Ore discharge and crushing system next to the unloading station underground
By designing a crushing chamber and a reasonable arrangement of mine warehouses in an underground mine, and using a bottom-unloading mine truck to carry it, the low mining efficiency problems caused by poor ore flowability and small height difference in traditional systems are solved, and high efficiency is achieved ore crushing and improving capabilities.
Patent Information
- Application Number
- CN202111448976.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-12-01
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2041-12-01
AI Technical Summary
The traditional underground ore crushing system has a small height difference from the unloading position to the vertical shaft lifting and loading position and poor ore liquidity, resulting in low mining efficiency, and serious natural accumulation of ore and cart sticking in the ore warehouse, which reduces production efficiency.
Design an ore slitting and crushing system adjacent to the unloading station underground, including crushing chambers, original ore warehouses, unloading stations, powder ore warehouses, metrology chambers and bottom unloading mine trucks. By siding the crushing chambers in a lateral direction, use limited The unloading stations and mine warehouses are arranged reasonably in the height difference space, and the bottom-unloading mine truck is used to carry them, and the inclination angle of the mine warehouse is increased to improve the ore liquidity.
It effectively solves the problems of natural accumulation and sticking of ore, improves the efficiency and improvement of ore crushing capacity, improves mining efficiency, maximizes the capacity and processing capacity of the ore silo, and solves the problem of ore crushing with small height difference.
Smart Images

Figure CN114109485B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of mining of metal and non-metallic ores, and in particular to an underground ore discharge and crushing system adjacent to an unloading station, which is suitable for mining an ore body with a small height difference between the middle section of unloading and the middle section of loading and poor ore fluidity. Background Art
[0002] The layout of the underground ore crushing system in the existing technology is mainly to solve the relationship between the main shaft, crusher chamber, upper and lower ore bins (chute), unloading chamber, beltway, metering chamber and other projects; this relationship is determined by two directions: one is the relative position relationship of each single project in the underground crushing system in the horizontal direction; the other is the relative position relationship of each single project in the vertical direction.
[0003] The traditional ore discharge and crushing process is to arrange a vibrating ore discharger at the bottom of the ore bin, and use a side-unloading mine car to discharge the ore sideways into the ore bin located above the crusher. The ore is placed into the crusher through the ore discharger, and the crushed ore enters the lower ore bin, and then is loaded into the skip bucket through the loading belt for lifting (see attached Figure 5-6 ), the long axis of the ore bin in this arrangement is in the same vertical plane as the center line of the crusher (i.e., the horizontal projections of the two coincide), and is parallel to the long axis of the ore unloading. For the small height difference between the unloading position in the middle of the transportation and the loading position of the shaft, the ore fluidity is poor, and the natural repose angle of the ore is smaller than the ore body, this structural setting has the defect of low mining efficiency. The specific reasons are as follows:
[0004] (1) Since the unloading height in the middle of the transportation section and the loading height of the skip are fixed and cannot be adjusted, the length of the unloading bin is short and the bottom angle of the bin is gentle. The bottom angle of the bin is usually only about 35 degrees. Due to the high viscosity of the ore, the ore with an angle less than 60 degrees in the bin hardly flows and naturally accumulates on one side of the bin, which greatly reduces the effective volume and effective opening in the bin, thereby reducing production efficiency. The unloading and crushing capacity is only 450,000 t / a.
[0005] (2) The long axis of the ore bin and the center line of the crusher are in the same vertical plane (the horizontal projections of the two coincide), and the inclination angle of the ore bin close to the crushing chamber is about 80 degrees, which limits the volume of the ore bin;
[0006] In addition, due to the high viscosity of the ore, the ore adheres to the bottom of the car during side unloading, making it difficult to unload completely. In actual work, the ore, which accounts for about one-third of the volume of the mine car, is attached to the bottom of the car for a long time, greatly reducing transportation efficiency.
