Installing the substrate manufacturing system
By combining the rule base and actual performance teaching data, Gaussian process or Bayesian model is used to estimate the machine parameters of new parts, solving the problems of complexity in adjusting new parts and low production efficiency, and achieving fast and efficient parts loading operations. .
Patent Information
- Application Number
- CN202080024179.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2019-03-29
- Filing Date
- 2020-03-13
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2040-03-13
AI Technical Summary
When using new components in existing mounting substrate manufacturing systems, machine parameters need to be frequently adjusted to ensure the quality of component loading operations, resulting in a decrease in production efficiency. Especially for new components that have not been produced with actual production results, the adjustment process is complex and time-consuming.
Using a method that combines the rule base and actual performance teaching data, estimate the machine parameters of new parts through Gaussian process regression model or Bayesian statistical model, generate prediction distributions and calculate posterior distributions, and provide appropriate machine parameters to reduce adjustment time and improve efficiency.
There is no need to spend a lot of time adjusting parameters every time a component is replaced. Appropriate machine parameters can be estimated before component loading, which improves production efficiency, reduces man-hours, and ensures consistency with the experience of suppliers or skilled users.
Smart Images

Figure CN113632023B_ABST
Abstract
Description
Technical Field
[0001] The present disclosure relates to a mounting substrate manufacturing system for a component mounting machine. Background Art
[0002] The mounting substrate manufacturing system for manufacturing mounting substrates is provided with a component mounting line, and the component mounting line is provided with a component mounting device for performing component mounting operations on the substrate. The component mounting operations performed by the component mounting device are composed of various operation operations such as the suction operation of taking out the component from the component supply part by a suction nozzle, the recognition operation of photographing and recognizing the taken out component, and the mounting operation of transferring and mounting the component on the substrate. In these operation operations, it is required to perform precise operations with high precision and high efficiency for precise components, and therefore, machine parameters for performing each operation operation in a good operation mode are pre-set according to the type of component. Moreover, the component data in which these machine parameters are associated with the type of component is stored as a component library.
[0003] These component data are not necessarily set to optimal values that enable the work operation to be performed in an optimal operation mode, and may need to be corrected at any time in response to malfunctions that occur when performing the component mounting operation.
[0004] However, in the correction work of component data, a high degree of professionalism based on the expertise and experience related to component installation is required, so in the past, a lot of time and labor caused by trial and error had to be spent on the production site. In other words, when performing the component mounting operation, even if an unfavorable situation such as poor recognition of the component or adsorption error occurs, it is actually the case that how to correct which parameter item depends largely on the operator's expertise. Therefore, when entrusting data correction to an unskilled operator, trial and error caused by inappropriate data correction becomes repeated, resulting in not only the operating efficiency of the data correction operation, but also the improvement of the operating quality of the component mounting operation.
[0005] Therefore, as a countermeasure, Patent Document 1 discloses a mounting substrate manufacturing system that corrects at least one machine parameter included in component data based on the performance of component mounting work.
[0006] Prior Art Literature
[0007] Patent Literature
[0008] Patent Document 1: Japanese Patent Application Publication No. 2019-4129 Summary of the invention
[0009] Problems to be solved by the invention
[0010] However, in the mounting substrate manufacturing system disclosed in Patent Document 1, since the correction work is performed for the component with poor performance, once the component mounting work is started, the correction work is performed only after the poor performance is confirmed. Therefore, when a new component without actual production results is used, the production efficiency is reduced because the temporary component mounting work execution time, that is, the time required to generate the results confirmation is spent every time the component is changed.
[0011] Furthermore, in recent years, there is also a method of using accumulated data and applying machine learning technology to output various parameters of the device equipped with new parts, etc. However, sometimes the values of various parameters are not consistent with the experience of suppliers or experienced users, which may cause confusion on site.
[0012] Therefore, an object of the present disclosure is to provide a mounting substrate manufacturing system capable of estimating appropriate machine parameters for a new component without generating labor hours for confirmation results.
[0013] Means for solving problems
[0014] In order to achieve the above-mentioned purpose, one embodiment of the present invention involves an installation substrate manufacturing system that manufactures an installation substrate with components mounted on the substrate, and the installation substrate manufacturing system comprises: at least one component mounting device that performs a component mounting operation of mounting the component on the substrate; a rule base that can calculate at least one machine parameter used by the component mounting device to perform the component mounting operation; an operation information aggregation unit that aggregates the results of the processing performed by the component mounting device together with the operation information according to the component data; and an estimation unit that selects component data of the operation results that exceed a given benchmark from the operation information aggregation unit as actual performance instruction data (instructor data), and uses the actual performance instruction data, the rule base and basic information of the new component to estimate at least one machine parameter of the new component.
[0015] In addition, these overall or specific methods can be implemented through systems, methods, integrated circuits, computer programs, or recording media such as computer-readable CD-ROMs, or through any combination of systems, methods, integrated circuits, computer programs, and recording media.
[0016] Effects of the Invention
[0017] According to the present disclosure, it is possible to estimate appropriate machine parameters for man-hours in which a new component does not generate a confirmed result. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1It is a diagram for explaining the structure of a mounting substrate manufacturing system according to an embodiment.
[0019] Figure 2 It is a diagram showing an example of operation information summary data according to the embodiment.
[0020] Figure 3 It is an explanatory diagram of the data structure of component data used in the mounting substrate manufacturing system according to the embodiment.
[0021] Figure 4 This is a diagram showing an example of a rule base set by a vendor according to the embodiment.
[0022] Figure 5 This is a diagram showing an example of a rule base set by a user according to an embodiment.
[0023] Figure 6 This is a diagram showing an example of actual performance teaching data according to the embodiment.
[0024] Figure 7 This is a flowchart showing the operation until the production of a new component starts in the mounting substrate manufacturing system in the present embodiment.
[0025] Figure 8 This is a diagram showing an example of a graphical model of a statistical model according to Example 1 of the embodiment.
[0026] Fig. 9 This is a diagram showing an example of a graphical model of a statistical model according to Example 2 of the implementation method.
[0027] Fig.10 This is a diagram for explaining adjustment of weights of a plurality of rules included in a rule base according to Example 3 of the implementation method.
[0028] Fig.11 This is a diagram showing an example of a graphical model of a Gaussian process model.
[0029] Fig.12 This is a diagram showing an example of a graphical model of a statistical model according to Example 4 of the implementation method.
[0030] Fig.13 This is a diagram showing an example of another graphical model of the statistical model involved in Example 4 of the implementation method.
[0031] Fig.14 This is a diagram showing an example of a graphical model of a statistical model according to Example 5 of the implementation method.
[0032] Fig.15This is a diagram showing an example of a graphical model of a statistical model according to Example 6 of the implementation method.
[0033] Fig.16 is a bubble chart showing machine parameters estimated by the hybrid method involved in the present disclosure.
[0034] Fig.17 If you select more than one Fig.16 The bubbles shown indicate the component information.
