A foundation pit support system and construction method for a newly added basement in an existing factory building

By adopting a combination system of existing factory support, working pile support and steel pipe support in existing factory buildings, combined with micro-perturbation construction method and servo system, the problems of stability and construction safety of the enclosure structure during foundation pit construction are solved, and the problem of "construction safety" is achieved. Effective protection of old buildings and improvement of construction safety.

CN113338303BActive Publication Date: 2024-12-03CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110704325.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-06-24
Publication Date
2024-12-03
Estimated Expiration
2041-06-24

AI Technical Summary

Technical Problem

When constructing foundation pits in existing factories, how to ensure the stability of foundation pit enclosure structure during construction, avoid excessive disturbances to old buildings, and ensure construction safety, especially when the foundation pit stops water not reach the design In the case of deformation of the enclosure structure.

Method used

Adopt a combination system of existing factory support, working pile support and steel pipe support, including permanent foundation reinforcement, temporary wall column reinforcement, working pile support, enclosed steel support and servo system. The construction of working piles is carried out through the micro-disturbance construction method to reduce the old The disturbance of the old building and the expansion and retraction adjustment of the steel support is achieved through hydraulic cylinders and movable ends, and the axial force of the steel support is monitored and automatically compensated in real time.

Benefits of technology

It effectively ensures the stability and construction safety of existing factories during foundation pit construction, reduces disturbances to old buildings, improves the safety and efficiency of construction, and ensures the stability and safety of the enclosure structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113338303B_ABST
    Figure CN113338303B_ABST
Patent Text Reader

Abstract

The present invention provides a foundation pit enclosure system and construction method for a newly added basement in an existing factory building, which reinforces the existing factory building to ensure the stability of the existing factory building during the construction process. At the same time, the foundation pit is driven by a micro-disturbance method to reduce the disturbance to the existing old buildings and improve the safety of the construction; the foundation pit construction uses a micro-disturbance method to drive the foundation pit to reduce the disturbance to the existing factory building and improve the safety of the construction. The existing factory building is not touched during the construction process, and the existing factory building is effectively protected. During the construction process, a servo system is set on the steel support to automatically compensate for the axial force. The system can compensate and unload according to the set axial force to ensure that the axial force is at a stable level, thereby ensuring the safety of the foundation pit and the existing factory building. In addition, monitoring points are set on the wall, and the wall is monitored in real time to ensure the safety of the foundation pit construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of foundation pit construction, and in particular relates to a foundation pit enclosure system and a construction method for a newly added basement in an existing factory building. Background Art

[0002] Foundation pit support is a measure of support, reinforcement and protection for the side walls of the foundation pit and the surrounding environment to ensure the safety of underground structure construction and the surrounding environment of the foundation pit. Common types of foundation pit support mainly include pile support, underground continuous wall support, cement retaining wall, steel sheet pile, soil nail wall, support in the foundation pit or a combination of two or more of them.

[0003] Some foundation pits are constructed inside existing factory buildings. The existing factory buildings have been built for a long time, the buildings are aging, and the foundations are shallow. If the foundation pit water stop does not meet the design requirements or the deformation of the retaining structure is too large, it will cause excessive settlement around the building or uneven settlement, resulting in cracks in the walls of the existing factory buildings. Therefore, the temporary reinforcement of the existing factory buildings must be completed before the construction of the retaining structure. When constructing the above foundation pits, the protection requirements for the existing factory buildings are high. The disturbance should be as small as possible during the construction of the retaining structure or the excavation of the foundation pit. How to ensure the stability of the foundation pit retaining structure during the construction process and avoid collision with the existing factory buildings during the construction process is the focus of safety risk control of this project.

[0004] Therefore, it is necessary to provide an improved technical solution to address the above-mentioned deficiencies in the prior art. Summary of the invention

[0005] The purpose of the present invention is to overcome the above-mentioned deficiencies in the prior art and to provide a construction method capable of carrying out foundation pit construction in an existing building.

[0006] In order to achieve the above object, the present invention provides the following technical solutions:

[0007] A foundation pit support system for a newly added basement in an existing factory building, including existing factory building support, construction pile support and steel pipe support;

[0008] The existing plant support includes:

[0009] Permanent reinforcement of the foundation: excavation of the foundation of the existing plant in sections and reinforcement with concrete pouring;

[0010] Temporary reinforcement of wall columns: angle steel is wrapped on the outside of the column of the existing factory building, and channel steel is set on the inside to form a lattice column. Multiple horizontal square tubes are horizontally set on both sides of the wall. The intersection of the horizontal square tubes and the lattice column is fixedly connected. Vertical square tubes corresponding to the horizontal square tubes are set on both sides of the wall. Through-wall components are correspondingly connected between the horizontal square tubes on the inside and outside of the wall, and through-wall components are correspondingly connected between the vertical square tubes, so that the horizontal square tubes and the vertical square tubes form a whole;

[0011] The construction method pile support includes:

[0012] Construction piles, a plurality of which are arranged at the outer edge of the foundation pit, and the adjacent sides of any two adjacent construction piles overlap each other to form a water-stop curtain wall;

[0013] Insert steel, which is embedded in the method pile along the axial direction of the method pile;

[0014] The steel pipe support comprises:

[0015] Containment steel, a plurality of said containment steels are evenly distributed inside the foundation pit;

[0016] Steel purlins are horizontally welded to the enclosure steel through steel support plates;

[0017] Steel supports, multiple steel supports are evenly distributed in the foundation pit, and two ends of the steel supports are correspondingly abutted against the retaining steel sections located on opposite sides of the foundation pit.

