Threaded steel bar anchoring structure and construction method thereof

By using the threaded steel bar anchor structure and the limited cooperation between the expansion sleeve and the anchor pad in the prestressed system, the problems of anchor damage and mortar entry at the fixed end are solved, and the reliable connection between the prestressed bars and the anchor structure is achieved and the safety of construction is achieved. sex.

CN113323274BActive Publication Date: 2024-10-29HEFEI VSL ENG CORP ON LIM
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202110684016.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-06-21
Publication Date
2024-10-29
Estimated Expiration
2041-06-21

AI Technical Summary

Technical Problem

In the construction of the existing prestressed system, the fixed end anchors are easily damaged or rusted, and during the concrete pouring process, the mortar may enter the embedded pipes, causing the lower anchor unit to be unable to enter the grouting cover, affecting the prestressed tendons and lower anchor pads. Failure to cooperate may cause construction accidents.

Method used

The threaded steel bar anchor structure is adopted. The anchor pad and expansion sleeve are pre-embedded in the anchor seat. The expansion sleeve is inserted into the anchor pad. The pre-tensioning makes the expansion sleeve and anchor pad form a limited fit to ensure that the prestressed tendons and anchoring structure reliable connection. The construction method includes positioning fixed end components, pre-embedded caps, anchor pads and cable pipes, connecting expansion sleeves to the prestressed tendons, and forming a resistive fit through the deformation of the expansion sleeves and the anchor pads to achieve the detachability of the prestressed tendons. type connection.

Benefits of technology

It achieves reliable connection between prestressed tendons and anchor structures, ensures the safety and reliability of construction, avoids the risk of mortar entering embedded pipes, and simplifies the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113323274B_ABST
    Figure CN113323274B_ABST
Patent Text Reader

Abstract

The present invention belongs to the field of building construction technology, and particularly relates to a threaded steel bar anchoring structure and a construction method thereof, wherein an anchor pad is embedded and fixed in the anchor seat, the prestressed tendon is inserted into the expansion sleeve and the two form a limit fit in the direction of the preload force, the expansion sleeve is inserted into the anchor pad, and when the expansion sleeve is squeezed by an axial external force during pre-tensioning, the sleeve body is radially expanded and deformed outwards and forms an axial resistance limit fit with the anchor pad. The prestressed tendon of the present invention is detachably connected to the components embedded in the anchor seat, and the connection structure is simple and the construction is convenient. During construction, pre-tensioning is first performed to squeeze and deform the expansion sleeve, and then it is connected to the anchor pad as a whole, which can effectively ensure the reliable connection between the prestressed tendon and the threaded steel bar anchoring structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and particularly relates to a fixed-end threaded steel bar anchoring structure and a construction method thereof. Background Art

[0002] Conventional prestressed system construction usually starts with connecting the prestressed tendons to the fixed end anchors, embedding the fixed end anchors in the components, and traction of the other end of the prestressed tendons by equipment to ensure their posture. The prestressed tendons embedded at one end cannot be replaced, and the exposed section is prone to damage or rust during construction, affecting the prestressing tension and, in turn, the structural safety of the building.

[0003] Chinese patent document CN102392415A discloses a vertical prestressed anchoring system and a construction method thereof, which discloses a rectangular fixed-end anchor plate 2, a through hole on a lower anchor pad 3 which is rectangular and sized to pass through a lower-end anchor unit, and an end face of the lower anchor pad 3 which is provided with a rectangular concave notch perpendicular to the rectangular through hole; during construction, the lower anchor pad 3, a grouting cover 12 and a pre-buried pipe 5 are pre-buried before pouring concrete, and after the concrete is poured, the prestressed tendons are sent into the grouting cover 12 together with the lower-end anchor unit, the prestressed tendons are rotated to drive the lower-end anchor unit to rotate, and then the prestressed tendons are lifted to allow the lower-end anchor unit to enter the concave notch of the lower anchor pad 3. However, during the concrete pouring process, the mortar needs to be vibrated, and the disturbed mortar can easily enter the interior of the pre-buried pipe from the damaged opening or the connection between the pre-buried pipe and the fixed-end anchor. After these slurries enter the grouting cover and solidify, the lower-end anchor unit may not be able to enter the grouting cover, resulting in the prestressed tendons being unable to cooperate with the lower anchor pad. In addition, when the distance between the pre-buried fixed-end anchor and the component surface is large, it is difficult to determine whether the fixed-end anchor plate 2 enters the concave notch of the lower anchor pad 3. If the fixed-end anchor plate 2 is tensioned without entering the concave notch, the lower-end anchor unit may be detached from the lower anchor pad 3, causing a construction accident. Summary of the invention

[0004] The purpose of the present invention is to provide a fixed-end threaded steel bar anchoring structure with a simple structure and reliable connection, and a prestressed system construction method using the fixed-end threaded steel bar anchoring structure.

