A prefabricated foundation embedded structure and installation method thereof

Through the combination of prefabricated foundation embedded structure and positioning regulator, the problem of difficult to ensure the installation accuracy of embedded parts is solved, high stiffness and precise positioning are achieved, and the normal operation of the building or equipment is ensured.

CN113089848BActive Publication Date: 2024-12-06陈德湛
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202110519394.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-05-12
Publication Date
2024-12-06
Estimated Expiration
2041-05-12

AI Technical Summary

Technical Problem

The installation accuracy of existing embedded parts during construction is difficult to ensure, resulting in the structure deviating from the design state and affecting the normal operation of the building or equipment.

Method used

A prefabricated foundation embedded structure, including an integrated embedded skeleton and positioning regulator, forms a high-rigid space truss structure through welding, and uses vertical and horizontal positioning regulators to accurately adjust the position of the embedded parts to ensure installation. Accuracy.

Benefits of technology

The flatness and installation accuracy of the embedded parts are improved, the post-revision work is reduced, the displacement caused by vibration is prevented, and the accuracy and structural stability of the final product are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113089848B_ABST
    Figure CN113089848B_ABST
Patent Text Reader

Abstract

The present invention discloses a prefabricated foundation embedded structure and an installation method thereof, wherein the prefabricated foundation embedded structure comprises an integrated embedded skeleton; the integrated embedded skeleton comprises an embedded part assembly and a steel skeleton; the embedded part assembly comprises embedded parts and embedded part anchor bars; the steel skeleton comprises longitudinal steel bars, vertical steel bars, and diagonal steel bars; the longitudinal steel bars, vertical steel bars, and diagonal steel bars are welded to each other to form a steel frame; the embedded part anchor bars are welded to the embedded parts at intervals to form a combined embedded part assembly; the embedded part assembly and the steel skeleton are welded to each other to form an integrated frame-shaped space truss structure. The integrated embedded skeleton of the present application is a space truss structure formed by welding the embedded part assembly and the steel skeleton, which has high overall rigidity and is not easily deformed, and is conducive to ensuring the flatness of the embedded parts, thereby being able to accurately ensure the accuracy of the final product.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an engineering structure and a construction method, and in particular to a prefabricated foundation embedded structure and an installation method thereof. Background Art

[0002] Embedded parts are very common in engineering projects and are often used to connect various steel structure components with concrete components. The installation accuracy of embedded construction has a significant impact on the installation of other components in the later stage. If the size and installation positioning deviation of the embedded parts are too large, a lot of laborious correction work will be required during the later installation: negative deviation requires welding of steel plates, and positive deviation requires grinding of embedded parts, which will cause the structure to deviate from the design state and affect the normal operation of the completed building or equipment.

[0003] In terms of design, embedded parts are often not taken seriously in conventional design drawings. Designers calculate the thickness and the length and number of anchor bars according to the stress conditions of the embedded parts and draw a simple large-scale drawing without considering how to install them during construction and how to ensure the accuracy of the final product.

[0004] In fact, the embedded parts designed in this way are in a suspended state in the concrete. The embedded parts and anchor bars are not connected to other reliably fixed components at all. How to ensure their position when pouring concrete has become a problem that the construction unit needs to solve.

[0005] After the constructors process the embedded parts according to the large-scale drawing, they often manually weld some brackets with short steel bars on site, weld the embedded parts to the brackets, and place the lower end of the brackets on the bottom mold or cushion. The disadvantages of this method are that the brackets are made arbitrarily and their own dimensions are difficult to accurately control; secondly, the fixing effect is not good, and it is very easy to shift during the strong vibration during the pouring of concrete, resulting in deviations in positioning and elevation. Summary of the invention

[0006] In order to overcome the deficiencies of the prior art, one of the objectives of the present invention is to provide a prefabricated foundation embedded structure.

[0007] A second object of the present invention is to provide a method for installing a prefabricated foundation embedded structure.