[0018] As described above, for the existing factory building newly added basement foundation pit retaining system, preferably, after the foundation pit construction is completed, the column is permanently reinforced and the wall is repaired, wherein the permanent reinforcement of the column includes:

[0019] Channel steels are arranged on both sides of the column, the height of the channel steels matches the height of the column, and a plurality of embedded parts are arranged on the channel steels to connect the column; the two channel steels are anchored at the existing factory building ring beam through steel tie plates.

[0020] In the above-mentioned newly added basement foundation pit retaining system of the existing factory building, preferably, inclined supports are respectively provided on the inner and outer sides of the corresponding walls of the lattice columns.

[0021] As described above, for the existing factory building newly added basement foundation pit retaining system, preferably, the permanent reinforcement of the foundation includes:

[0022] The cushion layer is set at the bottom layer and is made of concrete;

[0023] The foundation reinforcement steel bar is provided with a plurality of foundation dowel bars implanted in the circumference of the foundation, and the foundation dowel bars are provided in a plurality of directions in the longitudinal direction; a plurality of horizontal distribution bars are arranged around the foundation, and a plurality of vertical distribution bars are connected to the outer edges of the horizontal distribution bars to form corresponding ring bars arranged on the foundation;

[0024] The formwork is enclosed on the outside of the foundation reinforcement steel bars to pour concrete into the inside.

[0025] In the newly added basement foundation pit retaining system for an existing factory building as described above, preferably, a channel steel is fixedly connected to the bottom of the vertical square tube.

[0026] As described above, in the existing factory building newly added basement foundation pit enclosure system, preferably, at least one end of the steel support is provided with a flexible end, and the flexible end includes:

[0027] A receiving groove, fixedly connected to the end of the steel support;

[0028] The movable end head is slidably extended and retracted in the receiving groove along the length direction of the steel support;

[0029] An anchor plate, fixedly connected to one end of the movable end relative to the steel support;

[0030] A hydraulic cylinder is correspondingly connected between the movable end head and the accommodating groove to drive the movable end head to extend and retract along the length direction of the steel support.

[0031] As described above, in the existing factory building newly added basement foundation pit containment system, preferably, the hydraulic cylinder is controlled by a servo system, and the servo system includes:

[0032] A monitoring device for real-time monitoring of the axial force of the steel support;

[0033] A main control cabinet, electrically connected to the monitoring device, and controlling the hydraulic system according to the monitoring data of the monitoring device;

[0034] A hydraulic system, correspondingly connected to the hydraulic cylinder, providing driving force for the hydraulic cylinder;

[0035] The wireless operation module is communicatively connected to the main control cabinet to send a control command to the main control cabinet.

[0036] As described above, in the newly added basement foundation pit retaining system for the existing factory building, preferably, the basement corresponding to the foundation pit is two-story, and correspondingly, the steel support is two-story.

[0037] A construction method for a newly added basement foundation pit of an existing factory building, the method comprising:

[0038] Step S1, excavating the foundation of the existing factory building in sections and pouring concrete for reinforcement;

[0039] Step S2, angle steel is wrapped around the outside of the column of the existing factory building, and channel steel is arranged on the inside to form a lattice column, multiple horizontal square tubes are horizontally arranged on both sides of the inner and outer walls, and the intersections of the horizontal square tubes and the lattice columns are fixedly connected, and vertical square tubes correspondingly connected to the horizontal square tubes are arranged on both sides of the inner and outer walls of the wall, and through-wall components are correspondingly connected between the horizontal square tubes on the inner and outer sides of the wall, and through-wall components are correspondingly connected between the vertical square tubes, so that the square tubes and the lattice columns form a whole;

[0040] Step S3, a plurality of the construction method piles are arranged at the outer edge of the foundation pit, and the adjacent sides of any two adjacent construction method piles overlap each other to form a water-stop curtain wall;

[0041] Step S4, the inserted steel is embedded into the method pile along the axial direction of the method pile;

[0042] Step S5, a plurality of the enclosure steels are evenly distributed inside the foundation pit;

[0043] Step S6, horizontally welding the steel support plate to the enclosure steel;

[0044] Step S7, multiple steel supports are evenly distributed in the foundation pit, and two ends of the steel supports are correspondingly abutted against the retaining steel sections located at opposite sides of the foundation pit.

[0045] As described above, the construction method for the newly added basement foundation pit of the existing factory building is preferably to carry out the construction of the method piles by the micro-disturbance method, and to carry out the construction in the same row of method piles in the order of driving one and jumping one, and to complete the insertion of the internal steel section within 2 hours after the completion of the construction of the method piles.

