A method for constructing a composite structure of straw landfill and grain mill for ecological management of erosion gullies
The composite structure composed of ecological bag mills and straw bales solves the problem of limited application scope of existing technology, achieves a wider erosion gully control effect, and improves structural stability and straw utilization.
Patent Information
- Application Number
- CN202111056292.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-09-09
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-09-09
AI Technical Summary
The existing treatment method of using straw to fill the entire erosion ditch is only suitable for erosion ditches with a ditch depth of less than 2 meters, a small water catchment area, and smooth downstream drainage, and its scope of application is limited.
A composite structure composed of ecological grain bags, straw bales, anchoring concrete columns, blocking concrete columns, soil, willows and vegetation is used to build ecological grain grain squares, concrete column blocking, anchoring, and soil covering through channel shaping and straw filling. Methods of slope cutting and vegetation restoration were used to construct a composite structure of straw filling and grain square for ecological management of erosion gullies.
It increases the erosion base level, reduces the area occupied by slope cutting, extends the flexibility of the construction period, improves structural stability, and increases the utilization rate of straw, making it suitable for a wider range of erosion ditch management.
Smart Images

Figure CN113585180B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for constructing a composite structure for controlling erosion gullies. Background Art
[0002] Soil erosion in the Northeast Black Soil Region is a long-term soil problem and an important factor restricting the protection of black soil. Gully erosion is the most serious manifestation of soil erosion and one of the main types of soil erosion in the Northeast Black Soil Region. Gully erosion is extremely fast. Gully head erosion causes the gully length to continue to extend, the gully bottom to cut down, and the gully bank to collapse, resulting in rapid development of gully depth and width. Gully erosion not only produces silt, silts downstream reservoirs and rivers, continuously devours arable land, reduces land utilization, restricts agricultural mechanized production, but also threatens the safety of villages and roads.
[0003] At present, the main methods of gully erosion control are gully head protection projects, mortar masonry, gabions, wickerwork and other types of gullies, combined with forest and grass measures to consolidate and raise the gully bed, stop gully bottom cutting and gully bank expansion, and restore vegetation ecology. There are disadvantages such as slope cutting occupying land, expensive raw materials, large engineering volume, high labor costs, and seasonal influences on the construction period. The Northeast Black Soil Region is the main grain producing area in my country. The main grain crops are corn, soybeans, rice, etc., and the amount of straw is very sufficient. The existing control method of using straw to fill the entire gully to achieve reclamation effect, but it is only applicable to gullies with characteristics such as gully depth less than 2 meters, small catchment area, and smooth downstream drainage, and the scope of application is limited. Summary of the invention
[0004] The present invention aims to solve the technical problem that the existing method of using straw to fill the entire erosion ditch is only applicable to erosion ditches with a ditch depth of less than 2 meters, a small catchment area, and smooth downstream drainage, and has a limited scope of application, and provides a method for constructing a composite structure of straw landfill and grain workshop for ecological management of erosion ditch.
[0005] The composite structure of landfill straw and grain for ecological management of erosion gullies of the present invention is composed of an ecological bag grain 1, a straw bundle 3, an anchoring concrete column 6, a blocking concrete column 7, soil 11, willow branches and vegetation;
[0006] The ecological bag valley 1 is arranged in the original ditch bottom 5, the water-facing surface of the ecological bag valley 1 is a vertical structure, the back-water slope ratio is 1:0.8, and an overflow port 1-1 is arranged at the center of the upper end of the ecological bag valley 1; multiple rows of straw bales 3 are arranged vertically upstream of the ecological bag valley 1, each straw bale 3 is a cylindrical structure, the straw bales 3 are closely adjacent to each other, and are closely adjacent to the water-facing surface of the ecological bag valley 1, the straw bales 3 are all arranged on the horizontal first ditch bottom 9, and the slopes 8 on both sides of the straw bales 3 are vertical structures; an energy dissipation pool 4 is arranged downstream of the ecological bag valley 1, and an energy dissipation sill 2 is arranged downstream of the energy dissipation pool 4, the energy dissipation pool 4 and the energy dissipation sill 2 are both arranged on the horizontal second ditch bottom 10, the upper surface of the energy dissipation sill 2 is a horizontal structure, and soil 11 is arranged on the upper surface of the straw bale 3; the second ditch bottom 10 is higher than the first ditch bottom 9; the back-water surface of the energy dissipation sill 2 is closely adjacent to the downstream straw bales 3; a plurality of willow branches are evenly arranged on the soil 11;
[0007] Two anchoring concrete columns 6 are vertically and evenly arranged on the backwater side of the ecological bag valley 1, and the bottom of the anchoring concrete column 6 is inserted into the original ditch bottom 5; a blocking concrete column 7 is horizontally arranged between the backwater side of the ecological bag valley 1 and the two anchoring concrete columns 6, and the two ends of the blocking concrete column 7 are respectively arranged in the slopes 8 on both sides; the slope ratio of the slopes 8 on both sides is 1:1.5, and ecological bag slope protection is arranged on the slopes 8 on both sides, and vegetation is arranged on the slopes above the ecological bag slope protection.
