Earthquake-proof trench filling device
By using a filling device composed of a box and a hard rod, and using construction debris to fill the anti-seismic trench, the problem of the complexity and high cost of the existing support device is solved, a low-cost, long-life vibration isolation effect is achieved, and the gap structure resists Interrupts vibration and reduces maintenance requirements.
Patent Information
- Application Number
- CN202211051379.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-30
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-08-30
AI Technical Summary
The support device for existing anti-seismic trenches is complex and costly, and the shock-absorbing materials are prone to aging and require frequent maintenance. Filled anti-seismic trenches present challenges in terms of cost and maintenance, and the cover is easy to fall off, weakening the vibration isolation effect.
A filling device consisting of multiple boxes and hard rods is used. The box is filled with granular filling material. The lower end of the box is provided with an arc groove. The hard rod separates each two layers of boxes in the arc groove. The filling material is construction debris or garbage, the cover is placed on the device, and gaps are set between the boxes to block vibration.
It achieves low-cost, long-life vibration isolation effect, reduces ground separation, uses waste materials, reduces maintenance requirements, avoids cover falling off, and effectively absorbs and reduces vibration.
Smart Images

Figure CN115387399B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of construction, and in particular relates to an anti-seismic trench filling device. Background Art
[0002] An earthquake-proof trench is a shallow seismic trench dug near buildings and other facilities to prevent or reduce vibration hazards. The earthquake-proof trench can effectively cut off the propagation path of vibration waves. At the junction of the earthquake-proof trench and the soil, part of the incident wave will be reflected and scattered and change the propagation direction, which will weaken the vibration energy transmitted to the protected building to a certain extent.
[0003] The earthquake-proof trench can not only prevent external vibrations from being transmitted to the protected buildings, but also prevent seismic waves from spreading to the surrounding areas during the earthquake-resistant test, thereby effectively protecting the surrounding buildings.
[0004] During construction, since the setting of the seismic trench destroys the integrity of the soil, corresponding support measures need to be taken for the trench wall. For example, when the seismic trench is excavated, the trench wall is sloped or supported with sheet piles to prevent landslides from blocking the vibration transmission medium and making it continuous and unable to achieve the vibration isolation effect. However, when the ground load on both sides of the seismic trench is large, support devices are required to ensure the stability of the soil on both sides of the seismic trench. The problem with setting support devices is that the support devices will become the medium for vibration transmission, which will weaken the seismic effect of the seismic trench.
[0005] As a deep trench, the seismic trench will cause safety hazards if it is not backfilled or protected, but backfilling or filling will weaken the vibration blocking effect of the seismic trench.
[0006] The invention patent with application number CN202011331604.6 and titled "A seismic isolation device and seismic isolation system" discloses a seismic isolation device, which is arranged between two side walls for horizontal seismic isolation, including a top plate, a bottom plate, a spring and a viscous damper. The top plate is connected to one of the two side walls, and the bottom plate is connected to the other side wall. The viscous damper is arranged between the top plate and the bottom plate, and its two ends are respectively against the top plate and the bottom plate. The number of the springs is multiple and arranged in parallel. The multiple springs are evenly distributed on the outside of the viscous damper, and the two ends of each spring are respectively against the top plate and the bottom plate. The seismic isolation device can prevent the seismic isolation structure from having a large horizontal swing effect.
[0007] The invention patent with application number CN201911353825.0 and titled "An isolation trench with viscoelastic isolation and damping device and its isolation method" discloses an isolation trench with viscoelastic isolation and damping device and its isolation method, wherein the isolation trench includes an isolation trench, a supporting pile row and a pile row shock-absorbing support unit. The supporting pile row isolates the propagation of vibration together with the isolation trench while supporting the soil; the pile row shock-absorbing support unit has the characteristic of variable stiffness, and the viscoelastic shock-absorbing pads arranged in the pile row shock-absorbing support unit form a softening layer with weaker stiffness between the isolation trenches, isolating the propagation of vibration from the isolation trench to the protected building, and the viscoelastic shock-absorbing pads used have strong energy consumption capacity, which can consume a large amount of vibration energy; when the supporting structure undergoes a large deformation, the pile row shock-absorbing support unit will provide sufficient support force to prevent the instability of the supporting structure due to the rapid increase in stiffness, thereby ensuring the safety of the isolation trench. In addition, the components in the viscoelastic isolation support are replaceable, ensuring its long-term performance.
