Longitudinal and transverse bracing installation and disassembly device for complex foundation pit support system and its use method

By designing the installation and disassembly devices of vertical and horizontal braces of the complex foundation pit support system, and using components such as leveling piers, force-transmitting bolsters, and transverse components, the problems of narrow working space and complicated lifting processes in deep foundation pit construction have been solved, and the problem has been achieved. The precise installation and efficient disassembly of steel supports improves construction safety and efficiency.

CN113550328BActive Publication Date: 2024-10-01NO 3 ENG COMPANY LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110952964.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-08-19
Publication Date
2024-10-01
Estimated Expiration
2041-08-19

AI Technical Summary

Technical Problem

In the construction of large-span, high-density deep foundation pits, due to the narrow working space, staggered arrangement of vertical and horizontal braces, and complex hoisting techniques, installation operations are difficult, safety hazards are high, and construction efficiency is low.

Method used

A device for installing and dismantling vertical and horizontal braces of a complex foundation pit support system is designed, including leveling piers, force-transmitting pads, traversing components and supporting components. The precise docking and position adjustment of the steel supports are achieved through the traversing drive components and jacks. , simplifying the installation and removal process.

Benefits of technology

It improves the operating efficiency of the supporting structure, ensures construction safety, reduces manual auxiliary input, enhances the controllability and construction accuracy of the steel support position, and reduces safety hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113550328B_ABST
    Figure CN113550328B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of building construction technology, and in particular to a device for installing and disassembling longitudinal and transverse braces of a complex foundation pit support system and a method for using the device. The device for installing and disassembling longitudinal and transverse braces of a complex foundation pit support system comprises a leveling pad, a force transmission pad is installed on the upper part of the leveling pad, a transverse member is installed on the upper part of the force transmission pad, and a supporting member is installed on the upper part of the transverse member; the transverse member comprises a roller support seat installed on the upper part of the force transmission pad, and a transverse roller group is rotatably installed in the roller support seat. The present invention decomposes the structure of the entire device, which can be transported manually and assembled at the bottom of the foundation pit. It is suitable for the small working space at the bottom of the foundation pit. The device is flexible and convenient to install and disassemble, and the various components are independent of each other. The components that match the environment can be replaced arbitrarily according to different construction environments. At the same time, the supporting members that match the steel supports of different specifications can also be replaced. It is flexible and changeable, has a wide range of uses, and is easy to promote.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a longitudinal and transverse brace installation and disassembly device for a complex foundation pit support system and a use method thereof. Background Art

[0002] In the construction of some deep foundation pits with large spans, high density, and staggered and overlapping vertical and horizontal braces, due to the narrow working space, staggered arrangement of vertical and horizontal braces, tight lattice columns, and layered arrangement of vertical and horizontal braces, the steel supports need to be hoisted in sections using the hoisting technology. The space is small and the positions of the steel supports at overlapping places are frequently adjusted, making them difficult to connect. This makes installation difficult, and it is easy to touch the installed supports and lattice columns during the process. It is difficult for personnel to operate, the construction efficiency is low, and there are major safety hazards, endangering the safety of deep foundation pit operations. Summary of the invention

[0003] In order to solve the problems of staggered and overlapping vertical and horizontal supports in deep foundation pits, small working space, cumbersome construction operations using hoisting technology, long duration, and endangering the safety of deep foundation pit support structures, a vertical and horizontal support installation and disassembly device for a complex foundation pit support system and a method for using the device are provided, which can achieve precise docking of the assembly, installation, and disassembly of the vertical and horizontal supports, have a simple process, improve the operating efficiency of the support structure, and ensure the safety of the installation and disassembly of the support structure.

[0004] The technical solution adopted by the present invention to achieve the above-mentioned purpose is: a device for installing and removing longitudinal and transverse braces of a complex foundation pit support system, comprising a leveling pad, a force transmission pad is installed on the upper part of the leveling pad, a transverse member is installed on the upper part of the force transmission pad, and a supporting member is installed on the upper part of the transverse member;

[0005] The transverse movement member comprises a roller support seat installed on the upper part of the force transmission pad, and a transverse movement roller group is rotatably installed in the roller support seat;

[0006] The supporting member comprises a jack bottom support installed on the upper part of the transverse roller group, the upper surfaces of both ends of the jack bottom support are respectively provided with jack fixing sleeves, the upper part of the jack fixing sleeve is opened, a jack is installed in the jack fixing sleeve, a top support seat is installed above the jack fixing sleeve, the top support seat is connected to the jack driving, a top support is provided between the two top support seats, and a plurality of universal balls are provided on the upper surface of the top support;

[0007] The roller support seat is provided with a transverse driving assembly, and the transverse driving assembly drives the supporting member to move transversely on the transverse member.

