A sunken station for closely passing under existing buildings and structures and a construction method thereof

By changing the direction of the guide hole and using the pipe shed support structure during subway construction, the roof slab of the subway station is sunk, and the problem of conflict between existing buildings and the main structure space is solved, and the rapid development of underground projects and cost savings are achieved.

CN114542128BActive Publication Date: 2024-11-15CHINA RAILWAY 14TH BUREAU GRP TUNNEL ENG CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210088421.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-25
Publication Date
2024-11-15
Estimated Expiration
2042-01-25

AI Technical Summary

Technical Problem

In subway construction, when existing structures and main structures conflict in space, existing technology usually requires demolishing or relocating existing structures, resulting in loss of manpower and material resources and economic pressure, especially when existing structures have a relatively large range of invasion lines. Small and does not affect the use of the main structure.

Method used

A sunken station structure and construction method are adopted that closely sticks under the existing structure. By changing the direction of the guide hole during the construction of the hole pile method, the roof plate is gradually sinking, and the pipe shed support structure is used to avoid existing buildings. Structure, realizes the underpass of the main structure. The method includes dividing the construction section into a standard section, a transition section and a downward section, gradually sinking the top plate of the transition section using the hole pile method, and supporting the pipe shed during the construction of the underpass section to ensure structural stability and settlement control.

Benefits of technology

It effectively avoids the re-wire and demolition of existing buildings, controls settlement during construction, realizes the rapid development of underground projects and space utilization, and reduces construction costs and manpower and material losses.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114542128B_ABST
    Figure CN114542128B_ABST
Patent Text Reader

Abstract

In order to solve the problem that the existing structure has a small intrusion range that does not affect the use of the main structure, and demolition will cause economic and human and material losses, the present invention proposes a sunken station and construction method for closely passing under existing buildings and structures, including a standard section, a transition section, and an underpass section; by changing the direction of the guide tunnel in the pile construction method, the top plate of the transition section is gradually sunk to the underpass section, and the underpass section passes under the existing building, so that the main body avoids the existing buildings.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of rail transit engineering, and in particular relates to a sunken station for closely passing under existing buildings and structures and a construction method. Background Art

[0002] During subway construction, conflicts between existing structures and main buildings often occur in space. Usually, the solution to spatial conflicts is to demolish or relocate existing buildings, but the rerouting or demolition of existing buildings will cause a lot of manpower and material losses.

[0003] If the existing structure has a small intrusion range and does not affect the use of the main structure, the demolition of existing buildings will cause a large loss of manpower and material resources, and even cause economic pressure. Summary of the invention

[0004] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a sunken station structure and construction method for closely passing under existing buildings and structures. By changing the direction of the guide tunnel in the pile method construction, the top plate is gradually sunk, so that the main body can avoid the existing buildings and structures.

[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:

[0006] In a first aspect, an embodiment of the present invention provides a method for constructing a sunken station that is closely attached to and passes under an existing building structure, comprising the following steps:

[0007] Step 1, divide the construction section into standard section I, transition section I, underpass section, transition section II and standard section II;

[0008] Step 2: Use the hole pile method to construct the main structure of standard section I and standard section II, and reserve steel bar joints to achieve the connection between standard section I and transition section I, and between standard section II and transition section II;

[0009] Step 3: Use the hole pile method to construct the transition section I. During the construction process, the top plate of the transition section I is gradually sunk by gradually sinking the guide hole. When the distance from the connection position of the transition section I and the underpass section is set, a pipe-roof support structure is constructed under the existing building. The direction of the steel pipe of the pipe-roof support structure is the same as the direction of the main excavation and is perpendicular to the existing building.

[0010] Step 4: Use the hole pile method to construct the underpass section below the pipe-roof support structure;

[0011] Step 5: Carry out the construction of transition section II. By raising the guide tunnel excavation path, the top plate height is increased, the structural cross-section is increased, and it is connected to the standard section II on the other side.

[0012] In a second aspect, an embodiment of the present invention further provides a sunken station structure obtained by utilizing the construction method and closely fitting under an existing building.