[0007] For the above reasons, the ore piled on one side of the ore bin and stuck on the bottom of the vehicle often needs to be processed manually, which not only increases the labor cost, but also indirectly affects the mining efficiency. Summary of the invention
[0008] In view of the above problems, the present invention provides a mining method suitable for a mine with stable rock mass, small height difference between the mid-stage transportation unloading position and the shaft hoisting loading position, poor ore fluidity, and a natural repose angle of the ore not exceeding 60 degrees.
[0009] The purpose of the present invention is achieved through the following technical solutions:
[0010] An underground ore discharge and crushing system close to the unloading station: suitable for metal and non-metal mining with stable rock mass, height difference between the mid-stage transportation unloading position and the shaft hoisting loading position less than 30 meters, poor ore fluidity, and natural repose angle of the ore less than 60 degrees;
[0011] The technical solution includes a crushing chamber, a raw ore bin, an unloading station, a powder ore bin, a metering chamber, and a bottom-dumping mine car for transporting ore from each middle section;
[0012] A crushing chamber, a powder ore bin and a metering chamber are arranged vertically below the middle section of the lowest mining layer, and an unloading station is arranged on the side of the crushing chamber, and the crushing chamber is located on the side of the discharge port of the unloading station and is close to the unloading station; the floor elevation of the crushing chamber is lower than the floor elevation of the unloading station, and the long axis direction of the crushing chamber is parallel to the long axis direction of the unloading station;
[0013] The unloading station is a bottom unloading station, which is connected to the transport middle section of the lowest mining middle section and cooperates with the bottom unloading mine car to transport ore; the upper mining middle section is connected to the side of the unloading station through the upper middle section chute;
[0014] An ore bin is arranged on the side of the crushing chamber, the bin body of the ore bin is arranged obliquely, and its axis is perpendicular to the long axis direction of the unloading station. The top of the ore bin is connected to the bottom of the unloading station through the discharge port, and the bottom of the ore bin is connected to the side of the crushing chamber; a crusher is arranged in the crushing chamber, and the center line of the crusher and the long axis direction of the unloading station are perpendicular to each other;
[0015] The silo body of the powder ore bin is arranged obliquely, the top of the powder ore bin is connected to the bottom of the crushing chamber, and the bottom of the powder ore bin is connected to the side or top of the metering chamber;
[0016] The metering chamber is connected to a blind shaft for ore lifting, and a metering bucket is arranged inside the metering chamber;
[0017] The crushing chamber serves the lowest layer and the mining sections above. The ore of the lowest layer mining section is transported by bottom unloading mine cars and directly unloaded into the raw ore bin from the discharge port of the unloading station; the ore of the upper mining section (i.e., the sections above the lowest section) is unloaded by bottom unloading mine cars to the upper section chute from the upper mining section to the lowest mining section and enters the unloading station, and is collected into the raw ore bin 4 through the discharge port;
[0018] The ore entering the raw ore bin goes down into the crushing chamber. The ore crushed by the crusher falls into the powder ore bin and goes down along the powder ore bin into the measuring chamber. After being weighed by the measuring bucket, it is loaded into the skip and lifted to the surface along the blind shaft.
[0019] Furthermore, the height difference between the unloading station bottom plate and the crushing chamber bottom plate is 11 to 12 meters, and the height difference between the crushing chamber bottom plate and the metering chamber bottom plate or the loading position is 12 to 13 meters.
[0020] Furthermore, the horizontal distance between the crushing chamber and the unloading station is 4 to 6 meters, and the wall of the crushing chamber located on the side of the raw ore bin is reinforced, and the wall thickness is not less than 0.8 meters.
[0021] Furthermore, the inclination angle of the ore bin is 60 degrees.
[0022] Furthermore, the cross-section of the ore bin is circular, the minimum distance between the ore bin wall and the crushing chamber wall should be greater than or equal to 1 meter, and the lining of the ore bin is reinforced with manganese steel plates not less than 20 mm thick; the volume of the ore bin is 100 to 109 cubic meters, and the walls are cast with reinforced concrete.
