A shield construction method for water-rich soft soil liquefaction stratum

By using thick ground connecting walls, horizontal freezing reinforcement and three sealing devices in the water-rich soft soil liquefied stratum, combined with emergency decompression and dewatering wells and monitoring and control, the geological environment impact and construction complexity problems during the shield tunneling construction were solved. , improve construction efficiency and safety, and reduce costs.

CN115163099BActive Publication Date: 2024-10-29CCCC TUNNEL ENG CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202211024178.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-25
Publication Date
2024-10-29
Estimated Expiration
2042-08-25

AI Technical Summary

Technical Problem

In water-rich soft soil liquefied strata, the initial construction of shield tunnels faces problems such as surface uplift and collapse, water and sand gushing from cave doors, etc. The existing reinforcement measures are complex, time-consuming, and costly, affecting construction efficiency and safety.

Method used

Thick ground connecting wall end reinforcement, horizontal freezing reinforcement and three sealing devices are used, combined with emergency decompression and dewatering wells and monitoring and control, to ensure the safe passage of the shield machine and synchronous grouting.

Benefits of technology

Through end freezing reinforcement, three water-stop seals and monitoring and control, the possibility of danger is reduced, construction efficiency is improved, costs are reduced, and safety is ensured.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

A shield starting construction method for water-rich soft soil liquefied strata. The present invention includes the following steps: S1 end starting reinforcement; S2 tunnel door sealing installation; S3 tunnel door chiseling, shield machine penetrating into the face, and assembling negative ring; S4 shield tail passes through the starting tunnel opening and starts synchronous grouting; in S1, the shield starting end adopts thick ground connecting wall, and the end reinforcement adopts horizontal grouting and horizontal freezing reinforcement; S2 includes tunnel door water stop device installation, bracket installation and reaction frame installation, and the tunnel door water stop device installation includes the layout of tunnel door embedded parts and three sealing settings; the bracket is installed on the left and right sides of the tunnel door and is reinforced by I-beams; the longitudinal axis of the shield machine coincides with the design axis of the tunnel; the end face of the reaction frame is perpendicular to the axis of the bracket. Its beneficial effect is to form multiple safety protection measures, reduce the possibility of dangerous situations, and at the same time, it is not affected by geology and surrounding environment, does not need to be relocated or traffic diverted, is convenient for construction, and has high construction efficiency, low cost and high safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a shield construction method, in particular to a shield construction method for a water-rich soft soil liquefied stratum, and belongs to the technical field of shield construction. Background Art

[0002] With the development of urban underground space development technology, shield construction has been widely promoted and applied due to its high degree of mechanization, small impact on the ground environment, safety and high efficiency. During the shield construction process, affected by geological conditions, tunnel direction and other factors, the initial stage often faces difficulties such as surface uplift and collapse, water and sand gushing from the tunnel gate, etc., especially in water-rich soft soil liquefaction strata. Due to the disturbance of the stratum and the abundance of groundwater, the soil is highly fluid, and there are dense surrounding buildings and structures. It is easy to have problems such as instability of the initial posture of the construction site, damage to the shield machine head and buildings and structures.

[0003] The processing flow of the shield starting section includes: end starting reinforcement → tunnel door sealing installation → tunnel door chiseling (remaining inner steel bars) → chiseling inner steel bars, shield machine entering the face, assembling negative ring → shield tail passing through the starting tunnel, and starting synchronous grouting. In water-rich soft soil layers, corresponding soil reinforcement measures are often implemented in advance at the starting end, such as high-pressure rotary jet piles, three-axis mixing piles, etc., to improve self-stability through soil reinforcement and improvement, thereby ensuring the safe and smooth start of the shield. The above-mentioned end starting reinforcement occupies a large construction site, and often requires traffic diversion in urban environments.

[0004] At present, due to the existence of various pipelines and underground facilities in urban underground spaces, the implementation of the above-mentioned reinforcement measures is bound to lead to problems such as pipeline relocation, complex construction, long construction period and high construction costs, which will affect the construction efficiency of shield tunneling, increase construction costs and cause many problems affecting safe construction. At the same time, the installation of tunnel gate sealing, that is, tunnel gate sealing and water stopping, is directly related to the possibility of dangerous situations. In addition, it is necessary to formulate deformation warning values ​​for buildings and ground according to the structural types of adjacent important buildings, their sensitivity to settlement and the allowable value of settlement, timely feedback information, and follow-up grouting and supplementary grouting. In this way, when grouting on the ground, there are problems such as the inability to implement fixed-point grouting, large grouting volume and high construction cost. Summary of the invention

[0005] In order to overcome the above-mentioned deficiencies in the existing shield initial construction in water-rich soft soil liquefaction strata, the present invention provides a shield initial construction method in water-rich soft soil liquefaction strata.

