Traction network based on 50% backup of circuit breaker and fault distance measurement method and connection method

By combining cable collection and GOOSE communication methods, the problem of mutual secondary windings and complex current loops in the traction network under the cable connection method is solved, the synchronization and reliability of the fault location data of the traction network are achieved, and the convenience of maintenance is improved.

CN114384367BActive Publication Date: 2024-10-29CHENGDU SOUTHWEST JIAOTONG UNIV XUJI ELECTRIC
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202111263205.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-10-28
Publication Date
2024-10-29
Estimated Expiration
2041-10-28

AI Technical Summary

Technical Problem

When the cable connection method is used to connect the current to the traction network based on the 50% backup of the circuit breaker, it is easy to cause problems such as excessive number of secondary windings, complex current loops, and inconvenient maintenance.

Method used

By combining the cable collection method and the GOOSE communication method, the backup feeder protection device is used to collect the opposite side line current with the cable, and when the backup line is put into use, the GOOSE communication method is used to obtain the opposite side line current, reducing the flow of secondary windings and current loop cables number to achieve ranging data interaction.

Benefits of technology

Without adding additional current-to-current secondary windings and current loop cables, the synchronization and reliability of traction network fault location data are achieved, reducing the need for current-to-current secondary windings and circuit loop cables, and improving the convenience of maintenance. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114384367B_ABST
    Figure CN114384367B_ABST
Patent Text Reader

Abstract

The present invention discloses a traction network based on 50% spare circuit breakers and a fault ranging method and connection method thereof, wherein the traction network includes an up line, a down line, a spare line, a first feeder protection device, a second feeder protection device and a spare feeder protection device connected in parallel; the up line is connected to the first feeder protection device and the second feeder protection device through a cable, the down line is connected to the first and second feeder protection devices through a cable, and the spare circuit breaker is connected to the spare feeder protection device through a cable; the spare feeder protection device is respectively connected to the first feeder protection device and the second feeder protection device in a GOOSE communication mode. In the present invention, when the traction network is operating normally, the ranging data interaction has high synchronization and reliability; when the up circuit breaker or the down circuit breaker fails and the spare circuit breaker is put into operation, the ranging data interaction can also be realized without increasing the number of current mutual secondary windings and the current loop cable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of traction network distance measurement data interaction, and in particular to a traction network based on 50% backup of circuit breakers and a fault distance measurement method and a connection method. Background Art

[0002] In order to improve the power supply capacity of the electrified railway traction network using direct power supply, the railway project adopts the double-line direct supply connection method of up and down parallel connection, and adopts the method based on 50% backup of circuit breakers to improve the power supply reliability of the traction network. At this time, there is mutual impedance between the up and down lines in the traction network. In this regard, when the railway project performs fault distance measurement on the traction network, the up and down current ratio method that can eliminate the influence of mutual impedance is usually adopted. However, the up and down current ratio method distance measurement requires the simultaneous collection of the line current on this side and the line current on the opposite side. When the backup circuit breaker is put into use, the current flowing through the backup circuit breaker may be the up line current or the down line current. At this time, if the current is connected to the traction network by cable connection, there are problems such as too many current mutual secondary windings, complex current loops and inconvenient maintenance.

[0003] In view of this, this application is hereby filed. Summary of the invention

[0004] The technical problem to be solved by the present invention is that the use of cable connection to connect current to the existing traction network based on 50% backup of circuit breakers can easily lead to problems such as excessive number of current-interconnected secondary windings, complex current loops and inconvenient maintenance. The purpose is to provide a traction network based on 50% backup of circuit breakers and a fault ranging method and connection method, which can realize ranging data interaction without increasing the number of current-interconnected secondary windings and current loop cables.

[0005] The present invention is achieved through the following technical solutions:

[0006] First, the present invention provides a traction network based on 50% backup of circuit breakers, comprising an up line, a down line, a backup line, a first feeder protection device, a second feeder protection device and a backup feeder protection device; the up line, the down line and the backup line are connected in parallel with each other; the up line is connected to the first feeder protection device and the second feeder protection device through a cable, the down line is connected to the first feeder protection device and the second feeder protection device through a cable, and the backup circuit breaker is connected to the backup feeder protection device through a cable; the backup feeder protection device is respectively connected to the first feeder protection device and the second feeder protection device in a GOOSE communication mode.