[0035] Fig.18 It is a summary diagram showing the machine parameters estimated by the hybrid method involved in the present disclosure. DETAILED DESCRIPTION
[0036] One embodiment of the present disclosure relates to an installation substrate manufacturing system that manufactures an installation substrate with components mounted on the substrate, and the installation substrate manufacturing system comprises: at least one component mounting device that performs a component mounting operation of mounting the component on the substrate; a rule base that can calculate at least one machine parameter used by the component mounting device to perform the component mounting operation; an operation information aggregation unit that aggregates results of processing performed by the component mounting device together with operation information according to component data; and an estimation unit that selects component data of operation results exceeding a given benchmark from the operation information aggregation unit as actual performance teaching data, and uses the actual performance teaching data, the rule base, and basic information of the new component to estimate at least one machine parameter of the new component.
[0037] This makes it possible to estimate appropriate machine parameters for new parts that do not generate work hours for verification. Therefore, even when using new parts with no actual production results, it is not necessary to spend time on temporary part loading operations every time a part is changed, thereby suppressing a decrease in production efficiency.
[0038] Here, the estimation unit uses a Gaussian process regressor that uses the basic information of the component included in the component data of the operating results exceeding the given benchmark and the corresponding machine parameter values as learning data to estimate the basic information of the new component, thereby generating a predicted distribution of the machine parameters that can be applied to the new component, generating the output of the rule base according to a normal distribution with the machine parameters that can be applied to the new component as the average, and then calculating the posterior distribution of the machine parameters that can be applied to the new component, and outputting the calculated average of the posterior distribution as the machine parameter applied to the new component among the applicable machine parameters.
[0039] According to this, it is possible to estimate appropriate machine parameters that are consistent with the experience of suppliers and skilled users before the component installation operation without generating the time required to confirm the performance of the new component. Therefore, even when using a new component with no actual production performance, it is not necessary to spend time on the temporary component installation operation every time the component is changed, thereby suppressing the decline in production efficiency.
[0040] Furthermore, for example, the rule base may include two or more non-uniform rules that produce different outputs for calculating at least one machine parameter of the new component.
[0041] In addition, for example, the estimation unit may use a Bayesian statistical model to estimate basic information of the new component, thereby generating a predicted distribution of machine parameters that can be applied to the new component, generating an output of the rule base based on a distribution with the machine parameters that can be applied to the new component as parameters, and then calculating the posterior distribution of the machine parameters that can be applied to the new component, and outputting the average of the calculated posterior distribution as the machine parameters that can be applied to the new component among the applicable machine parameters.
[0042] In addition, for example, the estimation unit uses a Bayesian statistical model that uses the basic information of the component included in the component data of the operating results exceeding the given benchmark and the corresponding machine parameter values as learning data to estimate the basic information of the new component, thereby generating a predicted distribution of the machine parameters that can be applied to the new component, and based on the distribution with the machine parameters that can be applied to the new component as parameters, generates the output of the two or more non-uniform rules, and then calculates the posterior distribution of the machine parameters that can be applied to the new component, and outputs the average of the calculated posterior distribution as the machine parameter output that is applied to the new component among the applicable machine parameters.
[0043] Furthermore, for example, the characteristics of the component data of the operating results exceeding the given benchmark may also be different in the rule base and the machine learning.
[0044] Furthermore, for example, an interface unit may be provided that displays the machine parameters applied to the new component output by the estimation unit and the machine parameters actually used by the component mounting device to perform the component mounting work.
[0045] In addition, these overall or specific methods can be implemented through systems, methods, integrated circuits, computer programs, or recording media such as computer-readable CD-ROMs, or through any combination of systems, methods, integrated circuits, computer programs, and recording media.
[0046] Hereinafter, the embodiments of the present disclosure are described in detail using the accompanying drawings. In addition, the embodiments described below all show a preferred specific example of the present disclosure. The numerical values, shapes, materials, constituent elements, configuration positions of constituent elements, connection methods, steps, order of steps, etc. shown in the following embodiments are examples, and their main purpose is not to limit the present disclosure. In addition, among the constituent elements in the following embodiments, the constituent elements that are not recorded in the independent claims representing the highest concept of the present disclosure are described as arbitrary constituent elements that constitute a more preferred method. In addition, in this specification and the accompanying drawings, for constituent elements that have substantially the same functional structure, repeated descriptions are omitted by marking the same figure marks.
[0047] (Implementation Method)
[0048] First, refer to Figure 1 The structure of the mounting substrate manufacturing system 1 will be described.
[0049] [Installation substrate manufacturing system 1]
[0050] Figure 1 1 is a diagram for explaining the structure of a mounting substrate manufacturing system 1 according to the present embodiment. The mounting substrate manufacturing system 1 has a function of manufacturing a mounting substrate on which components are mounted. Figure 1 In the embodiment, the mounting substrate manufacturing system 1 includes a plurality of (here, two) component mounting lines 12A and 12B.
[0051] [Component installation lines 12A, 12B]
[0052] Component mounting devices 13A1, 13A2, and 13A3 are arranged in the component mounting line 12A, and component mounting devices 13B1, 13B2, and 13B3 are arranged in the component mounting line 12B. That is, the mounting substrate manufacturing system 1 has a structure having at least one component mounting device 13, and the component mounting device 13 performs a component mounting operation of mounting a component on a substrate. The component mounting devices 13A1, 13A2, and 13A3 are connected to each other by a communication network 2a constructed by a local area network or the like. In addition, the component mounting devices 13A1, 13A2, and 13A3 are connected to a client terminal 9A having a component library 5a and an operation information totaling unit 10a via a data communication terminal 11a.
[0053] Similarly, the component mounting devices 13B1 , 13B2 , and 13B3 are connected to each other via the communication network 2 b , and are connected to a client terminal 9B including a component library 5 b and an operation information totaling unit 10 b via a data communication terminal 11 b .
[0054] In the following, when it is not necessary to distinguish between the component mounting lines 12A and 12B, they are simply collectively referred to as the component mounting line 12. Similarly, when it is not necessary to distinguish between the component mounting devices 13A1, 13A2, 12A3 and the component mounting devices 13B1, 13B2, 13B3, they are simply collectively referred to as the component mounting device 13.
[0055] [Client terminals 9A, 9B]
[0056] like Figure 1 As shown, the client terminals 9A and 9B include component libraries 5a and 5b and operation information aggregation units 10a and 10b.
[0057] The client terminals 9A and 9B are connected to the server 3 via a communication network 2 constructed by a local area network or the Internet (public line) or the like.
[0058] In the client terminals 9A and 9B, data required for the production of mounting substrates by the component mounting lines 12A and 12B are downloaded from the server 3 via the communication network 2. That is, the production data of the mounting substrates produced by the component mounting lines 12A and 12B, that is, the production data (not shown) stored in the server 3, are downloaded from the server 3 to the client terminals 9A and 9B via the communication network 2. Here, the production data is data stored in the server 3 and used for mounting substrates produced in the factory including the component mounting lines 12A and 12B. The production data specifies the data required for producing a mounting substrate of one substrate type using the component mounting device 13. For example, in the production data, for each component of the mounting object, the component name of the component mounted on the mounting substrate of the substrate type, the component code for specifying the component through the component library, the mounting position of the component in the mounting substrate, and the mounting angle and mounting angle are specified. Furthermore, in the production data, the conditions on the equipment side used for the production of the mounting substrate, that is, the equipment condition data indicating the setting state in the component mounting device 13, etc. can also be specified for each component name.
