A distributed energy station layout structure

By setting up the first foundation pit in the distributed energy station to share the circulating water pipe, the problem of needing to excavate two foundation pits in the existing technology is solved, and the construction period and cost are significantly reduced.

CN115059524BActive Publication Date: 2024-10-22HUANENG (QINGYUAN) GAS TURBINE THERMAL POWER CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210737860.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-24
Publication Date
2024-10-22
Estimated Expiration
2042-06-24

AI Technical Summary

Technical Problem

The existing distributed energy station requires the excavation of two foundation pits for circulating water pipes, which requires a long construction period and high costs.

Method used

Design a distributed energy station layout structure, in which a first foundation pit is provided between the first steam turbine and the second steam turbine. The first circulating water pipe and the second circulating water pipe are both arranged in the first foundation pit and pass through the water inlet main pipe. The water pipe is shared with the water outlet main pipe, reducing the number of foundation pits and construction costs.

Benefits of technology

Only one foundation pit for circulating water pipes needs to be excavated, which reduces the construction period and cost, while saving the number of water pipes and construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115059524B_ABST
    Figure CN115059524B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of distributed energy stations, and in particular to a distributed energy station layout structure, comprising a first gas turbine, a first steam turbine, a second steam turbine, and a second gas turbine arranged in sequence from left to right, the first steam turbine being connected to a first circulating water pipe for introducing circulating water into the first steam turbine, and the second steam turbine being connected to a second circulating water pipe for introducing circulating water into the second steam turbine; a first foundation pit is provided between the first steam turbine and the second steam turbine, and the first circulating water pipe and the second circulating water pipe are both provided in the first foundation pit, therefore, only one circulating water pipe pit needs to be excavated, thereby reducing the construction period and construction cost of the circulating water pipe; and a water inlet main pipe and a water outlet main pipe are provided in the first foundation pit, so that the first steam turbine and the second steam turbine can share a part of the water pipe, thereby saving the number of circulating water pipes and construction cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of distributed energy stations, and in particular to a distributed energy station layout structure. Background Art

[0002] Distributed energy stations fueled by natural gas are the main direction of my country's energy development. Distributed energy stations are arranged near users in a small-scale, small-capacity, modular manner, and convert fuel into electricity, heat, steam and other products at the same time. It is an energy supply system based on the concept of energy cascade utilization, integrating heating and power generation. Distributed energy stations have greatly improved energy utilization and have good social and energy-saving benefits.

[0003] The existing distributed energy station layout structure is as follows Figure 1 As shown, the first steam turbine 2 and the second steam turbine 3 are arranged in a translational manner. The circulating water pipe 21 of the first steam turbine 2 and the circulating water pipe 31 of the second steam turbine 3 need to enter and exit the steam turbine building from two locations respectively. Therefore, two circulating water pipe foundation pits need to be excavated. The construction period of the circulating water pipe foundation pit is long and the cost is high. Summary of the invention

[0004] The technical problem to be solved by the present invention is that in the existing distributed energy station combined plant, the circulating water pipe of each steam turbine needs to enter and exit the main plant from two locations respectively, and two circulating water pipe pits need to be excavated. The construction period of the circulating water pipe foundation pit is long and the cost is high.

[0005] In order to solve the above technical problems, the present invention provides a distributed energy station arrangement structure, comprising a first gas turbine, a first steam turbine, a second steam turbine, and a second gas turbine arranged in sequence from left to right, the first steam turbine being connected to a first circulating water pipe for introducing circulating water into the first steam turbine, and the second steam turbine being connected to a second circulating water pipe for introducing circulating water into the second steam turbine;

[0006] A first foundation pit is provided between the first steam turbine and the second steam turbine, a water inlet main pipe and a water outlet main pipe are provided in the first foundation pit, the first circulating water pipe and the second circulating water pipe are both arranged in the first foundation pit, and the water inlet of the first circulating water pipe and the water inlet of the second circulating water pipe are both connected to the water inlet main pipe, and the water outlet of the first circulating water pipe and the water outlet of the second circulating water pipe are both connected to the water outlet main pipe.

[0007] As a preferred solution, the distributed energy station layout structure also includes a first factory building and a second factory building and a third factory building respectively arranged on both sides of the first factory building; the first steam turbine and the second steam turbine are both arranged in the first factory building, the first gas turbine is arranged in the second factory building, and the second gas turbine is arranged in the third factory building.

[0008] As a preferred solution, the length of the first factory building in the left-right direction is greater than or equal to 48 meters and less than or equal to 52 meters.

[0009] As a preferred solution, the length of the second factory building in the left-right direction is greater than or equal to 28 meters and less than or equal to 32 meters.

[0010] As a preferred solution, the length of the third factory building in the left-right direction is greater than or equal to 28 meters and less than or equal to 32 meters.

[0011] As a preferred solution, the first foundation pit is arranged in the middle of the first plant building, and a first condensate pump and a second condensate pump are respectively provided on the left and right sides of the first plant building. The first condensate pump is connected to the first steam turbine to cool the steam in the first steam turbine; the second condensate pump is connected to the second steam turbine to cool the steam in the second steam turbine.