[0008] The method for constructing the composite structure of straw landfill and grain mill for ecological management of erosion gullies of the present invention is as follows:
[0009] 1. Channel shaping: Design the location where the valley arches are to be placed in advance, and use an excavator to dig and shape the slopes on both sides vertically downward to the bottom of the ditch at 1.4m~1.5m above the ditch bottom at the upstream of each valley arch, so that the slope of the slopes on both sides after excavation is 90°, and the slopes on both sides above the excavation position remain unchanged; then dig the ditch bottom between two adjacent valley arches downward into a two-layer step structure, and each step is flat;
[0010] 2. Straw filling: Place multiple cylindrical straw bundles with a diameter and height of 1.4m to 1.5m vertically and tightly upstream of each grain workshop and on the flat trench bottom dug in step 1, where the flat trench bottom is the lower flat trench bottom in the step structure;
[0011] 3. Constructing the Eco-bag Valley Square: Place the Eco-bag Valley Square at a pre-designed location. The length of the top of the Eco-bag Valley Square along the direction of water flow is 0.8m~1m, the height of the Eco-bag Valley Square is 2m~2.1m, the backwater slope ratio of the Eco-bag Valley Square is 1:0.8, and the water-facing surface is vertically set. The water-facing surface of the Eco-bag Valley Square is closely connected with the straw set in step 2; the depth of the channel slopes on both sides of the top of the Eco-bag Valley Square is 2m~2.5m; an overflow port is set at the top center of the Eco-bag Valley Square; each An energy dissipation pool and an energy dissipation sill are arranged in sequence downstream of the eco-bag valley. The length of the energy dissipation pool parallel to the water flow direction is 3m~4m, the height of the energy dissipation sill is 0.5m~0.6m, and the length of the energy dissipation sill parallel to the water flow direction is 0.5m~0.6m; slope protection is arranged on both sides of the downstream of each eco-bag valley with a vertical height of 2m~2.5m; the energy dissipation sill is arranged on the plane ditch bottom dug in step 1, and the plane ditch bottom is a higher plane ditch bottom in the step structure, and the energy dissipation sill is closely adjacent to the straw bale downstream thereof;
[0012] 4. Concrete column blocking and anchoring: A blocking concrete column with a diameter of 0.25m is horizontally set 1m below the lowest point on the backwater side of the overflow outlet. The length direction of the blocking concrete column is perpendicular to the water flow direction, and the two sides of the blocking concrete column are respectively inserted into the slopes on both sides; two anchoring concrete columns with a diameter of 0.25m are set next to the side of the blocking concrete column away from the valley, and the two anchoring concrete columns are set vertically, and the lower end of the anchoring concrete column is inserted into the soil at the bottom of the ditch to a depth of 1m, and the height of the anchoring concrete column is 4m~5m; the anchoring concrete column and the blocking concrete column are tied with wire;
[0013] 5. Soil covering: Cover the straw bales filled in step 2 with 0.3m~0.5m thick soil, and use a machine to level and cover the soil. The soil comes from the remaining soil in step 1. The upper edge of the energy dissipation sill is flush with the soil on the straw bales downstream.
