeline between the unit compressor 19 and the outlet of the indoor unit. A liquid valve 22 is arranged on the pipeline between the indoor heat exchanger 20 and the inlet of the indoor unit.

[0111] In the refrigerant recovery equipment of the present embodiment, the indoor unit at least includes an organic unit compressor 19, a fluorine injection device 23, an indoor heat exchanger 20, a throttle valve 24, an air valve 21 and a liquid valve 22, and also includes an inlet and an outlet of the indoor unit. Usually, the air valve 21 and the liquid valve 22 are also provided with a fluorine injection nozzle. The air valve 21 and the liquid valve 22 can only be opened or closed manually. When the air valve 21 and / or the liquid valve 22 are closed, the fluorine injection nozzle on the air valve 21 or the liquid valve 22 can only be connected to the outdoor unit or the indoor unit. The present application assumes that when the air valve 21 or the liquid valve 22 is closed, its own fluorine injection nozzle is connected to the outdoor unit and is not connected to the indoor unit; the outdoor unit at least includes an outdoor heat exchanger 25, an inlet of the outdoor unit and an outlet of the outdoor unit.

[0112] In one embodiment, a refrigerant recovery device includes a refrigeration unit, the refrigeration unit includes an indoor unit and an outdoor unit, and the refrigerant recovery device also includes the above-mentioned refrigerant adjustment device.

[0113] See also Figure 2 As shown, in one embodiment, the indoor unit also includes a unit compressor 19 and an indoor heat exchanger 20, the unit compressor 19 is arranged between the indoor heat exchanger 20 and the outlet of the indoor unit, a fluorine injection device 23 is arranged on the pipeline between the unit compressor 19 and the indoor heat exchanger 20, an air valve 21 is arranged on the pipeline between the unit compressor 19 and the outlet of the indoor unit, a liquid valve 22 is arranged on the pipeline between the indoor heat exchanger 20 and the inlet of the indoor unit, the exhaust pipe 17 is connected to the air valve 21, and the intake pipe 18 is connected to the fluorine injection device 23.

[0114] See also Figure 3 As shown, in another embodiment, the indoor unit further includes a unit compressor 19 and an indoor heat exchanger 20, the unit compressor 19 is arranged between the indoor heat exchanger 20 and the outlet of the indoor unit, a fluorine injection device 23 is arranged on the pipeline between the unit compressor 19 and the indoor heat exchanger 20, an air valve 21 is arranged on the pipeline between the unit compressor 19 and the outlet of the indoor unit, a liquid valve 22 is arranged on the pipeline between the indoor heat exchanger 20 and the inlet of the indoor unit, the exhaust pipe 17 is connected to the fluorine injection device 23, and the intake pipe 18 is connected to the air valve 21.

[0115] The fluorine injection device 23 is, for example, a fluorine injection nozzle.

[0116] like Figure 2 and Figure 3 As shown, the indoor unit and the outdoor unit can be connected through a gas connection pipe and a liquid connection pipe, the gas connection pipe connects the outlet of the indoor unit and the inlet of the outdoor unit, and the liquid connection pipe connects the inlet of the indoor unit and the outlet of the outdoor unit. Figure 1As shown, no gas connection pipes and liquid connection pipes are required. The first interface 4 is directly connected to the inlet of the indoor unit, the second interface 5 is directly connected to the outlet of the outdoor unit, the third interface 6 is directly connected to the inlet of the outdoor unit, and the fourth interface 7 is directly connected to the outlet of the indoor unit.

[0117] In one embodiment, the control method of the refrigerant recovery equipment includes: detecting whether the vacuum pumping of the refrigerant adjustment device is qualified; when the vacuum pumping of the refrigerant adjustment device is qualified, closing the other valves of the refrigerant adjustment device, opening the gas valve 21 and the liquid valve 22, opening the valve B, and testing the refrigeration unit; after the test of the refrigeration unit is completed, using the refrigerant adjustment device to transport the refrigerant in the outdoor unit and the refrigerant adjustment device to the indoor unit; closing all valves of the refrigerant adjustment device, closing the gas valve 21 and the liquid valve 22, disconnecting the connection between the first interface 4 and the inlet of the indoor unit, disconnecting the connection between the fourth interface 7 and the outlet of the indoor unit, and completing the test of the refrigeration unit.

[0118] The steps of detecting whether the vacuum pumping of the refrigerant adjustment device is qualified include: keeping the gas valve 21 and the liquid valve 22 in a closed state; opening all valves of the refrigerant adjustment device, controlling the refrigerant adjustment device to start vacuum pumping; detecting the pressure PH on the exhaust pipe 2 and the pressure PL on the suction pipe 1, and stopping the vacuum pumping when the vacuum pumping pressure meets the vacuum degree requirement; closing valve E and maintaining the time t1 to detect whether the vacuum degree of the refrigerant adjustment device meets the vacuum degree requirement. If so, the vacuum pumping is considered qualified.

[0119] The steps of using the refrigerant adjustment device to transport the refrigerant in the outdoor unit and the refrigerant adjustment device to the indoor unit include: closing the gas valve 21, valve B, valve D and valve E, opening the liquid valve 22, valve A and valve C; starting the first compressor 8 to press the refrigerant of the outdoor unit into the indoor unit.