[0005] To achieve the above objectives, the technical solution adopted by the present invention is:

[0006] A threaded steel bar anchoring structure, an anchor plate is pre-embedded and fixed in the anchor seat, the prestressed steel bar is inserted into the expansion sleeve and the two form a limit fit in the direction of the preload force, the expansion sleeve is inserted into the anchor plate, and when the expansion sleeve is squeezed by an axial external force, the sleeve body is radially expanded outwardly and forms an axial resistance limit fit with the anchor plate.

[0007] A prestressed system construction method comprises the following steps:

[0008] A. Positioning and fixing end components;

[0009] A1. Connect the cap, anchor plate and cable tube in sequence and embed them in the anchor seat. The through hole of the anchor plate connects the tube hole of the cable tube and the inner cavity of the cap;

[0010] A2. Connect the expansion sleeve and anchor sleeve to the prestressed tendon, with the expansion sleeve located above the anchor sleeve. Then, feed the prestressed tendon from the upper end of the cable threading tube into the anchor seat, so that the expansion sleeve is inserted into the anchor pad.

[0011] B. Pre-tensioning the prestressed tendons to deform the expansion sleeve and form a resistance fit with the anchor plate to limit the displacement of the expansion sleeve toward the tensioning end;

[0012] C. Re-tension the anchoring mechanism and complete the anchoring construction.

[0013] Compared with the prior art, the present invention has the following technical effects: the prestressed tendons and the components embedded in the anchor seat are detachably connected, and the connection structure is simple and the construction is convenient. During construction, the expansion sleeve is first pre-tensioned to be squeezed and deformed, and then connected to the anchor plate as a whole, which can effectively ensure the reliable connection between the prestressed tendons and the threaded steel bar anchoring structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The following is a brief description of the contents and symbols in the drawings of this specification:

[0015] Figure 1 It is a schematic diagram of a part of the threaded steel bar anchorage structure being embedded in the anchorage seat;

[0016] Figure 2 This is a schematic diagram of the pre-tensioning front expansion sleeve and the embedded anchor pad;

[0017] Figure 3 yes Figure 2 The enlarged schematic diagram of the middle C part;

[0018] Figure 4 This is a schematic diagram of the expansion sleeve being deformed by pre-tensioning;

[0019] Figure 5 yes Figure 4 The enlarged schematic diagram of the middle D part;

[0020] Figure 6 This is a schematic diagram when the prestressed tendons are tensioned again;

[0021] Figure 7 It is a schematic diagram when the anchoring construction is completed;

[0022] Figure 8 , 12 14 is a schematic diagram of an expansion sleeve;

[0023] Fig. 9 , 10 11 yes Figure 7 EE cross-sectional views of different embodiments;

[0024] Fig.13 yes Fig.12 FF section view in;

[0025] Fig.15 yes Fig.14 GG section view in;

[0026] Fig.16 is a top view of the anchor pad;

[0027] Fig.17 It is a cross-sectional schematic diagram of the anchor plate.

[0028] In the figure: A. anchor seat, B. prestressed tendon, 10. anchor plate, 11. through hole, 20. expansion sleeve, 21. large diameter pipe section, 22. small diameter pipe section, 221. weak pipe section, 23. step surface, 30. anchor sleeve, 31. cap, 32. cable tube, 40. support tube. DETAILED DESCRIPTION

[0029] The specific implementation of the present invention is further described in detail below through description of embodiments in conjunction with the accompanying drawings.

[0030] A threaded steel bar anchoring structure, an anchor plate 10 is pre-embedded and fixed in an anchor seat A, a prestressed tendon B is inserted into an expansion sleeve 20 and the two form a limit fit in the direction of the preload force, the expansion sleeve 20 is inserted into the anchor plate 10, and when the expansion sleeve 20 is squeezed by an axial external force, the sleeve body is radially expanded outwardly and forms an axial resistance limit fit with the anchor plate 10, so that the prestressed tendon B that is limited by the expansion sleeve 20 also forms an axial limit fit with the anchor plate 10, thereby realizing a reliable connection between the prestressed tendon B and the anchor plate 10.