[0012] As a preferred solution, a beam structure is provided at the top of the first foundation pit, and a power distribution room is provided at the upper end of the beam structure.

[0013] Compared with the prior art, the present invention has the following beneficial effects:

[0014] In the distributed energy station layout structure of the present invention, a first foundation pit is provided between the first steam turbine and the second steam turbine, and the circulating water pipe of the first steam turbine and the circulating water pipe of the second steam turbine are both arranged in the first foundation pit. Therefore, only one circulating water pipe foundation pit needs to be excavated, thereby reducing the number of foundation pit constructions and the construction period; moreover, a water inlet main pipe and a water outlet main pipe are provided in the first foundation pit, so that the first steam turbine and the second steam turbine can share a part of the water pipe, thereby saving the number of circulating water pipes and the construction cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is the layout structure diagram of the existing distributed energy station;

[0016] Figure 2 This is a structural diagram of the distributed energy station of the present invention;

[0017] In the figure, 1, the first gas turbine; 2, the first steam turbine; 21, the first circulating water pipe; 211, the first water inlet pipe; 212, the first water outlet pipe; 22, the first condensate pump; 3, the second steam turbine; 31, the second circulating water pipe; 311, the second water inlet pipe; 312, the second water removal pipe; 32, the second condensate pump; 4, the second gas turbine; 5, the water inlet main pipe; 6, the water outlet main pipe; 7, the first plant; 8, the second plant; 81, the first waste heat boiler; 9, the third plant; 91, the second waste heat boiler. DETAILED DESCRIPTION

[0018] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0019] In the description of the present invention, it should be understood that the orientation or positional relationship indicated by the terms "upper", "lower", "left", "right", "top", "bottom", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention. It should be understood that the terms "first", "second", etc. are used in the present invention to describe various information, but such information should not be limited to these terms, which are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, the "first" information may also be referred to as the "second" information, and similarly, the "second" information may also be referred to as the "first" information.

[0020] like Figure 2As shown, a preferred embodiment of a distributed energy station layout structure of the present invention comprises a first gas turbine 1, a first steam turbine 2, a second steam turbine 3, and a second gas turbine 4 arranged in sequence from left to right, the first steam turbine 2 is connected to a first circulating water pipe 21 for introducing circulating water into the first steam turbine 2, and the second steam turbine 3 is connected to a second circulating water pipe 31 for introducing circulating water into the second steam turbine 3; a first foundation pit is arranged between the first steam turbine 2 and the second steam turbine 3, a water inlet main pipe 5 and a water outlet main pipe 6 are arranged in the first foundation pit, the first circulating water pipe 21 and the second circulating water pipe 31 are both arranged in the first foundation pit, and the water inlet of the first circulating water pipe 21 and the water inlet of the second circulating water pipe 31 are both connected to the water inlet main pipe 5, and the water outlet of the first circulating water pipe 21 and the water outlet of the second circulating water pipe 31 are both connected to the water outlet main pipe 6. Since the first circulating water pipe 21 and the second circulating water pipe 22 are both arranged in the first foundation pit, the distributed energy station layout structure of this embodiment only needs to excavate and remove the circulating water pipe pit, which reduces the construction period and construction cost of the circulating water pipe; in addition, the water inlet main pipe 5 and the water outlet main pipe 6 arranged in the first foundation pit enable the first steam turbine 2 and the second steam turbine 3 to share a part of the water pipe, further reducing the construction period and construction cost of the circulating water pipe.

[0021] Specifically, one end of the first steam turbine 2 connected to the first circulating water pipe 21 and one end of the second steam turbine 3 connected to the second circulating water pipe 31 are arranged opposite to each other, the first circulating water pipe 21 includes a first water inlet pipe 211 and a first water outlet pipe 212, the second circulating water pipe 31 includes a second water inlet pipe 311 and a second water outlet pipe 312, the first water inlet pipe 211 and the second water inlet pipe 311 are both connected to the water inlet main pipe 5; the first water outlet pipe 212 and the second water outlet pipe 312 are both connected to the water outlet main pipe 6.

[0022] In this embodiment, the distributed energy station layout structure also includes a first plant 7 and a second plant 8 and a third plant 9 respectively arranged on both sides of the turbine room; the first steam turbine 2 and the second steam turbine 3 are both arranged in the first plant 7, the first gas turbine 1 is arranged in the second plant 8, and the second gas turbine 4 is arranged in the third plant 9.