[0007] Compared with the prior art, the present invention combines the cable collection method and the GOOSE communication method according to the composition characteristics of the double-line direct supply traction network equipment based on the 50% spare wiring method of the circuit breaker. Among them, the uplink line and the first feeder protection device and the second feeder protection device, the downlink line and the first feeder protection device and the second feeder protection device, and the circuit breaker and the spare feeder protection device are all connected by cables; and the spare feeder protection device is respectively connected to the first feeder protection device and the second feeder protection device in a GOOSE communication method. Through this connection method, when the spare line is put into use, the feeder protection device collects the current of the opposite line through the cable, and can make full use of the high synchronization and reliability of the cable collection of the opposite line current; when the spare line is put into use, the feeder protection device uses the GOOSE communication method to obtain the current of the opposite line, giving full play to the advantage of the GOOGSE communication method that there is no need to lay the current between the feeder protection device and the circuit transformer, so that the distance measurement data interaction can be realized without increasing the number of current mutual secondary windings and current loop cables.

[0008] As a further description of the present invention, the up line includes an up circuit breaker QF2, a current transformer CT2 and an up isolator QS2 connected in series in sequence, the down line includes a down circuit breaker QF1, a current transformer CT1 and a down isolator QS1 connected in series in sequence, and the standby line includes a standby circuit breaker QF3 and a current transformer CT3 connected in series in sequence; the up line, the down line and the standby line are connected to a bus; an up standby isolator BQS2 is included between the up line and the standby line, and a down standby isolator BQS1 is included between the down line and the standby line.

[0009] As a further description of the present invention, a parallel circuit breaker QF4 is included between the uplink line and the downlink line.

[0010] As a further description of the present invention, the busbar is 27.5KV.

[0011] Then, the present invention provides a fault distance measurement method for a traction network based on 50% backup of circuit breakers, comprising:

[0012] Step 1: Check whether the backup line is connected to the new double-track direct supply traction network; if the backup line is not connected, execute step 2; if the backup line is connected, execute step 3;

[0013] Step 2: Check whether the uplink line or the downlink line is normally connected. If the uplink line or the downlink line is normally connected, the uplink line or the downlink line collects the current of the opposite line by using a cable;

[0014] Step 3: Check the access mode of the new double-track direct-supply traction network. If the new double-track direct-supply traction network is connected to the uplink line, the first feeder protection device and the backup feeder protection device exchange the opposite line current through the GOOSE communication mode; if the new double-track direct-supply traction network is connected to the downlink line, the second feeder protection device and the backup feeder protection device exchange the opposite line current through the GOOSE communication mode;

[0015] Step 4: Use the opposite line current and the uplink and downlink current ratio method to perform fault location measurement.

[0016] As a further description of the present invention, in step 2, the method for checking whether the up line is normally connected is: checking whether the up line standby isolation BQS2, the standby circuit breaker QF3, the up line circuit breaker QF2 and the up line isolation QS2 are closed; if the up line standby isolation BQS2, the standby circuit breaker QF3, the up line circuit breaker QF2 and the up line isolation QS2 are all closed, the up line is normally connected;

[0017] The method for checking whether the downlink line is normally connected is: checking whether the downlink standby disconnector BQS1, the standby circuit breaker QF3, the downlink circuit breaker QF1 and the downlink disconnector QS1 are in close position; if the downlink standby disconnector BQS1, the standby circuit breaker QF3, the downlink circuit breaker QF1 and the downlink disconnector QS1 are all in close position, the downlink line is normally connected.

[0018] As a further description of the present invention, in order to solve the problem of delayed reception and transmission of data when transmitting data using the GOOSE communication mode, in the step 3, data synchronization processing is performed on the GOOSE communication mode.

