Construction method of tunnel gully section
By sequentially drilling grouting holes, flushing, water pressure testing and anchoring, and using anchor cables for segmented grouting reinforcement, the problem of potential safety hazards of TBM during the excavation of the tunnel gully section has been solved, and the stability of the surrounding rock has been improved. safety and construction efficiency, reducing costs.
Patent Information
- Application Number
- CN202210869361.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-22
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-07-22
AI Technical Summary
TBM has safety hazards during the excavation process of the tunnel gully section. The construction time is long, the cost is high, and the equipment is easily damaged, making it difficult to pass smoothly.
Drill grouting holes in sequence, select appropriate flushing methods according to geological conditions, conduct pressure water testing and anchoring, use anchor cables for segmented grouting reinforcement, and conduct effect inspections.
Through surface pre-grouting reinforcement, the integrity and stability of the surrounding rock are enhanced, the risk of loosening and collapse of the surrounding rock is reduced, the safety and efficiency of TBM excavation is improved, and the construction cost is reduced.
Smart Images

Figure CN115370371B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of civil engineering technology, and in particular to a method for constructing a tunnel gully section. Background Art
[0002] The full-face tunnel boring machine (TBM) is an intelligent equipment commonly used in mechanized construction. During the TBM excavation process, tunnel fault zones may be encountered. Tunnel fault zones often occur where the top of the tunnel is a gully. The inventors found that when TBM passes through a tunnel fault zone, there are great safety hazards, long excavation time, high costs, and even possible damage to the TBM equipment and difficulty in passing smoothly. Therefore, how to reduce the safety hazards of TBM excavation construction in the gully section of the tunnel is an urgent problem to be solved. Summary of the invention
[0003] The main purpose of this application is to provide a method for constructing a tunnel gully section, and how to reduce the potential safety hazards of TBM excavation construction in the tunnel gully section is an urgent problem to be solved.
[0004] In order to achieve the above-mentioned purpose, a tunnel gully section construction method is provided according to the present application.
[0005] The tunnel gully section construction method according to the present application includes: S1: staking out the positions of grouting holes in sequence on the surface of the gully section, and then drilling the grouting holes according to the hole positions in accordance with the principle of sequence encryption; wherein, the rows of grouting holes and the holes of the same row of grouting holes are constructed in two sequences, and the surface of the gully section is the terrain surface above the tunnel; S2: selecting a corresponding drilling flushing method to flush the grouting holes according to different geological conditions and on-site grouting tests, and selecting a corresponding fissure flushing method to flush the fissures in the grouting holes according to different geological conditions; S3: within the first preset time period after the grouting holes are flushed, Water pressure test, wherein a preset proportion of grouting holes are selected from the first-order grouting holes in the second-order construction for single-point water pressure test, and all remaining grouting holes except the preset proportion of grouting holes are subjected to a simple water pressure test; S4: installing grouting anchor cables and anchoring the grouting anchor cables, installing grouting plugs, anchor piers and rigging after the anchoring time reaches the second preset period, and tightening the grouting anchor cables by anchor cable tensioners; wherein W-shaped steel belts are used to connect the grouting anchor cables in the same row; S5: delayed grouting is carried out by segmented grouting method, and grouting is terminated when the preset grouting construction time is reached; S6: after the grouting is completed, the grouting effect is checked.
[0006] Optionally, after the grouting anchor cable is tightened by the anchor cable tensioner, the method further comprises: detecting the pre-tensioning force of the grouting anchor cable; if the pre-tensioning force decreases within a third preset time period, performing secondary tensioning on the grouting anchor cable with the decreased pre-tensioning force.
[0007] Optionally, after drilling the grouting hole, the method further includes: inspecting the grouting hole according to drilling requirements, the drilling requirements including: an axial deviation between an actual construction drilling axis and a preset drilling axis is less than 5°, a deviation between an actual construction hole position of a grouting anchor and a layout hole position corresponding to the grouting hole is less than or equal to 10 cm, and a drilling depth is greater than or equal to a preset drilling depth and less than or equal to the preset drilling depth plus 100 mm.
[0008] Optionally, the borehole flushing method includes open water flushing from the bottom of the hole to the outside of the hole, pressure wind flushing, and wind and water combined flushing, and the fissure flushing method includes pressure water flushing, pressure wind flushing, and wind and water rotation flushing.