[0008] Furthermore, there are two transverse drive assemblies, which are respectively arranged at two ends of the roller support seat.

[0009] Furthermore, the transverse driving assembly includes a rocker support seat fixed on the roller support seat, a roller is installed on the rocker support seat, the roller is driven by the rocker, one end of the pull rope is connected to the roller, and the other end of the pull rope is connected to the pull rope connecting rod arranged on the base of the jack.

[0010] Furthermore, the leveling pier includes two upper and lower support plates, and a plurality of pillars are arranged between the two support plates.

[0011] Furthermore, the leveling piers are arranged in 2-4 rows, and the leveling piers are distributed on the lower surface of the force transmission pad.

[0012] Furthermore, the support is in an arc shape, and a plurality of universal balls are arranged on the inner surface of the arc.

[0013] Furthermore, a plurality of supporting ribs are provided on the lower surface of the top support.

[0014] Furthermore, grooves are respectively provided at both ends of each roller of the transverse roller group, and a protrusion matching the grooves is provided on the lower surface of the jack base.

[0015] Furthermore, the leveling pad and the force transmission pad, the force transmission pad and the roller support seat, the jack base support and the transverse roller group are all overlapped, the jack fixing sleeve and the jack base support are welded, the jack fixing sleeve and the top support seat are overlapped, the top support seat is driven up and down by the jack, the top support seat and the top support and supporting ribs are all welded, and the supporting base of the universal ball and the top support are welded.

[0016] The method for using the longitudinal and transverse bracing installation and disassembly device of the complex foundation pit support system includes the following steps:

[0017] Step 1: The device components are prefabricated, the leveling pad, the force transmission pad, the transverse member, the support member and the transverse drive assembly are prefabricated, and the components that need to be pre-connected are assembled and connected;

[0018] Step 2: Assemble the device. Delineate the device assembly area according to the length and position of the steel support. Assemble the device from bottom to top. First, place the leveling pad at the bottom of the foundation pit in the assembly area, place the force transmission pad on the leveling pad, place the roller support seat on the force transmission pad, place the jack base on the transverse roller group in the roller support seat, and then connect the two ends of the pull rope to the roller and the pull rope connecting rod respectively to keep the jack base stable on the transverse roller group, then place the jack in the jack fixing sleeve, and finally place the top support seat on the jack fixing sleeve;

[0019] Step 3: Install the steel support. Move the steel support to the top support. First, turn the rocker to drive the jack bottom support to move horizontally on the transverse roller group through the pull rope, and then roughly adjust the axial position of the steel support. Then start the jack to lift the top support seat, and fine-tune the axis position of the steel support to make the axis positions of the two sections of steel supports to be assembled consistent. Finally, push the steel support to move longitudinally to the installation area of ​​the two sections of steel supports. Rotate the steel support to make the flange bolt holes at the ends of the two sections of steel supports to be connected butt joint. Tighten the bolts to complete the installation of the two sections of steel supports. Connect two or more sections of steel supports in turn according to the above method. After the steel support connection is completed, disassemble and assemble the device for recycling.

[0020] Step 4: Steel support removal. After the foundation pit structure construction is completed and the conditions for steel support removal are met, the steel support is removed by this device using a method opposite to the steel support installation process.

[0021] Technical effects and advantages of the present invention:

[0022] (1) The present invention disassembles the structure of the entire device, which can be carried manually and assembled at the bottom of the foundation pit. It is suitable for situations where the working space at the bottom of the foundation pit is small. The device is flexible and convenient to install and disassemble, and each component is independent of each other. Components that match the environment can be replaced at will according to different construction environments. At the same time, supporting components that match steel supports of different specifications can also be replaced. The device is flexible and versatile, has a wide range of uses, and is easy to promote and apply over a large area.

[0023] (2) The large-span lateral movement of the steel support is achieved through the linkage of the rocker and the pull rope in the lateral drive assembly. The operation is simple and light.

[0024] (3) The jacking support seat is lifted by a jack, and the steel support axis is fine-tuned through the jacking support and the universal ball to meet the accuracy requirements of use. At the same time, the investment in manual assistance in the lifting process is greatly reduced. The position of the steel support is controllable and the safety is high.