[0019] As a further description of the present invention, the method for implementing data synchronization processing on the GOOSE communication mode includes:

[0020] Step 3.1: Start the feeder protection device on this side and trigger the fault distance measurement module on this side;

[0021] Step 3.2: The fault distance measurement module on this side sends a GOOSE signal to the feeder protection device on the opposite side, triggering the feeder protection device on the opposite side to start;

[0022] Step 3.3: The opposite-side feeder protection device records the opposite-side line current and transmits the opposite-side line current back to the local-side feeder protection device in the form of a GOOSE signal.

[0023] Finally, the present invention provides a method for connecting a traction network based on 50% backup of a circuit breaker, comprising:

[0024] S1: connect the up circuit breaker QF2, current transformer CT2 and up partition QS2 in series to form an up line;

[0025] S2: connect the downlink circuit breaker QF1, current transformer CT1 and downlink partition QS1 in series to form a downlink line;

[0026] S3: connect the standby circuit breaker QF3 and the current transformer CT3 in series to form a standby line;

[0027] S4: connecting the uplink line, the downlink line and the standby line in parallel on a bus;

[0028] S5: an uplink backup partition BQS2 is set between the uplink line and the backup line, and a downlink backup partition BQS1 is set between the downlink line and the backup line.

[0029] As a further description of the present invention, a parallel circuit breaker QF4 is provided between the up line and the down line.

[0030] Compared with the prior art, the present invention has the following advantages and beneficial effects:

[0031] 1. A traction network based on 50% backup of circuit breakers and a fault distance measurement method and connection method thereof provided by an embodiment of the present invention collects distance measurement data of the opposite line current through a cable, thereby ensuring synchronization and reliability of data interaction;

[0032] 2. A traction network based on 50% backup of circuit breakers and a fault distance measurement method and connection method thereof provided in an embodiment of the present invention, wherein the distance measurement data of the line current on the interactive side is exchanged by GOOSE communication mode, and the current is laid differently between the feeder protection device and the current transformer, which can reduce the demand for the current transformer secondary winding and the circuit loop cable, and the distance measurement data interaction can be realized without increasing the number of current transformer secondary windings and the current loop cable;

[0033] 3. The embodiment of the present invention provides a traction network based on 50% backup of circuit breakers and a fault distance measurement method and connection method thereof, which can realize synchronous data transmission using the GOOSE communication method. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0035] Figure 1A schematic diagram of traction network wiring based on 50% backup of circuit breakers provided in Example 1 of the present invention;

[0036] Figure 2 A logic block diagram of the distance measurement data interaction judgment method provided in Embodiment 2 of the present invention;

[0037] Figure 3 This is a schematic diagram of the interaction of distance measurement data of the protection device under the GOOSE communication mode provided in Example 2 of the present invention. DETAILED DESCRIPTION

[0038] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with embodiments and drawings. The exemplary embodiments of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.

[0039] In the following description, a large number of specific details are set forth in order to provide a thorough understanding of the present invention. However, it is apparent to one of ordinary skill in the art that these specific details are not necessarily employed to practice the present invention. In other embodiments, in order to avoid obscuring the present invention, well-known structures, circuits, materials, or methods are not specifically described.

[0040] Throughout the specification, references to "one embodiment," "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in conjunction with the embodiment or example is included in at least one embodiment of the present invention. Therefore, the phrases "one embodiment," "an embodiment," "an example," or "an example" appearing in various places throughout the specification do not necessarily all refer to the same embodiment or example. In addition, particular features, structures, or characteristics may be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. In addition, it will be appreciated by those of ordinary skill in the art that the figures provided herein are for illustrative purposes and that the figures are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.

[0041] In the description of the present invention, the directions or positional relationships indicated by terms such as “front”, “rear”, “left”, “right”, “up”, “down”, “vertical”, “horizontal”, “high”, “low”, “inside” and “outside” are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description. They do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, they should not be understood as limiting the scope of protection of the present invention.