[0046] Beneficial effects: Foundation pit construction is carried out in existing factory buildings, and the existing factory buildings are reinforced to ensure the stability of the existing factory buildings during the construction process. At the same time, micro-disturbance methods are used to drive piles in the foundation pit to reduce disturbances to existing old buildings and improve construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] The drawings constituting a part of the present application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. Among them:

[0048] Figure 1 A schematic diagram of the lattice column structure in a specific embodiment provided by the present invention;

[0049] Figure 2 A schematic structural diagram of temporary reinforcement of wall columns in a specific embodiment provided by the present invention;

[0050] Figure 3 A schematic diagram of monitoring point distribution in a specific embodiment provided by the present invention;

[0051] Figure 4 This is a schematic diagram of the structure of permanent reinforcement of the foundation in a specific embodiment provided by the present invention;

[0052] Figure 5 A schematic structural diagram of a steel support in a specific embodiment provided by the present invention;

[0053] Figure 6 A schematic diagram of the installation of a steel purlin in a specific embodiment provided by the present invention;

[0054] Figure 7 It is a schematic diagram of the driving of construction piles in a specific embodiment provided by the present invention.

[0055] In the figure, 1, foundation pit; 2, construction pile; 3, steel support; 4, hydraulic cylinder; 5, movable end; 6, receiving groove; 7, steel purlin; 8, monitoring point; 9, vertical distribution reinforcement; 10, foundation dowel; 11, retaining steel; 12, horizontal distribution reinforcement; 13, foundation; 14, vertical square tube; 15, horizontal square tube; 16, column; 17, wall; 18, channel steel; 19, angle steel. DETAILED DESCRIPTION

[0056] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention belong to the scope of protection of the present invention.

[0057] In the description of the present invention, the terms "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings. They are only for the convenience of describing the present invention and do not require that the present invention must be constructed and operated in a specific orientation. Therefore, they should not be understood as limitations on the present invention. The terms "connected" and "connected" used in the present invention should be understood in a broad sense. For example, they can be fixed connections or detachable connections; they can be directly connected or indirectly connected through intermediate components. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0058] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments. It should be noted that the embodiments and features in the embodiments of the present invention can be combined with each other without conflict.

[0059] like Figure 1-7 As shown, a foundation pit support system for a newly added basement in an existing factory building includes existing factory building support, construction pile support and steel pipe support;

[0060] Existing plant support includes:

[0061] The foundation is permanently reinforced. The foundation 13 of the existing factory building is excavated in sections. After the excavation is completed, concrete is poured for reinforcement to ensure the stability of the existing factory building during the foundation pit construction process.

[0062] Temporary reinforcement of wall columns, first of all, the column reinforcement, angle steel 19 is wrapped on the outside of the body, and channel steel 18 is set on the inside to form a lattice column, and the main body is wrapped inside the lattice column; multiple horizontal square tubes 15 are horizontally arranged on both sides of the inside and outside of the wall 17, and the horizontal square tubes 15 are fixedly connected to the intersection of the lattice column, and the multiple horizontal square tubes 15 are equidistantly distributed in the longitudinal direction; vertical square tubes 14 corresponding to the horizontal square tubes 15 are arranged on both sides of the inside and outside of the wall 17, and multiple vertical square tubes 14 are equidistantly distributed in the horizontal direction. The length is adapted to the length of the wall 17, and the length of the vertical square tube 14 is adapted to the height of the wall 17; a through-wall component is correspondingly connected between the horizontal square tubes 15 on the inner and outer sides of the wall 17, and a through-wall component is correspondingly connected between the vertical square tubes 14. The horizontal square tubes 15 and the vertical square tubes 14 on both sides of the wall 17 are fixedly connected by the through-wall components so that the horizontal square tubes 15 and the vertical square tubes 14 form a whole, thereby improving the stability of the wall 17 and avoiding the collapse of the wall 17 during the construction of the foundation pit 1.

[0063] The pile support method includes:

[0064] Construction method piles 2, multiple construction method piles 2 are arranged on the outer edge of the foundation pit 1, and the adjacent sides of any two adjacent construction method piles 2 overlap each other to form a water-stop curtain wall; an inserted steel section is arranged in the construction method pile 2, and the inserted steel section is embedded in the construction method pile along the axial direction of the construction method pile 2.

[0065] Steel pipe support includes:

[0066] The retaining steel sections 11 are evenly distributed on the inner side of the foundation pit 1 and are used to provide longitudinal support to the steel supports 3 .

[0067] The steel enclosure purlin 7 is horizontally welded to the enclosure steel 11 through a steel support plate, wherein the steel support plate is a corbel support plate welded to the enclosure steel 11 .

[0068] Steel supports 3, multiple steel supports 3 are evenly distributed in the foundation pit 1, and two ends of the steel supports 3 correspondingly abut against the enclosure steel 11 located on the opposite sides of the foundation pit 1.

[0069] Foundation pit 1 is constructed in the existing factory building, and the existing factory building is reinforced to ensure the stability of the existing factory building during the construction process. At the same time, the micro-disturbance method is used to drive the construction piles 2 in the foundation pit 1 to reduce the disturbance to the existing old buildings and improve the safety of the construction.