[0023] Furthermore, the inclination angle of the powder ore bin is 60 degrees.
[0024] Furthermore, the cross-section of the powder ore bin is circular, and the volume of the powder ore bin is 75 to 77 cubic meters.
[0025] Furthermore, the specifications of the crushing chamber are 10 to 15 meters in length, 8 to 10 meters in width, 12 to 15 meters in height, and the top plate is arched.
[0026] Furthermore, the crushing chamber is provided with an equipment large parts road and a pedestrian passage. The equipment large parts road adopts an inclined shaft arrangement to connect to the middle level tunnel, and is connected to the auxiliary shaft through the middle level tunnel; the pedestrian passage adopts a ladder road, which leads from the top of the crushing chamber to the middle level tunnel and is used for emergency pedestrians and ventilation.
[0027] Furthermore, a dust removal hole is provided at the top of the crushing chamber, which is connected to the water bin in the middle level tunnel and is used for dust removal of the crushing equipment in the chamber.
[0028] The beneficial effects of the present invention are:
[0029] The ore discharge and crushing system provided by the present invention covers a complete set of process technology and safety assurance technologies, and is suitable for mines with stable rock mass, small height difference between the middle section of ore unloading and the middle section of ore loading, poor ore fluidity, ore unloading cars sticking to the bottom, and ore natural repose angle not exceeding 60 degrees. It uses bottom-unloading ore cars to unload ore, adopts an innovative layout form, and arranges crushing chambers laterally for crushing, making full use of the limited height difference between the unloading elevation and the loading elevation, and reasonably arranges the positions of the unloading station, the original ore bin, and the powder ore bin in a limited space, so that the unloading and lifting capacity of the blind shaft system matches the crushing and lifting capacity of the main shaft, realizing the maximization of the ore bin capacity and ore processing capacity, and effectively solving the problems of ore crushing with a height difference of less than 30 meters between the unloading position and the loading position, natural accumulation of ore in the ore bin, and sticking to the car; the technical solution of the present invention solves the damage of large pieces of ore to the blind shaft bucket while improving the ore crushing efficiency and lifting capacity, and obtains greater economic and social benefits.
[0030] The technical solution of the present invention is described in detail below in conjunction with the accompanying drawings and specific implementation methods. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 The figure is a schematic diagram of the ore discharge and crushing process of the present invention (mainly reflecting the relationship between the unloading station, upper ore bin, crushing chamber, lower ore bin and ore loading chamber on the vertical elevation);
[0032] Figure 2 The diagram is a relationship diagram between the crushing chamber and the large-piece passage of the present invention (mainly reflecting the relationship between the large-piece passage, the safety exit, and the dust removal passage in the crushing chamber);
[0033] Figure 3 The diagram is a plan view of the relationship between the crushing chamber, the unloading station, the safety exit and the dust removal hole of the present invention;
[0034] Figure 4 It is a schematic plan view of the crushing chamber of the present invention;
[0035] Figure 5 This is a schematic diagram of a traditional ore discharge and crushing system;
[0036] Figure 6 An overhead view of a conventional ore chute and crushing system. DETAILED DESCRIPTION
[0037] In the figure: 1-upper middle chute, 2-upper chute ore discharger, 3-unloading station, 4-raw ore bin, 5-feeding ore discharger, 6-crushing chamber, 7-crusher, 8-powder ore bin, 9-metering ore discharger, 10-metering chamber, 11-metering bucket, 12-skip, 13-blind shaft, 14-equipment large parts road, 15-middle level tunnel, 16-pedestrian passage, 17-dust removal hole, 18-side unloading mine car, 19-unloading ore bin, 20-accumulated ore. Example
[0038] The ore discharge and crushing scheme of the present invention is suitable for metal and non-metal mining with stable rock mass, height difference between the mid-stage transportation unloading position and the shaft hoisting loading position less than 30 meters, poor ore fluidity, and natural repose angle of the ore less than 60 degrees.