[0009] Optionally, the flushing water pressure during flushing of the grouting holes and the cracks in the holes is selected to be 80% of the grouting pressure. If the flushing water pressure is greater than 1MPa, the flushing water pressure is selected to be 1MPa. The flushing wind pressure during flushing of the grouting holes and the cracks in the holes is selected to be 50% of the grouting pressure. If the flushing wind pressure exceeds 0.5MPa, the flushing wind pressure is selected to be 0.5MPa.
[0010] Optionally, the water pressure during the single-point water pressure test and the simple water pressure test is 80% of the grouting pressure. If the water pressure pressure is greater than 1MPa, 1MPa is selected as the water pressure pressure. The duration of the simple water pressure test is 20 minutes, the water pressure flow rate is measured every 5 minutes, and the permeability is calculated based on the last water pressure flow rate value.
[0011] Optionally, during the delayed grouting process, the cement is 42.5MPa sulfate-resistant cement, and the cement slurry is selected from three water-cement ratio levels of 2:1, 1:1, and 0.5:1.
[0012] Optionally, the first preset period is 24 hours, the second preset period is 30 minutes, and the third preset period is 48 hours.
[0013] Optionally, during the construction of the grouting anchor cable, if the pre-tightening force is less than 90% of the preset tensioning force, a new grouting anchor cable is added.
[0014] Optionally, the segment lengths in the segmented grouting method are: 3.0 m for the first segment, 5.0 m for the second segment and below; and the preset grouting construction time is greater than 7 min and less than or equal to 8 min.
[0015] Optionally, the preset proportion of grouting holes is 20% of the grouting holes.
[0016] Optionally, the grouting effect inspection includes: using acoustic waves to measure the wave velocity of the rock mass to inspect the consolidation grouting quality, and conducting a comprehensive assessment based on the borehole water pressure test, geophysical exploration results before and after grouting, grouting construction data, and borehole coring data.
[0017] In the tunnel gully section construction method of the embodiment of the present application, the hole positions of the grouting holes are firstly laid out in sequence on the surface of the gully section, and then the grouting holes are drilled according to the hole positions in accordance with the principle of sequence encryption; wherein, the rows of grouting holes and the holes in the same row of grouting holes are constructed in two sequences, and the surface of the gully section is the gully terrain surface above the tunnel; then, according to different geological conditions and on-site grouting tests, the corresponding drilling flushing method is selected to flush the grouting holes, and according to different geological conditions, the corresponding fissure flushing method is selected to flush the fissures in the grouting holes; after the grouting holes are flushed, the pressure is pressed within the first preset period of time. Water test, wherein a preset proportion of grouting holes are selected from the first-sequence grouting holes in the second-sequence construction for single-point water pressure test, and a simple water pressure test is performed on all the remaining grouting holes except the preset proportion of grouting holes; after the water pressure test, the grouting anchor cables are installed and anchored, and when the anchoring time reaches the second preset period, the grouting plugs, anchor piers and rigging are installed, and the grouting anchor cables are tightened by the anchor cable tensioner; wherein, the grouting anchor cables in the same row are connected by W-shaped steel belts; finally, the segmented grouting method is used for delayed grouting, and the grouting is terminated when the preset grouting construction time is reached; after the grouting is completed, the grouting effect is checked. It can be seen that in the construction method of the embodiment of the present application, when encountering the tunnel gully section, the surrounding rock is first reinforced by grouting reinforcement on the surface of the gully section, which enhances the integrity of the broken surrounding rock, improves the self-bearing capacity of the surrounding rock, and inhibits the loosening and collapse of the surrounding rock. Therefore, it can effectively prevent the TBM from being damaged or buried during the excavation process, reduce construction safety hazards, and improve construction efficiency. In addition, the grouting method selected is the anchor grouting method, which can further enhance the integrity of the surrounding rock compared to the anchor grouting method. In addition, the specific grouting construction process design of the embodiment of the present application is ingenious, the grouting quality is easy to control, and the application environment is friendly. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:
[0019] Figure 1 It is a flow chart of a tunnel gully section construction method provided according to an embodiment of the present application;
[0020] Figure 2 is a cross-sectional view of a tunnel gully section provided according to an embodiment of the present application;
[0021] Figure 3 It is a plane schematic diagram of the grouting hole position provided according to an embodiment of the present application;
[0022] Figure 4-Figure 5 is a cross-sectional view of a pulp hole provided according to an embodiment of the present application;
[0023] Figure 6 It is a schematic diagram of the construction of a grouting anchor cable provided according to an embodiment of the present application.