[0006] The technical solution adopted by the present invention to solve its technical problems is: a shield starting construction method for water-rich soft soil liquefied strata, comprising the following steps: S1, starting reinforcement of the end; S2, installation of tunnel door seal; S3, chiseling out the tunnel door, the shield machine penetrating into the heading face, and assembling the negative ring; S4, the shield tail passes through the starting tunnel opening and starts synchronous grouting.

[0007] In step S1, a thick ground-connected wall is used at the starting end of the shield, and horizontal grouting and horizontal freezing reinforcement are used for the end reinforcement, wherein the horizontal freezing reinforcement uses a "cup-shaped" freezing wall to reinforce the soil.

[0008] In step S2, the tunnel door sealing installation includes the installation of the tunnel door water stop device, the installation of the bracket and the installation of the reaction frame.

[0009] A. The installation of the tunnel gate water stop device includes: layout of tunnel gate embedded parts and three-stage sealing settings, including:

[0010] A1. Arrangement of embedded parts for portals, including the setting of annular steel plates at the portal ends and embedded steel bars to maintain rigid joints between the portal structure and the end wall;

[0011] A2. Set up three seals at the starting tunnel entrance

[0012] For the first seal, a reverse shield tail brush is fixed inside the steel ring of the tunnel gate;

[0013] The second seal, the extended steel ring is connected to the portal steel ring by bolts and welding, the extended steel ring corresponds to the hole of the rubber curtain, and the rubber curtain is connected to the folding plate by bolts;

[0014] The third seal is to install a rubber curtain, a flap and a circular ring plate on the outside of the extended steel ring away from the tunnel gate. The extended steel ring and the circular ring plate form a steel box structure, and the circular ring plate is provided with grouting holes.

[0015] B. The bracket is installed by using I-beams to reinforce the left and right sides of the portal, and the double I-beams at the front end are connected to the structural wall.

[0016] C. The reaction frame is installed after the shield main machine is assembled, wherein: the longitudinal axis of the shield machine coincides with the design axis of the tunnel; the end face of the reaction frame is perpendicular to the axis of the bracket, and the verticality error between the end face of the reaction frame and the axis of the bracket is ≤±3mm; the negative ring segment fits tightly with the reaction frame support ring.

[0017] In step S1, the starting tunnel is provided with horizontal freezing holes, temperature measuring holes and horizontal exploration holes, wherein the horizontal exploration holes are symmetrically distributed between the inner circle freezing holes and the center of the tunnel, between the middle circle and the inner circle freezing holes, and between the middle circle and the steel ring based on the center line of the tunnel.

[0018] Preferably, the diameter of the horizontal exploration hole is φ40~63mm, and the depth of the horizontal exploration hole is ≥1000mm.

[0019] In step S1, the average temperature of the frozen wall is ≤-12°C, and the average temperature at the junction of the frozen wall and the continuous wall is ≤-5°C; the uniaxial compressive strength of the frozen soil is ≥3.6MPa, the flexural strength is ≥2MPa, and the shear strength is ≥1.5MPa.

[0020] In step S1, the size of the ground connection wall at the starting end of the shield is 1200±100mm; the horizontal freezing adopts a "cup-shaped" freezing wall to reinforce the soil, the inner circle reinforcement length of the horizontal freezing of the tunnel portal is ≥4m, and the thickness of the "cup-shaped" freezing wall on the outside of the shield machine is ≥2m and the length is ≥11m.

[0021] After the initial end is reinforced in step S1, an emergency pressure relief well is set between the frozen bodies.

[0022] Start dewatering in the dewatering well and lower the water level to below 1m below the tunnel bottom. Stop dewatering after the shield tunneling completes the casting of the portal ring beam and reaches the designed strength. At the same time, add more than 2 horizontal exploration holes at the bottom of the portal and on the side walls on both sides of the portal.