[0014] 6. Slope cutting and leveling: Take the straw landfill and soil covering in step 5 as the erosion reference surface, cut the slopes on both sides above the erosion reference surface at a slope ratio of 1:1.5, cover with soil again and level the surface of the straw bale;
[0015] 7. Planting willows: Plant willows on the straw covering soil. If the above construction is carried out in spring, plant willows on the covering soil in the spring of the current year. If the construction is carried out in the other three seasons, plant willows on the covering soil in the spring of the following year.
[0016] 8. Slope vegetation restoration: Based on the local dominant grass species and shrub species, vegetation restoration is carried out on the slopes on both sides of the ditch.
[0017] The advantages of the present invention are:
[0018] First, the present invention burys straw upstream of the eco-bag valley 1, which can directly raise the erosion base level by about 2m (straw burying + covering with soil), and second, can protect the eco-bag valley 1 from being washed away;
[0019] Second, the present invention can solve the outstanding problem of slope cutting and land occupation in gully erosion control. After the straw is buried, the slope is cut according to the slope ratio of 1:1.5, and the land occupation on each side can be reduced by about 3m in the direction perpendicular to the water flow;
[0020] 3. In addition to the need to plant willows in spring, the straw landfill and ecological bag grain construction do not need to be carried out after autumn harvest and before freezing, so the construction period is relatively flexible, solving the problem of short construction period; because the straw has good water retention performance, the survival rate and growth of shrub willow are higher than those of solid soil;
[0021] Fourth, the present invention utilizes concrete poles for blocking and anchoring, thereby increasing the stability of the eco-bag grain workshop 1 and the ditch-filling straw bundle 3;
[0022] 5. Most of the large amount of straw produced each year is used for comprehensive utilization and returned to the field, but some of it is still burned, polluting the environment. The present invention uses straw for gully erosion control. On the one hand, the raw material price is low and the amount of straw is sufficient to meet the gully erosion landfill control needs. On the other hand, consuming part of the straw can reduce the amount of burning and increase the straw utilization rate. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 A schematic diagram of a composite structure of landfilled straw and a grain mill for ecological management of erosion gullies according to a first embodiment;
[0024] Figure 2 for Figure 1 A top view of
[0025] Figure 3 for Figure 2 AA section view. DETAILED DESCRIPTION
[0026] Specific implementation method 1: This implementation method is a composite structure of landfill straw and grain square for ecological management of erosion gullies, such as Figure 1-Figure 3 As shown, it is specifically composed of an ecological bag grain workshop 1, straw bundles 3, anchoring concrete columns 6, blocking concrete columns 7, soil 11, willow branches and vegetation;
[0027] The ecological bag valley 1 is arranged in the original ditch bottom 5, the water-facing surface of the ecological bag valley 1 is a vertical structure, the back-water slope ratio is 1:0.8, and an overflow port 1-1 is arranged at the center of the upper end of the ecological bag valley 1; multiple rows of straw bales 3 are arranged vertically upstream of the ecological bag valley 1, each straw bale 3 is a cylindrical structure, the straw bales 3 are closely adjacent to each other, and are closely adjacent to the water-facing surface of the ecological bag valley 1, the straw bales 3 are all arranged on the horizontal first ditch bottom 9, and the slopes 8 on both sides of the straw bales 3 are vertical structures; an energy dissipation pool 4 is arranged downstream of the ecological bag valley 1, and an energy dissipation sill 2 is arranged downstream of the energy dissipation pool 4, the energy dissipation pool 4 and the energy dissipation sill 2 are both arranged on the horizontal second ditch bottom 10, the upper surface of the energy dissipation sill 2 is a horizontal structure, and soil 11 is arranged on the upper surface of the straw bale 3; the second ditch bottom 10 is higher than the first ditch bottom 9; the back-water surface of the energy dissipation sill 2 is closely adjacent to the downstream straw bales 3; a plurality of willow branches are evenly arranged on the soil 11;
[0028] Two anchoring concrete columns 6 are vertically and evenly arranged on the backwater side of the ecological bag valley 1, and the bottom of the anchoring concrete column 6 is inserted into the original ditch bottom 5; a blocking concrete column 7 is horizontally arranged between the backwater side of the ecological bag valley 1 and the two anchoring concrete columns 6, and the two ends of the blocking concrete column 7 are respectively arranged in the slopes 8 on both sides; the slope ratio of the slopes 8 on both sides is 1:1.5, and ecological bag slope protection is arranged on the slopes 8 on both sides, and vegetation is arranged on the slopes above the ecological bag slope protection.