[0024] In the figure, 1-surface of gully section, 2-grouting hole, 3-hole position, 4-tunnel, 5-Ⅰsequence grouting hole, 6-grouting anchor cable, 7-grouting plug, 8-anchor pier, 9-rigging, 10-hole top line, 11-surrounding rock, 12-axis line, 13-Ⅱsequence grouting hole, 14-grouting section, 15-non-grouting section, 16-anchor agent, 17-grouting pump, 18-grouting barrel. DETAILED DESCRIPTION
[0025] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0026] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0027] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0028] Embodiment 1:
[0029] Combination Figure 1-6, a tunnel gully section construction method of an embodiment of the present application is specifically described: Figure 1 As shown, the method comprises the following steps S1-S6: S1. Locate the hole positions 3 of the grouting holes 2 in sequence on the surface 1 of the gully section, and then drill the grouting holes 2 according to the hole positions according to the principle of sequence encryption; wherein, the rows of the grouting holes 2 and the holes of the same row of grouting holes 2 are divided into two-sequence construction, and the surface 1 of the gully section is the terrain surface above the tunnel 4; S2. Select the corresponding drilling flushing method according to different geological conditions and on-site grouting tests to flush the grouting holes, and select the corresponding fissure flushing method according to different geological conditions to flush the fissures in the grouting holes; S3. Perform pressure flushing within the first preset period after the grouting holes are flushed. Water test, wherein, a preset proportion of grouting holes 2 are selected from the first-order grouting holes 5 in the second-order construction for single-point water pressure test, and all remaining grouting holes 2 except the preset proportion of grouting holes 2 are subjected to a simple water pressure test; S4. The grouting anchor cable 6 is installed and anchored. When the anchoring time reaches the second preset period, the grouting stopper 7, the anchor pier 8 and the rigging 9 are installed, and the grouting anchor cable 6 is tightened by the anchor cable tensioner; wherein, the grouting anchor cables 6 in the same row are connected by W-shaped steel belts; S5. The segmented grouting method is used for delayed grouting, and the grouting is terminated when the preset grouting construction time is reached; S6. After the grouting is completed, the grouting effect is checked.
[0030] For the gully section surface 1 in step S1, a cross-sectional view of the gully section of a tunnel is provided, such as Figure 2 As shown, the cave top line 10 is a straight line corresponding to the inner top of the tunnel 4, the depression above the cave top line 10 is a gully, and above the cave top line 10 is the surrounding rock 11. The surface of the surrounding rock 11 is gully-shaped, that is, the gully section surface 1. In addition, the layout of the hole position 3 of the grouting hole 2 can be specifically carried out by a GPS measuring instrument or a total station. Among them, the GPS measuring instrument is a global positioning system (Global Positioning System, GPS) measuring instrument. According to the GPS measuring instrument or the total station, it can accurately locate and lay out the hole position 3 according to the designed layout point. After the layout of the hole position 3 is completed, the grouting hole 2 can be drilled. When drilling the grouting hole 2, a geological drill is used for drilling. The specific geological drill can be a pneumatic rock drill or a hydraulic rock drill, such as a GY100 rock drill. When drilling, drill downward from the gully surface vertically to the cave top line 10. The depth of the grouting hole 2 is also set in advance, and drilling is carried out according to the preset drilling depth. As Figure 3 As shown, it is a plane schematic diagram of the hole positions 3 of the grouting hole 2. The dotted line in the middle is the axis 12 of the tunnel 4. The hole positions 3 are distributed in the direction of the axis 12 and in the directions on both sides of the axis 12. Figure 3The distance between the middle hole position 3 and the distance between the rows are schematic, and can be adjusted according to actual needs in practical applications. The two-sequence construction in step S1 is to divide the grouting hole 2 into the I-sequence grouting hole 5 and the II-sequence grouting hole 13, and grout the I-sequence grouting hole 5 and the II-sequence grouting hole 13 in order. In addition, after the grouting hole 2 is drilled, the grouting hole 2 is