[0059] Similarly, among the component data in the component library 5, component data used in the mounting substrates produced by the component mounting lines 12A and 12B, respectively, are downloaded to the component libraries 5a and 5b of the client terminals 9A and 9B.
[0060] In the component installation lines 12A and 12B, during production, component libraries 5a and 5b are used to perform component mounting operations. When an error occurs during the component mounting operation, the user changes the component data of the component libraries 5a and 5b. In addition, the error here is, for example, an error in the adsorption action when the mounting head takes out the component from the component supply unit by vacuum adsorption. In addition, the error here can also be an error when the component recognition camera photographs and recognizes the taken out component, an installation error when the mounting head mounts the taken out component on the substrate, and an error in the defective judgment determined by the inspection process in the subsequent process of the installation line.
[0061] Figure 2 It is a diagram showing an example of the operation information summary data according to the present embodiment.
[0062] The client terminals 9A and 9B include the above-mentioned operation information aggregation units 10a and 10b. The operation information aggregation units 10a and 10b aggregate the results of the processing executed on the component mounting device 13 for each component data together with the operation information.
[0063] More specifically, the operation information totaling units 10a and 10b perform the following processing, namely, totaling the results of the component mounting operations performed by the component mounting lines 12A and 12B for the production of mounting substrates according to the component data, and accumulating them as operation information totaling data. Here, the so-called component mounting operation results are totaling the above-mentioned errors according to the components, and further totaling the number of components mounted on the substrate that are not related to the errors, and on this basis, calculating the error rate and the result as the result. That is, for example, Figure 2 As shown in an example of the operation information summary data of , the performance of the component mounting operation is expressed as "adsorption rate %", "recognition rate %", "installation rate %", "inspection error rate %", etc. Figure 2 The operation information summary data shown includes the performance of the component mounting operation for each component as a result of the processing performed by the component mounting device 13. Figure 2 As shown, in the operation information summary data, multiple conditions of basic information of each component and multiple machine parameters (actual performance) actually applied in the component mounting operation are included as operation information. The multiple conditions of the basic information of the component will be described later, and correspond to the shape, size, etc. specified in the basic information of the component data. The multiple conditions of the basic information of the component correspond to the shape, size, etc. specified in the basic information 15 of the component data 14 described later. The multiple machine parameters (actual performance) correspond to the nozzle setting, adsorption, etc. specified in the machine parameters of the component data described later, and the value of the component data itself or the value updated by the user, etc. is included as the actual performance.
[0064] [Server 3]
[0065] The server 3 has a function of providing various data used in the mounting substrate manufacturing system 1 to the client terminals 9A and 9B. Figure 1 As shown, the server 3 includes a rule library 4, a component library 5, actual performance teaching data 6, and a calculation processing unit 7c. The server 3 is connected to an interface unit 8 via a wire or wireless connection. In addition, the server 3 stores the above-mentioned production data.
[0066] Figure 3 It is an explanatory diagram of the data structure of the component data 14 used in the mounting substrate manufacturing system 1 according to the present embodiment.
[0067] The component library 5 is a component data 14 (see Figure 3 ) is edited into a component library in the form of a master library and is configured on the server 3. The component library 5 is a library storing a plurality of component data 14, and the component data 14 is configured to include at least one machine parameter used by the component mounting device 13 to perform the component mounting operation and basic component information related to the component.
[0068] Here, if Figure 3 As shown, in the component data 14, basic information 15 and machine parameters 16 are defined as major classification items.
[0069] The basic information 15 is information indicating the properties inherent to the component. Figure 3 The shape 15a, the size 15b and the component information 15c are illustrated.
[0070] Shape 15a is information related to the shape of the component. As a sub-classification item of shape 15a, "shape" is specified to indicate the outer shape of the component according to the shape classification such as rectangle and cylinder. As a sub-classification item of size 15b, "outer dimensions" indicating the size of the component, "electrode position" indicating the number or position of electrodes formed for connection on the component, etc. are specified. Component information 15c is attribute information of the component. As a sub-classification item of basic information 15, "component category" indicating the type of the component, "polarity" indicating whether there is directionality in the outer shape of the component, "polarity mark" indicating the shape of the mark marked on the component when there is polarity, "mark position" indicating the position of the mark when there is a polarity mark, etc. are specified.
[0071] The machine parameter 16 is a parameter used by the component mounting device 13 to perform the component mounting operation. More specifically, the machine parameter 16 is a control parameter used to control the component mounting device 13 when the component mounting operation is performed by the component mounting device 13 arranged in the component mounting line 12 with the component specified by the component data 14 as the target. The machine parameter 16 is estimated by the server 3 using a hybrid method described later, which uses both the rule base 4 and the component data whose performance is good as the actual performance.
[0072] exist Figure 3 In FIG. 1 , as the classification items of the machine parameter 16 , nozzle setting 16 a , speed parameter 16 b , recognition 16 c , suction 16 d , and mounting 16 e are exemplified.
[0073] The nozzle setting 16a is data related to the nozzle used when the component is adsorbed and held. As a sub-classification item of the nozzle setting 16a, the "nozzle" for determining the type of nozzle that can be selected is specified. The speed parameter 16b is a control parameter related to the moving speed of the nozzle in the operation of taking out the component by the nozzle and installing it on the substrate. As a sub-classification item of the speed parameter 16b, the "adsorption speed" and "adsorption time" when the component is adsorbed and held, and the "installation speed" and "installation time" when the held component is installed on the substrate are specified.
[0074] Identification 16c is a control parameter related to the execution of the identification process, which uses the component recognition camera to capture and recognize the components taken out from the component supply unit through the suction nozzle. As sub-classification items of identification 16c, "camera type" that determines the type of camera used for imaging, "lighting mode" that indicates the lighting mode used when imaging, and "recognition speed" when recognizing the image obtained by imaging are specified.
[0075] Adsorption 16d is a control parameter related to the adsorption operation when the adsorption nozzle takes out the component from the component supply unit. As sub-classification items of adsorption 16d, "adsorption position X" and "adsorption position Y" indicating the adsorption position when the adsorption nozzle lands on the component are defined.
[0076] Installation 16e is a control parameter related to the installation action, which moves the mounting head that holds the component by suction through the suction nozzle to the substrate and causes the suction nozzle to move up and down to install the component on the substrate. As a sub-category of Installation 16e, the "installation load" is defined as the load that presses the component against the substrate when the suction nozzle is lowered and the component lands on the substrate. Figure 3In the installation 16e, as a sub-classification item, "2nd level action (descending)", "2nd level action offset (descending)", "2nd level action speed (descending)", "2nd level action (ascending)" and the like are further exemplified for regulating the action modes such as switching height position, high and low speed when the speed of the lifting action of lowering and raising the suction nozzle is switched between high and low levels.
[0077] Figure 4 This is a diagram showing an example of a rule base set by a vendor according to the present embodiment. Figure 5 This is a diagram showing an example of a rule base set by a user according to the present embodiment.
[0078] The rule base 4 is a rule base that is retained by the server 3 and used by the server 3 so as to be able to calculate at least one machine parameter. Figure 4 As illustrated, the rule base 4 stores one or more rules each consisting of a condition part and an output.