[0029] Specific embodiment 2: This embodiment is different from the specific embodiment 1 in that the energy dissipation sill 2 and the energy dissipation pool 4 are both made of ecological bags. The rest is the same as the specific embodiment 1.
[0030] Specific embodiment 3: This embodiment is different from specific embodiment 1 or 2 in that the anchoring concrete column 6 and the blocking concrete column 7 are both made of concrete. The rest is the same as specific embodiment 1 or 2.
[0031] Specific implementation method 4: This implementation method is a construction method of a composite structure of landfilled straw and grain square for ecological management of erosion gullies in specific implementation method 1, and the specific process is as follows:
[0032] 1. Channel shaping: Design the location where the valley arches are to be placed in advance, and use an excavator to dig and shape the slopes on both sides vertically downward to the bottom of the ditch at 1.4m~1.5m above the ditch bottom at the upstream of each valley arch, so that the slope of the slopes on both sides after excavation is 90°, and the slopes on both sides above the excavation position remain unchanged; then dig the ditch bottom between two adjacent valley arches downward into a two-layer step structure, and each step is flat;
[0033] 2. Straw filling: Place multiple cylindrical straw bundles with a diameter and height of 1.4m to 1.5m vertically and tightly upstream of each grain workshop and on the flat trench bottom dug in step 1, where the flat trench bottom is the lower flat trench bottom in the step structure;
[0034] 3. Construction of Eco-bag Valley Square: Place the Eco-bag Valley Square at a pre-designed location. The length of the top of the Eco-bag Valley Square along the direction of water flow is 0.8m~1m, the height of the Eco-bag Valley Square is 2m~2.1m, the backwater slope ratio of the Eco-bag Valley Square is 1:0.8, the water-facing surface is vertically set, and the water-facing surface of the Eco-bag Valley Square is closely connected to the straw set in step 2; the depth of the channel slope on both sides of the top of the Eco-bag Valley Square is 2m~2.5m; an overflow port is set at the center of the top of the Eco-bag Valley Square; the downstream of each Eco-bag Valley Square is based on The energy dissipation pool and energy dissipation sill are set up for the first time. The length of the energy dissipation pool parallel to the water flow direction is 3m~4m, the height of the energy dissipation sill is 0.5m~0.6m, and the length of the energy dissipation sill parallel to the water flow direction is 0.5m~0.6m; slope protection is set on both sides of the downstream of each eco-bag valley with a vertical height of 2m~2.5m; the energy dissipation sill is set on the plane ditch bottom dug in step 1, and the plane ditch bottom is a higher plane ditch bottom in the step structure, and the energy dissipation sill is closely adjacent to the straw bundle downstream thereof; the energy dissipation sill and energy dissipation pool are both composed of eco-bags;
[0035] 4. Concrete column blocking and anchoring: A blocking concrete column with a diameter of 0.25m is horizontally set 1m below the lowest point on the backwater side of the overflow outlet. The length direction of the blocking concrete column is perpendicular to the water flow direction, and the two sides of the blocking concrete column are respectively inserted into the slopes on both sides; two anchoring concrete columns with a diameter of 0.25m are set next to the side of the blocking concrete column away from the valley, and the two anchoring concrete columns are vertically set, and the lower end of the anchoring concrete column is inserted into the soil at the bottom of the ditch to a depth of 1m, and the height of the anchoring concrete column is 4m~5m; the anchoring concrete column and the blocking concrete column are tied with wire; the material of the anchoring concrete column 6 and the blocking concrete column 7 are both concrete;
[0036] 5. Soil covering: Cover the straw bales filled in step 2 with 0.3m~0.5m thick soil, and use a machine to level and cover the soil. The soil comes from the remaining soil in step 1. The upper edge of the energy dissipation sill is flush with the soil on the straw bales downstream.