[0008] One of the purposes of the present invention is achieved by adopting the following technical scheme: a prefabricated foundation embedded structure, including an integrated embedded frame; the integrated embedded frame includes an embedded part assembly and a steel frame; the embedded part assembly includes embedded parts and embedded part anchor bars; the steel frame includes longitudinal steel bars, vertical steel bars, and diagonal steel bars; the longitudinal steel bars, vertical steel bars, and diagonal steel bars are welded to each other to form a steel frame; the embedded part anchor bars are welded to the embedded parts at intervals to form a combined embedded part assembly; the embedded part assembly and the steel frame are welded to each other to form an integrated frame-shaped space truss structure.

[0009] Furthermore, the prefabricated foundation embedded structure also includes a vertical positioning adjuster and a horizontal positioning adjuster for installing the integrated embedded frame on the foundation concrete cushion layer.

[0010] Furthermore, the vertical positioning adjuster includes a bracket, an extended expansion bolt, a nut, a washer and a binding wire; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; the lower nut, the lower gasket, the bracket, the upper gasket and the upper nut are sequentially installed on the extended expansion bolt; the surface of the screw of the extended expansion bolt is provided with a thread, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling a hole; the binding wire binds the bracket and the integrated embedded frame into a whole.

[0011] Furthermore, the bracket is a steel plate with round holes, or the bracket is a steel bar with holes at both ends formed by bending both ends of the steel bar.

[0012] Furthermore, the horizontal positioning adjuster includes a zigzag-type extended expansion bolt, a nut, a washer and a binding wire; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; the lower nut, the lower gasket, the upper gasket and the upper nut are sequentially installed on the zigzag-type extended expansion bolt; the surface of the screw of the zigzag-type extended expansion bolt is provided with a thread, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling a hole; the binding wire binds the zigzag-type extended expansion bolt and the integrated embedded frame into a whole.

[0013] Furthermore, the prefabricated foundation embedded structure also includes a foundation bottom plate steel bar component arranged at the bottom of the integrated embedded frame, and the foundation bottom plate steel bar component is composed of two layers of bidirectional horizontal orthogonal steel meshes.

[0014] The second object of the present invention is achieved by adopting the following technical solution: a method for installing a foundation pre-buried structure, comprising the following steps:

[0015] (1) Pouring foundation concrete cushion;

[0016] (2) Lay out the lines according to the drawing and determine the position of the integrated embedded frame;

[0017] (3) Install the foundation slab reinforcement components;

[0018] (4) Install the bottom plate dowels and tie them firmly to the foundation bottom plate reinforcement components;

[0019] (5) Lay out lines to determine the positions of vertical and horizontal positioning adjusters, and drill holes in the foundation concrete cushion layer;

[0020] (6) Install the extended expansion bolt of the vertical positioning adjuster into the drilled hole to fix it on the foundation concrete cushion layer;

[0021] (7) Install the lower nut, lower gasket, bracket, upper gasket, and upper nut on the exposed extended expansion bolt in sequence, and adjust the positions of the upper nut and lower nut so that the bracket is at an appropriate vertical height;

[0022] (8) Install the zigzag extended expansion bolt of the horizontal positioning adjuster into the drilled hole to fix it on the foundation concrete cushion layer;

[0023] (9) Install the lower nut, lower washer, upper washer, and upper nut on the exposed zigzag extension bolt in sequence, and adjust the positions of the upper nut and lower nut so that the nut and washer are at a suitable level;

[0024] (10) Place the integrated embedded frame on the bracket of the vertical positioning adjuster;

[0025] (11) The broken-line extension bolt of the horizontal positioning adjuster is bent from the root to intersect with the longitudinal reinforcement of the integrated embedded frame. The position of the longitudinal reinforcement should be between the nut and washer of the horizontal positioning adjuster;

[0026] (12) Adjust the horizontal position of the integrated embedded frame, and use the binding wire of the vertical positioning adjuster to bind it firmly with the bracket of the vertical positioning adjuster; use the binding wire of the horizontal positioning adjuster to bind it firmly with the screw of the broken line type extended expansion bolt of the horizontal positioning adjuster;

[0027] (13) Measure the elevation of different positions on the top of the embedded component assembly on the integrated embedded frame. If it does not meet the requirements, adjust the nut on the vertical positioning adjuster to move the bracket up and down until the correct elevation is reached. Finally, tighten the nuts on the upper and lower sides of the bracket to clamp the bracket to achieve vertical positioning.