[0023] In step S2, rubber curtains and folding plates are used in the first and second sealing layers, and more than two grouting holes are evenly arranged on the steel box.

[0024] A reverse shield tail brush is added inside the tunnel portal steel ring, and a circle of arc-shaped plug plates is arranged between the shield body of the reverse shield tail brush and the steel box.

[0025] When the shield tail passes through the starting hole and starts synchronous grouting in step S4, monitoring and control are performed.

[0026] The monitoring control includes: monitoring point arrangement and control processing, wherein:

[0027] The monitoring points are arranged in the form of a monitoring section orthogonal to the shield axis, with the two initial shield axes as the center and the monitoring points spread out to the left and right sides; the points are arranged overlapping in the overlapping area of ​​the settlement zone between the two axes, and after the monitoring of one line is completed, monitoring will continue when the other line passes through.

[0028] The control process includes: establishing a monitoring network, analyzing monitoring data and feeding back monitoring data, wherein:

[0029] The monitoring network is established to mark the pipe segments, shield machines and reinforcement area contours at the end positions; direct settlement observation points are set up near the buried buildings, and deformation warning values ​​for buildings and the ground are formulated based on the structural type of the buildings, their sensitivity to settlement, and the allowable value of settlement.

[0030] The monitoring data analysis is performed on the monitoring data of the monitoring point in front of the shield. When the ground deformation at the monitoring point in front of the shield is within the range of -5mm to +5mm, and the ground deformation is within the range of -30mm to +10mm when the shield passes, the shield construction proceeds normally; when the ground deformation at the monitoring point in front of the shield exceeds -5mm to +5mm, or the ground deformation is controlled to exceed the range of -30mm to +10mm when the shield passes, secondary grouting is performed.

[0031] The monitoring data feedback will feed back the monitoring data to the shield driver in a timely and accurate manner during the construction of the shield starting section.

[0032] The beneficial effects of the present invention are that multiple safety protection measures are formed through end freezing reinforcement, three water-stop seals and the setting of a steel box at the beginning of the shield, thereby reducing the possibility of dangerous situations. At the same time, it is not affected by the geology and surrounding environment, does not require relocation or traffic diversion, is convenient for construction, and has high construction efficiency, low cost and high safety. DETAILED DESCRIPTION

[0033] The present invention will be further described below in conjunction with the embodiments. However, those skilled in the art should be aware that the present invention is not limited to the specific embodiments listed, and all embodiments should be included in the protection scope of the present invention as long as they conform to the spirit of the present invention.

[0034] In the description of the present invention, it should be noted that the terms "vertical", "up", "down", "left", "right", "horizontal", etc., indicating directions or positional relationships, are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.

[0035] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0036] The present invention provides a shield construction method for water-rich soft soil liquefaction stratum, comprising the following steps:

[0037] S1, end reinforcement;

[0038] S2, installation of door seal;

[0039] S3, the tunnel door is chiseled out, the shield machine penetrates the tunnel face, and the negative ring is assembled;

[0040] S4. The shield tail passes through the starting hole and starts synchronous grouting.

[0041] In step S1, a thick ground-connected wall is used at the starting end of the shield, and horizontal grouting and horizontal freezing reinforcement are used for the end reinforcement, wherein the horizontal freezing reinforcement uses a "cup-shaped" freezing wall to reinforce the soil.

[0042] Further, in step S1, the starting tunnel is provided with horizontal freezing holes, temperature measuring holes and horizontal exploration holes, wherein the horizontal exploration holes are symmetrically distributed between the inner circle freezing holes and the center of the tunnel, between the middle circle and the inner circle freezing holes, and between the middle circle and the steel ring based on the center line of the tunnel.

[0043] Preferably, the size of the horizontal exploration hole is φ40~63mm, and the depth of the horizontal exploration hole is ≥1000mm.

[0044] Preferably, the designed average temperature of the frozen wall is ≤-12°C, and the average temperature at the junction of the frozen wall and the continuous wall is ≤-5°C; the uniaxial compressive strength of the frozen soil is ≥3.6MPa, the flexural strength is ≥2MPa, and the shear strength is ≥1.5MPa.

[0045] Preferably, the size of the ground connection wall at the starting end of the shield is 1200±100mm.