[0037] 6. Slope cutting and leveling: Take the straw landfill and soil covering in step 5 as the erosion reference surface, cut the slopes on both sides above the erosion reference surface at a slope ratio of 1:1.5, cover with soil again and level the surface of the straw bale;
[0038] 7. Planting willows: Plant willows on the straw covering soil. If the above construction is carried out in spring, plant willows on the covering soil in the spring of the current year. If the construction is carried out in the other three seasons, plant willows on the covering soil in the spring of the following year.
[0039] 8. Slope vegetation restoration: Based on the local dominant grass species and shrub species, vegetation restoration is carried out on the slopes on both sides of the ditch.
[0040] Specific implementation method 5: This implementation method is different from specific implementation method 4 in that: in step 3, slope protection is set on both sides of the downstream of each eco-bag valley with a vertical height of 2m. Other aspects are the same as specific implementation method 4.
[0041] The present invention is verified by the following tests:
[0042] Experiment 1: This experiment is a method for constructing a composite structure of straw landfill and grain square for ecological management of erosion gullies. Figure 1-Figure 3 As shown, the specific process is as follows:
[0043] 1. Channel shaping: Design the location where the valley sheds are to be placed in advance, and use an excavator to dig and shape the slopes on both sides vertically downward to the bottom of the ditch at the upstream of each valley shed and 1.4m above the ditch bottom, so that the slope of the slopes on both sides after excavation is 90°, and the slopes on both sides above the excavation position remain unchanged; then dig the ditch bottom between two adjacent valley sheds downward into a two-layer step structure, and each step is flat;
[0044] 2. Straw filling: Place multiple cylindrical straw bundles with a diameter and height of 1.4m vertically and tightly upstream of each grain workshop and on the flat trench bottom dug in step 1, where the flat trench bottom is the lower flat trench bottom in the step structure;
[0045] 3. Constructing an ecological bag valley: placing an ecological bag valley at a pre-designed position, the length of the top of the ecological bag valley along the direction of water flow is 1m, the height of the ecological bag valley is 2m, the backwater slope ratio of the ecological bag valley is 1:0.8, the water-facing surface is vertically arranged, and the water-facing surface of the ecological bag valley is closely connected with the straw arranged in step 2; the depth of the channel slopes on both sides of the top of the ecological bag valley is 2m; an overflow port is arranged at the top center of the ecological bag valley; an energy dissipation pool and an energy dissipation sill are arranged in sequence downstream of each ecological bag valley, the length of the energy dissipation pool parallel to the direction of water flow is 3m, the height of the energy dissipation sill is 0.5m, and the length of the energy dissipation sill parallel to the direction of water flow is 0.5m; slope protection is arranged on both sides of the downstream of each ecological bag valley with a vertical height of 2m; the energy dissipation sill is arranged on the plane ditch bottom dug in step 1, and the plane ditch bottom is a higher plane ditch bottom in the step structure, and the energy dissipation sill is closely adjacent to the straw bundle downstream thereof;
[0046] 4. Concrete column blocking and anchoring: A blocking concrete column with a diameter of 0.25m is horizontally set 1m below the lowest point on the backwater side of the overflow outlet. The length direction of the blocking concrete column is perpendicular to the water flow direction, and the two sides of the blocking concrete column are respectively inserted into the slopes on both sides; two anchoring concrete columns with a diameter of 0.25m are set next to the side of the blocking concrete column away from the valley, and the two anchoring concrete columns are set vertically, and the lower end of the anchoring concrete column is inserted into the soil at the bottom of the ditch to a depth of 1m, and the height of the anchoring concrete column is 4m~5m; the anchoring concrete column and the blocking concrete column are tied with wire;
[0047] 5. Soil covering: Cover the straw bales filled in step 2 with 0.5m thick soil, and use a machine to level and cover the soil. The soil comes from the remaining soil in step 1. The upper edge of the energy dissipation sill is flush with the soil on the straw bales downstream.