inspected according to the drilling requirements. The drilling requirements include: the actual construction drilling axis and the preset drilling axial deviation are less than 5°, the actual construction hole position 3 of the grouting anchor 6 and the hole position 3 corresponding to the grouting hole 2 The deviation is less than or equal to 10cm, and the drilling depth is greater than or equal to the preset drilling depth and less than or equal to the preset drilling depth plus 100mm. If the drilling requirements are not met, grouting is required before re-drilling. When the drilling encounters caves, collapsed holes or falling blocks that make it difficult to drill, grouting can be carried out first, and then drilling. For example Figure 4 and Figure 5 The following are cross-sectional views of grouting hole 2. Figure 4 The gully section was discovered after a portion of the excavation had been completed, so the grouting hole 2 above the tunnel 4 could only be drilled to the top of the tunnel 4. Figure 5 In the middle, for the part of the gully section that has not been excavated in front, the grouting will be carried out through the tunnel 4, that is, the grouting hole 2 is drilled until it reaches the bottom of the tunnel 4. In addition, it should be noted that if Figure 4 and Figure 5 As shown in the figure, the grouting hole 2 is divided into a grouting section 14 and a non-grouting section 15. During grouting, only the grouting section 14 is grouted. The non-grouting section 15 is a preset section downward from the surface. The length of the non-grouting section 15 is determined according to industry standards or geological characteristics. Figure 4 and Figure 5 The specific distance values are only for reference and can be adjusted according to actual needs in practical applications.
[0031] After the drilling of the grouting hole 2 is completed, step S2 is entered to flush the borehole (grouting hole 2). In step S2, the borehole flushing method includes open water flushing from the bottom of the hole to the outside of the hole, pressure wind flushing, and wind and water combined flushing. The fissure flushing method includes pressure water flushing, pressure wind flushing, and wind and water rotation flushing. Further, the flushing water pressure when flushing the grouting hole 2 and the fissures in the hole selects 80% of the grouting pressure. If the flushing water pressure is greater than 1MPa, the flushing water pressure selects 1MPa; the flushing wind pressure when flushing the grouting hole 2 and the fissures in the hole selects 50% of the grouting pressure. If the flushing wind pressure exceeds 0.5MPa, the flushing wind pressure selects 0.5MPa. In this embodiment, the grouting pressure needs to select a suitable grouting pressure according to the compressive strength of the surrounding rock. In addition, the selection of these values of "80%, 1MPa, 50%, 0.5MPa" can be adjusted in a small range according to actual needs and industry standards.
[0032] After the grouting holes 2 and the fissures in the holes are flushed according to the flushing method of step S2, step S3 is entered to perform a water pressure test. In step S3, the first preset time period is 24 hours, that is, the water pressure test must be performed within 24 hours after the flushing is completed. If the water pressure test is not performed within 24 hours, the grouting holes 2 and the fissures in the holes need to be flushed again before the water pressure test. In addition, in step S3, 20% of the grouting holes 2 in the I-sequence grouting holes 5 are selected for a single-point water pressure test, and the remaining 80% of the I-sequence grouting holes 5 and all the II-sequence grouting holes 13 are subjected to a simple water pressure test. Among them, the water pressure pressure during the single-point water pressure test and the simple water pressure test selects 80% of the grouting pressure. If the water pressure pressure is greater than 1MPa, the water pressure pressure selects 1MPa; the duration of the simple water pressure test is 20 minutes, the water pressure flow is measured every 5 minutes, and the water permeability is calculated based on the last water pressure flow value. The water pressure test results are expressed in water permeability. The specific water permeability calculation formula is as follows: q = Q / (p·L); where q is the water permeability, Q is the water pressure flow, p is the water pressure, and L is the length of the test section. In addition, the selection of values such as "20%, 80%, 1MPa, 20min, 5min" can be adjusted in a small range according to actual needs and industry standards.