[0046] Preferably, the horizontal freezing adopts a "cup-shaped" freezing wall to reinforce the soil, and the inner ring reinforcement length of the horizontal freezing design of the tunnel portal is ≥4m; the "cup-shaped" freezing wall thickness on the outer side of the shield machine is ≥2m and the length is ≥11m, ensuring that the shield body closes the tunnel portal before leaving the reinforcement area.

[0047] After completing the initial reinforcement of the end in step S1, an emergency decompression well is set between the frozen bodies, wherein the bottom of the well is 3±0.1m below the bottom of the reinforcement area.

[0048] Start dewatering in the dewatering wells according to on-site needs. When the water level drops to below 1m below the tunnel bottom, stop dewatering after the shield tunneling completes the casting of the portal ring beam and reaches the designed strength. At the same time, add more than 2 horizontal exploration holes at the bottom of the portal and on the side walls on both sides of the portal.

[0049] In step S2, the tunnel door sealing installation includes the tunnel door water stopping device installation, the bracket installation and the reaction frame installation.

[0050] A. The installation of the tunnel gate water stop device includes: layout of tunnel gate embedded parts and three-stage sealing settings, including:

[0051] A1. Arrangement of embedded parts for portals, including the setting of annular steel plates at the ends of portals and embedded steel bars to maintain a rigid joint between the portal structure and the end wall.

[0052] A2. Set up three seals at the starting tunnel entrance

[0053] For the first seal, a reverse shield tail brush is fixed inside the steel ring of the tunnel gate;

[0054] The second seal, the extended steel ring is connected to the portal steel ring by bolts and welding, the extended steel ring corresponds to the hole of the rubber curtain, and the rubber curtain is connected to the folding plate by bolts;

[0055] The third seal is to install a rubber curtain, a flap and a circular ring plate on the outside of the extended steel ring away from the tunnel gate. The extended steel ring and the circular ring plate form a steel box structure, and the circular ring plate is provided with grouting holes.

[0056] B. The bracket is installed by using I-beams to reinforce the left and right sides of the portal, and the double I-beams at the front end are connected to the structural wall.

[0057] C. The reaction frame is installed after the shield main machine is assembled, wherein: the longitudinal axis of the shield machine should coincide with the design axis of the tunnel; the end face of the reaction frame is perpendicular to the axis of the bracket, and the verticality error between the end face of the reaction frame and the axis of the bracket is ≤±3mm, so that the negative ring segment and the reaction frame support ring fit tightly.

[0058] Further, in step S2, the first and second seals are made of rubber curtains and folding plates, and a plurality of grouting holes are evenly arranged on the steel box, and the grouting holes are used for initial emergency plugging. A reverse shield tail brush is added inside the steel ring of the tunnel gate, and a circle of arc-shaped plug plates is arranged between the shield body of the reverse shield tail brush and the steel box.

[0059] When the shield tail passes through the starting hole and starts synchronous grouting in step S4, monitoring and control are performed, and the monitoring and control includes: monitoring point arrangement and control processing, wherein:

[0060] The monitoring points are arranged in the form of a monitoring section orthogonal to the shield axis, with the two initial shield axes as the center and the monitoring points spread out to the left and right sides; the points are arranged overlapping in the overlapping area of ​​the settlement zone between the left and right axes, and after the monitoring of one line is completed, monitoring will continue when the other line passes through.

[0061] The control process includes: establishing a monitoring network, analyzing monitoring data and feeding back monitoring data, wherein:

[0062] The monitoring network is established to mark the pipe segments, shield machines and reinforcement area contours at the end positions; direct settlement observation points are set up for buried adjacent structures, and deformation warning values ​​for structures and ground are formulated based on the structural types of structures, their sensitivity to settlement, and the allowable value of settlement. A complete monitoring network is established to provide timely feedback and to conduct timely follow-up grouting and supplementary grouting.

[0063] The monitoring data analysis is conducted on the monitoring data of the monitoring point in front of the shield. When the ground deformation at the monitoring point in front of the shield is within the range of -5mm to +5mm, and the ground deformation when the shield passes is within the range of -30mm to +10mm, the shield construction proceeds normally; when the ground deformation at the monitoring point in front of the shield exceeds -5mm to +5mm, or the ground deformation is controlled to exceed the range of -30mm to +10mm when the shield passes, secondary grouting should be carried out.