[0028] (14) After vertical positioning, tighten the nut of the horizontal positioning adjuster so that the nut and washer of the horizontal positioning adjuster clamp the binding wire of the horizontal positioning adjuster to achieve horizontal positioning;

[0029] (15) Install the transverse positioning block on the integrated embedded frame, and then install the foundation side form. The foundation side form should be pressed against the transverse positioning block to achieve the positioning of the foundation side form;

[0030] (16) Finally, pour concrete on the foundation side formwork, allowing the concrete to completely penetrate into the foundation bottom plate steel components and the integrated embedded frame.

[0031] Further, in step (2), the integrated embedded frame includes an embedded part assembly and a steel frame; the embedded part assembly includes embedded parts and embedded part anchor bars; the steel frame includes longitudinal steel bars, vertical steel bars, and oblique steel bars; a plurality of vertical steel bars are arranged at intervals, four longitudinal steel bars are inserted in each vertical steel bar, and are fixed to the four inner corners of the vertical steel bars by welding; the oblique steel bars are located on the left and right inner sides of the vertical steel bars, one end of the oblique steel bars is welded to the longitudinal steel bars located above, and the other end is welded to the longitudinal steel bars located below; a plurality of oblique steel bars are connected end to end to form a broken line; the embedded part anchor bars are welded to the vertical steel bars at intervals; the embedded parts are welded to the embedded part anchor bars; the embedded part assembly and the steel frame are welded to each other to form an integrated frame-shaped space truss structure.

[0032] Furthermore, in step (3), the foundation slab reinforcement member is composed of two layers of bidirectional horizontal orthogonal reinforcement meshes.

[0033] Further, in step (5), the vertical positioning adjuster includes a bracket, an extended expansion bolt, a nut, a washer and a binding wire; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; the lower nut, the lower washer, the bracket, the upper washer and the upper nut are sequentially installed on the extended expansion bolt; the surface of the screw of the extended expansion bolt is provided with a thread, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling a hole; the binding wire binds the bracket and the integrated embedded skeleton into a whole; the bracket is a steel plate with a circular hole, or the bracket is a steel bar with holes at both ends formed by bending the two ends of the steel bar;

[0034] The horizontal positioning adjuster includes a zigzag-type extended expansion bolt, a nut, a washer and a binding wire; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; a lower nut, a lower gasket, an upper gasket and an upper nut are sequentially installed on the zigzag-type extended expansion bolt; a thread is provided on the screw surface of the zigzag-type extended expansion bolt, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling a hole; the binding wire binds the zigzag-type extended expansion bolt and the integrated embedded frame into a whole.

[0035] Compared with the prior art, the present invention has the following beneficial effects:

[0036] (1) The integrated embedded frame of the present application is a spatial truss structure formed by welding the embedded component assembly and the steel frame together. It has high overall rigidity and is not easy to deform, which is conducive to ensuring the flatness of the embedded components.

[0037] (2) In addition, all integrated embedded frames are prefabricated in the factory with high processing precision.