[0008] It can be seen that the use of a support device with a shock-absorbing effect is the optimal solution under the current construction level. However, the structure of the support device is relatively complex and the installation cost is high. The shock absorption core of the support device lies in the shock-absorbing material or shock-absorbing system, as well as the supporting performance. The shock-absorbing material is prone to aging during long-term use, and the shock-absorbing system requires frequent maintenance or overhaul to maintain good shock absorption and provide reliable supporting performance. As time goes by, the use effect of the support device will be discounted, and the maintenance cost is increasing. The filled anti-seismic ditch is undoubtedly more advantageous in terms of cost and maintenance.
[0009] Therefore, if a filled seismic trench with good vibration isolation effect can be provided, it can provide a reliable option for the construction party when setting up the seismic trench. Summary of the invention
[0010] The purpose of the present invention is to provide a device which has low setting cost, good vibration isolation effect, is friendly to the environment and can fill the anti-seismic groove.
[0011] In order to solve the above technical problems, the present invention discloses an anti-seismic trench filling device, including a filling device body for filling the anti-seismic trench, the filling device body is composed of a plurality of boxes and hard rods stacked up and down, the boxes are filled with granular filling materials, and the lower end surface of the boxes is parallel to the length direction and is provided with a plurality of first arc-shaped grooves;
[0012] The filling device body includes multiple layers of shock-absorbing bodies stacked up and down, each layer of shock-absorbing bodies includes 2-3 rows of boxes, and the boxes between every two layers of shock-absorbing bodies are stacked up and down in an alternating manner; a hard rod is provided between every two layers of shock-absorbing bodies to separate each layer of shock-absorbing bodies, and the hard rod is located in the first arc-shaped groove. The hard rod ensures that the interval between every two layers of shock-absorbing bodies is not less than 0.5 cm; the radius of the first arc-shaped groove is greater than the radius of the hard rod, and each layer of shock-absorbing bodies can move slightly with the hard rod as a track.
[0013] Preferably, the box body comprises a rectangular box body with an upper opening, and a cover is provided on the upper side of the box body.
[0014] Preferably, a plurality of second arc-shaped grooves are provided on the upper end surface of the cover corresponding to the first arc-shaped grooves, and the hard rods are located in the first arc-shaped grooves and the second arc-shaped grooves.
[0015] Preferably, the filling material is construction debris or building waste.
[0016] Preferably, it also includes an anti-seismic trench cover plate for sealing the upper end opening of the anti-seismic trench.
[0017] Preferably, the anti-seismic trench cover plate is concealed on the filling device body, and gaps are left between the anti-seismic trench on both sides or one side of the anti-seismic trench cover plate and the anti-seismic trench.
[0018] Preferably, in the shock-absorbing body, there is a first gap between the boxes in the width direction of the shock-proof groove, and there is a second gap between the boxes in the length direction of the shock-proof groove.
[0019] Preferably, when the ground load on both sides of the seismic trench is small, the first gap between the two boxes of the same layer of shock-absorbing bodies is not filled.
[0020] Preferably, when the ground load on both sides of the seismic trench is relatively large, the first gap between the two boxes of the same layer of shock-absorbing bodies is filled with a buffer layer.
[0021] Preferably, the buffer layer is a rubber pad or shock-absorbing particles filled into the first gap when paving the box body; the shock-absorbing particles include sand or rubber particles.
[0022] The anti-seismic trench filling device of the present invention has at least the following advantages:
[0023] 1. The filling materials can be obtained locally, and a large amount of excavated earth, construction debris or construction waste can be used. The construction waste that should have been treated as garbage can be reused, reducing the transportation volume of construction waste, which is low-carbon and environmentally friendly.