[0048] 6. Slope cutting and leveling: Take the straw landfill and soil covering in step 5 as the erosion reference surface, cut the slopes on both sides above the erosion reference surface at a slope ratio of 1:1.5, cover with soil again and level the surface of the straw bale;
[0049] 7. Planting willows: Plant willows on the straw covering soil. If the above construction is carried out in spring, plant willows on the covering soil in the spring of the current year. If the construction is carried out in the other three seasons, plant willows on the covering soil in the spring of the following year.
[0050] 8. Slope vegetation restoration: Based on the local dominant grass species and shrub species, vegetation restoration is carried out on the slopes on both sides of the ditch.
[0051] The advantages of this test are:
[0052] First, this experiment landfilled straw upstream of Eco-bag Valley 1. First, it can directly raise the erosion base level by about 2m (straw landfill + soil covering), and second, it can increase the protection of Eco-bag Valley 1 from being washed away;
[0053] Second, this test can solve the outstanding problem of slope cutting and land occupation for gully erosion control. By cutting the slope with a slope ratio of 1:1.5, the land occupation can be reduced by 3m on each side in the direction perpendicular to the water flow.
[0054] 3. In addition to the fact that willow planting must be carried out in spring, straw landfill and ecological bag grain construction do not need to be carried out after autumn harvest and before freezing. The construction period is relatively flexible, which solves the problem of short construction period. At the same time, because straw has good water retention performance, the survival rate and growth of shrub willow are higher than those in solid soil.
[0055] Fourth, this test uses concrete poles for blocking and anchoring to increase the stability of the eco-bag grain square 1 and the ditch-filling straw bundle 3;
[0056] 5. Most of the large amount of straw produced each year is used for comprehensive utilization and returned to the fields, but some of it is still burned, polluting the environment. In this experiment, straw is used for gully erosion control. On the one hand, the raw material price is low and the amount of straw is sufficient to meet the needs of gully erosion landfill control. On the other hand, consuming some straw can reduce the amount of burning and increase the utilization rate of straw.
Claims
1. A method for constructing a composite structure of straw landfill and grain square for ecological management of erosion gullies, characterized in that The landfill straw / grain compound structure for ecological gully management is composed of an ecological bag grain box (1), straw bundles (3), anchoring concrete columns (6), blocking concrete columns (7), soil (11), willow branches and vegetation; The ecological bag valley (1) is set in the original ditch bottom (5), the water-facing surface of the ecological bag valley (1) is a vertical structure, the back surface slope ratio is 1:0.8, and an overflow port (1-1) is set at the center of the upper end of the ecological bag valley (1); multiple rows of straw bundles (3) are vertically set upstream of the ecological bag valley (1), each straw bundle (3) is a cylindrical structure, the straw bundles (3) are closely adjacent to each other, and are closely adjacent to the water-facing surface of the ecological bag valley (1), and the straw bundles (3) are all set on the horizontal first ditch bottom (9), and the straw bundles ( 3) The slopes (8) on both sides are vertical structures; an energy dissipation pool (4) is set downstream of the eco-bag valley (1); an energy dissipation bank (2) is set downstream of the energy dissipation pool (4); the energy dissipation pool (4) and the energy dissipation bank (2) are both set on a horizontal second ditch bottom (10); the upper surface of the energy dissipation bank (2) is a horizontal structure; the upper surface of the straw bundle (3) is set on the soil (11); the second ditch bottom (10) is higher than the first ditch bottom (9); the back surface of the energy dissipation bank (2) is closely adjacent to the downstream straw bundle (3); and a plurality of willow branches are evenly arranged on the soil (11); Two anchoring concrete columns (6) are vertically and evenly arranged on the backwater side of the eco-bag valley (1), and the bottoms of the anchoring concrete columns (6) are inserted into the original ditch bottom (5); a blocking concrete column (7) is horizontally arranged between the backwater side of the eco-bag valley (1) and the two anchoring concrete columns (6), and the two ends of the blocking concrete column (7) are respectively arranged in the slopes (8) on both sides; the slope ratio of the slopes (8) on both sides is 1:1.5, and eco-bag slope protection is arranged on the slopes (8) on both sides, and vegetation is arranged on the slopes above the eco-bag slope protection; The method for constructing the composite structure of straw landfill and grain mill for ecological erosion control is as follows:
1. Channel shaping: Pre-design the location for placing the ravines. Use an excavator to dig vertically downwards to the ravine bottom at the upstream of each ravine and 1.4m to 1.5m above the ravine bottom, shaping the slopes on both sides to 90° after excavation. The slopes on both sides above the excavation point remain unchanged. Then, dig the ravine bottom between two adjacent ravines downwards to form a two-layer step structure, with each step being flat.