[0079] Below, use Figure 4 as well as Figure 5 The rule base 4 is described below. The conditional part of the rule is composed of a plurality of conditions of the basic information of the component. The output of the rule is composed of a plurality of machine parameters that are considered to be suitable for the combination of the plurality of conditions of the basic information of the component.
[0080] For example, K1_rul, one of the conditions representing basic information in rule R1, is a condition such as whether the component is larger than a certain size. That is, the multiple conditions of basic information correspond to Figure 3 The basic information 15 of the component data 14 shown in FIG. 14 specifies the shape 15a, size 15b, etc. The plurality of machine parameters correspond to Figure 3 The nozzle setting 16a, the suction 16d, and the like specified in the machine parameters 16 of the component data 14 shown may be values of the component data itself, or may include values updated by the user or the like.
[0081] Thus, in the rule base 4, for example, Figure 4 The rules entered by the supplier as shown may also include, for example, Figure 5 The rules are input by the user as shown. That is, the rules can also be added by the user.
[0082] like Figure 4 As shown, in the rule base 4, the rules R1, R2, and R3 input by the supplier are set to be able to output machine parameters for the basic information of all parts. More specifically, when the supplier inputs the rules, a combination of conditions of the basic information is set so as to cover the basic information of all parts, and all machine parameters are set in the combination of conditions of all the basic information.
[0083] On the other hand, Figure 5 As shown in FIG. 1 , in the rule base 4, the rule R4 added by the user may also be a simple rule consisting of only a part of the condition part of the basic information and a part of the machine parameters of the output. Figure 4 As shown by "NaN" in the , when the user adds rules, there may be parts with unset condition parts. This "NaN" means that the shape does not matter as long as the conditions of other condition parts such as the shape are met. In other words, if the component data meets the conditions of the set other condition parts, rule R4 is applied.
[0084] In addition, users can Figure 1 The interface unit 8 shown in FIG. 1 inputs rules into the rule base 4. That is, the interface unit 8 has the function of an input unit used when the user inputs rules into the rule base 4. In addition, the interface unit 8 may also have the function of a display unit for displaying the rules included in the rule base 4 or input by the user. Furthermore, the interface unit 8 may also display the machine parameters output by the calculation processing unit 7 for application to the new component and the machine parameters actually used by the component mounting device 13 to perform the component mounting operation. In addition, as a function of the display unit, it may also be set to display only the rules added by the user.
[0085] Figure 6 This is a diagram showing an example of the actual performance teaching data 6 according to the present embodiment.
[0086] Regarding server 3, as described above, Figure 1 As shown, a calculation processing unit 7 is provided. The calculation processing unit 7 is an example of an estimation unit, for example, and selects component data of operation results exceeding a predetermined reference from the operation information aggregation units 10a and 10b as actual performance teaching data.
[0087] In the present embodiment, the calculation processing unit 7 of the server 3 selects component data of operation results exceeding a given benchmark from the operation information aggregation units 10a and 10b of the client terminals 9A and 9B as actual performance teaching data 6. Here, the so-called given benchmark is, for example, a 90% performance. Therefore, the component data of operation results exceeding the given benchmark will also be referred to as component data with excellent performance below. More specifically, the server 3 downloads (acquires) basic information of components for component data with excellent performance from the operation information aggregation data from the client terminals 9A and 9B, as well as machine parameters (actual performance) that are machine parameters actually applied (used) in the component mounting operation. In addition, Figure 6 , an example is shown in which component data with a score exceeding 90% is regarded as component data with excellent scores. Figure 6 middle, Figure 2Among the components P1 to P6 shown, basic information and machine parameters (actual performance) for the components P1 to P3 and P6 are accumulated as actual performance teaching data 6 .
[0088] Furthermore, if Figure 6 As shown, the server 3 adds the rule base output value for the basic information of each component to the basic information and machine parameters (actual performance) of the component data with good performance obtained above, and accumulates them as actual performance teaching data. In addition, the rule base output value is the machine parameters for the basic information of each component obtained by referring to the rule base 4. Figure 6 , shown as machine parameters (rule base output).
[0089] Furthermore, the calculation processing unit 7 (estimation unit) of the server 3 estimates at least one machine parameter of the new component using the actual performance teaching data 6, the rule base 4, and the basic information of the new component. In the present embodiment, when the basic information of the new component is input, the calculation processing unit 7 of the server 3 first registers the basic information in the component library 5, and then obtains the rule base output for the new component by referring to the rule base 4. Then, using both the rule base output and the actual performance teaching data 6, the appropriate machine parameter is estimated and output.
[0090] In addition, in the calculation processing unit 7, in order to estimate the appropriate machine parameters, operation processing based on Bayesian estimation is performed. More specifically, the calculation processing unit 7 estimates the basic information of the new component using a Gaussian process regression model (Gaussian process regressor), and the Gaussian process regression model uses the basic information of the component included in the component data of the operating results exceeding a given benchmark and the corresponding machine parameter values as learning data. As a result, the calculation processing unit 7 generates a predicted distribution of machine parameters that can be applied to the new component. Here, the rule base output is generated by a normal distribution with the machine parameters that can be applied to the new component as the average. Therefore, the calculation processing unit 7 calculates the posterior distribution of the machine parameters that can be applied to the new component, and outputs the average of the calculated posterior distribution as the machine parameters that can be applied to the new component among the applicable machine parameters.
[0091] The calculation processing unit 7 of the server 3 registers the outputted appropriate machine parameters in the component library 5. Then, the component data is downloaded by, for example, the component library 5a of the component mounting line using the component, so that the component mounting device 13 can use the component data in production.
[0092] [Operation of Mounting Board Manufacturing System 1]
[0093] Next, the operation of the mounting substrate manufacturing system 1 configured as above will be described.
[0094] Figure 7 This is a flowchart showing the operation of the mounting substrate manufacturing system 1 in the present embodiment until the production of a new component starts.
[0095] First, it is assumed that basic information of a new component is input to the server 3 by a user or the like (S11). Then, the server 3 registers (sets) the basic information of the new component in the component library 5 (S12).
[0096] Next, the server 3 uses the basic information of the new component and refers to the rule base 4 ( S13 ) to obtain the rule base output for the new component.
[0097] Next, the server 3 estimates and outputs appropriate machine parameters for the new component (S14) using the basic information of the new component, the rule base output, and the actual performance teaching data 6. In this way, the server 3 estimates appropriate machine parameters for the new component by using a hybrid method of the rule base output and the actual performance teaching data 6.
[0098] Next, the server 3 registers the appropriate machine parameter output in step S14 at a position corresponding to the basic information of the new component in the component library 5 ( S15 ).
[0099] Next, for example, the client terminal 9A downloads the component data of the new component from the component library of the server 3 to the component library 5a of the component mounting line 12A that uses the new component (S16).
[0100] Then, the component mounting line 12A starts production of the new component using the component data of the new component (S17).
[0101] [Effects, etc.]