[0064] The monitoring data feedback will feed back the monitoring data to the shield driver in a timely and accurate manner during the construction of the shield starting section, so that the shield driver can adjust the construction parameters in a timely manner according to the situation reflected on the ground.

[0065] Example:

[0066] S1, end reinforcement

[0067] (1) A 1200 mm thick ground-connected wall is used at the starting end of the shield tunnel, and the end is reinforced by horizontal grouting and horizontal freezing.

[0068] (2) The starting tunnel is arranged with 58 horizontal freezing holes, 8 temperature measuring holes and 11 horizontal exploration holes (3, 3 and 5 horizontal exploration holes are drilled between the inner circle freezing holes and the center of the tunnel, between the middle circle and the inner circle freezing holes, and between the middle circle and the steel ring, respectively. The horizontal exploration hole specifications are φ40~63mm and the horizontal exploration hole length is ≥1000mm). The average temperature of the frozen wall is ≤-12℃, and the average temperature at the junction with the continuous wall is ≤-5℃. The uniaxial compressive strength of the frozen soil is 3.6MPa, the flexural strength is 2MPa, and the shear strength is 1.5MPa.

[0069] (3) Horizontal freezing uses a "cup-shaped" freezing wall to reinforce the soil. The inner ring reinforcement length of the horizontal freezing design of the tunnel portal is 4m, and the thickness of the cup wall freezing wall on the outer side of the shield machine is 2m, with a total length of 11m, to ensure that the shield can close the tunnel portal before leaving the reinforcement area, ensuring the safety of the start.

[0070] Six emergency decompression wells are set up between the frozen bodies, and the bottom of the decompression wells is 3m below the bottom of the reinforcement area. At the same time, decompression wells are started to dewater according to the needs of on-site construction, and dewatering is stopped when the water level drops to 1m below the bottom of the tunnel, the shield tunneling completes the pouring of the tunnel gate ring beam and reaches the strength requirements.

[0071] S2. Tunnel door seal installation

[0072] The installation of tunnel door sealing includes: installation of tunnel door water stop device, installation of bracket and installation of reaction frame, among which the installation of tunnel door water stop device includes:

[0073] (1) Arrangement of portal embedded parts, including the setting of annular steel plates at the portal ends and embedded steel bars to maintain a rigid joint between the portal structure and the end wall.

[0074] (2) Three-line seal design: add a set of steel boxes at the starting tunnel portal to form three lines of seal.

[0075] Firstly, as the first seal, a circle of tunnel gate brushes is welded at 400±50mm inside the tunnel gate steel ring; as the second seal, an extended steel ring with a length of 400±50mm is used to correspond to the holes of the rubber curtain, and the rubber curtain is connected to the folding pressure plate by bolts; as the third seal, a rubber curtain, a flap and a circular ring plate are installed on the outside of the extended steel ring away from the tunnel gate. The extended steel ring and the circular ring plate form a steel box structure, and grouting holes are arranged on the circular ring plate.

[0076] (3) Bracket installation: I-beams are used to reinforce the left and right sides of the portal, and the double I-beams at the front end are connected to the structural wall.

[0077] (4) Installation of the reaction frame: The reaction frame should be installed after the main shield machine is assembled, where: the longitudinal axis of the shield machine coincides with the design axis of the tunnel; the end face of the reaction frame is perpendicular to the axis of the starting bracket, and the verticality error is ≤±3mm, so that the negative ring segment and the reaction frame support ring fit tightly.

[0078] Specifically, the layout and construction control of the embedded parts of the tunnel gate are as follows:

[0079] The tolerance of the inner diameter of the embedded steel ring is +10~+20mm; when installing the embedded steel ring: the verticality error is ≤±10mm, the lateral inclination error is ≤±10mm, the plane position error is ≤±10mm, and the elevation error is ≤±10mm. The steel ring must be firmly embedded in the concrete to avoid looseness that affects its use.

[0080] Before the shield machine enters the hole, bolts, curtain rubber plates, annular plates, fixed plates and flaps are installed in sequence on the outer ends of the embedded steel rings, and finally the nuts are tightened.