[0120] The step of using the refrigerant adjustment device to transport the refrigerant in the outdoor unit and the refrigerant adjustment device to the indoor unit also includes: detecting the pressure ratio of the first compressor 8; when the pressure ratio of the first compressor 8 is n=PH / PL>n1, closing the valve C, opening the valve D, and starting the second compressor 14, wherein n1 is the set pressure ratio, which is a preset pressure ratio value, equivalent to a critical value, and is related to the performance requirements of the first compressor 8 or the second compressor 14 itself; detecting whether the pressure PL of the suction line 1 reaches the set pressure; when the pressure PL of the suction line 1 reaches the set pressure, maintaining the current vacuum degree for t2 time, and then stopping the first compressor 8 and the second compressor 14. If the first compressor 8 itself can meet the pressure ratio n≤n1 and the vacuum degree meets the requirements, there is no need to start the second compressor 14.

[0121] After closing all valves of the refrigerant adjustment device and closing the gas valve 21 and the liquid valve 22, the steps also include: opening valve B and valve D, starting the second compressor 14; pressing the refrigerant into the gas-liquid separator 12; when the pressure PL of the suction pipeline 1 reaches the set pressure, maintaining the current vacuum degree for t2 time, stopping the second compressor 14, and closing valve B and valve D.

[0122] When vacuuming for the first time, the vacuum pump 15 is directly connected to the atmosphere, and when vacuuming is performed subsequently, the vacuum pump 15 is connected to the recovery container.

[0123] During production test, indoor unit and outdoor unit are in separate state, and because outdoor unit is very simple, it is not equipped with complicated electric control system, but indoor unit is complicated in structure and equipped with electric control system, so on production line, indoor unit is mainly tested online and refrigeration system leak detection is performed. Common practice is: indoor unit is perfused with a small amount of refrigerant for leak detection, outdoor unit adopts test fixture to be equipped with sufficient refrigerant, indoor and outdoor units are connected and run with refrigerant in test fixture of outdoor unit, after test is completed, liquid valve 22 is closed, refrigerant is all pressed into test fixture of outdoor unit through compressor 19 of unit, and this includes a small amount of refrigerant used for leak detection of indoor unit. Due to the use of test fixture of the same outdoor unit, after testing multiple indoor units, the refrigerant for leak detection of numerous original indoor units will also be accumulated one by one in the test fixture of outdoor unit, resulting in more and more refrigerant in the test fixture, which can only be discharged or adjusted regularly, which will affect the accuracy of test and also cause waste of production cost, extension of production time and reduce production efficiency.

[0124] After the refrigerant adjustment device of the present application is connected to the outdoor unit, the refrigerant adjustment device and the outdoor unit will be used as test tools for online testing on the production line. It is only necessary to connect the first interface 4 to the inlet of the indoor unit and the fourth interface 7 to the outlet of the indoor unit. At the same time, the rated filling amount of the unit is required to replace the original small amount of refrigerant for leak detection in the indoor unit.

[0125] The working process of the refrigerant adjustment device in this application during production testing is as follows:

[0126] ①→After the refrigerant adjustment device is connected to the indoor unit, the gas valve 21 and the liquid valve 22 are in the original closed state and should not be opened. After ensuring that the connection is accurate and tight, open all valves AE on the refrigerant adjustment device. After the various valves are in place according to the following table, the refrigerant adjustment device starts the first vacuum operation. During the first vacuum operation, it is not necessary to connect the refrigerant recovery container, and the vacuum pump 15 is directly connected to the atmosphere:

[0127] Valve A Valve B Valve C Valve D Valve E Air valve Liquid valve Open Open Open Open Open closure closure

[0128] The vacuum pump 15 starts running until the first pressure sensor 10 and the second pressure sensor 11 detect that the vacuum pressure meets the vacuuming requirement, then the vacuum pump 15 is stopped and the valve E is closed for t1 minute. If the vacuum degree still meets the requirement, the vacuuming is considered qualified and the next step can be performed. Otherwise, after checking all connections, the valve E is opened and the vacuuming is restarted until the requirement is met.

[0129] ②→After the vacuuming meets the requirements, close all valves AE on the refrigerant adjustment device, then manually open the gas valve 21 and liquid valve 22 to connect the indoor unit and the outdoor unit, and finally open valve B to start the test of the refrigeration unit. At this time, the action status of various valves is as follows:

[0130] Valve A Valve B Valve C Valve D Valve E Air valve Liquid valve closure Open closure closure closure Open Open

[0131] ③→After the refrigeration unit test is completed, it indicates that the indoor unit has passed the production. You can disconnect from the test tooling of the outdoor unit and enter the next production process. At this time, all the refrigerant originally poured into the indoor unit needs to be transferred back, so the refrigerant on the outdoor unit and the refrigerant adjustment device pipeline must be pressed into the indoor unit. Close the gas valve 21, valve B, valve D and valve E, open the liquid valve 22, valve A and valve C, and then start the first compressor 8 to press the refrigerant of the outdoor unit into the indoor unit. At this time, the pipeline between the valve A outlet, valve B outlet and liquid valve 22 is high-pressure gaseous refrigerant. The status of each valve is as follows:

[0132] Valve A Valve B Valve C Valve D Valve E Air valve Liquid valve Open closure Open closure closure closure Open