[0013] The beneficial effects of the above embodiments of the present invention are as follows:

[0014] The sunken station structure and construction method proposed by the present invention for closely fitting under existing buildings and structures avoids the need for rerouting and demolishing existing buildings and structures during construction by means of a concave top plate and a pipe shed to support existing buildings and structures, and controls the settlement during construction. In today's rapidly developing underground engineering construction, it has a relatively broad application prospect.

[0015] In the present invention, when constructing the transition section, the pipe shed support frame is fixed above the steel arch frame inside the guide tunnel near the corner of the transition section by welding. When constructing the underpass section, when constructing the primary lining structure, the primary lining steel arch frame is fixed below the pipe shed by welding to achieve multiple supports of the pipe shed. After the steel arch frame construction is completed, the pipe shed and the steel arch frame are sprayed with concrete to further enhance the support effect.

[0016] In order to ensure the supporting effect of the pipe curtain, the size of the pipe curtain is strictly controlled in the design to ensure that it can pass under the existing structure and can be overlapped at the steel arch frames in the transition zone on both sides; during the construction process, when the primary lining structure is constructed in the pilot tunnel, each steel arch frame support is fixed to the bottom of the pipe shed support structure that has been driven in by welding in sequence. After the pipe shed support structure is connected to the primary lining steel arch frame by welding, concrete is sprayed to further strengthen the pipe shed support structure. This method is carried out in sequence until the construction of the primary lining structure of the underpass section is completed and all the steel arch frames are welded to the pipe shed support structure.

[0017] In view of the problem that the top plate of the transition section has a certain inclination angle and the formwork is difficult to support, the present invention adopts wooden wedges to ensure that the formwork is fixed during support. When constructing different sections, the present invention adopts the method of steel bar joints and appropriately increases the area of ​​the formwork so that the steel bars of different sections are closely connected, solving the problem of connection between different sections. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0019] Figure 1It is a schematic diagram of the overall construction process of the present invention;

[0020] Figure 2 , Figure 3 It is a schematic diagram of the main structure and section division of the present invention;

[0021] Figure 4 , Figure 5 , Figure 6 This is a schematic diagram of the main construction connection of different sections of the present invention;

[0022] Figure 7 , Figure 8 , Fig. 9 It is a schematic diagram of the arrangement of the pipe shed support structure;

[0023] Fig.10 , Fig.11 It is a three-dimensional schematic diagram of the arrangement of the pipe-roof support structure;

[0024] Fig.12 It is a schematic diagram of the inclined template support;

[0025] Fig.13 , Fig.14 This is a schematic diagram of the construction of the pipe shed support structure;

[0026] Fig.15 This is another schematic diagram of the construction of the transition zone (without soil);

[0027] Fig.16 This is another schematic diagram of the construction of the transition zone (with soil status);

[0028] Fig.17 It is a schematic diagram of the main structure after the construction is completed;

[0029] In the figure: the distances or sizes between parts are exaggerated to show the positions of various parts, and the schematic diagram is for illustration only.

[0030] 1 existing buildings and structures, 2- pipe-roof supporting structure, 3- standard section, 4- transition section, 5- underpass section, 6- steel bar joint, 7- steel bar connector, 8- thread, 9- main reinforcement, 10- top slab concrete, 11- surrounding soil, 12- primary lining steel arch frame, 13- pipe-roof steel pipe, 14- support frame. DETAILED DESCRIPTION

[0031] It should be noted that the following detailed descriptions are illustrative and intended to provide further explanation of the present invention. Unless otherwise specified, all technical and scientific terms used in the present invention have the same meanings as those commonly understood by those skilled in the art to which the present invention belongs.

[0032] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present invention. As used herein, unless otherwise explicitly stated in the present invention, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "include" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof;

[0033] For the convenience of description, if the words "up", "down", "left" and "right" appear in the present invention, they only indicate that they are consistent with the up, down, left and right directions of the drawings themselves, and do not limit the structure. They are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0034] As introduced in the background technology, there are deficiencies in the prior art. In order to solve the problem that the existing structure has a small intrusion range that does not affect the use of the main structure (the intrusion range does not exceed 70cm), and the removal will cause economic and human and material losses, the present invention proposes a sunken station structure and construction method for closely passing under existing buildings and structures. It is aimed at solving the problem encountered when there is a spatial conflict with existing buildings and structures with a small intrusion range during the construction of subway stations.