[0039] The ore discharge and crushing system includes a crushing chamber 6, a raw ore bin 4, an unloading station 3, a powder ore bin 8, a metering chamber 10, and a bottom-unloading mine car for carrying each middle section of ore;
[0040] A crushing chamber 6, a powder ore bin 8 and a metering chamber 10 are vertically arranged below the middle section of the lowest mining layer, and an unloading station 3 is arranged on the side of the crushing chamber 6, so that the crushing chamber 6 is located on one side of the discharge port of the unloading station 3 and is adjacent to the unloading station 3, the long axis direction of the crushing chamber 6 is parallel to the long axis direction of the unloading station 3, and the bottom plate elevation of the crushing chamber 6 is lower than the bottom plate elevation of the unloading station 3.
[0041] The unloading station 3 is a bottom unloading station, and a curved track unloading mechanism is provided in the unloading station; the bottom unloading station is horizontally connected with the transportation level of the lowest mining middle section, and the upper mining middle section is connected with the side of the bottom unloading station through the upper middle section chute 1, and an upper chute ore placing machine 2 is arranged at the end of the upper middle section chute 1 (i.e., the connection point between the upper middle section chute and the unloading station).
[0042] The specifications of the crushing chamber are 10 to 15 meters in length, 8 to 10 meters in width, and 12 to 15 meters in height, and its top plate is arched; the height difference between the unloading station bottom plate and the crushing chamber bottom plate is 11 to 12 meters, and the horizontal distance between the crushing chamber 6 and the unloading station 3 is 4 to 6 meters.
[0043] An ore bin 4 is arranged on the side of the crushing chamber 6. The bin body of the ore bin 4 is inclined at an angle of 60 degrees to the horizontal plane, and its axis is perpendicular to the long axis direction of the unloading station 3. The top of the ore bin 4 is connected with the bottom of the unloading station 3 through the discharge port, and the bottom of the ore bin 4 is connected with the side of the crushing chamber 6, and a feeder 5 is arranged at the connection between the ore bin and the crushing chamber.
[0044] The wall of the crushing chamber close to the raw ore bin should be reinforced, and the wall thickness should not be less than 0.8 meters; a crusher 7 is arranged in the crushing chamber 6, and the center line of the crusher 7 and the long axis direction of the unloading station 3 are perpendicular to each other.
[0045] The body of the powder ore bin 8 is arranged at an inclination, and the angle between the body and the horizontal plane is 60 degrees; the top of the powder ore bin 8 is connected to the bottom of the crushing chamber 6, and the bottom of the powder ore bin is connected to the side or top of the metering chamber 10, and a metering ore discharger 9 is arranged at the connection between the lower end of the powder ore bin and the metering chamber (the entrance of the metering chamber); the height difference between the bottom plate of the crushing chamber and the bottom plate of the metering chamber or the loading position is 12 to 13 meters.
[0046] The metering chamber 10 is connected to a blind shaft 13 for ore lifting, and a metering bucket 11 is arranged inside the metering chamber 10 .
[0047] In this embodiment, the crushing chamber is 10 meters long, 8.5 meters wide and 12 meters high; the horizontal distance between the crushing chamber and the wall of the unloading station is 4 meters (the closest distance shall not be less than 4 meters), and the wall of the crushing chamber on the side of the original ore bin is reinforced, and the wall thickness is ≥0.8 meters; the height difference between the bottom plate of the unloading station and the bottom plate of the crushing chamber is 12 meters, and the height difference between the bottom plate of the crushing chamber and the bottom plate of the metering chamber or the loading position is 13 meters.