[0024] 2. The cover of an ordinary seismic trench may fall off, which is a safety hazard. In addition, the cover of the seismic trench will transmit vibrations, weakening the vibration isolation effect of the seismic trench. The seismic trench cover of the present invention is hidden on the filling device body, and there is no safety hazard of falling off into the seismic trench. Gaps are left between the seismic trench cover and the two sides or one side of the seismic trench, thereby effectively blocking the vibration from being transmitted through the seismic trench cover.
[0025] 3. The filling device body is composed of multiple boxes and hard rods stacked up and down, with a long service life, no maintenance and overhaul required, low setting cost and low maintenance cost.
[0026] 4. The anti-seismic trench is filled by the filling device body, which greatly reduces the physical separation of the ground due to the existence of the anti-seismic trench, so that the surrounding ground can be connected more easily and naturally.
[0027] 5. The filling device body can effectively block, absorb and reduce vibration: the vibration wave is absorbed by the filling material and the shock-absorbing particles, thereby buffering and reducing it; when the vibration wave propagates, it will cause the shock-absorbing body at some levels to move, that is, the vibration wave will be partially converted into kinetic energy. When the box body moves slightly horizontally, the relative position of the hard rod and the box body changes, causing the box body to rise slightly, thereby converting the kinetic energy into gravitational potential energy, thereby reducing the vibration energy. After the vibration disappears, the box body is reset under the action of gravity and the hard rod, thereby slowly releasing the absorbed gravitational potential energy; in addition, the existence of multiple gaps blocks, prolongs or interferes with the propagation path of the vibration wave, disrupts the propagation direction of the wave, and causes the vibration waves to interfere with each other and partially offset each other. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 The figure is a schematic diagram of the internal structure of an earthquake-proof trench filling device.
[0029] Figure 2 The figure is a schematic diagram of the top view of the structure of an earthquake-proof trench filling device.
[0030] Figure 3 A schematic diagram of the structure of a box.
[0031] Figure 4 A schematic diagram of the internal structure of another earthquake-proof trench filling device.
[0032] The numbers in the figure are: 1-filling device body, 2-box, 2A-0.2m wide box, 2B-0.3m wide box, 3-hard rod, 4-seismic groove, 5-first arc-shaped groove, 6-shock-absorbing body, 7-box body, 8-lid, 9-seismic groove cover plate, 10-first gap, 11-buffer layer, 12-second gap, 13-second arc-shaped groove. DETAILED DESCRIPTION
[0033] The present invention is further described in detail below through examples so that those skilled in the art can implement the invention with reference to the description.
[0034] Example 1
[0035] See also Figure 1-3 , an anti-seismic trench filling device, comprising a filling device body 1 for filling an anti-seismic trench 4, the filling device body 1 is composed of a plurality of boxes 2 and hard rods 3 stacked up and down, the boxes 2 are filled with granular filling materials, and the lower end surface of the boxes 2 is parallel to the length direction and is provided with a plurality of first arc-shaped grooves 5;
[0036] The filling device body 1 includes multiple layers of shock-absorbing bodies 6 stacked up and down, each layer of shock-absorbing bodies 6 includes 2-3 rows of boxes, and the boxes between every two layers of shock-absorbing bodies 6 are stacked up and down in an alternating manner; a hard rod 3 is provided between every two layers of shock-absorbing bodies to separate each layer of shock-absorbing bodies, and the hard rod 3 is in the first arc-shaped groove 5, and the hard rod 3 makes the interval between every two layers of shock-absorbing bodies 6 not less than 0.5 cm; the radius of the first arc-shaped groove 5 is greater than the radius of the hard rod 3, and each layer of shock-absorbing bodies 6 can move slightly with the hard rod 3 as a track. The box can be made of glass fiber reinforced plastic, metal, reinforced concrete and other materials, and the hard rod can be made of stainless steel, high-strength plastic, hard rubber, stone pillars and other materials. Hard rubber and the like may be deformed under long-term heavy pressure, but can still play a role in separating boxes and reducing shock. The cross section of the hard rod can be circular or elliptical.