[0035] In a typical embodiment of the present invention, Figure 1 As shown, this embodiment provides a method for constructing a sunken station that is close to and passes under existing buildings and structures. First, the construction section is divided into a standard section, a transition section, and an underpass section according to the size. The transition section is a sunken section. In the process from the transition section 4 to the underpass section 5, the height of the section gradually decreases. When dividing the sections, the length of each section and the inclination angle of the transition section should be strictly controlled. For example, Figure 2 , Figure 3 As shown, the standard section 3 on the left side sinks to the underpass section 5 through the transition section 4, and then the underpass section 5 rises to the standard section 3 through the transition section 4 on the right side.

[0036] After the division is completed, the main structure of the standard section 3 on both sides is constructed first by using the hole pile method. When the main structure is constructed to the edge of the transition section 4, the transition section 4 is constructed. Before the construction of the transition section, it should be ensured that the main structure of the secondary lining has been repaired to the edge and the steel bar joints are reserved.

[0037] The hole pile method is used to construct the right transition section 4. By gradually sinking the guide tunnel, the top plate of the transition section is sunk, and the cross-sectional size is gradually reduced. A certain primary support steel arch frame is selected near the corner of the transition section to overlap the pipe shed support structure. The overlapping method is to fix the bearing frame on the top of the steel arch frame by welding, and then arrange the pipe shed steel pipe, and the pipe shed steel pipe is horizontally and closely passed under the existing building. In order to ensure the support effect of the pipe shed, the two ends of the pipe shed should extend more than 2m beyond the edge of the existing structure. After the transition section is completed, the hole pile method is used to construct the underpass section. After the soil is excavated, the excavation surface is reinforced by grouting. When the primary lining structure is constructed, the steel arch frame is welded to the bottom of the pipe shed structure, and then concrete is sprayed. After the underpass section is completed, the other side (left side) is completed by the same method. When constructing the transition section, the pipe shed support frame is fixed on the top of the steel arch frame inside the guide tunnel near the corner of the transition section by welding. During the construction of the underpass section, when constructing the primary lining structure, the primary lining steel arch frame is fixed under the pipe shed by welding to achieve multiple supports of the pipe shed. After the steel arch frame construction is completed, the pipe shed and the steel arch frame are sprayed with concrete to further enhance the support effect.

[0038] Furthermore, in order to better connect the structures on both sides with the close-fitting structure in the middle, steel bar joints are extended at the edges of the structures on both sides, and the two parts of the steel bars are overlapped through the joints. Furthermore, in order to facilitate the support of the top plate and improve the transition effect of the transition section, the inclination angle of the transition area is controlled within a range below 30°. Furthermore, in order to reserve sufficient space for pipe shed support operation, the edge of the underpass section should exceed the edge of the existing building by 1.5-2.0m. Furthermore, in order to improve the support effect of the pipe shed, the support frame of the pipe shed should be fixed above the primary lining steel arch frame by welding, and during the construction of the underpass section, each primary lining steel arch frame should be fixed to the pipe shed support structure by welding, and reinforced by spraying concrete. Furthermore, in order to improve the support effect of the pipe shed, attention should be paid to the posture control of the pipe shed during the pipe shed support process, so that the upper and lower deviations of the pipe shed do not exceed 3cm, and attention should be paid to the overlap effect on both sides.

[0039] The invention proposes to utilize the sinking of the top plate to avoid spatial conflicts with existing buildings and structures, and to lower the height of the top plate by changing the path of the guide tunnel, thereby achieving the purpose of passing through.