[0081] The embedded parts mainly include: an annular steel plate at the end of the portal, embedded steel bars to ensure the rigid connection between the portal structure and the end wall, etc. The outer ring diameter of the annular steel plate is 7000mm, and the inner ring diameter is 6700mm. In order to firmly embed the annular plate into the end wall structure, a C16 anchor bar is welded on the back of the annular plate at an interval of about 2.5°. After the annular steel plate is processed and formed, it will be embedded in time when the relevant project is under construction.

[0082] Specifically, the construction of the three-sealing setting is carried out in two steps:

[0083] During the construction of the starting end wall, the embedded parts of the starting tunnel must be buried well. During the burying process, the embedded parts must be connected with the end wall structural steel bars.

[0084] Before the shield is officially started, clean the ballast soil at the tunnel entrance and weld the whole circle of tunnel door brushes in time, install the rubber curtain, tunnel door brush, curtain, and extended steel ring. The installation order is to weld the tunnel door brush first and then install the M20 bolts. Align the rubber curtain with the bolts by hole to complete the installation of the curtain and extended steel ring; then install the rubber rolling curtain, circular ring plate and flap at the rear of the extended steel ring, and tighten the nuts; finally, set 6 Ø80mm grouting holes on the steel box, which are used for emergency plugging at the start. After the shield body completely enters the formation, a circle of arc steel plate is welded between the negative ring segment and the steel box to seal the tunnel door, ensuring safety and stability during the start-up process in the water-rich sand formation.

[0085] Specifically, during bracket installation,

[0086] The dimensions of the bracket are 250 mm in height, 5050 mm in width, and 3225 mm in radius. The material is Q235, and the track is 43# rail.

[0087] The bracket is reinforced in the following manner: 10 20b I-beams are used for reinforcement on the left and right sides respectively, and 4 double-jointed 32b I-beams are used for the front end to connect with the structural wall.

[0088] Specifically, in the installation of the reaction frame,

[0089] The dimensions of the reaction frame are 6.44m wide, 7.825m high, with a total weight of approximately 13 tons, and the material is Q235.

[0090] After the shield main machine is assembled, the reaction frame is installed: the reaction frame installation principle is that the longitudinal axis of the reaction frame should coincide with the tunnel design axis; the end face of the reaction frame should be perpendicular to the axis of the starting bracket, and the verticality error should be controlled within ±3mm to ensure that the negative ring segment and the reaction frame support ring fit tightly.

[0091] In addition, two exploration holes are added at the bottom of the tunnel portal and on the side walls on both sides of the tunnel portal to ensure the safety of the tunnel portal removal process.

[0092] S3. The tunnel gate is chiseled out, the shield machine penetrates the heading face, and the negative ring is assembled.

[0093] S4. The shield tail passes through the starting hole and starts synchronous grouting.

[0094] In step S4, monitoring and control are performed when the shield tail passes through the starting hole and starts synchronous grouting.

[0095] Monitoring and control include monitoring point arrangement and control processing.

[0096] (1) Monitoring point arrangement: The monitoring points are arranged in the form of a monitoring section orthogonal to the shield axis. The monitoring points are arranged on both sides of the two starting shield axes. The points are arranged overlapping in the overlapping area of ​​the settlement zone between the left and right axes. After the monitoring of one line is completed, the monitoring will continue when the other line passes through.

[0097] (2) Control processing includes: establishment of monitoring network, monitoring data analysis and monitoring data feedback, including:

[0098] 1) Establish a monitoring network

[0099] Mark the segments, shield machines, and reinforcement area contours at the end positions;

[0100] Establish direct settlement observation points for buried adjacent buildings and structures, formulate building and ground deformation warning values ​​based on the building structure type, its sensitivity to settlement, and the allowable value of settlement, establish a complete monitoring network, provide timely feedback, and conduct timely follow-up grouting and supplementary grouting.

[0101] 2) Monitoring data analysis

[0102] Analysis of the monitoring data from the monitoring point in front of the shield shows that when the ground deformation at the monitoring point in front of the shield does not exceed -5mm~+5mm, and the ground deformation is within the range of -30mm~+10mm when the shield passes, synchronous grouting is carried out; when the ground deformation at the monitoring point in front of the shield exceeds -5mm~+5mm, or the ground deformation is controlled to exceed the range of -30mm~+10mm when the shield passes, secondary grouting should be carried out.

[0103] 3) During the construction of the shield starting section, the monitoring data will be fed back to the shield driver in a timely and accurate manner, so that the shield driver can adjust the construction parameters in time according to the situation reflected on the ground.