[0038] (3) The combined use of the vertical positioning regulator and the horizontal positioning regulator of the present application enables reliable positioning of the embedded parts assembly and the steel skeleton, and realizes the vertical and horizontal positioning of the entire integrated embedded skeleton. The positioning regulator adopts the form of screws and nuts, which can finely adjust the vertical position of the bracket, thereby adjusting the overall elevation of the embedded parts assembly on the integrated embedded skeleton to the same level, and realizing the precise vertical positioning of the embedded parts; in addition, the combined use of the horizontal positioning regulator, by tightening the nut, can accurately define the horizontal position of the embedded parts assembly and the steel skeleton, thereby locking the vertical and horizontal positions of the entire integrated embedded skeleton, avoiding a large amount of correction work caused by the displacement of the embedded parts due to manual installation in the later stage, and preventing the displacement of the embedded parts due to strong vibration during the pouring of concrete, so as to accurately ensure the accuracy of the final product.

[0039] (4) In this installation method, the embedded parts assembly and the steel frame are made into an integrated embedded frame, which is prefabricated to achieve pre-configuration and improve assembly efficiency. In addition, in the existing construction process, the foundation bottom plate steel bar components need to be inserted into the embedded parts and steel frame components (the function is equivalent to the integrated embedded frame of the present invention) to form a certain connection relationship with them, but the construction process is complicated and time-consuming; the foundation bottom plate steel bar components of the present application do not need to be inserted into the integrated embedded frame, and the connection relationship between the integrated embedded frame and the foundation bottom plate steel bar components is achieved by adding bottom plate dowels to connect the two structures, which can greatly improve the assembly and construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 This is a construction effect diagram of the prefabricated foundation embedded structure (strip shape) and the pouring foundation concrete cushion layer in Example 1 of the present invention;

[0041] Figure 2 for Figure 1 A schematic diagram of the cross section of region a in the middle;

[0042] Figure 3 for Figure 2 The cross-sectional diagram along line bb in the middle;

[0043] Figure 4 for Figure 2 Schematic diagram of the cross section along the cc line;

[0044] Figure 5 This is a schematic structural diagram of a vertical positioning regulator according to Embodiment 1 of the present invention;

[0045] Figure 6 This is a schematic diagram of the first structure of the bracket of Example 1 of the present invention;

[0046] Figure 7 This is a schematic diagram of a second structure of the bracket of Example 1 of the present invention;

[0047] Figure 8 This is a schematic diagram of the structure of the horizontal positioning regulator of Example 1 of the present invention;

[0048] Fig. 9 This is a construction effect diagram of the prefabricated foundation embedded structure (plate-shaped) and the pouring of the foundation concrete cushion layer in Example 2 of the present invention;

[0049] Fig.10 It is a plan view of the integrated embedded frame of Example 2 of the present invention;

[0050] Fig.11 for Fig.10 The cross-sectional diagram along the dd line;

[0051] Fig.12 for Fig.10 Schematic diagram of the cross section along line ee.

[0052] In the figure: 100, integrated embedded skeleton; 11, embedded parts assembly; 111, embedded parts; 112, embedded parts anchor bars; 12, steel skeleton; 121, longitudinal steel bars; 122, vertical steel bars; 123, oblique steel bars; 200, foundation slab steel bar component; 21, bottom layer orthogonal steel mesh; 22, surface layer orthogonal steel mesh; 300, vertical positioning adjuster; 31, bracket; 311, round hole; 32, extended expansion bolt; 33, nut; 34, washer; 35, binding wire; 400, horizontal positioning adjuster; 41, broken line extended expansion bolt; 42, nut; 43, washer; 44, binding wire; 500, bottom plate dowel bar; 600, horizontal positioning block; 700, foundation side form; A, foundation concrete cushion. DETAILED DESCRIPTION

[0053] The present invention is further described below in conjunction with the accompanying drawings and specific implementation methods. It should be noted that, under the premise of no conflict, the various embodiments or technical features described below can be arbitrarily combined to form a new embodiment.