[0033] After the water pressure test is completed, step S4 should be entered in time. In step S4, the anchoring agent 16 is used to anchor the grouting anchor cable 6. When the anchoring time reaches the second preset period, the stop plug 7, anchor pier 8 and rigging 9 are installed. The second preset period is 30 minutes, which means that the anchoring time must reach at least 30 minutes before the stop plug 7, anchor pier 8 and rigging 9 can be installed. When installing the stop plug 7, anchor pier 8 and rigging 9, the grouting anchor cable 6 must be tightened by the anchor cable tensioner, and after the grouting anchor cable 6 is tightened by the anchor cable tensioner, the pre-tightening force of the grouting anchor cable 6 needs to be tested; if the pre-tightening force decreases within the third preset period, the grouting anchor cable 6 with the decreased pre-tightening force is tightened twice. The third preset period is 48 hours. Installing the grouting anchor cable 6 means using the anchor cable method for grouting later. The embodiment of the present application selects the anchor cable instead of the anchor rod for grouting because the anchor cable can improve the integrity of the surrounding rock, fundamentally improve the mechanical properties of the surrounding rock, effectively control the displacement of the surrounding rock, and promote its stability.
[0034] In step S5, the segment length in the segmented grouting method is: 3.0m for the first segment, 5.0m for the second segment and below; the preset grouting construction time is greater than 7min and less than or equal to 8min. The preset grouting construction time is determined in the following way: when the grouting starts, the pressure reaches the design value as soon as possible, the contact section and the hole section with a large injection rate are gradually increased, and the grouting process must be measured and recorded when the slurry is changed and the grouting is completed. The measured value should be reflected in the original grouting record. According to experimental analysis, when the grouting construction time reaches more than 7min, the growth rate of the slurry diffusion radius is less than 10%. Therefore, combined with the uncontrollability of the on-site construction time, the reasonable grouting time is finally determined to be 7-8min, and the grouting can be ended when it meets the regulations. In the process of delayed grouting, the cement is 42.5MPa sulfate-resistant cement, and the cement slurry selects three water-cement ratios of 2:1, 1:1, and 0.5:1. In addition, during the grouting slurry preparation stage, materials should be added strictly according to the designed material ratio and stirred evenly. During the grouting operation, a filter screen should be placed at the slurry outlet to prevent the caking of the ingredients from blocking the grouting hole 2. Figure 6 As shown, it is a schematic diagram of a grouting anchor cable 6 during construction. Figure 6 The invention comprises an anchor 16, a stopper 17, an anchor pier 8, a rigging 9, a grouting pump 17, and a grouting bucket 18. The anchor 16 and the stopper 17 are both covered on the grouting anchor cable 6. During construction, the grouting slurry in the grouting bucket 18 is grouted into the grouting hole 2 through the grouting pump 17. In addition, "42.5MPa, 2:1, 1:1, 0.5:1" can be adjusted in a small range according to the actual construction requirements and industry standards.
[0035] Furthermore, during the construction of the grouting anchor cable 6, the preload force of the grouting anchor cable 6 also needs to be tested. If the preload force is detected to be less than 90% of the preset tension force, it means that there is a problem with the quality of the anchor cable, and a new grouting anchor cable 6 needs to be installed near the problematic anchor cable in time. After the construction is completed, the preload force of the anchor cable should also be tested regularly, and timely remedial measures should be taken after problems are detected.
[0036] In step S6, the grouting effect inspection includes: using acoustic waves to measure the wave velocity of the rock mass to check the quality of the consolidation grouting, and combining the borehole water pressure test, geophysical exploration results before and after grouting, grouting construction data, and drilling core data for comprehensive evaluation. After the evaluation results meet the construction requirements, the tunnel gully section reinforcement is completed, and then the TBM can proceed with excavation more safely.
[0037] Based on the above description, the beneficial effects of the embodiments of the present application are summarized as follows:
[0038] 1. Due to the poor geological conditions and poor stability of the surrounding rock in the tunnel gully section, surface pre-grouting reinforcement can enhance the integrity and stability of the broken surrounding rock, improve the self-bearing capacity of the surrounding rock, and inhibit the loosening and collapse of the surrounding rock, ensuring the smooth excavation of the TBM machine and effectively preventing the TBM machine from being buried or stuck.
[0039] 2. The surface pre-grouting reinforcement effect is safe and reliable, and the grouting quality is easy to control;
[0040] 3. The use of grouting anchor cable advance support method can greatly reduce labor intensity, improve the degree of mechanization, improve construction efficiency, and reduce support costs; compared with the anchor rod grouting method, anchor cable grouting can better enhance the integrity of the surrounding rock and improve the safety of construction;
[0041] 4. The construction plan is ingeniously designed, with high construction efficiency, good safety, friendly application environment and broad market prospects.
