Method for using a coke oven plug brick construction tool

By designing construction tools for coke oven plug bricks made of high-temperature resistant materials, using the flexibility of the adjusting rod and hook head and the design of the heat-insulating umbrella, the problem of sealing the oven holes in high-temperature environments has been solved, and construction efficiency and safety have been improved. It meets the demand for rapid production of coke ovens.

CN114562884BActive Publication Date: 2024-10-01ACRE COKING & REFRACTORY ENG CONSULTING CORP DALIAN MCC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210212406.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-04
Publication Date
2024-10-01
Estimated Expiration
2042-03-04

AI Technical Summary

Technical Problem

After the coke oven is transferred to the basement for heating, the plug bricks must be constructed to seal the oven holes in a high-temperature environment. It is difficult to effectively complete this task with existing technology, which affects the subsequent production schedule of the coke oven.

Method used

A coke oven plug brick construction tool including a hand-held rod, an adjusting rod, a fixed rod, a hook head and a heat-insulating umbrella is designed. It is made of high-temperature resistant materials. By adjusting the length and angle of the rod, the number of hook heads and the number of the heat-insulating umbrella Designed to quickly and efficiently complete the sealing of oven holes.

Benefits of technology

Construction personnel can operate at a remote location to avoid the impact of high temperatures, improve construction efficiency, simplify operations, reduce labor intensity, and ensure the safety and progress of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114562884B_ABST
    Figure CN114562884B_ABST
Patent Text Reader

Abstract

The present invention relates to a coke oven plug brick construction tool, comprising a hand-held rod, an adjusting rod, a fixed rod, a hook head and a heat-insulating umbrella; the hand-held rod is coaxially connected to the adjusting rod, and the adjusting rod is vertically connected to the fixed rod; one end of the adjusting rod is hinged to one end of the hand-held rod, and the other end of the adjusting rod is fixedly connected to the middle of the fixed rod; a plurality of hook heads are axially arranged on the adjusting rod, and the hook heads can move along the axial direction of the fixed rod and be locked and fixed at any position on the moving path; a heat-insulating umbrella is also arranged on the hand-held rod. The present invention adopts a special construction tool to quickly and efficiently complete the oven hole plugging work, and the construction tool has a simple structure, is easy to make, and is convenient to operate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of coke oven masonry and hot construction, and in particular to a coke oven plug brick construction tool and a use method thereof. Background Art

[0002] During the construction of a new coke oven, after the coke oven is heated in the basement, in order to ensure that the conditions for coal loading and production are met as soon as possible, the oven hole must be sealed in time. Usually, plug bricks are used to complete the hot masonry construction of the coal loading hole on the furnace top and the oven holes at the furnace heads on both sides of the machine coke. However, after the coke oven is heated in the basement, the temperature of the coke oven carbonization chamber is high. The coal loading hole cover and the furnace door need to be opened for the construction of plug bricks. Affected by the temperature and the position of the oven hole, it is difficult to complete the construction of the plug bricks without the help of special tools. Failure to effectively seal the oven hole in a timely manner will directly affect the subsequent production arrangements of the coke oven. Summary of the invention

[0003] The invention provides a coke oven plug brick construction tool and a use method thereof. The special construction tool can be used to quickly and efficiently complete the oven hole plugging work. The construction tool has a simple structure, is easy to manufacture, and is convenient to operate.

[0004] In order to achieve the above object, the present invention adopts the following technical solutions:

[0005] A coke oven plug brick construction tool comprises a hand-held rod, an adjusting rod, a fixed rod, a hook head and a heat-insulating umbrella; the hand-held rod is coaxially connected to the adjusting rod, and the adjusting rod is vertically connected to the fixed rod; one end of the adjusting rod is hinged to one end of the hand-held rod, and the other end of the adjusting rod is fixedly connected to the middle part of the fixed rod; a plurality of hook heads are axially arranged on the adjusting rod, and the hook heads can move axially along the fixed rod and be locked and fixed at any position on the moving path; a heat-insulating umbrella is also arranged on the hand-held rod.

[0006] The number of the hooks is 3.

[0007] The fixing rod is a telescopic rod, which is composed of a plurality of cylinder sections, each of which is provided with a hook head; two adjacent cylinder sections are connected by threads and locked and fixed by a locking sleeve.

[0008] The fixing rod is a hollow rod with a slide groove on one side, and a slider is provided at one end of the hook head, and the slider can move along the slide groove; a locking bolt is provided on the slider, and each hook head can be locked and fixed with the fixing rod through the corresponding locking bolt.