[0054] Example 1 Prefabricated foundation embedded structure (strip shape)

[0055] The prefabricated foundation embedded structure of the present embodiment 1 is in strip shape and is installed in the strip-shaped cast foundation concrete cushion layer A. Figure 1 For details, see the attached Figure 1-9As shown, the strip-shaped prefabricated foundation embedded structure includes an integrated embedded skeleton 100; the integrated embedded skeleton includes an embedded part assembly 11 and a steel skeleton 12; the embedded part assembly includes embedded parts 111 and embedded part anchor bars 112; the steel skeleton 12 includes longitudinal steel bars 121, vertical steel bars 122, and oblique steel bars 123; a number of vertical steel bars are arranged at intervals, four longitudinal steel bars are inserted in each vertical steel bar, and are fixed to the four inner corners of the vertical steel bars by welding; the oblique steel bars are located on the left and right inner sides of the vertical steel bars, one end of the oblique steel bars is welded to the longitudinal steel bars located above, and the other end is welded to the longitudinal steel bars located below; a plurality of oblique steel bars are connected end to end to form a broken line; the embedded part anchor bars are welded to the embedded parts at intervals to form an embedded part assembly; the embedded part assembly and the steel skeleton are welded to each other to form an integrated frame-shaped space truss structure. Among them, the vertical steel bars are preferably stirrups.

[0056] The integrated embedded frame of the present application is a spatial truss structure formed by welding the embedded component assembly 11 and the steel frame 12, which has high overall rigidity and is not easy to deform, which is conducive to ensuring the flatness of the embedded components. In addition, the integrated embedded frame is all prefabricated in the factory with high processing accuracy.

[0057] As a further preferred embodiment, the prefabricated foundation embedded structure also includes a foundation bottom plate reinforcement member 200 arranged at the bottom of the integrated embedded frame, and a vertical positioning adjuster 300 and a horizontal positioning adjuster 400 for installing the integrated embedded frame on the foundation concrete cushion layer.

[0058] The combined use of the vertical positioning regulator and the horizontal positioning regulator of the present application enables reliable positioning of the embedded component assembly and the steel frame, and realizes the vertical positioning and horizontal positioning of the entire integrated embedded frame. The positioning regulator adopts the form of screws and nuts, which can finely adjust the vertical position of the bracket, thereby adjusting the overall elevation of the embedded component assembly on the integrated embedded frame to the same level, and realizing the precise vertical positioning of the embedded component; in addition, the combined use of the horizontal positioning regulator, by tightening the nut, can accurately define the horizontal position of the embedded component assembly and the steel frame, thereby locking the vertical and horizontal positions of the entire integrated embedded frame, avoiding a large amount of correction work caused by the displacement of the embedded component due to manual installation in the later stage, and preventing the displacement of the embedded component due to strong vibration during the pouring of concrete, so as to accurately ensure the accuracy of the final product.

[0059] Specifically, the foundation slab reinforcement member 200 is composed of two layers of bidirectional horizontal orthogonal reinforcement meshes, namely a bottom layer orthogonal reinforcement mesh 21 and a surface layer orthogonal reinforcement mesh 22. The reinforcement meshes are bound with existing iron wires, and pads are used to support the two layers of reinforcement meshes to achieve positioning.

[0060] Specifically, the vertical positioning adjuster 300 includes a bracket 31, an extended expansion bolt 32, a nut 33, a washer 34 and a binding wire 35; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; wherein the specifications of the nut and the washer match the screw of the extended expansion bolt. The lower nut, the lower washer, the bracket, the upper washer and the upper nut are sequentially installed on the extended expansion bolt; the surface of the screw of the extended expansion bolt is provided with threads, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling; the binding wire binds the bracket and the integrated embedded frame into a whole.

[0061] As a further preferred solution, the bracket 31 is a steel plate with a circular hole 311, or the bracket is a steel bar with holes at both ends formed by bending both ends of the steel bar.

[0062] Specifically, the horizontal positioning adjuster 400 includes a zigzag lengthened expansion bolt 41, a nut 42, a washer 43 and a binding wire 44; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; wherein the specifications of the nut and the washer match the screw of the lengthened expansion bolt. The lower nut, the lower washer, the upper washer and the upper nut are sequentially installed on the zigzag lengthened expansion bolt; the screw surface of the zigzag lengthened expansion bolt is provided with threads, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling; the binding wire binds the zigzag lengthened expansion bolt and the integrated embedded frame into a whole.