[0070] In this embodiment, the horizontal square tubes 15 and the vertical square tubes 14 are both 160*80*10mm galvanized tubes, the horizontal square tubes 15 are spaced 1.5m apart, and the vertical square tubes 14 are spaced 3m apart. During construction, the horizontal square tubes 15 are constructed first, and then the vertical square tubes 14 are constructed.

[0071] In this embodiment, before construction, it is necessary to demolish the door openings and window openings of the non-load-bearing walls of the existing factory building and build filler walls. This part of the filler wall 17 is not used as a load-bearing wall 17 and does not require temporary reinforcement. It can be demolished as needed for reinforcement construction to avoid affecting the construction of other processes. When the non-load-bearing wall 17 is demolished, if the lintel and ring beam above and the supporting structure below are relatively intact, the filler wall can be directly demolished manually. After demolition, 1-2 supports can be set in the middle of the opening as needed. The support can be a square tube, a wooden support, etc.

[0072] The part of the load-bearing wall 17 that has no repair value cannot be reversibly repaired, so it needs to be demolished to facilitate re-construction. If the demolished area of ​​the load-bearing wall is large, brick columns can be built as needed for support.

[0073] Before demolishing the wall 17, the roof structure should be demolished first. During construction, ground scaffolding should be set up inside and outside the existing factory building. When demolishing the roof structure, the roof tiles should be removed first, and the purlins and the black rods should be removed. The demolished roof should be classified and placed for later recycling.

[0074] In this embodiment, scaffolding is set up on both sides of the existing factory wall 17 as an operation and safety platform, and the wall 17 is supported to a certain extent. The vertical spacing of the scaffolding poles is 1.5m, the pole row spacing is 0.9m, the large crossbar step spacing is 1.8m, the small crossbar of the frame is on the large crossbar, but the sweeping rod position should be set to the small crossbar below the large crossbar, and the inner pole is 350mm away from the structural surface. A full-length sweeping rod must be set up at the bottom, 200mm from the ground. The scissors brace is set on the outside of the scaffolding and is continuously set along the full height of the scaffolding. The scaffolding board must be fully laid on the operating layer of the shelf, and a small crossbar is appropriately added under the scaffolding board. No probe board should appear. The scaffolding board and the small crossbar are tied tightly with iron wire, and a flat net is hung below it. Two steps and one closure must be carried out between the building and the inner pole, and a fully enclosed dense safety net is set on the inside of the outer row of racks.

[0075] In another embodiment of the present application, after the construction of the foundation pit 1 is completed, the column 16 is permanently reinforced and the wall 17 is repaired, wherein the permanent reinforcement of the column 16 includes:

[0076] The angle steel 19 wrapped around the outside of the column 16 is removed and replaced with a channel steel 18, so that both the inner and outer sides of the main body are supported by the channel steel 18 3, the height of the channel steel 18 is adapted to the height of the column 16, and a plurality of embedded parts are provided on the channel steel 18 to connect the column 16; the two channel steels 18 are anchored at the existing factory building ring beam through a steel tie plate, wherein the embedded parts are inserted into the inside of the column 16, specifically, a socket is provided on the column 16, and the embedded parts can be connected to the column 16 by means of expansion bolts or anchoring agents.

[0077] During the permanent reinforcement, the channel steel 18 on the inner side of the wall 17 is the channel steel 18 for temporary reinforcement of the wall column to speed up the construction progress. 20# channel steel 18 is installed on both sides of the column, and the channel steel 18 corresponds to the top surface of the main body foundation 13, the elevation 3.65, and the elevation 7.65 of the embedded parts are welded and connected.

[0078] In another optional embodiment of the present application, oblique supports are respectively provided on the inner and outer sides of the corresponding wall 17 of the lattice column. The oblique supports are made of 20# channel steel 18 and are located at a height of 4.5 meters of the wall column.

[0079] In another optional embodiment of the present application, the permanent reinforcement of the foundation 13 includes:

[0080] The cushion layer is set at the bottom layer and is made of concrete;

[0081] Foundation reinforcement steel bars, multiple foundation dowel bars 10 are implanted in the circumferential direction of the foundation 13, and there are multiple foundation dowel bars 10 in the longitudinal direction, specifically 4, with a longitudinal spacing of 500mm; multiple horizontal distribution bars 12 are arranged around the foundation 13, and multiple vertical distribution bars 9 are correspondingly connected to the outer edges of the horizontal distribution bars 12 to form corresponding ring bars arranged on the foundation 13, wherein both ends of the vertical distribution bars 9 are correspondingly bent toward the foundation 13 and implanted into the foundation 13 to be connected to the foundation 13.

[0082] The formwork is enclosed on the outside of the foundation reinforcement steel bars to pour concrete into them. The embedded steel bars are C12 steel bars.