[0133] When the pressure ratio of the first compressor 8 is n=PH / PL>n1, it is not conducive to the operation of the first compressor 8. At this time, after closing valve C, immediately open valve D and start the second compressor 14 at the same time, and change from single compressor operation to dual compressor series operation to achieve high pressure ratio operation; when PL meets the vacuum degree, it indicates that the refrigerant of the outdoor unit has basically been pressed into the indoor unit. After maintaining the vacuum degree for t2 minutes, stop the first compressor 8 and the second compressor 14, and at the same time, all valves on the refrigerant adjustment device are closed, and then manually close the liquid valve 22 to complete the refrigerant migration of the refrigeration unit to the indoor unit. After the first compressor 8 and the second compressor 14 are closed, all valves on the refrigerant adjustment device are closed, and the high-pressure gaseous refrigerant at the outlet of valve A and valve B is blocked by valve A and valve B, and both gaseous and liquid refrigerants cannot flow back through valve A and valve B, so the liquid valve can be closed later. It should be noted that, because the pipeline between the valve A outlet, the valve B outlet and the liquid valve 22 retains high-pressure gaseous refrigerant, the pipeline space here is minimized as much as possible, which is beneficial to reducing the retention of refrigerant and keeping the retained refrigerant amount within the rated filling amount deviation as much as possible.

[0134] ④→After completing the above-mentioned manual closing action of the liquid valve 22, open valve B and valve D and start the second compressor 14 to press the refrigerant gas retained in the above-mentioned outdoor unit into the gas-liquid separator 12 until the second pressure sensor 11 meets the vacuum degree. After t2 minutes, stop the second compressor 14, close valve B and valve D again, and ensure that all valves of the refrigerant adjustment device are in the closed state.

[0135] ⑤→After the above two refrigerant migration tasks are completed and the gas valve 21 and the liquid valve 22 are ensured to be manually closed, the first interface 4 and the inlet connection of the indoor unit can be disconnected, and the fourth interface 7 and the outlet connection of the indoor unit can be disconnected. At this point, the production test process of the first set of indoor units is completed, and the next production process can be entered.

[0136] ⑥→After the next indoor unit is connected to the refrigerant adjustment device, the first vacuuming procedure of the first indoor unit will no longer be performed, but a secondary vacuuming operation will be used. The gas valve 21 and liquid valve 22 of the reconnected indoor unit are in the original closed state and should not be opened. After ensuring that the connection is accurate and tight, and after various valves are in place according to the following table, the refrigerant adjustment device starts the secondary vacuuming operation:

[0137] Valve A Valve B Valve C Valve D Valve E Air valve Liquid valve closure Open closure closure Open closure closure

[0138] The second vacuum pumping will not pump the refrigerant stored in the gas-liquid separator 12 into the outdoor atmosphere, thereby achieving the environmental protection goal and ensuring that the refrigerant migration amount of the subsequent indoor unit is more accurate. Because the refrigerant mass retained in the gas-liquid separator 12 of the previous set of indoor units is m, the refrigerant mass retained in the gas-liquid separator 12 of this set of indoor units is also approximately m, so the final refrigerant mass of the subsequent indoor units can basically remain unchanged before and after the test, and the factory rated filling amount of the unit is more accurate.

[0139] The vacuum pump 15 starts running until the first pressure sensor 10 and the second pressure sensor 11 detect that the vacuum pressure meets the vacuuming requirements. The vacuum pump 15 is stopped and the valve E is closed for t1 minutes. If the vacuum still meets the requirements, the vacuuming is considered qualified and the next step can be performed. Otherwise, after checking the connections, the valve E is opened again to vacuumize until the requirements are met. The subsequent production test of the refrigeration unit, the migration of the refrigerant to the indoor unit, and the migration of the remaining refrigerant to the gas-liquid separator 12 are the same as the operation ②→⑤ of the first unit.

[0140] Therefore, the operating steps for the first indoor unit are ①②③④⑤, and the operating steps for the second and subsequent indoor units are ⑥②③④⑤.

[0141] The control method of the above-mentioned refrigerant recovery equipment includes: closing valves A, C, D and E, opening valve B, and testing the refrigeration unit; after the refrigeration unit completes the test, opening valve D, starting the second compressor 14 to transfer the refrigerant to the gas-liquid separator 12; or opening valve C to transfer the refrigerant to the gas-liquid separator 12.

[0142] In this embodiment, if Figure 1 As shown, when the refrigerant filling amount in the refrigeration unit is adjusted online in real time through the refrigerant adjustment device, the excess refrigerant in the refrigeration unit is transferred to the gas-liquid separator 12 through the second compressor 14, or the valve C is directly opened to transfer the refrigerant to the gas-liquid separator 12 through the compression pipeline 3, so as to realize the adjustment of the refrigerant amount in the refrigeration unit.