[0063] Example 2 Prefabricated foundation embedded structure (plate-shaped)

[0064] The prefabricated foundation embedded structure of the present embodiment 1 is in the form of a plate, and is installed in the plate-shaped cast foundation concrete cushion layer A. Figure 1 For details, see the attached Figure 9-12 As shown, the plate-shaped prefabricated foundation embedded structure includes an integrated embedded skeleton 100; the integrated embedded skeleton includes an embedded part assembly 11 and a steel skeleton 12; the embedded part assembly includes embedded parts 111 and embedded part anchor bars 112; the steel skeleton 12 includes longitudinal steel bars 121, vertical steel bars 122, and oblique steel bars 123; the longitudinal steel bars are in a grid shape, a number of vertical steel bars are arranged at intervals and inserted in the longitudinal steel bars, a plurality of oblique steel bars are connected end to end to form a broken line shape, the oblique steel bars are connected to each vertical steel bar, and the three are welded to each other to form the steel skeleton 12; the embedded part anchor bars 112 are welded to the embedded parts 111 to form the entire embedded part assembly 11, and the embedded part assembly and the steel skeleton are welded to each other to form an integrated frame-shaped space truss structure.

[0065] The installation positions and methods of the remaining foundation slab reinforcement members 200, vertical positioning adjusters 300, horizontal positioning adjusters 400, slab dowels 500, transverse positioning blocks, and foundation side forms are similar to those in Example 1 and will not be described again here.

[0066] Example 3

[0067] A method for installing the pre-buried foundation structure as described in Embodiment 1-2 comprises the following steps:

[0068] (1) Pouring foundation concrete cushion A;

[0069] (2) Lay out the lines according to the drawing to determine the position of the integrated embedded frame 100;

[0070] (3) Installing the foundation slab reinforcement member 200;

[0071] (4) Install the bottom plate dowels 500 and tie them firmly to the foundation bottom plate steel bar component 200. In this step, in order to avoid the process of horizontally inserting the steel bar skeleton 12 one by one during the on-site construction of the foundation bottom plate steel bar component 200 and separating the steel bar skeleton 12 from the foundation bottom plate steel bar component 200, the bottom plate dowels 500 are added to connect the steel bar skeleton 12 and the foundation bottom plate steel bar component 200.

[0072] (5) Laying out the lines to determine the positions of the vertical positioning adjuster 300 and the horizontal positioning adjuster 400, and drilling holes in the foundation concrete cushion layer A;

[0073] (6) Install the extended expansion bolt 32 of the vertical positioning adjuster 300 in the drilled hole to fix it on the foundation concrete cushion layer A;

[0074] (7) Install the lower nut, lower gasket, bracket, upper gasket, and upper nut on the exposed extended expansion bolt in sequence, and adjust the positions of the upper nut and lower nut so that the bracket 31 is at an appropriate vertical height;

[0075] (8) Install the zigzag-shaped extended expansion bolt 41 of the horizontal positioning adjuster 400 into the drilled hole to fix it on the foundation concrete cushion layer A;

[0076] (9) Install the lower nut, lower washer, upper washer, and upper nut on the exposed zigzag extended expansion bolt 41 in sequence, and adjust the positions of the upper nut and lower nut so that the nut and washer are at a suitable level;

[0077] (10) Placing the integrated embedded frame 100 on the bracket 31 of the vertical positioning adjuster 300;

[0078] (11) The zigzag-line extension bolt 41 of the horizontal positioning adjuster 400 is bent from the root to intersect with the longitudinal steel bar 121 of the integrated embedded frame 100. The longitudinal steel bar 121 should be located between the nut 42 and the washer 43 of the horizontal positioning adjuster 400.