[0037] The box body 2 includes a rectangular box body 7 with an upper opening, and a cover 8 is provided on the upper side of the box body. The large opening on the upper part of the box body is convenient for workers to use a shovel to put the filling material into the box body 7. The cover 8 supports the hard rod 3. In addition, since the filling amount cannot be very accurate when the filling material is manually filled, the movable cover can adapt to this error to a certain extent. For example, when a large amount of filling material is loaded, the cover is higher than the normal position. When the height is small, it can be ignored. When the height is large, part of the filling material should be scraped out. For filling materials with larger particles, workers can also stand on the cover and vibrate and press appropriately to make the upper surface of the filling material flat. During long-term use, the filling material in the box may shrink in volume and decrease in surface height. At this time, the cover is deformed under pressure to adapt to this change.
[0038] The upper end surface of the cover 8 is provided with a plurality of second arc grooves 13 corresponding to the first arc groove 5, and the hard rod 3 is located in the first arc groove 5 and the second arc groove 13. The second arc groove is provided to facilitate the placement and positioning of the hard rod when placing the hard rod, and prevent the hard rod from moving during laying.
[0039] The filling material is construction debris or building waste, which is preferably crushed to have a particle size of no more than 5 cm.
[0040] It also includes an anti-seismic trench cover plate 9 for blocking the upper end opening of the anti-seismic trench 4.
[0041] The anti-seismic trench cover plate 9 is covered on the filling device body 1, and gaps are left between the two sides or one side of the anti-seismic trench cover plate 9 and the anti-seismic trench. The filling device body supports the anti-seismic trench cover plate, so that the anti-seismic trench cover plate can be placed without relying on the support of the two side edges of the anti-seismic trench. With the support of the filling device body, a gap can be left between the anti-seismic trench cover plate and the anti-seismic trench, which can effectively block the anti-seismic trench cover plate from transmitting vibration.
[0042] In the shock-absorbing body, there is a first gap 10 between the boxes in the width direction of the shock-proof groove, and a second gap 12 between the boxes in the length direction of the shock-proof groove. The second gap 12 is generally not filled, and the second gap 12 can effectively prevent the spread of vibration.
[0043] When the ground load on both sides of the seismic trench 4 is small, the first gap 10 between the two boxes 2 of the same layer of shock absorbers 6 is not filled. Since the first gap 10 forms a partition for vibration propagation, the vibration wave can only be transmitted to the upper and lower adjacent boxes through the contacting hard rods, thereby extending the propagation path of the vibration wave and increasing the mutual interference and absorption of the vibration wave.
[0044] In this embodiment, a box body with a length of 1-2m, a width of two types of 0.2 and 0.3m, and a height of 0.2-0.3m is used. The construction width of the earthquake-proof trench 4 is generally not less than 60cm, and the depth is generally not less than 2m. Taking a 60cm wide earthquake-proof ditch as an example, when laying the filling device body, first lay the first layer of shock-absorbing bodies from the bottom layer of the earthquake-proof ditch, lay a 0.2m wide box 2A on one side, and a 0.3m wide box 2B on the other side, leaving a gap between the two boxes, and then place a hard rod in the second arc-shaped groove to start laying the second layer of shock-absorbing bodies. At this time, a 0.3m wide box 2B is laid on one side, and a 0.2m wide box 2A is laid on the other side, so that the boxes between the first and second layers of shock-absorbing bodies are staggered (staggered), and then place a hard rod in the second arc-shaped groove; the third layer of shock-absorbing bodies is arranged according to the arrangement of the first layer of shock-absorbing bodies, and so on, completing the laying of the filling device body layer by layer, and finally covering the filling device body with the earthquake-proof ditch cover.
[0045] The filling device body 1 can be used in conjunction with sheet piles or side limits, which can make the trench wall smoother and the box body more neatly laid.
[0046] Example 2
[0047] See also Figure 4, which is similar to Example 1, but differs in that when the ground load on both sides of the seismic trench 4 is large, the first gap 10 between the two boxes 2 of the same layer of shock-absorbing body 6 is filled with a buffer layer 11. The buffer layer 11 can connect the box with the trench wall and between the boxes, so that the shock-absorbing body has support. The buffer layer 11 weakens the vibration wave and enables the shock-absorbing body to support the trench walls on both sides and provide stable support strength.