[0102] As described above, according to the mounting substrate manufacturing system 1 of the present disclosure, it is possible to estimate appropriate machine parameters for new components without generating work hours for confirming results. In addition, the mounting substrate manufacturing system 1 of the present disclosure estimates appropriate machine parameters by using a hybrid method of the rules included in the rule base 4 and the model learned using the actual results teaching data 6. Thus, it is possible to achieve the effect of estimating machine parameters that cannot be covered by only the rules using the model using the actual results teaching data, and to use the rules to estimate machine parameters that cannot be covered by only the model using the actual results teaching data. Therefore, the mounting substrate manufacturing system 1 of the present disclosure can estimate appropriate machine parameters that are commensurate with the experience of suppliers and skilled users before the component mounting operation without generating work hours for confirming results for new components. Thus, even when using a new component with no actual production results, it is not necessary to spend temporary component mounting operation implementation time each time the component is changed, thereby suppressing the decline in production efficiency.
[0103] (Example 1)
[0104] In the first embodiment, a specific method of the calculation processing based on the Bayesian estimation performed by the calculation processing unit 7 of the server is described. In this embodiment, the calculation processing unit 7 estimates the appropriate machine parameters using the statistical model. In addition, the following is set to represent a vector or a matrix. In addition, the following description is made on the estimation method of one machine parameter MP1, but the same processing is performed on all machine parameters.
[0105] Figure 8 This is a diagram showing an example of a graphical model of a statistical model according to Example 1 of the embodiment.
[0106] exist Figure 8 , the basic information of the new component is set to X_new_vec (bold), the name of the rule applied to the new component is set to rule 1, and its output (rule base output) is set to Y_new_rule. In addition, the appropriate machine parameter MP1 of the new component estimated by the calculation processing unit 7 is set to Y_new_true. In addition, the basic information of the n components of the actual performance teaching data is set to X_train_mat (bold), and the machine parameter MP1 of the actual performance teaching data is set to Y_train_true_vec (bold).
[0107] Here, X_new_vec (bold), X_train_mat (bold), and Y_train_true_vec (bold) can be expressed as follows.
[0108]
Mathematical formula 1
[0109] X_new_vec=[X_test1 ... X_test m ]
[0110]
Mathematical formula 2
[0111]
[0112]
Mathematical formula 3
[0113]
[0114] Each element of X_new_vec (bold) indicates basic information of a new component, each element of X_train_mat (bold) indicates basic information of multiple components of actual performance teaching data, and each element of Y_train_true_vec (bold) indicates actual performance parameters of n components of actual performance teaching data. m in each of these elements indicates the number of types of component information.
[0115] First, we use X_train_mat (in bold) as input and Y_train_true_vec (in bold) as output to learn the Gaussian process regression model.
[0116] After learning the regression model, it is considered that when X_new_vec (in bold) is input to the Gaussian process regression model, the output of the Gaussian process regression model is the prediction distribution of Y_new_true. It is known that the prediction distribution of the Gaussian process regression model is a normal distribution, and its mean and variance can be analytically calculated.
[0117] The prediction distribution of Y_new_true is expressed as the following (Formula 1). In (Formula 1), the mean of the prediction distribution is Y_new_true_gaussian, and the variance is σ_gaussian_r 2 . Further, as shown in the following (Formula 2), it is assumed that Y_new_true is taken as the average and σ_r_1 is taken as the average. 2 is a normal distribution with a variance of , and Y_new_rule_1 is generated as the output of the rule base for the new component.
[0118] Y_new_true~N(Y_new_true_gaussian, σ_gaussian_r 2 ) (Formula 1)
[0119] Y_new_rule_1~N(Y_new_true,σ_r_1 2 ) (Formula 2)
[0120] Here, the standard deviation σ_r is the average of all elements of Y_train_true_vec_rule_1 (bold) shown below, which is obtained by subtracting Y_new_rule1 from all elements of Y_train_true_vec (bold), converted into absolute values, or twice the average.
[0121]
Mathematical formula 4
[0122]
[0123] Furthermore, when the accuracy of Rule 1 applied to the new component is low, the standard deviation σ_r automatically increases, and an effect is obtained in which Rule 1 is not given importance in the estimation performed by the calculation processing unit 7 in this embodiment.
[0124] When obtaining the posterior distribution of Y_new_true, the prior distribution of Y_new_true is set to a normal distribution in (Formula 1), and is set to a normal distribution with Y_new_true as the average in (Formula 2). Therefore, a conjugate prior distribution can be set for Y_new_true.
[0125] According to the above, in (Formula 1) and (Formula 2), when the values other than Y_new_true are known, the posterior distribution of Y_new_true becomes a normal distribution, and the mean and variance of the posterior distribution can be calculated analytically. Therefore, the calculation processing unit 7 can calculate the mean of the posterior distribution of Y_new_true and output the mean of the posterior distribution of Y_new_true as the appropriate machine parameters of the new component to be estimated.
[0126] In addition, regarding the hyperparameters of the Gaussian process regression model for the output of (Formula 1), for example, when learning is performed using the basic information of multiple components of the actual performance teaching data as X_train_mat (bold) and Y_train_true_vec (bold) of the machine parameter MP1 representing the actual performance teaching data as teaching data, the prior distribution can be set in advance and Bayesian estimation can be performed, and the second optimal estimation can also be performed.
[0127] In addition, the method of outputting the predicted distribution of (Formula 1) is not limited to the case of using a Gaussian process regression model. For example, any model that can output the predicted distribution of Y_new_true, such as a Bayesian deep neural network or a Bayesian statistical model, will suffice.
[0128] In addition, in the distribution with Y_new_true in (Formula 2) as the average, it is not limited to the normal distribution, as long as it is a distribution with Y_new_true as a parameter (parameter). In other words, it can be a distribution with machine parameters that can be applied to the new component of the estimation object as parameters. In addition, at this time, when the posterior distribution of Y_new_true cannot be calculated analytically, Y_new_true that maximizes the posterior probability can be obtained and output as an appropriate machine parameter. Alternatively, it is also possible to sample from the posterior distribution using the Markov Chain Monte Carlo method and output the average of the obtained sampled values as an appropriate machine parameter.
[0129] (Example 2)
[0130] The rule base 4 of the server 3 may include two or more rules that are not the same as the plurality of rules for the new component used to calculate at least one machine parameter. In this case, a specific form of the calculation processing based on the Bayesian estimation performed by the calculation processing unit 7 of the server will be described as Example 2. In addition, the following description will focus on the differences from Example 1.
[0131] Fig. 9 This is a diagram showing an example of a graphical model of a statistical model according to Example 2 of the implementation method.
[0132] Sometimes, two rules for different rule base outputs are present in rule base 4 for a new part to be estimated. In this case, the names of these two rules are rule 2 and rule 3, such as Fig. 9 As shown, the output (rule base output) is set to Y_new_rule_2 and Y_new_rule_3.
[0133] In addition, as shown in the following (Formula 3), for Y_new_rule_2, it is assumed that Y_new_true in (Formula 3) is the average and σ_r_2 2 is a normal distribution with a variance. In addition, as shown in the following (Formula 4), for Y_new_rule_3, it is assumed that Y_new_true in (Formula 4) is the average and σ_r_3 2 is a normal distribution with a variance of . In addition, it is shown that the mean of the predicted distribution is Y_new_true_gaussian and the variance is σ_gaussian_r 2 It is assumed that Y_new_true is generated according to the normal distribution of (Formula 1) above.
