Guardrail plate installation and fastening device
Through the foot-pedal hydraulic jack piston rod and sleeve structure, the problem of not being tight at the overlapping points of the highway guardrail plate is solved, the close contact of the guardrail plate and the quality assurance of bolt installation is achieved, and the labor intensity of construction personnel is reduced and the improvement of construction personnel is improved. Construction efficiency.
Patent Information
- Application Number
- CN202011247597.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-11-10
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2040-11-10
AI Technical Summary
The overlapping points of the highway guardrail panels are not easy to fit tightly during the installation process, resulting in large gaps between the guardrail panels and limited manual force, making it difficult to ensure that the length of the external leakage of the fastening bolts meets the requirements, the labor intensity is high and the construction efficiency is efficient. Low.
The foot-pedal hydraulic jack piston rod is used to structure the sleeve, and the reaction force is provided through the hook and chain, so that the guardrail plate is in close contact, and the gap between the guardrail plate is tightened through the hydraulic jack, and the bolt jack is matched to the bolt jack to install the fastening bolts.
The tight fit between the guardrail plates is achieved, the labor intensity of construction personnel is reduced, the construction efficiency is improved, and the installation quality of the fastening bolts is ensured.
Smart Images

Figure CN114457731B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of road construction, relates to the installation of guardrail panels on both sides of a road, and specifically relates to a guardrail panel installation and fastening device. Background Art
[0002] Guardrails are usually installed on both sides of highways. Guardrails include poles set at regular intervals, with guardrail panels installed between the poles. The guardrail panels are made up of multiple panels overlapped in sequence. The ends of adjacent guardrail panels have a certain length of overlap, and fastening bolts need to be installed at the overlap. The ends of the bolts must be exposed for a certain length to install the barrier blocks. During the installation of common corrugated guardrails, the overlap of the guardrail panels is not easy to fit tightly, and there is a large gap between the two guardrail panels. When installing the bolts, the two guardrail panels need to be tightened, but the manpower is limited, not only the labor intensity is high, but also it is difficult to ensure that the length of the exposed thread of the connecting bolts meets the requirements. Summary of the invention
[0003] The object of the present invention is to solve the above-mentioned problem and provide a guardrail plate installation and fastening device which can make the guardrail plates fit tightly together and ensure that the installation of the fastening bolts meets the requirements.
[0004] The technical solution of the present invention is as follows:
[0005] A guardrail plate installation and fastening device is characterized in that it includes a foot-operated hydraulic jack, a sleeve is welded to the front end of the jack, the inner diameter of the sleeve is larger than the diameter of the jack piston rod, and the sleeve is sleeved on the periphery of the jack piston rod; the outer wall of the sleeve is provided with a thread, and an adjusting nut is screwed on it, two ear plates are symmetrically welded on the outer wall of the adjusting nut, each ear plate is connected to a chain, one end of the chain is connected to the ear plate, and the other end is connected to a hook.
[0006] The present invention adopts a foot-operated hydraulic jack piston rod to push the guardrail plate, and two hooks respectively hang on the upper and lower sides of the guardrail plate to provide reaction force, so that the overlapping parts of the two guardrail plates are in close contact. The structure is light and easy to use, which reduces the labor intensity of construction workers, improves construction efficiency, and ensures the installation quality of the guardrail plate fastening bolts. BRIEF DESCRIPTION OF THE DRAWINGS
[0007] Figure 1 It is a schematic diagram of the structure and use status of the present invention. DETAILED DESCRIPTION
[0008] like Figure 1As shown, the present invention includes a foot-operated hydraulic jack 1, a sleeve 2 is welded to the front end of the jack 1, the inner diameter of the sleeve 2 is larger than the diameter of the jack piston rod 3, and the sleeve is sleeved on the periphery of the jack piston rod 3; a thread is provided on the outer wall of the sleeve, and an adjusting nut 4 is screwed, two ear plates 5 are symmetrically welded on the outer wall of the adjusting nut, each ear plate is connected to a chain 6, one end of the chain is connected to the ear plate, and the other end is connected to a hook 7.
[0009] When the present invention is used, the adjusting nut 4 is rotated to adjust the front end length of the chain 6 to be longer than the jack piston rod, and then the two hooks 7 are respectively hung on the upper and lower sides of the overlap of the two guardrail plates 8, and the hydraulic jack oil inlet valve is opened. The jack piston rod is extended and pressed against the middle of the overlap of the two guardrail plates 8 through the foot oil pump, and the gap between the two guardrail plates is tightened, and then the fastening bolts 9 are installed.
[0010] When the present invention is implemented, a bolt cartridge 10 can be welded to the front end of the piston rod of the jack to facilitate bolt installation. The rear end cross section of the fastening bolt is usually hexagonal, and the inner cavity cross section of the bolt cartridge can be set to be consistent with the cross section of the rear end of the guardrail plate fastening bolt. When installing the fastening bolt 9, the rear end of the fastening bolt 9 is inserted into the bolt cartridge 10, and the front end of the bolt passes through the screw hole between the two guardrail plates 8. The piston rod pushes the rear end of the bolt forward to tighten the guardrail plate, and the nut is fastened to the front end of the bolt on the other side of the guardrail plate.
[0011] In order to facilitate the carrying of the present invention, a handle 11 can be welded on the side wall of the jack.
Claims
1. A guardrail plate installation and fastening device, characterized in that: It comprises a foot-operated hydraulic jack, a sleeve is welded to the front end of the jack, the inner diameter of the sleeve is larger than the diameter of the jack piston rod, and the sleeve is sleeved on the periphery of the jack piston rod; a thread is provided on the outer wall of the sleeve, and an adjusting nut is screwed on, two ear plates are symmetrically welded on the outer wall of the adjusting nut, each ear plate is connected to a chain, one end of the chain is connected to the ear plate, and the other end is connected to a hook; a bolt cartridge is welded to the front end of the piston rod of the jack, and the cross-section of the inner cavity of the bolt cartridge is consistent with the cross-section of the rear end of the guardrail plate fastening bolt; a handle is welded on the side wall of the jack.
Citation Information
Patent Citations
Rapid replacement system device of expressway guardrail board and use method
CN108589595A
W type guardrail board mounting plate
CN206916674U
Mounting and adjusting device for steel crash barrier
CN210341746U
Guardrail plate mounting and fastening device
CN213952052U