[0143] See also Figure 2 As shown, according to an embodiment of the present application, the control method of the above-mentioned refrigerant recovery equipment includes: closing the exhaust pipe 17 and the suction pipe 18; opening all valves of the refrigerant adjustment device, and starting the vacuum pump 15 to perform vacuum extraction; after the vacuum extraction is qualified, closing all valves of the refrigerant adjustment device, closing the gas valve 21 and the liquid valve 22, and opening the exhaust pipe 17 and the suction pipe 18; opening valve A and valve C, starting the first compressor 8 to transfer the refrigerant of the indoor unit to the outdoor unit; closing the exhaust pipe 17 and the suction pipe 18, and maintaining the indoor unit; when the maintenance of the indoor unit is completed, disconnecting the suction pipe 18 and the exhaust pipe 17 from the refrigeration unit; opening the gas valve 21 and the liquid valve 22 of the refrigeration unit.

[0144] The step of starting the first compressor 8 to transfer the refrigerant of the indoor unit to the outdoor unit also includes: detecting the pressure ratio of the first compressor 8; when the pressure ratio of the first compressor 8 is n=PH / PL>n1, closing valve C, opening valve D, and starting the second compressor 14, wherein n1 is the set pressure ratio; detecting whether the pressure PL of the suction pipe 1 reaches the set pressure; when the pressure PL of the suction pipe 1 reaches the set pressure, maintaining the current vacuum degree for t2 time, and then stopping the first compressor 8 and the second compressor 14; closing the suction pipe 18 and the exhaust pipe 17.

[0145] After the maintenance of the indoor unit is completed, the step of disconnecting the suction pipe 18 and the exhaust pipe 17 from the refrigeration unit also includes: opening the suction pipe 18 so that the refrigerant adjustment device and the indoor unit are in a connected state; opening valve E, turning on the vacuum pump 15 to evacuate the indoor unit until the vacuum degree meets the requirements; closing valve E, vacuum pump 15 and suction pipe 18 in sequence.

[0146] When the indoor unit system fails during laboratory online testing or actual use by users, the compressor 19 of the unit is prone to burnout, cylinder jamming, etc. At this time, the refrigerant needs to be emptied when maintaining the system of the indoor unit, which involves the problem of refrigerant recovery and storage. If the refrigerant adjustment device of the present application is adopted, the refrigerant of the indoor unit can be transferred to the outdoor unit, and then the indoor unit is systematically repaired. After the maintenance is completed and the vacuum is drawn, the refrigerant of the outdoor unit is released to the entire refrigeration unit, so there is no need for a special refrigerant recovery container, and at the same time, the refrigerant amount inside the refrigeration unit is guaranteed to be accurate.

[0147] The refrigerant migration process of the refrigerant adjustment device in this application when the indoor unit fails to repair the indoor unit is as follows:

[0148] ① Before connecting the refrigerant adjustment device, manually close the gas valve 21 and liquid valve 22 of the refrigeration unit, and then use the connecting pipe 16 to connect the second interface 5 and the third interface 6; use the air intake pipe 18 to connect the fourth interface 7 and the fluorine injection device 23 of the indoor unit, and the fluorine injection device 23 is, for example, a fluorine injection nozzle; use the exhaust pipe 17 to connect the first interface 4 and the fluorine injection nozzle of the gas valve 21 (or the fluorine injection nozzle of the liquid valve 22, or the fluorine injection nozzle connected to the gas valve 21 and the liquid valve 22 at the same time), because after the gas valve 21 or the liquid valve 22 is closed, the fluorine injection nozzle is connected to the outdoor unit, so the refrigerant discharged from the exhaust pipe 17 will enter the outdoor unit, and will not return to the indoor unit. It is particularly noted that the ends of the air intake pipe 18 and the exhaust pipe 17 connected to the indoor unit are equipped with opening and closing handles. After the handles are opened, the ejector pin inside the fluorine injection nozzle can be pressed in, thereby opening the fluorine injection nozzle to achieve connection.

[0149] ② After ensuring that the above connections are correct, close the opening and closing handles at the ends of the suction pipe 18 and the exhaust pipe 17, so that the refrigerant adjustment device and the indoor unit and outdoor unit are in a disconnected state.

[0150] ③ Open all valves AE of the refrigerant adjustment device, start the vacuum pump 15 to perform vacuum operation, and stop the vacuum pump 15 until the first pressure sensor 10 and the second pressure sensor 11 detect that the vacuum pressure meets the vacuum requirement. At the same time, close the valve E and keep it for t1 minute. If the vacuum degree still meets the requirement, the vacuum is considered qualified and the next step can be performed. Otherwise, check the connections at each location and then open the valve E to perform vacuum again until the requirement is met.

[0151] ④ After the vacuum is qualified, close all valves AE of the refrigerant adjustment device, and then manually open the opening and closing handles at the ends of the suction pipe 18 and the exhaust pipe 17 to connect the refrigerant adjustment device with the indoor unit and the outdoor unit.

[0152] ⑤ Open valve A and valve C, and then start the first compressor 8 to press the refrigerant of the indoor unit into the outdoor unit. When the pressure ratio of the first compressor 8 is n=PH / PL>n1, it is not conducive to the operation of the first compressor 8. At this time, close valve C and immediately open valve D and start the second compressor 14 at the same time, switching from single compressor operation to dual compressor series operation to achieve high pressure ratio operation; when PL meets the vacuum degree, it indicates that the refrigerant of the indoor unit has basically been pressed into the outdoor unit. After maintaining the vacuum degree for t2 minutes, stop the first compressor 8 and the second compressor 14, and at the same time, close all valves AE on the refrigerant adjustment device, and then manually close the handles at the ends of the suction pipe 18 and the exhaust pipe 17 to complete the migration of the refrigerant of the refrigeration unit to the outdoor unit.