[0134] Y_new_rule_2~N(Y_new_true,σ_r_2 2 ) (Formula 3)
[0135] Y_new_rule_3~N(Y_new_true,σ_r_3 2 ) (Formula 4)
[0136] In such a case, first, a normal distribution of the posterior distribution of Y_new_true represented by (Formula 5) can be analytically calculated based on (Formula 1) and (Formula 3) taking into account the influence of the actual performance teaching data and Rule 2.
[0137] Y_new_true~N(Y_new_true_gaussian_and_rule1,σ_gaussian_and_rule 1 2 )(Formula 5)
[0138] Next, the normal distribution that becomes the posterior distribution of Y_new_true in consideration of the influence of the actual performance teaching data and Rule 3 can be analytically calculated based on (Formula 4) and (Formula 5).
[0139] According to the above, by performing calculations as described above, statistics can be obtained that allow for the existence of multiple rules that do not have unified rule base outputs. Thus, even if there are two rules in the rule base 4 that have different rule base outputs for a new part to be estimated, the calculation processing unit 7 can calculate appropriate machine parameters. Thus, the user can easily set new rules in the rule base 4 without considering the unification with the rules set by the supplier.
[0140] Furthermore, the above calculation may be performed using a plurality of rules with smaller σ_r or only a single rule.
[0141] (Example 3)
[0142] In Example 2, when there are more than two inconsistent rules in the rule base 4, a method of recursively updating the statistical model by using each of the more than two inconsistent rules so that the statistical model reflects the more than two rules is described, but the method is not limited to this. In the rule base 4, when there are more than two inconsistent rules, the user can also adjust the weights when the statistical model reflects the rules. This case is described below as Example 3. In addition, in Example 3, the description focuses on the differences from Examples 1 and 2.
[0143] Fig.10 This is a diagram for explaining adjustment of weights of a plurality of rules included in the rule base 4 according to Example 3 of the embodiment.
[0144] exist Fig.10 In the example, the standard deviation of the learned statistical model is shown in the plurality of rules included in the rule base 4 through the interface unit 8. Fig.10 As shown, the interface unit 8 may also display the standard deviation σ_r of each rule together with the conditional part and output of the rule in the rule base 4 .
[0145] Here, for example, when the user wants to emphasize a specific rule, the standard deviation σ_r of the rule can be changed (set) to a smaller value in the interface unit 8. In this way, the statistical model can be updated to emphasize the rule set based on the experience of experienced users, so that the calculation processing unit 7 estimates more appropriate machine parameters for new parts.
[0146] In addition, Fig.10In FIG. 1 , an example is shown in which a specific skilled user U2 sets a new rule R7 when rule R5 is set. Fig.10 , user-dependent rules are shown.
[0147] Here, for example, the standard deviation σ_r may be set to be the same in several rules. In this case, for example, σ_r_S_7 of the adsorption speed of rule R7 is calculated as the average of the absolute values of the difference between the actual performance adsorption speed in the actual performance teaching data and the output of rule R5 and the difference between the actual performance adsorption speed and the output of rule R7 or twice thereof.
[0148] In addition, the user can also use the interface unit 8 to, before the calculation processing unit 7 performs the calculation processing, Fig.10 As shown in the example, a plurality of rules are registered in the rule base 4. Then, the interface unit 8 displays the standard deviation σ_r of each parameter of each rule. Then, in this case, the user can also set ON (open) or OFF (close) through the interface unit 8 after confirming the standard deviation σ_r of the rule. The rule set to OFF is not used in the above-mentioned calculation processing performed by the calculation processing unit 7. On the other hand, the rule set to ON is used in the above-mentioned calculation processing performed by the calculation processing unit 7.
[0149] (Example 4)
[0150] In the first and second embodiments, a normal distribution of the rule base output is generated only for the appropriate machine parameters of the new parts. However, in the method assuming a normal distribution, when the appropriate machine parameters have a property of not having a unique value but having a range, inappropriate estimation may be performed. Therefore, a Gaussian process regression model A, which is a Gaussian process regression model guided by a rule, may be used instead of the Gaussian process regression model. By replacing the Gaussian process regression model A with the Gaussian process of the first and second embodiments, the appropriate machine parameters can be calculated.
[0151] This case will be described below as Embodiment 4. In Embodiment 4, the description will also focus on the differences from Embodiments 1 and 2.
[0152] Fig.11 This is a diagram showing an example of a graphical model of a Gaussian process model. Fig.12 is a diagram showing an example of a graphical model of a statistical model involved in Example 4 of the implementation method. Figure 8 The same contents are marked with the same names and detailed descriptions are omitted.
[0153] The following is an explanation of the Gaussian process regression model A. First, assume that Y_train_true_vec (bold) is generated according to the Gaussian process regression model shown in (Equation 6) and (Equation 7). In (Equation 6) and (Equation 7), Y_train_f_vec (bold) is a probability variable, and Y_train_f_gaussian (bold), σ_train_f_mat (bold), and σ_gaussian are equivalent to the parameters learned by the Gaussian process regression model. So far, it is a general Gaussian process regression model. The graphical model of this Gaussian process model is as follows Fig.11 shown.
[0154] Furthermore, it is assumed that each element of Y_train_rule_vec (bold) is generated according to a normal distribution centered on each element of train_f_vec (bold). This example is shown in (Equation 8). In (Equation 8), Y_train_rule_vec (bold) is a vector of outputs of rules corresponding to each component of the actual performance teaching data. σ_r_[i] is the standard deviation of the rule. Such a graphical model of the model involved in this embodiment is as follows Fig.12 shown.
[0155]
Mathematical formula 5
[0156] Y_train_f_vec~N(Y_train_f_gaussian, σ_train_f_mat) (Formula 6)
[0157]
Mathematical formula 6
[0158] Y_train_true_vec~N(Y_train_f_vec, o_gaussian) (Formula 7)
[0159]
Mathematical formula 7
[0160] Y_train_rule_vec[n]~N(train_f_vec[n], σ_r_[i]) (Formula 8)
[0161] Here, Y_train_true_vec (bold words) and Y_train_rule_vec (bold words) can be set as known to calculate Y_train_f_gaussian (bold words), σ_train_f_mat (bold words), and σ_gaussian for learning. In addition, for σ_r_[i], the inverse gamma distribution can be set as the prior distribution to perform learning. Then, the Gaussian process regression model A obtained by the learning result is replaced with the Gaussian process of Example 1 and Example 2. In this way, even if it is set to have the property of having an amplitude, the appropriate machine parameters can be calculated.
[0162] Fig.13 This is a diagram showing an example of another graphical model of the statistical model involved in Example 4 of the implementation method.
[0163] In addition, in the Gaussian process regression model A, a deep Gaussian process regression in which the Gaussian process regression is multilayered may be used instead of the Gaussian process regression model. The graphical model in this case is shown in Fig.13 .exist Fig.13 In , the number of hidden layers is set to 2 and the number of units is set to 3, but the present invention is not limited thereto. In this way, by multi-layering the Gaussian process regression, a more complex relationship between component information and appropriate parameters can be learned.