[0083] In another optional embodiment of the present application, a channel steel 18 is fixedly connected to the bottom of the vertical square tube 14. To prevent the channel steel 18 from loosening, the channel steel 18 is welded to the vertical square tube. A plain concrete pier column with a specification of 500*500*600mm is set below the channel steel 18, and an embedded plate is installed on the pier column.

[0084] In another optional embodiment of the present application, at least one end of the steel support 3 is provided with a flexible end, and the flexible end includes:

[0085] The accommodating groove 6 is fixedly connected to the end of the steel support 3 accordingly.

[0086] The movable end 5 is slidably and telescopically arranged in the receiving groove 6 along the length direction of the steel support 3 .

[0087] The anchor plate is fixedly connected to one end of the movable end 5 relative to the steel support 3.

[0088] The hydraulic cylinder 4 is connected between the movable end 5 and the receiving groove 6 to drive the movable end 5 to extend and retract along the length direction of the steel support 3. The end steel plate, the double-channel steel 18 telescopic rod, the stiffening rib plate and other parts are assembled and welded into the movable end 5. The receiving groove 6 extends along the length direction of the steel support 3, so that the movable end 5 can be retracted in the receiving groove 6 similar to the "drawer" structure, and the movable end 5 is limited in the radial direction of the steel support 3 by the receiving groove 6. Under the action of the hydraulic cylinder 4, the movable end 5 moves in the receiving groove 6 to realize the telescopic function, thereby adjusting the support length. The steel pipe support should be prestressed during installation, and the prestressing is applied according to 35% to 70% of the designed axial force. During construction, the principle of "supporting as excavation" is strictly followed, the exposure time without support is controlled, the loss of prestress is regularly checked, and the prestress is added in time to ensure the stability of the enclosure structure. The telescopic rod of the movable end 5 is placed in the steel pipe containing the movable end, and the telescopic function can be realized under the action of the hydraulic cylinder 4, thereby adjusting the support length.

[0089] The hydraulic cylinder 4 is controlled by a servo system, which includes:

[0090] The monitoring device monitors the axial force of the steel support 3 in real time.

[0091] The main control cabinet is electrically connected to the monitoring device and controls the hydraulic system according to the monitoring data of the monitoring device.

[0092] The hydraulic system is correspondingly connected to the hydraulic cylinder 4 to provide driving force for the hydraulic cylinder 4.

[0093] The wireless operation module is connected to the main control cabinet for communication to send control commands to the main control cabinet.

[0094] Before erection, the steel support 3 is assembled according to the width of the foundation pit 1 and lifted to the preset position by the hoisting equipment. The flexible end of one end of the steel support 3 is pulled out and supported against the steel purlin 7, and prestress is applied to the steel support 3 through the flexible end. The model of the steel support 3 is 600*16mm steel pipes are connected with 10.9-grade M24 high-strength bolts between components. The high-strength bolts should be tightened twice, and the initial tightening torque value is 50%~70% of the final tightening; after the support is prestressed, tighten the loose bolts again. The support erection should be completed within 3 hours after the excavation of foundation pit 1. In order to ensure the overall support effect of the support system, the monitoring frequency should be increased within 12 hours before and after the support prestressing. If the prestress loss or the deformation rate of the enclosure structure has no obvious convergence is found, the prestress should be re-added to the design value.

[0095] A plurality of monitoring points 8 are set around the foundation pit 1 and the existing buildings for setting up monitoring devices. According to the monitoring results of the foundation pit 1, if the supporting axial force needs to be increased, the prestressing force can be increased in the background control platform of the servo system to meet the needs of deformation control of the foundation pit 1.

[0096] Among them, the monitoring device includes a displacement sensor and a force sensor, and the force and displacement of each hydraulic cylinder 4 can be collected and controlled separately. And it is displayed through the display screen in the monitoring station. The main control cabinet is connected to the display screen by communication. The monitoring station has an alarm module electrically connected to the main control cabinet; when the monitoring data exceeds the range, the main control cabinet issues a command to control the pump station, hydraulic system, hydraulic cylinder 4, etc., to realize the servo monitoring of the axial force of the steel support 3, and ensure the effective control of the axial force and the displacement of the side wall of the foundation pit 1. The main control cabinet can be controlled according to the specific engineering design parameters and the system acquisition data. When the acquisition data is within the design parameter range, the system works according to the preset program; the system is visible, controllable, and adjustable, and the axial force becomes smaller and compensates in time, and the high pressure is abnormally self-locked to prevent the steel support 3 from retracting. It has 24-hour real-time monitoring and dynamic control, and can frequently replenish pressure and alarm when the pressure suddenly drops too much. It can effectively control the deformation of the foundation pit 1, and adjust the control parameters according to the actual deformation to better protect the surrounding environment and facilities. The servo system can compensate and unload according to the set axial force to ensure that the axial force is at a stable level, thereby ensuring the safety of the foundation pit 1.

[0097] According to the monitoring results of foundation pit 1, if the supporting axial force needs to be increased, the prestressing force can be increased in the servo system background control platform to meet the needs of deformation control of foundation pit 1.

[0098] In some embodiments, the basement corresponding to the foundation pit 1 is two-story, and correspondingly, the steel support 3 is two-story.