[0104] It should be noted that the surface subsidence monitoring adopts the geometric leveling method. The leveling monitoring network is established based on the elevation control points provided by the owner. The measurement is carried out in accordance with the national second-class leveling measurement specifications. The monitoring points are observed after, before, before and after the closed leveling route.

[0105] In addition, the soil reinforcement adopts horizontal freezing reinforcement + horizontal grouting method, and the horizontal freezing length is 11m; 11 horizontal exploration holes are selected, and the reinforcement situation is determined according to the water flow of the horizontal exploration holes, and the freezing effect is verified.

[0106] At the same time, the end frozen body is divided into two sections, namely the full-section frozen body adjacent to the enclosure structure and the end of the frozen body, and 6 spare pressure relief wells are arranged at intervals; the steel box starting method is adopted, the rubber curtain is changed from one layer to two layers, the middle cavity is filled with inert slurry, and the front and rear rubbers are waterproofed and sealed with folding pressure plates and other measures, and an arc steel plate is added to the back water surface of the 0-ring segment. After the shield machine is completely entered into the tunnel, a full-ring vertical arc steel plate is used to weld the arc steel plate behind the 0 ring to the steel box for sealing, which greatly improves the sealing of the tunnel.

[0107] The shield construction method for starting construction in water-rich soft soil liquefied strata of the present invention is adopted. Under the condition of fully understanding the adverse geological conditions of water-rich soft soil, adjacent important buildings and structures, and pipeline settings, firstly, a reinforcement method of horizontal freezing + horizontal grouting is adopted, and at the same time, an emergency decompression and dewatering well is used as an auxiliary; secondly, the tunnel portal adopts a design method of "three seals + one emergency (decompression and dewatering well)", and after the start is completed, the curved steel plate on the back water surface of the zero-ring segment is welded to the steel box in an entire ring, which greatly improves the sealing performance of the tunnel portal; the grouting holes reserved on the steel box can be used to directly grout the corresponding parts under the tunnel in time, without the need for construction on the ground, and the range can be quickly locked, the grouting amount can be reduced, and the construction cost can be controlled.

[0108] It should be noted that the above-mentioned embodiments illustrate rather than limit the invention, and that those skilled in the art will be able to design many alternative embodiments without departing from the scope of the claims of this patent.

Claims

1. A shield construction method for water-rich soft soil liquefaction strata, comprising the following steps: S1, end reinforcement; S2, installation of door seal; S3, the tunnel door is chiseled out, the shield machine penetrates the tunnel face, and the negative ring is assembled; S4, the shield tail passes through the starting hole and starts synchronous grouting; Its characteristics are: exist In the step S1, a thick ground connecting wall is used at the starting end of the shield, and horizontal grouting and horizontal freezing reinforcement are used for the end reinforcement, wherein the horizontal freezing reinforcement uses a cup-shaped freezing wall to reinforce the soil; In step S2, the tunnel door sealing installation includes the installation of the tunnel door water stop device, the installation of the bracket and the installation of the reaction frame. A. The installation of the tunnel gate water stop device includes: layout of tunnel gate embedded parts and three-stage sealing settings, including: A1. Arrangement of embedded parts for portals, including the setting of annular steel plates at the portal ends and embedded steel bars to maintain rigid joints between the portal structure and the end wall; A2. Set up three seals at the starting tunnel entrance For the first seal, a reverse shield tail brush is fixed inside the steel ring of the tunnel gate; The second seal, the extended steel ring is connected to the portal steel ring by bolts and welding, the extended steel ring corresponds to the hole of the rubber curtain, and the rubber curtain is connected to the folding plate by bolts; The third seal is to install a rubber curtain, a flap and a circular plate on the side of the extended steel ring away from the tunnel gate. The extended steel ring and the circular plate form a steel box structure, and the circular plate is provided with grouting holes; B. The bracket is installed by using I-beams to reinforce the left and right sides of the portal, and the front double I-beams are connected to the structural wall; C. The reaction frame is installed after the shield machine is assembled, wherein: the longitudinal axis of the shield machine coincides with the design axis of the tunnel; the end face of the reaction frame is perpendicular to the axis of the bracket, and the verticality error between the end face of the reaction frame and the axis of the bracket is ≤±3mm; the negative ring segment is tightly fitted with the reaction frame support ring; In step S1, the starting tunnel is provided with horizontal freezing holes, temperature measuring holes, and horizontal exploration holes, wherein the horizontal exploration holes are symmetrically distributed between the inner circle freezing holes and the center of the tunnel, between the middle circle and the inner circle freezing holes, and between the middle circle and the steel ring based on the center line of the tunnel; When the shield tail passes through the starting hole and starts synchronous grouting in step S4, monitoring and control are performed. The monitoring control includes: monitoring point arrangement and control processing, wherein: The monitoring points are arranged in the form of a monitoring section orthogonal to the shield axis, with the two starting shield axes as the center and the monitoring points spread out to the left and right sides; the points are arranged to overlap in the overlapping area of ​​the settlement zone between the two axes, and after one line is monitored, the monitoring continues when the other line passes through; The control process includes: establishing a monitoring network, analyzing monitoring data and feeding back monitoring data, wherein: The monitoring network is established to mark the pipe segments, shield machines, and reinforcement area contours at the end positions; direct settlement observation points of adjacent buried structures are set up, and warning values ​​for deformation of structures and ground are formulated according to the structural types of structures, their sensitivity to settlement, and the allowable value of settlement; The monitoring data analysis is performed on the monitoring data of the monitoring point in front of the shield. When the ground deformation at the monitoring point in front of the shield is within the range of -5mm to +5mm, and the ground deformation is within the range of -30mm to +10mm when the shield passes, the shield construction is carried out normally; when the ground deformation at the monitoring point in front of the shield exceeds -5mm to +5mm, or the ground deformation is controlled to exceed the range of -30mm to +10mm when the shield passes, secondary grouting is performed; The monitoring data feedback will feed back the monitoring data to the shield driver in a timely and accurate manner during the construction of the shield starting section.