[0009] The body of the hook head is a conical structure, with the end with a smaller diameter facing outward; a hook hole is arranged on the stopper brick to match the hook head.

[0010] The adjusting rod is hinged to the hand-held rod through a hinge, and the hinge is provided with a locking mechanism; the length of the adjusting rod can be adjusted.

[0011] The heat-insulating umbrella is composed of an umbrella-shaped frame and a transparent umbrella cover. The transparent umbrella cover is covered on the umbrella-shaped frame and connected to a hand-held rod through the umbrella-shaped frame. An opening and closing mechanism is also provided at one end of the hand-held rod away from the hook head for controlling the opening or closing of the heat-insulating umbrella.

[0012] The hand-held rod, the adjusting rod, the fixing rod, the hook head and the heat-insulating umbrella are all made of high-temperature resistant materials.

[0013] A handle is also provided at one end of the hand-held rod away from the hook head, a heat-insulating rubber sleeve is provided on the outer side of the handle, and an anti-slip structure is provided on the outer surface of the heat-insulating rubber sleeve.

[0014] A method for using a coke oven plug brick construction tool comprises the following steps:

[0015] (1) For oven holes at different positions, adjust the hook head spacing to adapt it to the oven hole spacing;

[0016] (2) Adjust the length of the adjusting rod and the angle between the adjusting rod and the hand-held rod to meet the construction requirements;

[0017] (3) Hang the plug brick coated with fire mud on the corresponding hook, open the heat-insulating umbrella through the opening and closing mechanism, and then the construction worker holds the handle of the hand-held rod and inserts the plug brick into the coke oven through the coal loading hole or the open furnace door on the coke machine side;

[0018] (4) The construction workers observe through the heat-insulating umbrella, adjust the position of the stopper brick by using the hand-held rod, accurately place the stopper brick in the furnace hole, and then remove the hook head from the hook hole on the stopper brick. The construction of the stopper bricks at several furnace holes on the same side is completed in one operation.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] 1) Construction workers can operate while standing far away from the oven hole, which can avoid the influence of high temperature on construction work;

[0021] 2) The length of the adjusting rod and the angle between the adjusting rod and the fixed rod can be adjusted to facilitate the sealing of the oven hole;

[0022] 3) The temperature of the coke oven is relatively high at the end of the baking process, and the number of plug bricks for a single coke oven is about 2,000, which is a huge number. The coke oven plug brick construction tool of the present invention is provided with a plurality of hooks, each of which can hang a plug brick for construction, and can complete the plugging work of multiple baking oven holes on the same side at one time, thereby greatly improving the construction efficiency;

[0023] 4) Setting up a heat-insulating umbrella does not affect the observation of the construction process while providing insulation, and can complete the construction conveniently, quickly and efficiently to meet the construction progress requirements.

[0024] 5) The construction tools are simple in structure, light in weight, flexible and convenient to operate, saving time, reducing labor intensity, and highly safe. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 This is a schematic diagram of the structure of a coke oven plug brick construction tool according to the present invention. Figure 1 .

[0026] Figure 2 This is a schematic diagram of the structure of a coke oven plug brick construction tool according to the present invention. Figure 2 .

[0027] In the figure: 1. Hook 2. Fixed rod 3. Adjustment rod 4. Hinge 5. Heat insulation umbrella 6. Handle rod 7. Opening and closing mechanism; 8. Handle DETAILED DESCRIPTION

[0028] The specific implementation of the present invention will be further described below in conjunction with the accompanying drawings:

[0029] like Figure 1 , Figure 2 As shown, a coke oven plug brick construction tool described in the present invention comprises a hand-held rod 6, an adjusting rod 3, a fixed rod 2, a hook head 1 and a heat-insulating umbrella 5; the hand-held rod 6 is coaxially connected to the adjusting rod 3, and the adjusting rod 3 is vertically connected to the fixed rod 2; one end of the adjusting rod 3 is hinged to one end of the hand-held rod 6, and the other end of the adjusting rod 3 is fixedly connected to the middle part of the fixed rod 2; a plurality of hook heads 1 are axially arranged on the adjusting rod 3, and the hook heads 1 can move axially along the fixed rod 2 and be locked and fixed at any position on the moving path; a heat-insulating umbrella 5 is also arranged on the hand-held rod 6.

[0030] The number of the hook heads 1 is 3.

[0031] like Figure 1 As shown, the fixing rod 2 is a telescopic rod, which is composed of a plurality of cylinder sections, each of which is provided with a hook head 1; two adjacent cylinder sections are connected by threads and locked and fixed by a locking sleeve.