[0164] (Example 5)
[0165] In the embodiment and Examples 1 to 4, the machine parameters are described as quantitative variables, but the invention is not limited to this. It is also possible to consider a case where one or more machine parameters among a plurality of machine parameters are qualitative variables such as turning on or off a function of a certain device. In this case, a specific form of the calculation processing performed by the calculation processing unit 7 of the server will be described as Example 5. In addition, in Example 5, the description will be centered on the differences from Examples 1 to 4.
[0166] Fig.14 is a diagram showing an example of a graphical model of a statistical model according to Example 5 of the embodiment. Figure 8 The same contents are marked with the same names and detailed descriptions are omitted.
[0167] When the machine parameters are qualitative variables, the Gaussian process regressor is not used, but the Gaussian process classifier corresponding to the qualitative variables is used to learn the statistical model.
[0168] Hereinafter, the calculation processing unit 7 refers to the machine parameter of the qualitative variable set as the estimation object as MP2, and assumes that MP2 has an on (ON) and off (OFF) setting. In addition, the processing is performed by setting the case where MP2 is on (ON) to 1 and the case where MP2 is off (OFF) to 0.
[0169] When the Gaussian process classifier is applied, the latent variable vector F_train_true_vec (bold) is introduced, and the latent variable vector F_train_true_vec (bold) corresponds to the machine parameter MP2, Y_train_true_vec (bold), which is the qualitative variable of the actual performance teaching data. The elements of Y_train_true_vec (bold) and F_train_true_vec (bold) are as follows.
[0170]
Mathematical formula 8
[0171]
[0172]
Mathematical formula 9
[0173]
[0174] In addition, the relationship between the elements of Y_train_true_vec (bold characters) and F_train_true_vec (bold characters) is shown in the following (Formula 9).
[0175] Y_train_true=σ(F_train_true) (Formula 9)
[0176] In (Formula 9), function σ(z) is a function that converts a continuous value into a variable between 0 and 1. Function σ(z) may be, for example, a logical function as shown below.
[0177]
Mathematical formula 10
[0178]
[0179] like Fig.14As shown in the figure, in the Gaussian process classifier, if X_train_mat (bold) and Y_train_true_vec (bold) are given, the statistical model is trained so that F_train_true_vec (bold) can be output based on X_train (bold), and F_train_true_vec (bold) outputs a value as close to Y_train_true_vec (bold) as possible. In addition, unlike the Gaussian process regressor, this learning is difficult to perform analytically due to the influence of the function σ(z), so a method of learning using Laplace approximation is proposed.
[0180] Therefore, the statistical model is learned using the Laplace approximation. Therefore, it is known that after the statistical model is learned using the Laplace approximation, when X_new is input, the normal distribution shown in (Formula 10) is output as the predicted distribution of F_new_true.
[0181] F_new_true~N(F_new_gaussian, F_σ_gaussian 2 ) (Formula 10)
[0182] In the normal distribution shown in (Equation 10), the mean is F_new_gaussian and the variance is F_σ_gaussian 2 .
[0183] Here, F_new_true becomes a latent variable of the new component to be estimated. Therefore, in the Gaussian process classifier, it is estimated that when F_new_true is input to the function σ(z) and its output exceeds 0.5, the machine parameter is turned on.
[0184] In this embodiment, the known Gaussian process classifier and rule base output are combined by the method described below. That is, first, the Gaussian process classifier learned by the above method is used to predict X_train_mat (bold words), and the following F_train_true_pred_vec (bold words) is produced with the average of the output latent variables as each element.
[0185]
Mathematical formula 11
[0186]
[0187] Next, based on F_train_true_pred_vec (bold), all latent variables corresponding to components whose elements are 1 are extracted from Y_train_true_vec (bold) shown below, and the average value thereof is taken as F_rule1_mean.
[0188]
Mathematical formula 12
[0189]
[0190] Furthermore, from F_train_true_pred_vec (bold), all latent variables corresponding to components whose elements are 0 are extracted from Y_train_true_vec (bold) shown below, and the average value thereof is taken as F_rule0_mean.
[0191]
Mathematical formula 13
[0192]
[0193] Here, if the machine parameter MP2 is turned on (ON), the rule output (rule base output) is set as R8.
[0194] At this time, set the variance of R8 to F_rule1_dif 2 . F_rule1_dif 2 It is the average of all the elements of F_rule1_dif shown below, which is obtained by subtracting F_rule1_mean from all the elements of F_train_true_pred_vec (bold), converted into absolute values, or doubled.
[0195]
Mathematical formula 14
[0196]
[0197] Next, as expressed by the following (Equation 11), it is assumed that F_new_true is the average and F_rule1_dif 2 Generate F_rule1_mean using a normal distribution with variance.
[0198] F_rule1_mean~N(F_new_true,F_rurel_dif 2 ) (Formula 11)
[0199] As described above, according to (Formula 10) and (Formula 11), when all factors except F_new_true are known, the posterior distribution of F_new_true becomes a normal distribution, and its mean and variance can be calculated analytically.
[0200] Here, the output when the average of the posterior distribution of F_new_true is input to the function σ(z) is set to Y_new_true_probability. If Y_new_true_probability is greater than 0.5, Y_new_true=1 is set, and the appropriate machine parameters are output as ON. On the other hand, if Y_new_true_probability is less than 0.5, Y_new_true=0 is set, and the appropriate machine parameters are output as OFF.
[0201] In this way, the calculation processing unit 7 calculates the average of the posterior distribution of F_new_true as Y_new_true_probability, and can output appropriate machine parameters of the new component to be estimated even if the machine parameters are qualitative variables.
[0202] In addition, in the above description, the machine parameter is assumed to be a qualitative variable consisting of two levels (two options), but it is not limited to this. It is also possible that the machine parameter is a qualitative variable and has multiple levels. In this case, as long as the above method is performed for each level through one-versus-rest, and the posterior distribution of F_new_true is set to q(F_new_true), the following (Formula 12) can be calculated at each level.
[0203]
Mathematical formula 15
[0204] Y_new_true_probability_map=∫σ(F_new_true)q(F_new_true)dF_new_true (Formula 12)
[0205] When the function σ(z) is a logical function, it is difficult to perform integral calculation. In this case, a limited number of L sample values may be sampled from q(F_new_true), each sample value may be substituted into the function σ(z), and the average value thereof may be calculated as Y_new_true_probability_map. Then, the maximum level of Y_new_true_probability_map may be output as an appropriate machine parameter.
[0206] (Example 6)
[0207] In addition, similarly to the case where the machine parameters are quantitative, a Gaussian process classifier guided by a rule may be used instead of the Gaussian process classifier, or a Gaussian process classifier A may be used.
[0208] This case will be described below as Embodiment 4. In Embodiment 4, the description will also focus on the differences from Embodiments 1 and 2.
[0209] Fig.15 is a diagram showing an example of a graphical model of a statistical model involved in Example 6 of the implementation method. Figure 8 The same contents are marked with the same names and detailed descriptions are omitted.
[0210] Hereinafter, the Gaussian process classifier A will be described. First, it is assumed that Y_train_true_vec (bold letters) is generated by the Gaussian process classifier shown in (Formula 13).