[0079] (12) Adjust the horizontal position of the integrated embedded frame 100, and use the binding wire 35 of the vertical positioning adjuster 300 to bind it firmly with the bracket 31 of the vertical positioning adjuster; use the binding wire 44 of the horizontal positioning adjuster 400 to bind it firmly with the screw of the broken line type extended expansion bolt 41 of the horizontal positioning adjuster;

[0080] (13) Measure the elevation of different positions on the top of the embedded component assembly 11 on the integrated embedded frame 100. If the elevation is not satisfied, adjust the nut 33 on the vertical positioning adjuster 300 to move the bracket 31 up and down until the correct elevation is reached. Finally, tighten the nuts 33 on the upper and lower sides of the bracket 31 to clamp the bracket 31 to achieve vertical positioning.

[0081] (14) After vertical positioning, tighten the nut 42 of the horizontal positioning adjuster 400 so that the nut 42 and the washer 43 of the horizontal positioning adjuster 400 clamp the binding wire 44 of the horizontal positioning adjuster 400 to achieve horizontal positioning;

[0082] (15) Install the transverse positioning block 600 on the integrated embedded frame 100, and then install the base side form 700. The base side form 700 should be pressed against the transverse positioning block 600 to achieve the positioning of the base side form;

[0083] (16) Finally, pour concrete on the foundation side formwork 700 so that the concrete can completely penetrate into the foundation bottom plate reinforcement member 200 and the integrated embedded frame 100.

[0084] In this installation method, since the embedded component assembly 11 and the steel frame 12 are made into an integrated embedded frame 100, prefabrication is used to achieve pre-configuration and improve assembly efficiency. In addition, in the existing construction process, the foundation bottom plate steel bar component needs to be inserted into the embedded component and steel frame assembly (the function is equivalent to the integrated embedded frame 100 of the present invention) to form a certain connection relationship with it, but the construction process is complicated and time-consuming; the foundation bottom plate steel bar component 200 of the present application does not need to be inserted into the integrated embedded frame 100, and the connection relationship between the integrated embedded frame 100 and the foundation bottom plate steel bar component 200 is achieved by adding a bottom plate dowel 500 to connect the two structures, which can greatly improve the assembly and construction efficiency.

[0085] The above-mentioned embodiments are only preferred embodiments of the present invention and cannot be used to limit the scope of protection of the present invention. Any non-substantial changes and substitutions made by technicians in this field on the basis of the present invention shall fall within the scope of protection required by the present invention.

Claims

1. A method for installing a pre-buried foundation structure, It is characterized in that The steps include: (1) Pouring foundation concrete cushion; (2) Lay out the lines according to the drawing and determine the position of the integrated embedded frame; (3) Install the foundation slab reinforcement components; (4) Install the bottom plate dowels and tie them firmly to the foundation bottom plate reinforcement components; (5) Lay out the lines to determine the positions of the vertical and horizontal positioning adjusters, and drill holes in the foundation concrete cushion layer; (6) Install the extended expansion bolt of the vertical positioning adjuster into the drilled hole to fix it on the foundation concrete cushion; (7) Install the lower nut, lower gasket, bracket, upper gasket, and upper nut on the exposed extended expansion bolt in sequence, and adjust the positions of the upper nut and lower nut so that the bracket is at an appropriate vertical height; (8) Install the zigzag extended expansion bolt of the horizontal positioning adjuster into the drilled hole to fix it on the foundation concrete cushion layer; (9) Install the lower nut, lower washer, upper washer, and upper nut on the exposed zigzag extension bolt in sequence, and adjust the positions of the upper nut and lower nut so that the nut and washer are at a suitable level; (10) Place the integrated embedded frame on the bracket of the vertical positioning adjuster; (11) The broken-line extension bolt of the horizontal positioning adjuster is bent from the root so that it intersects with the longitudinal reinforcement of the integrated embedded frame. The position of the longitudinal reinforcement should be between the nut and washer of the horizontal positioning adjuster; (12) Adjust the horizontal position of the integrated embedded frame, and use the binding wire of the vertical positioning adjuster to bind it firmly with the bracket of the vertical positioning adjuster; use the binding wire of the horizontal positioning adjuster to bind it firmly with the screw of the broken line type extended expansion bolt of the horizontal positioning adjuster; (13) Measure the elevation of different positions on the top of the embedded component assembly on the integrated embedded frame. If it does not meet the requirements, adjust the nut on the vertical positioning adjuster to move the bracket up and down until it reaches the correct elevation. Finally, tighten the nuts on the upper and lower parts of the bracket to clamp the bracket to achieve vertical positioning. (14) After vertical positioning, tighten the nut of the horizontal positioning adjuster so that the nut and washer of the horizontal positioning adjuster clamp the binding wire of the horizontal positioning adjuster to achieve horizontal positioning; (15) Install the transverse positioning block on the integrated embedded frame, and then install the foundation side form. The foundation side form should be pressed against the transverse positioning block to achieve the positioning of the foundation side form; (16) Finally, pour concrete on the foundation side formwork, allowing the concrete to completely penetrate into the foundation slab reinforcement components and the integrated embedded frame.