[0031] For ease of positioning, Figure 7-10 As shown, the outer wall of the expansion sleeve 20 is a stepped column consisting of a large diameter pipe section 21 and a small diameter pipe section 22. Figure 1 , 2 As shown, the outer diameter of the small diameter pipe section 22 of the expansion sleeve 20 matches the diameter of the through hole 11 in the middle of the anchor plate 10 and is inserted into the through hole 11, the step surface 23 at the junction of the large and small diameter pipe sections 21 and 22 of the expansion sleeve 20 is against the upper end surface of the anchor plate 10, and the wall of the middle section or the end section of the small diameter pipe section 22 is thinned to form a weak pipe section 221. When in use, the weak pipe section 221 will be deformed under the action of external force.

[0032] Details are as attached Figure 11-14As shown in the figure, the outer wall of the small diameter pipe section 22 is recessed inward to form a weak pipe section 221. Figure 7-10 As shown in FIGS. 13 and 14 , the inner wall of the small diameter pipe section 22 protrudes outward to form a weak pipe section 221.

[0033] In the preferred embodiment, the top of the weak pipe section 221 is not lower than the lower plate surface of the anchor plate 10. Figure 2 As shown, when the external force squeezes the expansion sleeve 20, the top end of the weak pipe section 221 is located within the plate body of the anchor plate 10 or at the bottom plate body of the anchor plate 10, so that the squeezed deformation part is arranged adjacent to the bottom plate surface of the anchor plate 10 to ensure the resistance cooperation between the two.

[0034] The following construction methods can be used for the prestressed system using the above-mentioned fixed-end threaded steel bar anchor structure:

[0035] A. Positioning and fixing end components;

[0036] A1. Pre-embedded fixed end components, such as Figure 1 As shown, the cap 31 , the anchor plate 10 and the cable tube 32 are sequentially connected and pre-buried in the anchor seat A, and the through hole 11 of the anchor plate 10 connects the tube hole of the cable tube 32 with the inner cavity of the cap 31 .

[0037] In this embodiment, after step A1, the mortar pouring operation of the anchor seat A is performed, and after the strength of the anchor seat A meets the requirements, step A2 is entered.

[0038] A2, connect the expansion sleeve 20 and the anchor sleeve 30 to the prestressed tendon B, with the expansion sleeve 20 located above the anchor sleeve 30, and then send the prestressed tendon B from the upper end of the cable threading tube 32 into the anchor seat A, so that the expansion sleeve 20 is inserted into the anchor pad 10;

[0039] This embodiment is shown in the attached Figure 2 , 3 As shown, the step surface 23 at the junction of the large and small diameter pipe sections 21 and 22 of the expansion sleeve 20 is pressed against the upper end surface of the anchor plate 10. In other embodiments, a limit column or a positioning block can also be provided at the bottom of the cap 31 to abut against the prestressed tendon B, the expansion sleeve 20 or the anchor sleeve 30 to position the expansion sleeve 20.

[0040] In other embodiments, in order to prevent the mortar from entering the threaded steel bar anchoring structure and blocking the through hole 11 on the anchor plate 10 during vibration, the mortar pouring operation of the anchor seat A can be performed after step A2, and before step B, first determine whether the prestressed tendon B is damaged. If the prestressed tendon B is damaged, replace the prestressed tendon B. If the prestressed tendon B is intact, proceed to step B.

[0041] B. Pre-tensioning the prestressed tendons B to deform the expansion sleeve 20 and form a resisting fit with the anchor plate 10 to limit the displacement of the expansion sleeve 20 toward the tensioning end;

[0042] C. Re-tension the anchor mechanism and complete the anchoring construction. When re-tensioning the anchor mechanism, if the connection between the expansion sleeve 20 and the anchor plate 10 fails and the prestressed tendon B is detached from the anchor plate 10, the prestressed anchoring construction can be performed again according to steps A2, B, and C.