[0032] like Figure 2 As shown, the fixing rod 2 is a hollow rod with a slide groove on one side, and a slider is provided at one end of the hook head 1, and the slider can move along the slide groove; a locking bolt is provided on the slider, and each hook head 1 can be locked and fixed with the fixing rod 2 by a corresponding locking bolt.

[0033] The body of the hook head 1 is a conical structure, with the end with a smaller diameter facing outward; a hook hole is provided on the stopper brick to match the hook head 1.

[0034] The adjusting rod 3 is hinged to the hand-held rod 6 via a hinge 4 , and the hinge 4 is provided with a locking mechanism; the length of the adjusting rod 3 can be adjusted.

[0035] The heat-insulating umbrella 5 is composed of an umbrella-shaped frame and a transparent umbrella cover, wherein the transparent umbrella cover is covered on the umbrella-shaped frame and connected to a hand-held rod 6 through the umbrella-shaped frame; an opening and closing mechanism 7 is also provided at one end of the hand-held rod 6 away from the hook head 1 for controlling the opening or closing of the heat-insulating umbrella 5.

[0036] The hand-held rod 6, the adjusting rod 3, the fixing rod 2, the hook head 1 and the heat-insulating umbrella 5 are all made of high-temperature resistant materials.

[0037] The hand-held rod 6 is also provided with a handle 8 at one end away from the hook head 1 , and a heat-insulating rubber sleeve is provided on the outside of the handle 8 , and an anti-slip structure is provided on the outer surface of the heat-insulating rubber sleeve.

[0038] A method for using a coke oven plug brick construction tool comprises the following steps:

[0039] (1) For oven holes at different positions, adjust the distance between hook heads 1 to match the distance between oven holes;

[0040] (2) Adjust the length of the adjusting rod 3 and the angle between the adjusting rod 3 and the hand-held rod 6 to meet the construction requirements;

[0041] (3) The plug brick coated with fire mud is hung on the corresponding hook head 1, and the heat insulation umbrella 5 is opened by the opening and closing mechanism 7. Then the construction worker holds the handle 8 of the hand-held rod 6 and extends the plug brick into the coke oven from the coal loading hole or the open furnace door on the coke machine side;

[0042] (4) The construction worker observes through the heat-insulating umbrella 5, adjusts the position of the stopper brick by using the hand-held rod 6, accurately places the stopper brick in the furnace hole, and then removes the hook head 1 from the hook hole on the stopper brick. The construction of the stopper bricks at several furnace holes on the same side is completed in one operation.

[0043] The following embodiments are implemented on the premise of the technical solution of the present invention, and provide detailed implementation methods and specific operation processes, but the protection scope of the present invention is not limited to the following embodiments.

[0044] [Example 1]

[0045] In this embodiment, the structure of the coke oven plug brick construction tool is as follows: Figure 1 As shown, it includes an adjusting rod 3 and a hand-held rod 6 connected by a hinge 4, a fixing rod 2 for fixing the hook head 1, three hook heads 1 arranged on the fixing rod 2, and a handle 8 arranged at the other end of the hand-held rod 6; in addition, it also includes a heat-insulating umbrella 5.

[0046] The heat-insulating umbrella 5 is arranged on a hand-held rod 6, which consists of an umbrella-shaped frame and a transparent umbrella cover. The fixed rod 2, the adjusting rod 3 and the hand-held rod 6 are all hollow tubular structures. An opening and closing mechanism 7 for controlling the opening and closing of the heat-insulating umbrella 5 is provided on the hand-held rod 6 on the inner side of the handle 8, and the opening and closing mechanism 7 is controlled by a hand wheel.

[0047] The adjusting rod 3 and the hand-held rod 6 are hinged and can freely adjust the angle within a range of 180 degrees.

[0048] Both the adjusting rod 3 and the hand-held rod 6 adopt a telescopic structure, that is, the length of the rod body is adjustable.

[0049] In this embodiment, the fixing rod 2 adopts a telescopic structure, and the three hooks 1 are respectively arranged on different pipe sections, and the spacing between them is adjustable.

[0050] The outer side of the handle 8 is covered with a heat-insulating rubber sleeve, and the outer surface of the heat-insulating rubber sleeve is provided with an anti-slip structure.

[0051] In this embodiment, the method of using the coke oven plug brick construction tool is as follows:

[0052] (1) According to the oven holes at different positions, the spacing between the three hooks 1 is adjusted to meet the oven hole spacing requirements.