2. The installation method according to claim 1, It is characterized in that In step (2), the integrated embedded skeleton includes an embedded part assembly and a steel skeleton; the embedded part assembly includes embedded parts and embedded part anchor bars; the steel skeleton includes longitudinal steel bars, vertical steel bars, and oblique steel bars; a plurality of vertical steel bars are arranged at intervals, four longitudinal steel bars are inserted in each vertical steel bar, and are fixed to the four inner corners of the vertical steel bars by welding; the oblique steel bars are located on the left and right inner sides of the vertical steel bars, one end of the oblique steel bars is welded to the longitudinal steel bars located above, and the other end is welded to the longitudinal steel bars located below; a plurality of oblique steel bars are connected end to end to form a broken line; the embedded part anchor bars are welded to the vertical steel bars at intervals; the embedded parts are welded to the embedded part anchor bars; the embedded part assembly and the steel skeleton are welded to each other to form an integrated frame-shaped space truss structure.

3. The installation method according to claim 1, It is characterized in that In step (3), the foundation slab reinforcement member is composed of two layers of bidirectional horizontal orthogonal reinforcement meshes.

4. The installation method according to claim 1, It is characterized in that In step (5), the vertical positioning adjuster includes a bracket, an extended expansion bolt, a nut, a washer and a binding wire; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; the lower nut, the lower washer, the bracket, the upper washer and the upper nut are installed on the extended expansion bolt in sequence; the surface of the screw of the extended expansion bolt is provided with a thread, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling a hole; the binding wire binds the bracket and the integrated embedded skeleton into a whole; the bracket is a steel plate with a round hole, or the bracket is a steel bar with holes at both ends formed by bending the two ends of the steel bar.

5. The installation method according to claim 4, It is characterized in that The bracket is a steel plate with round holes, or the bracket is a steel bar with holes at both ends formed by bending both ends of the steel bar.

6. The installation method according to claim 1, It is characterized in that In step (5), the horizontal positioning adjuster includes a zigzag-type extended expansion bolt, a nut, a washer and a binding wire; the nut includes an upper nut and a lower nut; the washer includes an upper washer and a lower washer; the lower nut, the lower washer, the upper washer and the upper nut are sequentially installed on the zigzag-type extended expansion bolt; the screw surface of the zigzag-type extended expansion bolt is provided with a thread, and the lower end of the screw is installed in the foundation concrete cushion layer by drilling a hole; the binding wire binds the zigzag-type extended expansion bolt and the integrated embedded frame into a whole.

Citation Information

Patent Citations

  • Construction method for adjusting steel plate embedded parts to reach design and construction accuracy

    CN105350654A

  • Air-supported membrane building concrete anchor bolt pre-buried structure and construction method thereof

    CN105839786A

  • Prefabricated foundation embedded structure

    CN215519235U

  • Method and device for constructing foundation, and anchor bolt support device for construction

    JP2007211514A