2. The shield construction method for the water-rich soft soil liquefaction stratum according to claim 1, Its characteristics are: The diameter of the horizontal exploration hole is φ40~63mm, and the depth of the horizontal exploration hole is ≥1000mm.

3. The shield construction method for the water-rich soft soil liquefaction stratum according to claim 1, Its characteristics are: In step S1, the average temperature of the frozen wall is ≤-12°C, and the average temperature at the junction of the frozen wall and the continuous wall is ≤-5°C; the uniaxial compressive strength of the frozen soil is ≥3.6MPa, the flexural strength is ≥2MPa, and the shear strength is ≥1.5MPa.

4. The shield construction method for the water-rich soft soil liquefaction stratum according to claim 1, Its characteristics are: In step S1, The dimension of the ground connection wall at the starting end of the shield is 1200±100mm; The horizontal freezing adopts cup-shaped freezing wall to reinforce the soil, the inner circle reinforcement length of the horizontal freezing of the tunnel portal is ≥4m, and the cup-shaped freezing wall thickness on the outer side of the shield machine is ≥2m and the length is ≥11m.

5. The shield construction method for water-rich soft soil liquefaction stratum according to claim 1, Its characteristics are: After completing the reinforcement of the shield starting end in step S1, an emergency decompression well is set between the frozen bodies.

6. The shield construction method for water-rich soft soil liquefaction strata according to claim 5, Its characteristics are: Start dewatering in the dewatering well and lower the water level to below 1m below the tunnel bottom. Stop dewatering after the shield tunneling completes the casting of the portal ring beam and reaches the designed strength. At the same time, add more than 2 horizontal exploration holes at the bottom of the portal and on the side walls on both sides of the portal.

7. The shield construction method for water-rich soft soil liquefaction strata according to claim 1, Its characteristics are: In step S2, rubber curtains and folding plates are used in the first and second sealing layers, and more than two grouting holes are evenly arranged on the steel box.

8. The shield construction method for water-rich soft soil liquefaction strata according to claim 7, Its characteristics are: A reverse shield tail brush is added inside the tunnel gate steel ring, and a circle of arc-shaped plug plates is set between the shield body of the reverse shield tail brush and the steel box.

Citation Information

Patent Citations

  • Method for forming shield tunnel construction maintenance surroundings

    CN101251016A

  • Underneath passing water supply pipe and river starting and receiving construction method of water-rich sand layer shield tunneling machine

    CN113216987A