[0048] The crushing chamber is provided with two safety exits: a large equipment passage 14 and a pedestrian passage 16;
[0049] The equipment large-piece road 14 is arranged in an inclined shaft with an inclination angle of 25 degrees, connected to the crushing chamber from the auxiliary shaft opening through the middle level tunnel, used to lower large-piece equipment, materials and normal pedestrians, and a track is set in the equipment large-piece road (inclined shaft) to lift and stabilize the vehicle;
[0050] The pedestrian passage adopts a ladder path, which is arranged at the top of the crushing chamber 6 as an emergency safety exit, and leads to the middle level tunnel from the top of the crushing chamber 6, which is used for emergency pedestrians and ventilation.
[0051] In addition, a dust removal hole 17 is reserved on the other side of the top plate of the crushing chamber, the crusher is connected to the dust removal hole 17, and the water tank in the middle level tunnel is connected through the dust removal hole to remove dust from the crushing equipment in the chamber.
[0052] The cross-section of the ore bin 4 of this embodiment is circular, and the horizontal projection of its axis is perpendicular to the long axis of the unloading station to achieve sufficient unloading length and maximize the capacity of the ore bin. The volume of the ore bin is 100 to 109 cubic meters, and the ore storage capacity is about 218 tons (about the ore pulling volume of 5 trains); the wall of the ore bin is cast with reinforced concrete. In order to prevent the impact and friction of ore from damaging the side wall of the crushing chamber when the unloading station unloads ore, the minimum distance between the ore bin and the crushing chamber should be greater than or equal to 1 meter, and the lining of the ore bin is reinforced with a wear-resistant manganese steel plate not less than 20 mm thick to ensure safety and reliability between the ore bin and the crushing chamber.
[0053] The cross section of the powder ore bin 8 is also designed to be circular, with a volume of 75 to 77 cubic meters and a storage capacity of about 154 tons, which can meet the needs of 30 blind shaft skip liftings.
[0054] The crushing system of the ore discharge and crushing process of the present invention serves the mining sections of the lowest layer and above. The ore of the lowest mining section is transported by a bottom-discharging mine car and is directly unloaded into the original ore bin 4 from the discharge port of the unloading station 3; the upper mining sections are connected to the lowest mining section through the upper middle section chute 1, and the ore of the upper mining section is unloaded into the upper middle section chute 1 by the bottom-discharging mine car, goes down along the chute and is controlled by the upper chute ore discharger 2 at the end of the chute to be unloaded into the unloading station 3, and is merged into the original ore bin 4 through the discharge port; in this embodiment, each section adopts a bottom-discharging mine car for unloading operations, which effectively avoids the ore adhering to the bottom of the car and greatly improves the unloading efficiency.
[0055] The ore entering the raw ore bin 4 moves downward along the bin body, and is placed into the crushing chamber 6 located in the middle of the lowest layer for crushing under the control of the feeding ore discharger 5 located at the lower end of the raw ore bin. The ore crushed by the crusher 7 falls into the powder ore bin 8, and moves downward along the powder ore bin 8 and is discharged into the metering chamber 10 by the metering ore discharger 9. After being weighed by the metering bucket 11, it is loaded into the skip 12 and lifted to the surface along the blind shaft 13.
[0056] Compared with the traditional ore slitting and crushing process, the technical solution of the present invention constructs a crushing chamber close to the unloading station side, reasonably distributes the spatial position relationship of each single project in the underground crushing system, effectively increases the inclination angle of the ore bin, and solves the problems of short length of the unloading ore bin and gentle angle of the bin bottom leading to natural accumulation of ore affecting production efficiency. The unloading and crushing capacity is increased from 450,000 t / a of the existing technology to 1.2 million t / a, achieving the best match between the unloading and lifting capacity of the blind shaft system and the crushing and lifting capacity of the main shaft.
[0057] All operations of the process of the present invention are carried out under the support body to ensure construction safety:
[0058] ①. First, determine the length, width and height of the crushing chamber according to the specifications of the crusher and the overhead crane, and then perform numerical simulation calculations based on the mechanical properties of rock to verify the maximum span of the crushing chamber and the maximum area allowed to be exposed. After the chamber specifications are determined, the angle of the ore bin is determined according to the natural repose angle of 60 degrees of the ore, thereby determining the layout position and elevation of the chamber, and evenly distributing the volume of the raw ore bin and the powder ore bin, thereby determining this process layout.