2. Straw filling: Place multiple cylindrical straw bundles with a diameter and height of 1.4m to 1.5m vertically and tightly on the upper reaches of each grain building and on the flat trench bottom dug in step 1. The flat trench bottom is the lower flat trench bottom in the step structure; 3. Construction of Eco-bag Valley: Place the Eco-bag Valley at a pre-designed location. The length of the top of the Eco-bag Valley along the direction of water flow is 0.8m~1m, the height of the Eco-bag Valley is 2m~2.1m, the backwater slope ratio of the Eco-bag Valley is 1:0.8, the water-facing side is set vertically, and the water-facing side of the Eco-bag Valley is closely connected to the straw set in step 2; the depth of the channel slope on both sides of the top of the Eco-bag Valley is 2m~2.5m; an overflow port is set at the center of the top of the Eco-bag Valley; the downstream of each Eco-bag Valley is arranged in sequence. Set up a stilling pool and a stilling sill. The length of the stilling pool parallel to the water flow is 2m~3m, and the height of the stilling sill is 0.5m~0.6m. The length of the stilling sill parallel to the water flow is 0.5m~0.6m. Set up slope protection on both sides of the downstream of each eco-bag valley with a vertical height of 2m~2.5m. Set the stilling sill on the flat ditch bottom excavated in step 1. The flat ditch bottom is the higher flat ditch bottom in the step structure. The stilling sill is closely adjacent to the straw bale downstream. The stilling sill and the stilling pool are both made of eco-bags.
4. Concrete column blocking and anchoring: A blocking concrete column with a diameter of 0.25m is horizontally set 1m below the lowest point on the backwater side of the overflow outlet. The length direction of the blocking concrete column is perpendicular to the water flow direction, and the two sides of the blocking concrete column are respectively inserted into the slopes on both sides; two anchoring concrete columns with a diameter of 0.25m are set next to the side of the blocking concrete column away from the valley, and the two anchoring concrete columns are both set vertically, with the lower ends of the anchoring concrete columns inserted into the soil at the bottom of the ditch to a depth of 1m, and the height of the anchoring concrete columns is 4m~5m; the anchoring concrete columns and the blocking concrete columns are tied with wire; the materials of the anchoring concrete columns (6) and the blocking concrete columns (7) are both concrete; 5. Covering with soil: Cover the straw bales filled in step 2 with a thickness of 0.3m to 0.5m of soil. Use a mechanical leveling machine to cover the soil. The soil comes from the excess soil in step 1. The upper edge of the stilling sill should be flush with the soil on the straw bales downstream.
6. Slope cutting and leveling: Using the soil covering after straw landfill in step 5 as the erosion reference surface, cut the slopes on both sides above the erosion reference surface at a slope ratio of 1:1.5, cover with soil again and level the surface of the straw bale; 7. Planting willows: Plant willows on the straw covering soil. If the above construction is carried out in spring, plant willows on the covering soil in the spring of the same year; if the construction is carried out in the other three seasons, plant willows on the covering soil in the spring of the following year.
8. Slope vegetation restoration: Based on the local dominant grass species and shrub species, vegetation restoration is carried out on the slopes on both sides of the ditch.
2. The method for constructing a composite structure of straw landfill and grain mill for ecological gully management according to claim 1, characterized in that In step 3, slope protection is set up on both sides of the downstream of each eco-bag valley with a vertical height of 2m.
Citation Information
Patent Citations
Check dam of channel and construction method thereof
CN108842720A
Bundle stack ecological slope protection structure and construction method thereof
CN109610485A
Compound check dam water and soil conservation method
CN109930556A
Stepped straw check dam for treating erosion gully
CN113136880A
Landfill straw and check dam composite structure for ecologically managing erosion gully
CN215925860U