[0025] (4) A plurality of supporting ribs are provided on the lower surface of the top support, which play a role in strengthening the support of the top support and enhancing the strength of the top support. The top support is safer and more stable during the process of supporting and adjusting the steel support. The top support is arc-shaped and fits the steel support better, which facilitates the adjustment and installation of the steel support.

[0026] (5) Grooves are provided at both ends of the roller of the transverse roller group, and protrusions matching the grooves are provided on the lower surface of the jack base, so that the jack base is more stable when it moves laterally on the transverse roller group, and will not deviate, thus playing a role of limiting.

[0027] (6) The universal ball on the top support can meet the large-range longitudinal movement of the steel support and realize the position adjustment in a narrow space. At the same time, it can make the steel support rotate to ensure the docking accuracy of the bolt holes, which greatly improves the construction efficiency. During the entire construction process, the position of the steel support can be controlled to ensure that the steel support components to be installed do not collide with other steel support structures, which is safe and reliable.

[0028] (7) By following steps 1 to 4 of the description of the method of using the longitudinal and transverse bracing installation and disassembly device for the complex foundation pit support system, the overall method of using the device can be clearly understood, facilitating its promotion and application. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a structural front view of the present invention;

[0030] Figure 2 for Figure 1 Left view of;

[0031] Figure 3 It is a front view of the jacking support of the present invention;

[0032] Figure 4 It is a left side view of the jacking support of the present invention;

[0033] Figure 5 It is a front view of the jack base and the jack fixing sleeve of the present invention;

[0034] Figure 6 It is a left side view of the jack base and the jack fixing sleeve of the present invention;

[0035] Figure 7 It is a front view of the roller support seat, the transverse roller group and the force transmission pad of the present invention;

[0036] Figure 8 It is a left view of the roller support seat, the transverse roller group and the force transmission pad of the present invention;

[0037] Fig. 9 It is a structural schematic diagram of the leveling pad of the present invention;

[0038] In the figure: 1. leveling pad, 2. force transmission pad, 3. transverse roller group, 4. jack fixing sleeve, 5. jack, 6. top support, 7. roller, 8. pull rope, 9. jack bottom support, 10. top support seat, 11. universal ball, 12. support rib, 13. steel support, 14. roller support seat, 15. rocker support seat, 16. rocker, 17. pull rope connecting rod. DETAILED DESCRIPTION

[0039] The present invention is described in detail below with reference to the accompanying drawings and embodiments.

[0040] Example:

[0041] like Figure 1-9 As shown, the installation and disassembly device of the longitudinal and transverse braces of the complex foundation pit support system includes a leveling pad 1, a force transmission pad 2 is installed on the upper part of the leveling pad 1, the leveling pad 1 includes two upper and lower support plates, a plurality of pillars are arranged between the two support plates, the leveling pad 1 is in two rows, two in each row, and the number of the leveling pad 1 can be selected according to the scope of operation, the leveling pad 1 and the force transmission pad 2 are overlapped, a transverse member is installed on the upper part of the force transmission pad 2, and a supporting member is installed on the upper part of the transverse member;

[0042] The transverse moving member includes a roller support seat 14 installed on the upper part of the force transmission pad 2. The force transmission pad 2 and the roller support seat 14 are overlapped and connected. A transverse moving roller group 3 is rotatably installed in the roller support seat 14. Each roller of the transverse moving roller group 3 is provided with grooves at both ends, and the depth of the groove is 1 cm.

[0043] The supporting member includes a jack support 9 installed on the upper part of the transverse roller group 3. The lower surface of the jack support 9 is provided with a protrusion matching the groove on the transverse roller group 3. The jack support 9 and the transverse roller group 3 are overlapped. The upper surfaces of both ends of the jack support 9 are respectively provided with jack fixing sleeves 4. The jack fixing sleeve 4 and the jack support 9 are welded. The upper part of the jack fixing sleeve 4 is opened. The jack 5 is installed in the jack fixing sleeve 4. A top support seat 10 is installed above the jack fixing sleeve 4. The jack fixing sleeve The cylinder 4 and the top support seat 10 are overlapped, the top support seat 10 is connected to the jack 5 by driving, the top support seat 10 and the driving rod of the jack 5 are movably connected, the top support seat 10 is driven to move up and down by the jack 5, a top support 6 is arranged between the two top support seats 10, the top support 6 is in an arc shape, a plurality of supporting ribs 12 are arranged on the lower surface of the top support 6, the top support seat 10 and the top support 6 and the supporting ribs 12 are all welded, a plurality of universal balls 11 are arranged on the upper surface of the top support 6, and the supporting base of the universal ball 11 is welded to the top support 6;