[0023] The first foundation pit is arranged in the middle of the first plant 7. The first condensate pump 22 and the second condensate pump 32 are respectively arranged on the left and right sides of the first plant 7. The first condensate pump 22 is connected to the first steam turbine 2 to cool the steam in the first steam turbine 2; the second condensate pump 32 is connected to the second steam turbine 3 to cool the steam in the second steam turbine 3. A first waste heat boiler 81 is arranged outside the second plant 8, and a second waste heat boiler 91 is arranged outside the third plant 9. The water outlet of the first waste heat boiler 81 and the water outlet of the second waste heat boiler 91 are both connected to the water inlet main 5, and the water inlet of the first waste heat boiler 81 and the water inlet of the second waste heat boiler 91 are both connected to the water outlet main 6. When in use, the high-temperature flue gas generated by the first gas turbine 1 enters the first waste heat boiler 81, and the high-temperature flue gas generated by the second gas turbine 4 enters the second waste heat boiler 91. The water in the first waste heat boiler 81 and the second waste heat boiler 91 absorbs the heat of the high-temperature flue gas to form steam, and the steam enters the first steam turbine 2 and the second steam turbine 3 respectively through the water inlet main pipe 5, so that the first steam turbine 2 and the second steam turbine 3 drive the steam turbine generator to generate electricity. The low-temperature steam flowing out of the first steam turbine 2 and the second steam turbine 3 is condensed by the first condensate pump 22 and the second condensate pump 32 and then returned to the first waste heat boiler 81 and the second waste heat boiler 92 through the water outlet main pipe 6.

[0024] In this embodiment, the length H1 of the second plant 8 in the left-right direction and the length H3 of the third plant 9 in the left-right direction are greater than or equal to 28 meters and less than or equal to 32 meters. When the first steam turbine 2 and the second steam turbine 3 are arranged in a translational manner, since two locations of circulating water pipe foundation pits need to be reserved, the length H2 of the first plant 7 in the left-right direction is relatively large and generally needs to be set to 60 meters. In this embodiment, since the first steam turbine 2 and the second steam turbine 3 are arranged relative to each other, the first steam turbine 2 and the second steam turbine 3 can share a water pipe foundation pit. Therefore, in this embodiment, the length H2 of the first plant 7 in the left-right direction can be about 8 meters shorter than the conventional setting, so that the length H2 of the first plant 7 in the left-right direction in this embodiment is greater than or equal to 48 meters and less than or equal to 52 meters, saving the overall floor space of the distributed energy station plant.

[0025] In this embodiment, a beam structure is provided on the top of the first foundation pit, and a power distribution room is provided on the upper end of the beam structure. Specifically, the power distribution room is provided on the upper end of the beam structure and is located in the first factory building 7.

[0026] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.

Claims

1. A distributed energy station layout structure, It is characterized in that The invention comprises a first gas turbine (1), a first steam turbine (2), a second steam turbine (3), and a second gas turbine (4) which are arranged in sequence from left to right, wherein the first steam turbine (2) is connected to a first circulating water pipe (21) for introducing circulating water into the first steam turbine (2), and the second steam turbine (3) is connected to a second circulating water pipe (31) for introducing circulating water into the second steam turbine (3); A first foundation pit is provided between the first steam turbine (2) and the second steam turbine (3), a water inlet main pipe (5) and a water outlet main pipe (6) are provided in the first foundation pit, the first circulating water pipe (21) and the second circulating water pipe (31) are both arranged in the first foundation pit, and the water inlet of the first circulating water pipe (21) and the water inlet of the second circulating water pipe (31) are both connected to the water inlet main pipe (5), and the water outlet of the first circulating water pipe (21) and the water outlet of the second circulating water pipe (31) are both connected to the water outlet main pipe (6); a beam structure is provided on the top of the first foundation pit, and a power distribution room is provided at the upper end of the beam structure; the distributed energy station layout structure also includes a first plant (7) and a first power distribution room (7) and a power distribution room (7) respectively arranged on the first foundation pit; A second plant (8) and a third plant (9) are provided on both sides of the plant (7); the first steam turbine (2) and the second steam turbine (3) are both arranged in the first plant (7), the first gas turbine (1) is arranged in the second plant (8), and the second gas turbine (4) is arranged in the third plant (9); a first waste heat boiler (81) is provided outside the second plant (8), and a second waste heat boiler (91) is provided outside the third plant (9); a water outlet of the first waste heat boiler (81) and a water outlet of the second waste heat boiler (91) are both connected to the water inlet main pipe (5), and a water inlet of the first waste heat boiler (81) and a water inlet of the second waste heat boiler (91) are both connected to the water outlet main pipe (6).

2. The arrangement structure of the Bu-type energy station according to claim 1, It is characterized in that The length of the first factory building (7) in the left-right direction is greater than or equal to 48 meters and less than or equal to 52 meters.

3. The distributed energy station arrangement structure according to claim 1, It is characterized in that The length of the second factory building (8) in the left-right direction is greater than or equal to 28 meters and less than or equal to 32 meters.

4. The distributed energy station arrangement structure according to claim 1, It is characterized in that The length of the third factory building (9) in the left-right direction is greater than or equal to 28 meters and less than or equal to 32 meters.

5. The distributed energy station arrangement structure according to claim 1, It is characterized in that The first foundation pit is arranged in the middle of the first factory building (7), and a first condensate pump (22) and a second condensate pump (32) are respectively provided on the left and right sides of the first factory building (7), the first condensate pump (22) is connected to the first steam turbine (2) to cool the steam in the first steam turbine (2); the second condensate pump (32) is connected to the second steam turbine (3) to cool the steam in the second steam turbine (3).