[0048] The buffer layer 11 is a rubber pad or shock-absorbing particles filled into the first gap when paving the box body; the shock-absorbing particles include sand or rubber particles. In this embodiment, the buffer layer is a rubber pad.
[0049] The rubber pad can be directly bonded to both sides of the box body during production. However, in actual construction, due to uneven trench walls or inaccurate trench width control, after a layer of shock absorbers is laid, there may be an obvious gap between the rubber pad and the trench wall. In this case, soil or shock absorbing particles can be used to fill the gap. When using shock absorbing particles to fill the first gap, in order to prevent the shock absorbing particles from entering the gap between the upper and lower boxes, an extension or a baffle can be set at the lower edge of the box to prevent the shock absorbing particles from entering.
[0050] Various modifications to the above embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A seismic trench filling device, characterized in that: The filling device body includes a filling device body for filling the earthquake-proof groove, the filling device body is composed of a plurality of boxes and hard rods stacked up and down, the boxes are filled with granular filling materials, and the lower end surface of the boxes is parallel to the length direction and is provided with a plurality of first arc-shaped grooves; The filling device body includes multiple layers of shock-absorbing bodies stacked up and down, each layer of shock-absorbing bodies includes 2-3 rows of boxes, and the boxes between every two layers of shock-absorbing bodies are stacked up and down alternately; a hard rod is provided between every two layers of shock-absorbing bodies to separate each layer of shock-absorbing bodies, and the hard rod is in a first arc-shaped groove, and the hard rod ensures that the interval between every two layers of shock-absorbing bodies is not less than 0.5 cm; the radius of the first arc-shaped groove is greater than the radius of the hard rod, and each layer of shock-absorbing bodies moves slightly with the hard rod as a track.
2. The anti-seismic trench filling device according to claim 1, characterized in that: The box body comprises a rectangular box body with an upper opening, and a cover is arranged on the upper side of the box body.
3. The anti-seismic trench filling device according to claim 2, characterized in that: A plurality of second arc-shaped grooves are arranged on the upper end surface of the cover corresponding to the first arc-shaped grooves, and the hard rods are located in the first arc-shaped grooves and the second arc-shaped grooves.
4. The anti-seismic trench filling device according to claim 1, characterized in that: The filling material is construction waste.
5. The anti-seismic trench filling device according to claim 1, characterized in that: It also includes an anti-seismic trench cover plate for blocking the upper end opening of the anti-seismic trench.
6. The anti-seismic trench filling device according to claim 5, characterized in that: The anti-vibration trench cover plate is covered on the filling device body, and gaps are left between the two sides or one side of the anti-vibration trench cover plate and the anti-vibration trench.
7. The anti-seismic trench filling device according to claim 1, characterized in that: In the shock-absorbing body, a first gap is provided between the boxes in the width direction of the shock-proof groove, and a second gap is provided between the boxes in the length direction of the shock-proof groove.
8. The anti-seismic trench filling device according to claim 7, characterized in that: When the ground loads on both sides of the anti-seismic trench are small, the first gap between the two boxes of the shock-absorbing body on the same layer is not filled.
9. The anti-seismic trench filling device according to claim 7, characterized in that: When the ground loads on both sides of the seismic trench are relatively large, the first gap between the two boxes of the same layer of shock-absorbing bodies is filled with a buffer layer.
10. The anti-seismic trench filling device according to claim 9, characterized in that: The buffer layer is a rubber pad or shock-absorbing particles filled into the first gap when paving the box body; the shock-absorbing particles include sand or rubber particles.
Citation Information
Patent Citations
A seismic isolation trench incorporating a viscoelastic damping device and its seismic isolation method
CN111042211B
Shock isolation device and shock isolation system
CN112627375A
Shock insulation ditch additionally provided with viscoelastic shock insulating and reducing device and shock insulation method based on shock insulation ditch
CN111042211A
Rapid fabricated concrete water storage shock-insulation ditch
CN111270710A