[0099] The present invention also provides a construction method for a newly added basement foundation pit in an existing factory building, characterized in that the method comprises:

[0100] Before construction, the door and window openings of the non-load-bearing walls of the existing factory building were demolished and filled with masonry walls, as well as the parts of the load-bearing walls 17 that had no repair value.

[0101] Step S1, excavating the foundation 13 of the existing factory building in sections and pouring concrete for reinforcement.

[0102] Step S2, angle steel 19 is wrapped around the outer side of the column 16 of the existing factory building, and channel steel 18 is arranged on the inner side to form a lattice column, multiple horizontal square tubes 15 are horizontally arranged on the inner and outer sides of the wall 17, and the intersection of the horizontal square tubes 15 and the lattice column is fixedly connected, and vertical square tubes 14 correspondingly connected to the horizontal square tubes 15 are arranged on the inner and outer sides of the wall 17, and through-wall components are correspondingly connected between the horizontal square tubes 15 on the inner and outer sides of the wall 17, and through-wall components are correspondingly connected between the vertical square tubes 14, so that the square tubes and the lattice column form a whole.

[0103] Step S3, multiple construction method piles 2 are arranged at the outer edge of the foundation pit 1, and the adjacent sides of any two adjacent construction method piles 2 overlap each other to form a water-stop curtain wall; micro-disturbance construction method pile 2 construction: measure and lay out according to the design drawings, determine each hole position and grouting depth; move the construction method pile 2 pile foundation to the specified pile position and align it, and after the mixing shaft reaches the designed depth, lift the construction method pile 2 pile foundation while mixing; start the construction method pile 2 pile foundation, so that the construction method pile 2 pile foundation is stirred and sunk along the guide frame; while the construction method pile 2 pile foundation is pre-stirred and sunk, the background determines the mix ratio according to the design Prepare cement slurry. After the pile driver of method pile 2 sinks to the designed depth, start the mortar pump. When the slurry reaches the spraying port, spray and lift the pile foundation of method pile 2 at the designed lifting speed. When the pile foundation of method pile 2 is sprayed and lifted to the designed top surface elevation, turn off the mortar pump, and sink the pile foundation of method pile 2 again while stirring until the slurry overflows the ground. The adjacent sides of any two adjacent method piles 2 overlap each other to form a water-stop curtain wall. The construction of the same row of method piles 2 is carried out in the order of one hit and one jump. The construction order of the same row of method piles 2 is one hit and one jump. Figure 7 As shown, the construction sequence is: 1→3→5→2→4→6→8→10→12→7→9→11.

[0104] Step S4, the inserted steel is embedded into the method pile 2 along the axial direction.

[0105] Step S5, multiple retaining steel sections 11 are evenly distributed inside the foundation pit 1.

[0106] Step S6, horizontally weld the steel support plate to the retaining steel 11; after the foundation pit 1 is excavated to the preset support position, the retaining steel 11 is set, and the steel support plate is welded to the retaining steel 11, so that the steel support plate is installed in the same plane, and each section of the steel purlin 7 is hoisted on the steel support plate, and each section of the steel purlin 7 is welded into a whole.

[0107] Step S7 , a plurality of steel supports 3 are evenly distributed in the foundation pit 1 , and two ends of the steel supports 3 correspondingly abut against the enclosure steel sections 11 located at opposite sides of the foundation pit 1 .

[0108] A construction method for a newly added basement foundation pit 1 of an existing factory building, wherein construction piles 2 are constructed by a micro-disturbance method, and construction is carried out in a row of construction piles 2 in a construction sequence of driving one and jumping one. Insertion of internal steel sections is completed within 2 hours after the construction of the construction piles 2 is completed.

[0109] Construction of the first steel pipe support: After the foundation pit is excavated to the preset basement floor cushion bottom elevation, the basement floor cushion is constructed. After the construction is completed, the first steel pipe support is removed.

[0110] Removing the inserted steel: After the first steel pipe support is removed, remove the inserted steel in the construction pile 2. When removing the inserted steel, use a jack to repeatedly lift the inserted steel, cut it at a certain height, and then continue to lift it.

[0111] Place two jacks (model: QD-200T) on the top ring beam steadily, lift the inner steel lifting frame on both sides of the inner steel to be pulled out with a crane, turn on the high-pressure oil pump, and use two jacks to simultaneously hold up the crossbeam part of the lifting frame to pull out. When the jack stroke is in place, knock the hammer steel plate loose, and the lifting frame is slowly lowered to its original position with the jack. When the second pull-out is completed, the crane must use a wire rope to penetrate the round hole on the upper part of the inner steel to hang the inner steel. The inner steel is flame-cut, first cutting the web and then cutting the flange part (the principle of thin first and thick later) to prevent cracking caused by stress. If necessary, the cutting part should be preheated with a cutting flame before cutting (preheating temperature ≥ 200). The cutting edges and corners should be subjected to arc transition treatment, and the arc radius should not be less than 25mm. After cutting, the welding planer hammer should be used to tap the cut part of the inner steel to eliminate stress.