[0043] As attached Figure 3 , 4 As shown, the step B comprises the following steps:

[0044] B1. Sleeve the support tube 40 outside the prestressed tendon B and insert it into the anchor seat A, so that the support tube 40 and the upper end surface of the ring sleeve 20 form abutment fit;

[0045] B2, limiting the displacement of the support tube 40 in the axial direction of the prestressed tendon B, tensioning the prestressed tendon B so that the weak tube section 221 undergoes radial outward expansion deformation under the extrusion of the support tube 40 and the anchor sleeve 30;

[0046] As attached Figure 5 , 6 As shown, in the step C, the support tube 40 is taken out from the cable tube 32, the anchoring mechanism is tensioned again, and mortar is poured into the threaded steel bar anchoring structure to complete the anchoring construction.

Claims

1. A threaded steel bar anchoring structure, characterized in that: An anchor plate (10) is embedded and fixed in the anchor seat (A), the prestressed tendon (B) is inserted into the expansion sleeve (20) and the two form a limit fit in the direction of the preload force, the expansion sleeve (20) is inserted into the anchor plate (10), and when the expansion sleeve (20) is squeezed by an axial external force, the sleeve body is radially expanded and deformed, and forms an axial resistance limit fit with the anchor plate (10); The outer wall of the expansion sleeve (20) is a stepped column formed by a large diameter pipe section (21) and a small diameter pipe section (22); the outer diameter of the small diameter pipe section (22) of the expansion sleeve (20) matches the diameter of the middle through hole (11) of the anchor plate (10) and is inserted into the through hole (11); the step surface (23) at the junction of the large and small diameter pipe sections (21, 22) of the expansion sleeve (20) is in contact with the upper end surface of the anchor plate (10); the wall of the middle section or the end section of the small diameter pipe section (22) is thinned to form a weak pipe section (221); The outer wall of the small diameter pipe section (22) is concave inwards or the inner wall is convex outwards to form a weak pipe section (221); The top end of the weak pipe section (221) is not lower than the lower plate surface of the anchor plate (10).

2. A method for constructing a prestressed system using the threaded steel bar anchor structure according to claim 1, comprising the following steps: A. Positioning and fixing end components; A1. The cap (31), the anchor plate (10) and the cable threading tube (32) are sequentially connected and pre-buried in the anchor seat (A), and the through hole (11) of the anchor plate (10) is connected to the tube hole of the cable threading tube (32) and the inner cavity of the cap (31); A2, connecting the expansion sleeve (20) and the anchor sleeve (30) to the prestressed tendon (B), with the expansion sleeve (20) being located above the anchor sleeve (30), and then sending the prestressed tendon (B) from the upper end of the cable threading tube (32) into the anchor seat (A), so that the expansion sleeve (20) is inserted into the anchor pad (10); B. Pre-tensioning the prestressed tendons (B) to deform the expansion sleeve (20) and form a resisting fit with the anchor plate (10) to limit the displacement of the expansion sleeve (20) toward the tensioning end; C. Re-tension the anchoring mechanism and complete the anchoring construction.

3. The prestressed system construction method according to claim 2, characterized in that: In the step A2, the step surface (23) at the junction of the large-diameter and small-diameter pipe sections (21, 22) of the expansion sleeve (20) is pressed against the upper end surface of the anchor plate (10).

4. The prestressed system construction method according to claim 2, characterized in that: After step A2, the mortar pouring operation of the anchor seat (A) is carried out. Before step B, it is first determined whether the prestressed tendon (B) is damaged. If the prestressed tendon (B) is damaged, the prestressed tendon (B) is replaced. If the prestressed tendon (B) is intact, proceed to step B.

5. The prestressed system construction method according to claim 2, characterized in that: The step B comprises the following steps: B1. Sleeve the support tube (40) outside the prestressed tendon (B) and insert it into the anchor seat (A), so that the support tube (40) and the upper end surface of the expansion sleeve (20) form abutment fit; B2, limiting the displacement of the support tube (40) in the axial direction of the prestressed tendon (B), tensioning the prestressed tendon (B) so that the weak tube section (221) undergoes radial outward expansion deformation under the compression of the support tube (40) and the anchor sleeve (30); In the step C, the support tube (40) is taken out from the cable threading tube (32), and the anchoring mechanism is tensioned again to complete the anchoring construction.

Citation Information

Patent Citations

  • Vertical prestressed anchorage system and construction method thereof

    CN102392415A

  • Threaded steel anchoring structure

    CN215670542U

  • Expasion sleeve bolt

    CN2175829Y