[0042] Example 1

[0043] This embodiment provides a traction network based on 50% backup of circuit breakers. Compared with the existing double-line direct supply traction network based on 50% backup wiring of circuit breakers, the traction network of this embodiment adds cables between the feeder protection device and the up line, down line and backup line for collecting the current of the opposite line, and each feeder protection device exchanges distance measurement data through the GOOSE communication method. The wiring method is referenced Figure 1 As shown in the figure, the traction network based on 50% backup of the circuit breaker includes an up line, a down line, a backup line, a first feeder protection device, a second feeder protection device and a backup feeder protection device; the up line, the down line and the backup line are connected in parallel with each other; the up line is connected to the first feeder protection device and the second feeder protection device through a cable, the down line is connected to the first feeder protection device and the second feeder protection device through a cable, and the backup circuit breaker is connected to the backup feeder protection device through a cable; the backup feeder protection device is respectively connected to the first feeder protection device and the second feeder protection device in a GOOSE communication mode.

[0044] Among them, the up line includes an up circuit breaker QF2, a current transformer CT2 and an up isolator QS2 connected in series in sequence, the down line includes a down circuit breaker QF1, a current transformer CT1 and a down isolator QS1 connected in series in sequence, and the standby line includes a standby circuit breaker QF3 and a current transformer CT3 connected in series in sequence; the up line, the down line and the standby line are connected to a bus, which also includes a 27.5KV transformer; an up standby isolator BQS2 is included between the up line and the standby line, and a down standby isolator BQS1 is included between the down line and the standby line.

[0045] In addition, a parallel circuit breaker QF4 is included between the up line and the down line.

[0046] Since there is mutual impedance between the uplink and downlink lines of the current double-line direct supply traction network, the error of the reactance distance measurement method is large. Therefore, the existing technology usually uses the uplink and downlink current ratio method to eliminate the influence of mutual impedance for fault distance measurement. The uplink and downlink current ratio method requires the simultaneous collection of the line current I1 on this side and the line current I2 on the opposite side. When the standby circuit breaker QF3 is put into operation, I3 may be the downlink line current or the uplink line current. If the cable connection method is adopted, there will be too many current mutual secondary windings, complex current loops and inconvenient maintenance during the implementation of the project. However, this example combines the method of collecting distance measurement data using cables and the method of exchanging distance measurement data using the GOOSE communication method according to the equipment composition characteristics of the double-line direct-supply traction network based on the 50% backup wiring method of the circuit breaker. When the backup line is put into use, the feeder protection device collects the current of the opposite line through the cable, which can fully utilize the high synchronization and reliability of the cable in collecting the current of the opposite line; when the backup line is put into use, the feeder protection device uses the GOOSE communication method to obtain the current of the opposite line, giving full play to the advantage of the GOOSE communication method that there is no need to lay current between the feeder protection device and the circuit transformer, thereby realizing the interaction of distance measurement data without increasing the number of current mutual secondary windings and current loop cables.

[0047] Example 2

[0048] Corresponding to the above-mentioned embodiment 1, this embodiment provides a fault location method for a traction network based on 50% backup of circuit breakers, comprising:

[0049] Step 1: Check whether the backup line is connected to the new double-track direct-supply traction network according to the circuit breaker, isolation position signal and installation position of the feeder protection device; if the backup line is not connected, execute step 2; if the backup line is connected, execute step 3.

[0050] Step 2: Check whether the up line or the down line is normally connected, corresponding to the traction network of Example 1, that is, check whether the up line standby disconnector BQS2, the standby circuit breaker QF3, the up line circuit breaker QF2 and the up line disconnector QS2 are closed. If the up line standby disconnector BQS2, the standby circuit breaker QF3, the up line circuit breaker QF2 and the up line disconnector QS2 are all closed, the up line is normally connected; the method for checking whether the down line is normally connected is: check whether the down line standby disconnector BQS1, the standby circuit breaker QF3, the down line circuit breaker QF1 and the down line disconnector QS1 are closed. If the down line standby disconnector BQS1, the standby circuit breaker QF3, the down line circuit breaker QF1 and the down line disconnector QS1 are all closed, the down line is normally connected. Determine whether the standby circuit breaker is standing by the down line or the up line circuit breaker.

[0051] If the uplink line or the downlink line is normally connected, the uplink line or the downlink line collects the current of the opposite line by using a cable.