[0044] Two transverse driving components are provided on the roller support seat 14, which are respectively arranged at the two ends of the roller support seat 14. The transverse driving component drives the supporting member to move laterally on the transverse roller group 3 of the transverse member. The transverse driving component includes a rocker support seat 15 fixed on the roller support seat 14, and a roller 7 is installed on the rocker support seat 15. The roller 7 is driven to rotate by a rocker 16. One end of a pull rope 8 is connected to the roller 7, and the other end of the pull rope 8 is connected to a pull rope connecting rod 17 arranged on the jack base 9. The transverse driving component here can also be other components that can achieve the same function.

[0045] The method for using the longitudinal and transverse bracing installation and disassembly device of the complex foundation pit support system includes the following steps:

[0046] Step 1: The device components are prefabricated. First, the leveling pad 1, the force transmission pad 2, the transverse member, the support member and the transverse driving assembly are prefabricated, and the components that need to be pre-connected are assembled and connected, including assembling the transverse roller group 3 with the roller support seat 14, welding and fixing the rocker support seat 15 of the transverse driving assembly with the roller support seat 14, and pre-installing the rocker 16 and the roller 7 respectively. The jack fixing sleeve 4 is welded and fixedly connected with the jack bottom support 9, the top support seat 10 is welded and fixedly connected with the top support 6 and the supporting rib 12, and the supporting base of the universal ball 11 is welded and fixedly connected with the top support 6;

[0047] Step 2: Assemble the device. Delineate the device assembly area according to the length and position of the steel support 13. Assemble the device from bottom to top in sequence. First, place the leveling pad 1 at the bottom of the foundation pit in the assembly area at a spacing of 1m. The bottom of the leveling pad 1 needs to be padded so that the upper surface heights of all leveling pads 1 are basically the same. Place the force transmission pad 2 on the leveling pad 1 so that there is no overhang around the force transmission pad 2. Place the roller support seat 14 on the force transmission pad 2, and place the jack base 9 on the transverse roller in the roller support seat 14. On the cylinder group 3, make the protrusion on the jack bottom support 9 coincide with the groove on the transverse roller group 3, then connect the two ends of the pull rope 8 to the roller 7 and the pull rope connecting rod 17 respectively, so that the jack bottom support 9 remains stable on the transverse roller group 3, and then place the jack 5 in the jack fixing sleeve 4, and finally place the top support seat 10 on the jack fixing sleeve 4. During construction, set the number of the device according to the length of the steel support 13 to be assembled; if the steel support is installed in one section, only two sets of devices are needed for installation;

[0048] Step 3: Installation of the steel support. The steel support 13 is transported to the top support 6. The rocker 16 is first rotated to drive the jack bottom support 9 to move horizontally on the transverse roller group 3 through the pull rope 8, and then the axial position of the steel support 13 is roughly adjusted. After the approximate position is adjusted to the right position, the jack 5 is then started to lift the top support seat 10, and the axial position of the steel support 13 is fine-tuned to make the axial positions of the two sections of the steel support 13 to be assembled consistent. Finally, the steel support 13 is pushed to move longitudinally to the installation area of ​​the two sections of the steel support 13, and the steel support 13 is rotated to make the flange bolt holes at the ends of the two sections of the steel support to be connected butt joint. The installation of the two sections of the steel support 13 is completed by tightening the bolts. According to the above method, two or more sections of the steel support 13 are connected in turn. After the steel support 13 is connected, the device is disassembled and assembled for recycling. According to different installation environments and steel support installation requirements, any component in the device can be replaced at will to meet different installation requirements.

[0049] Step 4: Steel support removal. After the foundation pit structure construction is completed and the conditions for removing the steel support 13 are met, the device is used to remove the steel support using a method opposite to the steel support installation process. First, the device is assembled under the steel support 13 that needs to be removed, so that the steel support 13 is placed on the top support 6, and then the connected steel supports 13 are disassembled. Finally, the disassembled steel support 13 is moved out of the foundation pit through the cooperation of the support member, the transverse member and the transverse drive assembly. After the steel support 13 is disassembled, the device is disassembled and re-used until all the steel supports 13 are disassembled.

[0050] The device and its use method can be applied to the installation and disassembly of steel supports in different foundation pits, which is convenient, fast and safe, saves manpower and material resources, improves work efficiency and saves costs.

[0051] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation modes, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.