[0059] ②. Adopt rock reinforcement technology, and excavate the foundation pit of the unloading station and the crushing chamber to form a large-span arch support process. Before excavation, use cement slurry long anchor cables to pre-reinforce the top plate rock. After pre-reinforcement, excavate the foundation pit of the unloading station and the top of the crushing chamber. After excavation, use the middle construction partition beam to separate the crushing chamber and the unloading station to reduce the excavation span. Parallel resin long anchor cables are constructed on one side of the unloading station to reinforce the top plate; 4-meter-long mortar anchor rods are used on the side of the crushing chamber to reinforce the top plate according to the 1m×1m grid to ensure construction safety.
[0060] ③. Segmented excavation and segmented pouring technology for large-span chambers. The crushing chamber is 10 meters long, and the vault is poured in three times, first excavating and supporting from the chute side, then constructing the middle part, and finally constructing the original rock side, each construction is 3.0 to 3.5 meters.
[0061] ④. Construction technology from top to bottom in the crushing chamber: first excavate and support the vault, then excavate and support downwards. The vault reinforcement is connected to the anchor rods of the top plate construction, and the concrete of the vault part is suspended. Under the protection of the top plate, the chamber wall part is then excavated downwards in sequence.
[0062] ⑤. The construction of a crushing chamber next to the unloading station effectively solved the crushing problem when the height difference between the unloading level and the loading level was only 20 meters.
[0063] ⑥. Use digital electronic detonators and blasting vibration testers. Use high-precision digital electronic detonators to excavate the chamber using controlled blasting technology, and regularly use blasting vibration testers to test blasting vibrations, effectively control the amount of single-shot explosives, avoid the impact of chamber excavation on the surrounding main chutes and blind shafts, and ensure safe construction.
[0064] ⑦. Use the empty area scanner and VS150-MK3 3D laser scanner to scan the excavation contour, accurately calculate the excavation volume and the thickness of the surrounding engineering rock mass, and adjust the support thickness.
[0065] Finally, it should be noted that the above embodiments are used to illustrate the technical solution of the present invention rather than to limit it. Technicians in the relevant field may modify the implementation methods or make equivalent substitutions for some technical features without departing from the essence of the technical solution of the present invention, and all of these should be included in the scope of protection required by the present invention.
Claims
1. An underground ore discharge and crushing system close to the unloading station, suitable for metal and non-metal mining with stable rock mass, height difference from the mid-stage transportation unloading position to the shaft hoisting loading position less than 30 meters, poor ore fluidity, and natural repose angle of ore less than 60 degrees; Features: It comprises a crushing chamber (6), a raw ore bin (4), an unloading station (3), a powder ore bin (8), a metering chamber (10), and a bottom-dumping mine car for transporting each middle section of ore; A crushing chamber (6), a powder ore bin (8), and a metering chamber (10) are vertically arranged below the middle section of the lowest mining layer, and an unloading station (3) is arranged on the side of the crushing chamber (6) so that the crushing chamber (6) is located on one side of the discharge port of the unloading station (3) and is adjacent to the unloading station (3); the floor elevation of the crushing chamber (6) is lower than the floor elevation of the unloading station (3), the height difference between the floor of the unloading station and the floor of the crushing chamber is 11 to 12 meters, the horizontal distance between the crushing chamber and the unloading station is 4 to 6 meters, and the long axis direction of the crushing chamber (6) is parallel to the long axis direction of the unloading station (3); The unloading station (3) is a bottom unloading station, which is connected to the transport middle section of the lowest mining middle section and cooperates with the bottom unloading mine car to transport ore; the upper mining middle section is connected to the side of the unloading station (3) through the upper middle section chute (1); A raw ore bin (4) is arranged on the side of the crushing