[0053] (2) According to the oven holes at different positions, adjust the adjustment rod 3 to a suitable construction angle.

[0054] (3) Hang three plug bricks coated with fire mud on the corresponding three hooks 1 respectively, open the heat-insulating umbrella 5, and then the construction worker holds the handle 8 with both hands and extends the other end of the plug brick into the coke oven through the coal loading hole or the open furnace door on the coke machine side;

[0055] (4) The construction worker observes through the heat-insulating umbrella 5, and puts the three stopper bricks into the corresponding furnace holes at the same time by controlling the hand-held rod 6, and then slowly removes the hook head 1 from the hook hole on the stopper brick, completing the stopper brick construction of the three furnace holes on one side at a time.

[0056] [Example 2]

[0057] In this embodiment, the structure of the coke oven plug brick construction tool is as follows: Figure 2 As shown, a slide groove is axially provided on one side of the fixing rod, and the three hook heads are slidably connected to the fixing rod through corresponding sliders and the slide grooves. After the hook head spacing is adjusted, the hook heads are locked and fixed in corresponding positions by locking bolts provided on the slider.

[0058] The remaining structure of the coke oven plug brick construction tool and its use method are the same as those in the embodiment.

[0059] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A method for using a coke oven plug brick construction tool, It is characterized in that The coke oven plug brick construction tool comprises a hand-held rod, an adjusting rod, a fixed rod, a hook head and a heat-insulating umbrella; the hand-held rod is coaxially connected with the adjusting rod, and the adjusting rod is vertically connected with the fixed rod; one end of the adjusting rod is hinged with one end of the hand-held rod, and the other end of the adjusting rod is fixedly connected with the middle part of the fixed rod; a plurality of hook heads are axially arranged on the adjusting rod, and the hook heads can move along the axial direction of the fixed rod and be locked and fixed at any position on the moving path; the hand-held rod is also provided with a heat-insulating umbrella; The fixing rod is a telescopic rod, which is composed of several sections of cylinders, each of which is provided with a hook; two adjacent sections of cylinders are connected by threads and locked and fixed by a locking sleeve; Alternatively, the fixing rod is a hollow rod with a slide groove on one side, and a slider is provided at one end of the hook head, and the slider can move along the slide groove; a locking bolt is provided on the slider, and each hook head can be locked and fixed with the fixing rod through the corresponding locking bolt; The adjusting rod is hinged to the hand-held rod through a hinge, and the hinge is provided with a locking mechanism; the length of the adjusting rod can be adjusted; the heat-insulating umbrella is composed of an umbrella-shaped frame and a transparent umbrella cover, the transparent umbrella cover is covered on the umbrella-shaped frame, and is connected to the hand-held rod through the umbrella-shaped frame; an opening and closing mechanism is also provided at one end of the hand-held rod away from the hook head, for controlling the opening or closing of the heat-insulating umbrella; The method for using the coke oven plug brick construction tool comprises the following steps: (1) For oven holes at different positions, adjust the hook head spacing to adapt it to the oven hole spacing; (2) Adjust the length of the adjusting rod and the angle between the adjusting rod and the hand-held rod to meet the construction requirements; (3) Hang the plug brick coated with fire mud on the corresponding hook, open the heat-insulating umbrella through the opening and closing mechanism, and then the construction worker holds the handle of the hand-held rod and inserts the plug brick into the coke oven through the coal loading hole or the open furnace door on the coke machine side; (4) The construction workers observe through the heat-insulating umbrella, adjust the position of the stopper brick by using the hand-held rod, accurately place the stopper brick in the furnace hole, and then remove the hook head from the hook hole on the stopper brick. The construction of the stopper bricks at several furnace holes on the same side is completed in one operation.

2. A method for using a coke oven plug brick construction tool according to claim 1, It is characterized in that The number of the hooks is 3.

3. A method for using a coke oven plug brick construction tool according to claim 1, It is characterized in that The body of the hook head is a conical structure, with the end with a smaller diameter facing outward; a hook hole is arranged on the stopper brick to match the hook head.

4. A method for using a coke oven plug brick construction tool according to claim 1, It is characterized in that The hand-held rod, the adjusting rod, the fixing rod, the hook head and the heat-insulating umbrella are all made of high-temperature resistant materials.

5. A method for using a coke oven plug brick construction tool according to claim 1, It is characterized in that A handle is also provided at one end of the hand-held rod away from the hook head, a heat-insulating rubber sleeve is provided on the outer side of the handle, and an anti-slip structure is provided on the outer surface of the heat-insulating rubber sleeve.