[0042] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A method for constructing a tunnel gully section, characterized in that: The method comprises: S1: Locate the positions of grouting holes in sequence on the surface of the gully section, and then drill the grouting holes according to the hole positions in accordance with the principle of sequence densification; wherein the rows of grouting holes and the holes in the same row of grouting holes are constructed in two sequences, and the surface of the gully section is the gully terrain surface above the tunnel; S2: Selecting a corresponding drilling flushing method to flush the grouting hole according to different geological conditions and on-site grouting tests, and selecting a corresponding fissure flushing method to flush the fissures in the grouting hole according to different geological conditions; S3: performing a water pressure test within the first preset period of time after flushing the grouting holes, wherein a preset proportion of grouting holes in the first sequence of the second sequence construction are selected to perform a single-point water pressure test, and all remaining grouting holes except the preset proportion of grouting holes are subjected to a simple water pressure test; S4: installing grouting anchor cables and anchoring the grouting anchor cables, installing grouting stoppers, anchor piers and rigging after the anchoring time reaches a second preset period, and tightening the grouting anchor cables by means of an anchor cable tensioner; wherein the grouting anchor cables in the same row are connected by W-shaped steel belts; S5: Use the segmented grouting method to perform delayed grouting, and end the grouting when the preset grouting construction time is reached; S6: After the grouting is completed, check the grouting effect; After the grouting anchor cable is tightened by the anchor cable tensioner, the method further comprises: detecting the pre-tightening force of the grouting anchor cable; if the pre-tightening force decreases within a third preset time period, performing secondary tightening on the grouting anchor cable with the decreased pre-tightening force; After drilling the grouting hole, the method further includes: inspecting the grouting hole according to the drilling requirements, wherein the drilling requirements include: the deviation between the actual construction drilling axis and the preset drilling axial axis is less than 5°, the deviation between the actual construction hole position of the grouting anchor cable and the lofted hole position corresponding to the grouting hole is less than or equal to 10 cm, and the drilling depth is greater than or equal to the preset drilling depth and less than or equal to the preset drilling depth plus 100 mm; The drilling flushing method includes open water flushing from the bottom of the hole to the outside of the hole, pressure wind flushing, and wind and water combined flushing; the fissure flushing method includes pressure water flushing, pressure wind flushing, and wind and water rotation flushing; The flushing water pressure when flushing the grouting holes and the fissures in the holes is selected to be 80% of the grouting pressure. If the flushing water pressure is greater than 1MPa, the flushing water pressure is selected to be 1MPa. The flushing wind pressure when flushing the grouting holes and the fissures in the holes is selected to be 50% of the grouting pressure. If the flushing wind pressure exceeds 0.5MPa, the flushing wind pressure is selected to be 0.5MPa. The water pressure during the single-point water pressure test and the simple water pressure test is 80% of the grouting pressure. If the water pressure is greater than 1MPa, 1MPa is selected. The duration of the simple water pressure test is 20 minutes, the water pressure flow is measured every 5 minutes, and the water permeability is calculated based on the last water pressure flow value. The first preset period is 24 hours, the second preset period is 30 minutes, and the third preset period is 48 hours; The segment lengths in the segmented grouting method are: 3.0 m for the first segment, 5.0 m for the second segment and below; the preset grouting construction time is greater than 7 min and less than or equal to 8 min.
2. The tunnel gully section construction method according to claim 1, characterized in that: During the delayed grouting process, the cement is 42.5MPa sulfate-resistant cement, and the cement slurry is selected from three water-cement ratios of 2:1, 1:1, and 0.5:
1.
3. The tunnel gully section construction method according to claim 2, characterized in that: During the construction of the grouting anchor cable, if the pre-tensioning force is less than 90% of the preset tensioning force, a new grouting anchor cable is added.
Citation Information
Patent Citations
Tunnel information tracing accurate grouting method
CN101832142A
Tunnel stratum pre-reinforcing comprehensive grouting method
CN111852515A
Grouting bolt-cable composite beam and supporting method for advanced support of fractured surrounding rock in deep coal mines
US20210087931A1