[0153] ⑥ After the maintenance of the indoor unit system is completed, the indoor unit needs to be evacuated. Open the on-off handle at the end of the suction pipe 18 to connect the refrigerant adjustment device with the indoor unit, then open valve E of the refrigerant adjustment device (all other valves AD of the refrigerant adjustment device are closed), turn on the vacuum pump 15 to evacuate the indoor unit until the vacuum degree meets the requirements, and finally close valve E, vacuum pump 15 and the on-off handle at the end of the suction pipe 18 in sequence.

[0154] ⑦ Disconnect the air intake pipe 18 and the air exhaust pipe 17 on the refrigerant adjustment device from the refrigeration unit, open the air valve 21 and the liquid valve 22 of the refrigeration unit, and complete the system maintenance of the indoor unit.

[0155] In one embodiment, the control method of the refrigerant recovery equipment includes: closing all valves of the refrigerant adjustment device; opening the exhaust pipe 17; opening valve B; opening valve D, starting the second compressor 14 to migrate the refrigerant to the gas-liquid separator 12; or opening valve C to migrate the refrigerant to the gas-liquid separator 12.

[0156] In this embodiment, if Figure 2 As shown, when the refrigerant filling amount in the refrigeration unit is adjusted online in real time through the refrigerant adjustment device, after all valves AE of the refrigerant adjustment device are closed, open the opening and closing handle at the connection between the exhaust pipe 17 and the refrigeration unit, open valve B, and then open valve D to start the second compressor 14 to transfer excess refrigerant to the gas-liquid separator 12 or directly open valve C to transfer excess refrigerant to the gas-liquid separator 12.

[0157] See also Figure 3As shown, according to an embodiment of the present application, the control method of the refrigerant recovery equipment includes: closing the exhaust pipe 17 and the suction pipe 18; opening all valves of the refrigerant adjustment device, and starting the vacuum pump 15 to perform vacuum extraction; after the vacuum extraction is qualified, closing all valves of the refrigerant adjustment device, closing the gas valve 21 and the liquid valve 22, and opening the exhaust pipe 17 and the suction pipe 18; opening valve A and valve C, starting the first compressor 8 to transfer the refrigerant of the outdoor unit to the indoor unit; closing the exhaust pipe 17 and the suction pipe 18, and maintaining the outdoor unit; when the maintenance of the outdoor unit is completed, disconnecting the suction pipe 18 and the exhaust pipe 17 from the refrigeration unit; opening the gas valve 21 and the liquid valve 22 of the refrigeration unit.

[0158] The step of starting the first compressor 8 to transfer the refrigerant of the outdoor unit to the indoor unit also includes: detecting the pressure ratio of the first compressor 8; when the pressure ratio of the first compressor 8 is n=PH / PL>n1, closing valve C, opening valve D, and starting the second compressor 14, wherein n1 is the set pressure ratio; detecting whether the pressure PL of the suction pipe 1 reaches the set pressure; when the pressure PL of the suction pipe 1 reaches the set pressure, maintaining the current vacuum degree for t2 time, and then stopping the first compressor 8 and the second compressor 14; closing the suction pipe 18 and the exhaust pipe 17.

[0159] After the maintenance of the outdoor unit is completed, the step of disconnecting the suction pipe 18 and the exhaust pipe 17 from the refrigeration unit also includes: opening the suction pipe 18 so that the refrigerant adjustment device is in a connected state with the outdoor unit; opening valve E, turning on the vacuum pump 15 to evacuate the outdoor unit until the vacuum degree meets the requirements; and closing valve E, vacuum pump 15 and suction pipe 18 in sequence.

[0160] When the outdoor unit system fails during laboratory online testing or actual use by users, the refrigerant needs to be emptied when maintaining the outdoor unit system, which involves the problem of refrigerant recovery and storage. If the refrigerant adjustment device of the present application is used, the refrigerant of the outdoor unit can be transferred to the indoor unit, and then the outdoor unit is systematically repaired. After the maintenance is completed and the vacuum is drawn, the refrigerant of the indoor unit is released to the entire refrigeration unit. There is no need for a special refrigerant recovery container, and the amount of refrigerant inside the refrigeration unit is guaranteed to be accurate.

[0161] The refrigerant migration process of the refrigerant adjustment device in this application when the outdoor unit fails to repair the outdoor unit is as follows:

[0162] ① Before connecting the refrigerant adjustment device, manually close the gas valve 21 and liquid valve 22 of the refrigeration unit, and then use the connecting pipe 16 to connect the second interface 5 and the third interface 6; use the exhaust pipe 17 to connect the first interface 4 and the fluorine injection device 23 of the indoor unit, and the fluorine injection device 23 is, for example, a fluorine injection nozzle; use the suction pipe 18 to connect the fourth interface 7 and the fluorine injection nozzle of the gas valve 21 (or the fluorine injection nozzle of the liquid valve 22, or the fluorine injection nozzle connected to the gas valve 21 and the liquid valve 22 at the same time), because after the gas valve 21 or the liquid valve 22 is closed, the fluorine injection nozzle is connected to the outdoor unit, so the refrigerant sucked by the suction pipe 18 will enter the indoor unit through the refrigerant adjustment device, and will not return to the outdoor unit. It is particularly noted that the ends of the suction pipe 18 and the exhaust pipe 17 connected to the refrigeration unit are equipped with opening and closing handles. After the opening and closing handles are opened, the ejector pin inside the fluorine injection nozzle can be pressed in, thereby opening the fluorine injection nozzle to achieve connection.