[0052] Step 3: Check the access mode of the new double-track direct-supply traction network. If the new double-track direct-supply traction network is connected to the uplink line, the first feeder protection device and the backup feeder protection device exchange the opposite line current through the GOOSE communication mode; if the new double-track direct-supply traction network is connected to the downlink line, the second feeder protection device and the backup feeder protection device exchange the opposite line current through the GOOSE communication mode. When the GOOSE communication mode is used to exchange ranging data, in the traction network of the above embodiment 1, the state logic of each switch is as follows: Figure 2 shown.

[0053] Step 4: Use the opposite line current and the uplink and downlink current ratio method to perform fault location measurement.

[0054] When the backup line is connected to the traction network, depending on the location of the short-circuit point, the feeder protection devices of the upstream and downstream lines may be activated simultaneously, one side may be activated and the other side may not be activated, and there is also the problem of delayed data reception and transmission when transmitting data using communication.

[0055] In this regard, in step 3, this embodiment implements data synchronization processing on the GOOSE communication method, and its ranging data interaction method is as follows: Figure 3 As shown. Specifically including the following steps:

[0056] Step 3.1: Start the feeder protection device on this side and trigger the fault distance measurement module on this side;

[0057] Step 3.2: The fault distance measurement module on this side sends a GOOSE signal to the feeder protection device on the opposite side, triggering the feeder protection device on the opposite side to start;

[0058] Step 3.3: The opposite-side feeder protection device records the opposite-side line current and transmits the opposite-side line current back to the local-side feeder protection device in the form of a GOOSE signal.

[0059] Finally, the present invention provides a method for connecting a traction network based on 50% backup of a circuit breaker, comprising:

[0060] S1: connect the up circuit breaker QF2, current transformer CT2 and up partition QS2 in series to form an up line;

[0061] S2: connect the downlink circuit breaker QF1, current transformer CT1 and downlink partition QS1 in series to form a downlink line;

[0062] S3: connect the standby circuit breaker QF3 and the current transformer CT3 in series to form a standby line;

[0063] S4: connecting the uplink line, the downlink line and the standby line in parallel on a bus;

[0064] S5: an uplink backup partition BQS2 is set between the uplink line and the backup line, and a downlink backup partition BQS1 is set between the downlink line and the backup line.

[0065] from Figure 3 It can be seen that the time when the protection device on this side records the ranging data I1 is T1=t1+t3, and the time when the protection device on the opposite side records the ranging data I2 is T2=t1+t2. When t2=t3, the ranging data on both sides are synchronized. t2 is the delay of the ranging data in the channel, and t3 is the "ranging synchronization time" parameter. Because the two feeder protection devices are about 20cm apart, the channel delay is short and the delay is relatively fixed. After determining the value of t2 through experiments, the parameter t3 can be set to be the same as t2 to achieve interactive ranging data synchronization in the GOOSE communication mode.

[0066] Example 3

[0067] This embodiment provides a method for connecting a traction network corresponding to Embodiment 1, comprising the following steps:

[0068] S1: connect the up circuit breaker QF2, current transformer CT2 and up partition QS2 in series to form an up line;

[0069] S2: connect the downlink circuit breaker QF1, current transformer CT1 and downlink partition QS1 in series to form a downlink line;

[0070] S3: connect the standby circuit breaker QF3 and the current transformer CT3 in series to form a standby line;

[0071] S4: connecting the uplink line, the downlink line and the standby line in parallel on a bus;

[0072] S5: an uplink backup partition BQS2 is set between the uplink line and the backup line, and a downlink backup partition BQS1 is set between the downlink line and the backup line.

[0073] S6: A parallel circuit breaker QF4 is provided between the up line and the down line.