[0040] like Figure 4 , Figure 5 , Figure 6As shown, in order to make the main structure of different sections closely connected, the steel bars of the two sections are overlapped, that is, the steel bars are extended at the edge of the previous construction section, and the steel bars of the two different sections are connected by the steel bar connector 7 and the thread 8, and then the concrete is poured. In order to keep the concrete structure connected, the template should exceed the edge by 20-30cm during pouring.

[0041] like Figure 7 , Figure 8 , Fig. 9 , Fig.10 , Fig.11 As shown, in order to prevent the existing structure from settling, the pipe shed support method is used to support the existing structure. The pipe shed support system consists of support beams and pipe shed steel pipes. When the transition section is constructed to the corner, about 30-50cm away from the corner, the pipe shed construction is carried out. During the construction of the transition section, the pipe shed support frame is fixed above the steel arch frame inside the guide tunnel near the corner of the transition section by welding. During the construction of the underpass section, when the primary lining structure is constructed, the primary lining steel arch frame is fixed under the pipe shed by welding to achieve multiple supports of the pipe shed. After the steel arch frame construction is completed, the pipe shed and the steel arch frame are sprayed with concrete to further enhance the support effect.

[0042] Notes on pipe-roof support: ① The pipe-roof should be closely attached to and pass through existing buildings and structures; ② During the construction of the pipe-roof steel pipe, the horizontal posture of the pipe-roof steel pipe should be strictly controlled and adjusted in time to control the height difference at both ends within 3 cm; ③ Both ends of the pipe-roof should be overlapped with the primary lining steel arch frame, and the distance between the two ends of the pipe-roof and the edge of the existing structure should be greater than 2.0 meters.

[0043] like Fig.12 As shown in the figure, the inclined template of the transition section is supported by square wood, and the gap between the square wood and the inclined surface is filled with wooden wedges. If necessary, the wooden wedges and the square wood are nailed tightly with long nails to prevent slipping. At the same time, in order to ensure the fixation of the wooden wedges, steel pipe supports should be arranged on the side and bottom of the wooden wedges, and the steel pipe support frame should cover the formwork space.

[0044] The specific operation method is as follows:

[0045] 1. First, divide the construction section into standard section, transition section and underpass section according to the relative position with the existing buildings. The underpass section extends 1.5-2.0 meters from the edge of the existing structure on both sides, the angle of the transition section is controlled within 30°, and the length of the transition section on both sides is about 3-5 meters. In order to ensure the operating space of the pipe shed, the sinking distance of the transition section from the existing structure is 1.0-1.5 meters.

[0046] 2. Use the hole pile method to construct the standard section first, and reserve steel bar joints at the edge during the construction process. When the main body of the standard section is poured to the corner, the transition section can be constructed. Before the transition section is constructed, ensure that the main structure of the secondary lining has been repaired to the edge and reserve steel bar joints.

[0047] 3. Use the pile method to construct the transition section. By gradually sinking the guide tunnel, the top plate of the transition section is sunk to gradually reduce the cross-sectional size, thereby achieving the goal of sinking the top plate and allowing the main structure to avoid existing buildings.

[0048] 4. When the transition section is constructed to the corner and the distance from the corner is about 30-50cm, the pipe shed construction is carried out.

[0049] 5. When constructing the pipe shed support structure, the direction of the steel pipe of the pipe shed is the same as the direction of the main excavation, and is perpendicular to the existing buildings and structures. When the hole pile method is used for construction at the corresponding position, the support frame of the pipe shed is fixed above the steel arch frame of the primary lining structure in the guide tunnel by welding. The length of the pipe shed should be long enough, and should be 0.5-1.0 meters longer than the underpass section, to ensure that it can pass under the existing buildings and structures and that both sides can be overlapped to the primary lining steel arch frame in the transition area.

[0050] 6. After the construction of the transition section is completed, the hole pile method is used to construct the underpass section. First, the excavated soil is reinforced by grouting. When the primary lining structure is constructed in the guide tunnel, each steel arch support is fixed to the bottom of the pipe-roof support structure that has been driven in by welding in sequence according to the construction sequence. After the pipe-roof support structure is connected to the primary lining steel arch by welding, concrete is sprayed to further reinforce the pipe-roof support structure. Follow this method in sequence until the construction of the primary lining structure of the underpass section is completed and all steel arches are welded to the pipe-roof support structure. After the primary lining is completed, the secondary lining body is constructed.