[0163] ② After ensuring that the above connections are correct, close the opening and closing handles at the ends of the suction pipe 18 and the exhaust pipe 17, so that the refrigerant adjustment device and the indoor unit and outdoor unit are in a disconnected state.

[0164] ③ Open all valves AE of the refrigerant adjustment device, start the vacuum pump 15 to perform vacuum operation, and stop the vacuum pump until the first pressure sensor 10 and the second pressure sensor 11 detect that the vacuum pressure meets the vacuum requirement. At the same time, close valve E and keep it for t1 minute. If the vacuum degree still meets the requirement, the vacuum is considered qualified and the next step can be performed. Otherwise, check the connections and then open valve E to perform vacuum again until the requirement is met.

[0165] ④ After the vacuum is qualified, close all valves AE of the refrigerant adjustment device, and then manually open the opening and closing handles at the ends of the suction pipe 18 and the exhaust pipe 17 to connect the refrigerant adjustment device with the indoor unit and the outdoor unit.

[0166] ⑤ Open valve A and valve C, and then start the first compressor 8 to press the refrigerant of the outdoor unit into the indoor unit. When the pressure ratio of the first compressor 8 is n=PH / PL>n1, it is not conducive to the operation of the first compressor 8. At this time, close valve C and immediately open valve D and start the second compressor 14 at the same time, switching from single compressor operation to dual compressor series operation to achieve high pressure ratio operation; when PL meets the vacuum degree, it indicates that the refrigerant of the outdoor unit has basically been pressed into the indoor unit. After maintaining the vacuum degree for t2 minutes, stop the first compressor 8 and the second compressor 14, and at the same time, close all valves AE on the refrigerant adjustment device, and then manually close the opening and closing handles at the ends of the suction pipe 18 and the exhaust pipe 17 to complete the migration of the refrigerant of the refrigeration unit to the indoor unit.

[0167] ⑥ After the maintenance of the outdoor unit system is completed, the outdoor unit needs to be vacuumed. Open the opening and closing handle at the end of the suction pipe 18 to connect the refrigerant adjustment device with the outdoor unit, then open the valve E of the refrigerant adjustment device (all other valves AD of the refrigerant adjustment device are closed), turn on the vacuum pump 15 to vacuum the outdoor unit until the vacuum degree meets the requirements, and finally close the valve E, vacuum pump 15 and the handle at the end of the suction pipe 18 in sequence.

[0168] ⑦ Disconnect the air intake pipe 18 and the air exhaust pipe 17 on the refrigerant adjustment device from the refrigeration unit, open the gas valve 21 and liquid valve 22 of the refrigeration unit, and complete the system maintenance of the outdoor unit.

[0169] See also Figure 3 As shown, according to an embodiment of the present application, the control method of the refrigerant recovery equipment includes: closing all valves of the refrigerant adjustment device; opening the suction pipe 18; opening valve D, starting the second compressor 14 to migrate the refrigerant to the gas-liquid separator 12; or opening valve C to migrate the refrigerant to the gas-liquid separator 12.

[0170] In this embodiment, if Figure 3 As shown, when the refrigerant filling amount in the refrigeration unit is adjusted online in real time through the refrigerant adjustment device, after all valves AE of the refrigerant adjustment device are closed, the opening and closing handle at the connection between the suction pipe 18 and the refrigeration unit is opened, and then the valve D is opened, and the second compressor 14 is started to transfer the excess refrigerant to the gas-liquid separator 12, or the valve C is directly opened to transfer the excess refrigerant to the gas-liquid separator 12.

[0171] See also Figures 1 to 3 As shown, according to an embodiment of the present application, when the refrigerant recovery device includes a gas-liquid separator 12, the control method of the above-mentioned refrigerant recovery device includes: when it is necessary to supplement the refrigerant to the refrigeration unit, open the valve A after turning on the first compressor 8, and inject the refrigerant in the gas-liquid separator 12 into the refrigeration unit; calculate the refrigerant mass remaining in the gas-liquid separator 12, and obtain the refrigerant mass adjustment data in the refrigeration unit; after the refrigerant mass in the refrigeration unit is adjusted to the target mass, close the valve A and turn off the first compressor 8. In the above manner, when there is enough refrigerant in the gas-liquid separator 12 and the amount of refrigerant in the refrigeration unit is insufficient, the refrigerant in the gas-liquid separator 12 is filled into the refrigeration unit, thereby ensuring that the amount of refrigerant in the refrigeration unit can meet the operation requirements of the refrigeration unit.

[0172] It is easy for those skilled in the art to understand that, under the premise of no conflict, the above-mentioned advantageous methods can be freely combined and superimposed.

[0173] The above are only preferred embodiments of the present application and are not intended to limit the present application. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present application shall be included in the protection scope of the present application. The above are only preferred implementations of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and variations can be made without departing from the technical principles of the present application, and these improvements and variations should also be regarded as the protection scope of the present application.