[0074] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A traction network based on 50% backup of circuit breakers, characterized in that: It includes an up line, a down line, a standby line, a first feeder protection device, a second feeder protection device and a standby feeder protection device; the up line, the down line and the standby line are connected in parallel with each other; the up line is connected with the first feeder protection device and the second feeder protection device through a cable, the down line is connected with the first feeder protection device and the second feeder protection device through a cable, and the standby circuit breaker is connected with the standby feeder protection device through a cable; the standby feeder protection device is respectively connected to the first feeder protection device and the second feeder protection device in a GOOSE communication mode; The up line includes an up circuit breaker QF2, a current transformer CT2 and an up isolation QS2 connected in series, the down line includes a down circuit breaker QF1, a current transformer CT1 and a down isolation QS1 connected in series, and the standby line includes a standby circuit breaker QF3 and a current transformer CT3 connected in series; the up line, the down line and the standby line are connected to a bus; an up standby isolation BQS2 is included between the up line and the standby line, and a down standby isolation BQS1 is included between the down line and the standby line; A parallel circuit breaker QF4 is included between the uplink line and the downlink line.

2. A traction network based on 50% backup of circuit breakers according to claim 1, characterized in that: The busbar includes a 27.5KV transformer.

3. A fault location method for a traction network based on 50% backup of circuit breakers as claimed in claim 1, characterized in that: include: Step 1: Check whether the new double-track direct supply traction network is connected to the backup line; If the backup line is not connected, execute step 2; If the backup line has been connected, execute step 3; Step 2: Check whether the uplink line or the downlink line is normally connected. If the uplink line or the downlink line is normally connected, the uplink line or the downlink line collects the current of the opposite line by using a cable; Step 3: Check the access mode of the new double-track direct-supply traction network. If the new double-track direct-supply traction network is connected to the uplink line, the first feeder protection device and the backup feeder protection device exchange the opposite line current through the GOOSE communication mode; if the new double-track direct-supply traction network is connected to the downlink line, the second feeder protection device and the backup feeder protection device exchange the opposite line current through the GOOSE communication mode; Step 4: Use the opposite line current and the uplink and downlink current ratio method to perform fault location measurement.

4. A fault location method for a traction network based on 50% backup of circuit breakers according to claim 3, characterized in that: In the step 2, The method for checking whether the up line is normally connected is as follows: checking whether the up line standby isolator BQS2, the standby circuit breaker QF3, the up line circuit breaker QF2 and the up line isolator QS2 are in position; if the up line standby isolator BQS2, the standby circuit breaker QF3, the up line circuit breaker QF2 and the up line isolator QS2 are all in position, the up line is normally connected; The method for checking whether the downlink line is normally connected is: checking whether the downlink standby disconnector BQS1, the standby circuit breaker QF3, the downlink circuit breaker QF1 and the downlink disconnector QS1 are in close position; if the downlink standby disconnector BQS1, the standby circuit breaker QF3, the downlink circuit breaker QF1 and the downlink disconnector QS1 are all in close position, the downlink line is normally connected.

5. A fault location method for a traction network based on 50% backup of circuit breakers according to claim 3, characterized in that: In the step 3, data synchronization processing is performed on the GOOSE communication method.

6. A fault location method for a traction network based on 50% backup of circuit breakers according to claim 5, characterized in that: The method for implementing data synchronization processing on the GOOSE communication mode includes: Step 3.1: Start the feeder protection device on this side and trigger the fault distance measurement module on this side; Step 3.2: The fault distance measurement module on this side sends a GOOSE signal to the feeder protection device on the opposite side, triggering the feeder protection device on the opposite side to start; Step 3.3: The opposite-side feeder protection device records the opposite-side line current and transmits the opposite-side line current back to the local-side feeder protection device in the form of a GOOSE signal.

7. The method for connecting a traction network based on 50% backup of circuit breakers according to claim 1, characterized in that: include: S1: connect the up circuit breaker QF2, current transformer CT2 and up partition QS2 in series to form an up line; S2: connect the downlink circuit breaker QF1, current transformer CT1 and downlink partition QS1 in series to form a downlink line; S3: connect the standby circuit breaker QF3 and the current transformer CT3 in series to form a standby line; S4: connecting the uplink line, the downlink line and the standby line in parallel on a bus; S5: setting an uplink standby partition BQS2 between the uplink line and the standby line, and setting a downlink standby partition BQS1 between the downlink line and the standby line; S6: A parallel circuit breaker QF4 is provided between the up line and the down line.

Citation Information

Patent Citations

  • Feeder line fault distance measurement method and device in multi-line direct supply 50% standby mode

    CN114062853A