[0051] 7. After the underpass section is completed, the transition section on the other side will be constructed. By raising the guide tunnel excavation path, the top plate height will be increased, the structural section will be increased, and it will be connected to the standard section on the other side.

[0052] Finally, it should be noted that relational terms such as first and second are merely used to distinguish one entity or operation from another entity or operation, but do not necessarily require or imply any actual relationship or order between these entities or operations.

[0053] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for constructing a sunken station that is close to and passes under existing buildings and structures , It is characterized in that The following steps are involved: Step 1, divide the construction section into standard section I, transition section I, underpass section, transition section II and standard section II; Step 2: Use the hole pile method to construct the main structure of standard section I and standard section II, and reserve steel bar joints to achieve the connection between standard section I and transition section I, and between standard section II and transition section II; Step 3: Use the hole pile method to construct the transition section I. During the construction process, the top plate of the transition section I is gradually sunk by gradually sinking the guide hole. When the distance from the connection position of the transition section I and the underpass section is set, a pipe-roof support structure is constructed under the existing building. The direction of the steel pipe of the pipe-roof support structure is the same as the direction of the main excavation and is perpendicular to the existing building. Step 4: Use the hole pile method to construct the underpass section below the pipe-roof support structure; Step 5: Carry out the construction of transition section II, by increasing the top plate height and the structural section by raising the pilot tunnel excavation path, and connect it with the standard section II on the other side; The transition section is a sinking section, and the height of the section gradually decreases during the process from the transition section to the underpass section; Before the construction of transition section I, ensure that the secondary lining main structure of standard section I and standard section II has been repaired to the edge of transition section I and transition section II; The support frame of the pipe-roof support structure is fixed above the steel arch frame of the primary lining structure in the guide tunnel of the transition section I by welding; During the construction of the underpass section, when constructing the primary lining structure, the primary lining steel arch frame is fixed under the pipe shed by welding.

2. The method for constructing a sunken station for closely passing under an existing building structure as claimed in claim 1, It is characterized in that Both sides of the underpass section extend out 1.5-2.0 meters from the existing structure.

3. The method for constructing a sunken station for closely passing under an existing building structure as claimed in claim 1, It is characterized in that The included angles between the transition section I, transition section II and the underpass section are less than 30°.

4. The method for constructing a sunken station for closely passing under an existing building structure as claimed in claim 1, It is characterized in that The length of the pipe shed of the pipe shed support structure is 0.5-1.0 m longer than the length of the underpass section.

5. The method for constructing a sunken station for closely passing under an existing building structure as claimed in claim 1, It is characterized in that Both ends of the pipe shed of the pipe shed support structure should extend more than 2m beyond the edge of the existing structure.

6. The method for constructing a sunken station for closely passing under an existing building structure as claimed in claim 1, It is characterized in that The construction process of the underpass section is as follows: The excavated soil is reinforced by grouting. When constructing the primary lining structure in the pilot tunnel, each steel arch support is fixed to the bottom of the driven pipe-roof support structure by welding in sequence according to the construction sequence. After the pipe-roof support structure and the primary lining steel arch are connected as a whole by welding, concrete is sprayed to further reinforce the pipe-roof support structure. This method is carried out in sequence until the construction of the primary lining structure of the underpass is completed and all the steel arches are welded to the pipe-roof support structure. After the primary lining is completed, the secondary lining body is constructed.

7. The method for constructing a sunken station for closely passing under an existing building structure as claimed in claim 1, It is characterized in that During the construction of transition section I and transition section II, the inclined formwork is supported by square timber, and the gaps between the square timber and the inclined surface are tightly plugged with wooden wedges. Steel pipe supports are arranged on the sides and bottom of the wooden wedges, and the steel pipe support frames cover the entire formwork space.

8. A sunken station structure obtained by using the construction method described in any one of claims 1 to 7 and passing closely under an existing building.