Claims

1. A refrigerant adjustment device, characterized in that: The invention comprises an air intake pipeline (1), an air discharge pipeline (2) and a compression pipeline (3), wherein a first end of the compression pipeline (3) is connected to the air intake pipeline (1), a second end of the compression pipeline (3) is connected to the air discharge pipeline (2), the first end of the air discharge pipeline (2) comprises a first interface (4), and the second end comprises a second interface (5), the first end of the air intake pipeline (1) comprises a third interface (6), and the second end comprises a fourth interface (7), and a first compressor (8) is arranged on the compression pipeline (3), and the first compressor (8) is connected to the first compressor (8). A valve A is provided between the exhaust pipeline (2); the compression pipeline (3) and the exhaust pipeline (2) form a first node at a connection position; a valve B is provided on the exhaust pipeline (2) between the first node and the second interface (5); a valve C is provided on the compression pipeline (3) between the first compressor (8) and the suction pipeline (1); the refrigerant adjustment device further comprises a vacuum pipeline (9); a valve E is provided on the vacuum pipeline (9); the vacuum pipeline (9) is configured to evacuate the refrigerant adjustment device; A connecting pipe (16) is connected between the second interface (5) and the third interface (6), the first interface (4) is connected to an exhaust pipe (17), and the fourth interface (7) is connected to an intake pipe (18). A first opening and closing handle is provided at one end of the exhaust pipe (17) away from the first interface (4), and a second opening and closing handle is provided at one end of the intake pipe (18) away from the fourth interface (7).

2. The refrigerant adjustment device according to claim 1, characterized in that: The exhaust port of the first compressor (8) is provided with a first pressure sensor (10), and the intake pipeline (1) is provided with a second pressure sensor (11).

3. The refrigerant adjustment device according to claim 1, characterized in that: A gas-liquid separator (12) is also provided on the compression pipeline (3), and the air intake port of the first compressor (8) is connected to the outlet of the gas-liquid separator (12).

4. The refrigerant adjustment device according to claim 3, characterized in that: The refrigerant adjustment device also includes a recovery pipeline (13), a first end of the recovery pipeline (13) is connected to the intake pipeline (1), a second compressor (14) and a valve D are provided on the recovery pipeline (13), the valve D is located at the end where the intake port of the second compressor (14) is located, and the exhaust port of the second compressor (14) is connected to the inlet of the gas-liquid separator (12).

5. The refrigerant adjustment device according to claim 1, characterized in that: The vacuum pump (15) is also provided on the vacuum pumping pipeline (9), the valve E is provided at the suction end of the vacuum pump (15), and the vacuum pumping pipeline (9) is connected to the suction pipeline (1) or the exhaust pipeline (2).

6. A refrigerant recovery device, comprising a refrigeration unit, wherein the refrigeration unit comprises an indoor unit and an outdoor unit, characterized in that: The refrigerant recovery equipment further comprises a refrigerant adjustment device according to any one of claims 1 to 5.

7. The refrigerant recovery equipment according to claim 6, characterized in that: The first interface (4) is connected to the inlet of the indoor unit, the second interface (5) is connected to the outlet of the outdoor unit, the third interface (6) is connected to the inlet of the outdoor unit, and the fourth interface (7) is connected to the outlet of the indoor unit.

8. The refrigerant recovery equipment according to claim 7, characterized in that: The indoor unit further comprises a unit compressor (19) and an indoor heat exchanger (20); the unit compressor (19) is arranged between the indoor heat exchanger (20) and the outlet of the indoor unit; an air valve (21) is arranged on the pipeline between the unit compressor (19) and the outlet of the indoor unit; and a liquid valve (22) is arranged on the pipeline between the indoor heat exchanger (20) and the inlet of the indoor unit.

9. The refrigerant recovery equipment according to claim 6, characterized in that: The indoor unit further comprises a unit compressor (19) and an indoor heat exchanger (20); the unit compressor (19) is arranged between the indoor heat exchanger (20) and the outlet of the indoor unit; a fluorine injection device (23) is arranged on the pipeline between the unit compressor (19) and the indoor heat exchanger (20); an air valve (21) is arranged on the pipeline between the unit compressor (19) and the outlet of the indoor unit; a liquid valve (22) is arranged on the pipeline between the indoor heat exchanger (20) and the inlet of the indoor unit; the exhaust pipe (17) is connected to the air valve (21); and the intake pipe (18) is connected to the fluorine injection device (23).

10. The refrigerant recovery equipment according to claim 6, characterized in that: The indoor unit further comprises a unit compressor (19) and an indoor heat exchanger (20); the unit compressor (19) is arranged between the indoor heat exchanger (20) and the outlet of the indoor unit; a fluorine injection device (23) is arranged on the pipeline between the unit compressor (19) and the indoor heat exchanger (20); an air valve (21) is arranged on the pipeline between the unit compressor (19) and the outlet of the indoor unit; a liquid valve (22) is arranged on the pipeline between the indoor heat exchanger (20) and the inlet of the indoor unit; the exhaust pipe (17) is connected to the fluorine injection device (23); and the intake pipe (18) is connected to the air valve (21).