[0112] Grouting of interspaces of inserted steel: After the inserted steel is removed, grouting is performed in the spaces formed by the inserted steel. Foundation pit 1 is constructed in the existing factory building, and construction piles 2 are driven into foundation pit 1 using micro-disturbance construction method, which reduces disturbance to the existing old buildings and improves construction safety.

[0113] In this embodiment, the micro-disturbance pile uses ordinary silicate cement with a strength of 42.5, a cement content of 30%, a water-cement ratio of 0.8-1.0, and a retarder content of 5%. When the micro-disturbance pile penetrates the cave, it is first filled with cement slurry.

[0114] In another optional embodiment of the present application, construction preparation work needs to be completed before the construction of the construction pile 2, that is, reviewing the design drawings and leveling reference points, and setting up inclination observation points on the existing factory building; during the construction period, the construction site is monitored every day, deformation data is mastered, and corresponding measures are taken.

[0115] In another optional embodiment of the present application, the I-shaped foundation pit 1 is divided into area A, area B and area C, wherein the upper part of the foundation pit 1 is area A, the lower part is area B, and the middle part is area C, and the construction method piles 2 are constructed in sequence in the order of AC.

[0116] When the area corresponding to at least one of area A, area B and area C is the second-floor basement foundation pit 1.

[0117] When constructing the foundation pit 1 of the second-floor basement, the second steel pipe support construction is carried out on the foundation pit 1: after the foundation pit 1 is excavated to the preset support position, the steel support plate is welded to the enclosure steel 11 so that the steel support plate is installed on the same plane, and each section of the steel purlin 7 is hoisted on the steel support plate, and each section of the steel purlin 7 is welded into a whole; before the steel support 3 is erected, it is assembled according to the width of the foundation pit 1, and lifted to the preset position by the hoisting equipment, the active end of one end of the steel support 3 is pulled out and supported against the steel purlin 7, and prestress is applied to the steel support 3 through the active end.

[0118] Construction of the second-level basement: When the construction of the second-level basement floor corresponding to Foundation Pit 1 is completed, the second steel pipe support will be removed; when the main structure construction of the second-level basement of Foundation Pit 1 is completed, the first steel pipe support will be removed.

[0119] Specifically, if a certain area corresponds to the second-floor basement foundation pit 1, the construction steps are: construction preparation → temporary reinforcement of wall 17 and roof demolition → micro-disturbance method pile construction → earth excavation → top beam construction → first steel pipe support → earth excavation to the second support bottom elevation → construction of purlin and second steel pipe support → earth excavation to the basement floor cushion bottom elevation → (basement floor construction completed) → removal of the second steel support → (negative second floor structure construction completed) → removal of the first steel support → (negative first floor structure construction completed) → gap grouting after the steel section is removed.

[0120] In some embodiments, after the construction of foundation pit 1 is completed, the existing factory building is repaired by first plastering the wall, then laying a steel mesh on the wall, and anchoring the steel mesh, and then spraying it after the anchoring is completed.

[0121] In another optional embodiment of the present application, the monitoring devices installed at the wall 17 and the foundation include at least a horizontal monitoring module, a settlement monitoring module, an angle monitoring module, etc., which are used to grasp the status of the existing factory building in real time. If an abnormal situation is detected, the excavation of the foundation pit 1 should be stopped, and secondary reinforcement and repair of the existing factory building should be carried out.

[0122] In summary, the present invention provides a new basement foundation pit enclosure system and construction method for an existing factory building, which reinforces the existing factory building to ensure the stability of the existing factory building during the construction process. At the same time, the micro-disturbance method is used to drive the construction pile 2 of the foundation pit 1 to reduce the disturbance to the existing old building and improve the safety of the construction; the micro-disturbance method is used to drive the construction pile 2 of the foundation pit 1 during the construction of the foundation pit 1 to reduce the disturbance to the existing factory building and improve the safety of the construction. The existing factory building is not touched during the construction process, and the existing factory building is effectively protected. During the construction process, a servo system is set on the steel support to automatically compensate for the axial force. The system can compensate and unload according to the set axial force to ensure that the axial force is at a stable level, thereby ensuring the safety of the foundation pit 1 and the existing factory building. In addition, a monitoring point 8 is set on the wall 17, and the wall 17 is monitored in real time to ensure the safety of the construction of the foundation pit 1. It can be understood that the above description is only exemplary, and the embodiments of the present application are not limited to this.

[0123] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention are within the scope of protection of the pending claims of the present invention.