Claims

1. The method for using the longitudinal and transverse bracing installation and disassembly device of the complex foundation pit support system is characterized by: The installation and disassembly device of the longitudinal and transverse braces of the complex foundation pit support system includes a leveling pad, a force transmission pad is installed on the upper part of the leveling pad, a transverse member is installed on the upper part of the force transmission pad, and a supporting member is installed on the upper part of the transverse member; The transverse moving member comprises a roller support seat installed on the upper part of the force transmission pad, a transverse moving roller group is rotatably installed in the roller support seat, each roller of the transverse moving roller group is provided with grooves at both ends, and a protrusion matching the groove is provided on the lower surface of the jack base; The supporting member comprises a jack bottom support mounted on the upper part of the transverse roller group, the upper surfaces of both ends of the jack bottom support are respectively provided with jack fixing sleeves, the upper part of the jack fixing sleeve is open, a jack is installed in the jack fixing sleeve, a top support seat is installed above the jack fixing sleeve, the top support seat is connected to the jack driving, a top support is provided between the two top support seats, the top support is in an arc shape, and a plurality of universal balls are provided on the upper surface of the top support; The roller support seat is provided with a transverse driving assembly, and the transverse driving assembly drives the supporting member to move transversely on the transverse driving member; the transverse driving assembly includes a rocker support seat fixed on the roller support seat, and a roller is installed on the rocker support seat, and the roller is driven by the rocker, and one end of the pull rope is connected to the roller, and the other end of the pull rope is connected to the pull rope connecting rod provided on the bottom support of the jack; The method of use includes the following steps: Step 1: The device components are prefabricated, the leveling pad, the force transmission pad, the transverse member, the support member and the transverse drive assembly are prefabricated, and the components that need to be pre-connected are assembled and connected; Step 2: Assemble the device. Delineate the device assembly area according to the length and position of the steel support. Assemble the device from bottom to top. First, place the leveling pad at the bottom of the foundation pit in the assembly area, place the force transmission pad on the leveling pad, place the roller support seat on the force transmission pad, place the jack base on the transverse roller group in the roller support seat, and then connect the two ends of the pull rope to the roller and the pull rope connecting rod respectively to keep the jack base stable on the transverse roller group, then place the jack in the jack fixing sleeve, and finally place the top support seat on the jack fixing sleeve; Step 3: Install the steel support. Move the steel support to the top support. First, turn the rocker to drive the jack bottom support to move horizontally on the transverse roller group through the pull rope, and then adjust the axial position of the steel support. Then start the jack to lift the top support seat, and fine-tune the axis position of the steel support to make the axis positions of the two sections of steel supports to be assembled consistent. Finally, push the steel support to move longitudinally to the installation area of ​​the two sections of steel supports. Rotate the steel support to make the flange bolt holes at the ends of the two sections of steel supports to be connected butt joint. Tighten the bolts to complete the installation of the two sections of steel supports. Connect two or more sections of steel supports in turn according to the above method. After the steel support connection is completed, disassemble and assemble the device for recycling. Step 4: Steel support removal. After the foundation pit structure construction is completed and the conditions for steel support removal are met, the steel support is removed by this device using a method opposite to the steel support installation process.

2. The method for using the longitudinal and transverse bracing installation and disassembly device for the complex foundation pit support system according to claim 1 is characterized by: There are two transverse drive assemblies, which are respectively arranged at two ends of the roller support seat.

3. The method for using the longitudinal and transverse bracing installation and disassembly device for the complex foundation pit support system according to claim 1 is characterized by: The leveling pier comprises two upper and lower support plates, and a plurality of pillars are arranged between the two support plates.

4. The method for using the longitudinal and transverse bracing installation and disassembly device for the complex foundation pit support system according to claim 1 is characterized by: The leveling piers are arranged in 2 to 4 rows and are distributed on the lower surface of the force transmission pad.

5. The method for using the longitudinal and transverse bracing installation and disassembly device for the complex foundation pit support system according to claim 1 is characterized by: The lower surface of the top support is provided with a plurality of supporting ribs.

6. The method for using the longitudinal and transverse bracing installation and disassembly device for the complex foundation pit support system according to claim 5 is characterized by: The leveling pad and the force transmission pad, the force transmission pad and the roller support seat, the jack base support and the transverse roller group are all overlapped connections, the jack fixing sleeve and the jack base support are welded, the jack fixing sleeve and the top support seat are overlapped connections, the top support seat is driven up and down by the jack, the top support seat and the top support and supporting ribs are all welded connections, and the supporting base of the universal ball and the top support are welded.