11. A control method for a refrigerant recovery device as claimed in claim 8, wherein when the refrigerant recovery device comprises a gas-liquid separator, the method is characterized in that: The control method comprises: When it is necessary to replenish refrigerant to the refrigeration unit, the first compressor (8) is turned on and then valve A is opened to inject the refrigerant in the gas-liquid separator (12) into the refrigeration unit; Calculating the mass of the refrigerant remaining in the gas-liquid separator (12) and obtaining the refrigerant mass adjustment data in the refrigeration unit; After the refrigerant quality in the refrigeration unit is adjusted to the target quality, valve A is closed and the first compressor (8) is turned off.

12. A control method for a refrigerant recovery device as claimed in claim 9, characterized in that: include: Close the exhaust pipe (17) and the suction pipe (18); Open all valves of the refrigerant regulating device and start the vacuum pump (15) to evacuate the air; After the vacuum is qualified, close all valves of the refrigerant adjustment device, close the gas valve (21) and the liquid valve (22), and open the exhaust pipe (17) and the suction pipe (18); Open valve A and valve C, start the first compressor (8) to transfer the refrigerant of the indoor unit to the outdoor unit; Close the exhaust pipe (17) and the suction pipe (18) and perform maintenance on the indoor unit; When the maintenance of the indoor unit is completed, disconnect the suction pipe (18) and the exhaust pipe (17) from the refrigeration unit; Open the gas valve (21) and liquid valve (22) of the refrigeration unit.

13. The control method according to claim 12, characterized in that: The step of starting the first compressor (8) to transfer the refrigerant of the indoor unit to the outdoor unit also includes: detecting a pressure ratio of the first compressor (8); When the pressure ratio of the first compressor (8) is n=PH / PL>n1, the valve C is closed, the valve D is opened, and the second compressor (14) is started, wherein n1 is the set pressure ratio; Check whether the pressure PL of the suction line (1) reaches the set pressure; When the pressure PL of the suction line (1) reaches a set pressure, the current vacuum degree is maintained for a time period of t2, and then the first compressor (8) and the second compressor (14) are stopped; Close the intake pipe (18) and the exhaust pipe (17).

14. The control method according to claim 12, characterized in that: After the maintenance of the indoor unit is completed, the step of disconnecting the suction pipe (18) and the exhaust pipe (17) from the refrigeration unit also includes: Open the air intake pipe (18) so that the refrigerant adjustment device is in communication with the indoor unit; Open valve E and turn on the vacuum pump (15) to evacuate the indoor unit until the vacuum level meets the requirement; Close valve E, vacuum pump (15) and suction pipe (18) in sequence.

15. A control method for a refrigerant recovery device as claimed in claim 9, characterized in that: include: Close all valves of the refrigerant adjustment device; Open the exhaust pipe (17); Open valve B; Open valve D and start the second compressor (14) to transfer the refrigerant to the gas-liquid separator (12); or open valve C to transfer the refrigerant to the gas-liquid separator (12).

16. A control method for a refrigerant recovery device as claimed in claim 10, characterized in that: include: Close the exhaust pipe (17) and the suction pipe (18); Open all valves of the refrigerant regulating device and start the vacuum pump (15) to evacuate the air; After the vacuum is qualified, close all valves of the refrigerant adjustment device, close the gas valve (21) and the liquid valve (22), and open the exhaust pipe (17) and the suction pipe (18); Open valve A and valve C, start the first compressor (8) to transfer the refrigerant of the outdoor unit to the indoor unit; Close the exhaust pipe (17) and the suction pipe (18) and perform maintenance on the outdoor unit; When maintenance of the outdoor unit is completed, disconnect the suction pipe (18) and the exhaust pipe (17) from the refrigeration unit; Open the gas valve (21) and liquid valve (22) of the refrigeration unit.

17. The control method according to claim 16, characterized in that: The step of starting the first compressor (8) to transfer the refrigerant of the outdoor unit to the indoor unit also includes: detecting a pressure ratio of the first compressor (8); When the pressure ratio of the first compressor (8) is n=PH / PL>n1, the valve C is closed, the valve D is opened, and the second compressor (14) is started, wherein n1 is the set pressure ratio; Check whether the pressure PL of the suction line (1) reaches the set pressure; When the pressure PL of the suction line (1) reaches a set pressure, the current vacuum degree is maintained for a time period of t2, and then the first compressor (8) and the second compressor (14) are stopped; Close the intake pipe (18) and the exhaust pipe (17).

18. The control method according to claim 16, characterized in that: After the maintenance of the outdoor unit is completed, the step of disconnecting the suction pipe (18) and the exhaust pipe (17) from the refrigeration unit also includes: Open the air suction pipe (18) so that the refrigerant adjustment device is connected to the outdoor unit; Open valve E and turn on the vacuum pump (15) to evacuate the outdoor unit until the vacuum level meets the requirement; Close valve E, vacuum pump (15) and suction pipe (18) in sequence.

19. A control method for a refrigerant recovery device as claimed in claim 10, characterized in that: include: Close all valves of the refrigerant adjustment device; Open the suction pipe (18); Open valve D and start the second compressor (14) to transfer the refrigerant to the gas-liquid separator (12); or open valve C to transfer the refrigerant to the gas-liquid separator (12).