Claims

1. A new basement foundation pit support system for an existing factory building. It is characterized in that Including existing plant support, construction pile support and steel pipe support; The existing plant support includes: Permanent reinforcement of the foundation: excavation of the foundation of the existing plant in sections and reinforcement with concrete pouring; Temporary reinforcement of wall columns: angle steel is wrapped on the outside of the column of the existing factory building, and channel steel is set on the inside to form a lattice column. Multiple horizontal square tubes are horizontally set on both sides of the wall. The intersection of the horizontal square tubes and the lattice column is fixedly connected. Vertical square tubes corresponding to the horizontal square tubes are set on both sides of the wall. Through-wall components are correspondingly connected between the horizontal square tubes on the inside and outside of the wall, and through-wall components are correspondingly connected between the vertical square tubes, so that the horizontal square tubes and the vertical square tubes form a whole; The construction method pile support includes: Construction piles, a plurality of which are arranged at the outer edge of the foundation pit, and the adjacent sides of any two adjacent construction piles overlap each other to form a water-stop curtain wall; Insert steel, which is embedded in the method pile along the axial direction of the method pile; The steel pipe support comprises: Containment steel, a plurality of said containment steels are evenly distributed inside the foundation pit; Steel purlins are horizontally welded to the enclosure steel through steel support plates; Steel supports, multiple steel supports are evenly distributed in the foundation pit, and the two ends of the steel supports are respectively located on the retaining steel on the opposite sides of the foundation pit; after the foundation pit construction is completed, the column is permanently reinforced and the wall is repaired, wherein the permanent reinforcement of the column includes: Channel steels are arranged on both sides inside and outside the column, the height of the channel steels matches the height of the column, and a plurality of embedded parts are arranged on the channel steels to connect the column; the two channel steels are anchored at the existing factory building ring beam through steel tie plates; inclined supports are arranged on the inner and outer sides of the corresponding wall of the lattice column.

2. The existing factory building newly added basement foundation pit containment system according to claim 1, It is characterized in that The permanent reinforcement of the foundation includes: The cushion layer is set at the bottom layer and is made of concrete; The foundation reinforcement steel bar is provided with a plurality of foundation dowel bars implanted in the circumference of the foundation, and the foundation dowel bars are provided in a plurality of directions in the longitudinal direction; a plurality of horizontal distribution bars are arranged around the foundation, and a plurality of vertical distribution bars are connected to the outer edges of the horizontal distribution bars to form corresponding ring bars arranged on the foundation; The formwork is enclosed on the outside of the foundation reinforcement steel bars to pour concrete into the inside.

3. The existing factory building newly added basement foundation pit containment system according to claim 1, It is characterized in that A channel steel is fixedly connected to the bottom of the vertical square tube.

4. The existing factory building newly added basement foundation pit containment system according to claim 1, It is characterized in that At least one end of the steel support is provided with a flexible end, and the flexible end comprises: A receiving groove, the receiving groove is fixedly connected to the end of the steel support; A movable end head, the movable end head slides and retracts in the receiving groove along the length direction of the steel support; An anchor plate, the anchor plate is fixedly connected to one end of the movable end relative to the steel support; A hydraulic cylinder is correspondingly connected between the movable end head and the accommodating groove to drive the movable end head to extend and retract along the length direction of the steel support.

5. The existing factory building newly added basement foundation pit containment system according to claim 4, It is characterized in that The hydraulic cylinder is controlled by a servo system, and the servo system comprises: A monitoring device, wherein the monitoring device monitors the axial force of the steel support in real time; A main control cabinet, the main control cabinet is electrically connected to the monitoring device and controls the hydraulic system according to the monitoring data of the monitoring device; A hydraulic system, the hydraulic system correspondingly connected to the hydraulic cylinder to provide driving force for the hydraulic cylinder; A wireless operation module is communicatively connected to the main control cabinet to send a control command to the main control cabinet.

6. The existing factory building newly added basement foundation pit containment system according to claim 1, It is characterized in that The basement corresponding to the foundation pit is two-story, and correspondingly, the steel support is two-story.

7. A construction method for adding a new basement foundation pit to an existing factory building. It is characterized in that The method comprises: Step S1, excavating the foundation of the existing factory building in sections and pouring concrete for reinforcement; Step S2, angle steel is wrapped around the outside of the column of the existing factory building, and channel steel is arranged on the inside to form a lattice column, multiple horizontal square tubes are horizontally arranged on both sides of the inner and outer walls, and the intersections of the horizontal square tubes and the lattice columns are fixedly connected, and vertical square tubes correspondingly connected to the horizontal square tubes are arranged on both sides of the inner and outer walls of the wall, and through-wall components are correspondingly connected between the horizontal square tubes on the inner and outer sides of the wall, and through-wall components are correspondingly connected between the vertical square tubes, so that the square tubes and the lattice columns form a whole; Step S3, a plurality of construction method piles are arranged at the outer edge of the foundation pit, and the adjacent sides of any two adjacent construction method piles overlap each other to form a water-stop curtain wall; Step S4, the inserted steel is embedded into the method pile along the axial direction of the method pile; Step S5, multiple enclosure steels are evenly distributed inside the foundation pit; Step S6, horizontally welding the steel support plate to the enclosure steel; Step S7, multiple steel supports are evenly distributed in the foundation pit, and two ends of the steel supports are correspondingly abutted against the retaining steel sections located at opposite sides of the foundation pit.

8. The construction method for adding a new basement foundation pit to an existing factory building according to claim 7, It is characterized in that The construction of the method piles is carried out through the micro-disturbance method. The construction sequence of the method piles in the same row is followed: one hit and one jump. The insertion of the internal steel sections is completed within 2 hours after the completion of the method pile construction.