[0211] Furthermore, it is assumed that the elements of Y_train_real_true_vec (bold) are generated according to a Bernoulli distribution with the elements of Y_train_true_vec (bold) as parameters. This example is shown in (Formula 14). In addition, using the error rate σ_rule[i] of the rule, information about whether the rule is wrong is generated through Bernoulli distribution and output as miss_rule[i]. In the prior distribution of the error rate of the rule, the Beta distribution is set. This example is shown in (Formula 15). Furthermore, based on the noise σ_gauss, miss_gauss is generated according to the Bernoulli distribution. This example is shown in (Formula 16). Furthermore, Y_train_true_vec (bold) and Y_train_rule_vec (bold) are calculated according to (Formula 17) and (Formula 18). A graphical model of such a model is shown as follows. Fig.15 shown.
[0212]
Mathematical formula 16
[0213] Y_train_true_vec~N(Y_train_c_gaussian, σ_train_c_mat) (Equation 13)
[0214]
Mathematical formula 17
[0215] Y_train_real_true_vec[m]~B(Y_train_true_vec[m]) (Equation 14)
[0216] miss_rule[i]~B(σ_rule[i]) (Equation 15)
[0217] miss_gauss~B(σ_gauss) (Formula 16)
[0218]
Mathematical formula 18
[0219] Y_train_true_vec[n]=|Y_train_real_true_vec[m]-miss_gauss| (Formula 17)
[0220]
Mathematical formula 19
[0221] Y_train_rule_vet[n]=|Y_train_real_true_vec[m]-miss_rule[i]| (Formula 18)
[0222] Here, Y_train_true_vec (bold) and Y_train_rule_vec (bold) are known, and Y_train_c_gaussian (bold) and σ_train_c_mat (bold) are calculated to learn the Gaussian process learning classifier. The Gaussian process learning classifier learned in this way can also be used as Gaussian process learning classifierA, replacing the Gaussian process learning classifier in Example 5.
[0223] The above describes the mounting substrate manufacturing system involved in the embodiments etc. of one or more methods, but the present disclosure is not limited to the embodiments etc. As long as it does not depart from the main purpose of the present disclosure, the methods obtained by applying various modifications to the embodiments that can be thought of by those skilled in the art, and the methods constructed by combining the constituent elements in different embodiments can also be included in the scope of one or more methods.
[0224] For example, in the hybrid method described in the embodiment, the basic information of the components used in the rule base 4 and the component information used in the machine learning model may be different. In this case, the user can create a simple rule using only part of the component information.
[0225] Furthermore, for example, the interface unit 8 may display the device parameters estimated by the hybrid method described in the embodiment using a bubble graph.
[0226] Fig.16 is a bubble chart showing machine parameters estimated by the hybrid method involved in the present disclosure. Fig.17 If you have selected more than one Fig.16 The bubbles shown are information about the components. Fig.18 It is a summary diagram showing the machine parameters estimated by the hybrid method involved in the present disclosure.
[0227] That is, among the machine parameters, the machine parameters of the actual performance teaching data and the machine parameters estimated by the hybrid method for each component can also be used. Fig.16 The bubble diagram shown in Figure 2 shows the Fig.16 In , the size of the circle corresponds to the number of components. In addition, Fig.17 As shown, it is also possible to set the user to be able to select more than one Fig.16 Click the bubble to view the component information. Fig.16 In the example, components on the diagonal line are considered to be components for which the estimation based on the hybrid method has been successful, and components that are greatly deviated from the diagonal line are considered to be components for which the estimation has failed.
[0228] By using such a bubble chart, the user can select a component that failed in estimation, browse the component information, and obtain information for creating a new rule. In addition, the user can efficiently find a component whose actual performance machine parameters may be inappropriate.
[0229] In addition, if Fig.18 As shown, in the case where the machine parameter is not a continuous value but a qualitative variable, a summary diagram can also be shown.
[0230] Industrial Applicability
[0231] The present disclosure can be utilized in a mounting substrate manufacturing system that manufactures mounting substrates, and in particular, can be utilized in a mounting substrate manufacturing system that configures a server or the like that can estimate appropriate machine parameters for a new component.
[0232] Explanation of symbols
[0233] 1 Installing the substrate manufacturing system
[0234] 2.2a, 2b Communication Network
[0235] 3 Server
[0236] 4 Rule Base
[0237] 5.5a,5b Component Library
[0238] 6 Actual performance teaching data
[0239] 7. Computational Processing Unit
[0240] 8 Interface
[0241] 9A, 9B Client Terminal
[0242] 10a, 10b Operation information summary
[0243] 11a, 11b Data communication terminal
[0244] 12, 12A, 12B component installation line
[0245] 13, 13A1, 13A2, 13A3, 13B1, 13B2, 13B3 Component mounting device
[0246] 14 Component data
[0247] 15 Basic Information
[0248] 15a Shape
[0249] 15b Size
[0250] 15c Parts Information
[0251] 16 Machine parameters
[0252] 16a Nozzle Setting
[0253] 16b Speed parameter
[0254] 16c Identification
[0255] 16d Adsorption
[0256] 16e installation.
Claims
1. A mounting substrate manufacturing system for manufacturing a mounting substrate having components mounted on the substrate, the mounting substrate manufacturing system comprising: at least one component mounting device for performing a component mounting operation of mounting the component on a substrate; a rule base capable of calculating at least one machine parameter for the component mounting device to perform the component mounting operation; an operation information aggregation unit that aggregates the results of the processing executed by the component mounting device together with the operation information for each component data; and an estimating unit, selecting component data of operation results exceeding a given benchmark from the operation information totaling unit as actual performance teaching data, and estimating at least one machine parameter of the new component using the actual performance teaching data, the rule base, and basic information of the new component, The rule base includes two or more non-uniform rules that output different basic information of the new component to be estimated in order to calculate at least one machine parameter of the new component.
2. The mounting substrate manufacturing system according to claim 1, wherein: The estimation unit uses a Bayesian statistical model to estimate basic information of the new component, thereby generating a predicted distribution of machine parameters that can be applied to the new component, generating an output of the rule base based on a distribution with the machine parameters that can be applied to the new component as parameters, and then calculating the posterior distribution of the machine parameters that can be applied to the new component, and outputting the average of the calculated posterior distribution as the machine parameter output that is applied to the new component among the applicable machine parameters.
3. The mounting substrate manufacturing system according to claim 1, wherein: The estimation unit estimates the basic information of the new component using a Bayesian statistical model that uses the basic information of the component included in the component data of the operating results exceeding the given benchmark and the corresponding machine parameter values as learning data, thereby generating a predicted distribution of the machine parameters that can be applied to the new component, generating the output of the two or more non-uniform rules based on the distribution with the machine parameters that can be applied to the new component as parameters, and then calculating the posterior distribution of the machine parameters that can be applied to the new component, and outputting the average of the calculated posterior distribution as the machine parameter output that is applied to the new component among the applicable machine parameters.
4. The mounting substrate manufacturing system according to any one of claims 1 to 3, wherein: The characteristics of the component data of the operating results exceeding the given benchmark are different in the rule base and the machine learning.
5. The mounting substrate manufacturing system according to any one of claims 1 to 3, wherein: The mounting substrate manufacturing system includes an interface unit that displays the machine parameters applied to the new component output by the estimation unit and the machine parameters actually used by the component mounting device to perform the component mounting work.