chamber (6), the bin body of the raw ore bin (4) is arranged at an angle of 60 degrees, and its axis is perpendicular to the long axis direction of the unloading station (3), the top of the raw ore bin (4) is connected to the bottom of the unloading station (3) through the discharge port, the bottom of the raw ore bin (4) is connected to the side of the crushing chamber (6), and the minimum distance between the raw ore bin and the crushing chamber should be greater than or equal to 1 meter; a crusher (7) is arranged in the crushing chamber (6), and the center line of the crusher (7) and the unloading station (3) are perpendicular to each other. The long axis directions of the stations (3) are perpendicular to each other; the silo body of the powder ore bin (8) is arranged at an angle of 60 degrees, the top of the powder ore bin (8) is connected to the bottom of the crushing chamber (6), and the bottom of the powder ore bin is connected to the side or top of the metering chamber (10); the height difference between the bottom plate of the crushing chamber and the bottom plate of the metering chamber or the ore loading position is 12 to 13 meters; the metering chamber (10) is connected to a blind shaft (13) for ore lifting, and a metering bucket (11) is arranged inside the metering chamber (10); The crushing chamber (6) serves the lowest mining section and the mining sections above. The ore in the lowest mining section is transported by a bottom-unloading ore car and directly unloaded into the raw ore bin (4) from the discharge port of the unloading station (3); the ore in the upper mining section is unloaded by a bottom-unloading ore car to the upper middle section chute (1) from the upper mining section to the lowest mining section and enters the unloading station (3), and is collected into the raw ore bin (4) through the discharge port; The ore entering the raw ore bin (4) descends into the crushing chamber (6), and the crushed ore falls into the powder ore bin (8), and descends along the powder ore bin (8) into the measuring chamber (10), is weighed by the measuring bucket (11), and is loaded into the skip (12), and is lifted to the surface along the blind shaft (13).
2. The underground ore discharge and crushing system close to the unloading station according to claim 1 is characterized by: The wall of the crushing chamber located on the side of the original ore bin is reinforced, and the wall thickness is not less than 0.8 meters.
3. The underground ore discharge and crushing system close to the unloading station according to claim 1 is characterized by: The cross-section of the raw ore bin is circular, and the inner lining of the raw ore bin is reinforced with a manganese steel plate not less than 20 mm thick; the volume of the raw ore bin is 100 to 109 cubic meters, and the wall is cast with reinforced concrete.
4. The underground ore discharge and crushing system close to the unloading station according to claim 1 is characterized by: The powder ore bin has a circular cross-section and a capacity of 75 to 77 cubic meters.
5. The underground ore discharge and crushing system close to the unloading station according to claim 1 is characterized by: The specifications of the crushing chamber are 10 to 15 meters in length, 8 to 10 meters in width, 12 to 15 meters in height, and the top plate is arched.
6. The underground ore discharge and crushing system close to the unloading station according to claim 1 is characterized by: The crushing chamber is provided with an equipment large piece road (14) and a pedestrian passage (16). The equipment large piece road (14) is arranged in an inclined shaft to connect to the middle level tunnel, and is connected to the auxiliary shaft through the middle level tunnel; the pedestrian passage is a ladder road, which leads from the top of the crushing chamber (6) to the middle level tunnel and is used for emergency pedestrians and ventilation.
7. The underground ore discharge and crushing system close to the unloading station according to claim 1 is characterized by: A dust removal hole (17) is provided at the top of the crushing chamber, and the dust removal hole (17) is connected to the water tank in the middle level tunnel and is used for dust removal of the crushing equipment in the chamber.
Citation Information
Patent Citations
Ore pass crushing and transporting system
CN111396120A
Top chamber of underground coal bunker
CN203130111U
Downhole ore humping and crushing system adjacent to unloading station
CN216617574U
Method of mine construction for small kimberlite pipes by means of self-propelled mining machinery and complex for its lowering and lifting and ore delivery to surface
RU2158826C2