A method for handling position conflicts between shield tunneling and existing pipe jacking tunnel
By establishing a new pipe top work well and reinforcement structure in the conflict section between the pipe top tunnel and the shield tunnel, and using underground continuous walls and hydraulic groove milling machines to clear the conflict section, the large relocation scope, high cost and pipe top in the existing technology are solved. The problem of poor tunnel stability achieves more efficient and secure conflict handling.
Patent Information
- Application Number
- CN202211139900.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-19
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2042-09-19
AI Technical Summary
When the existing technology deals with conflicts between the shield excavation and existing pipe tunnels, the relocation scope is too large, the investment cost is high, the construction period is long, and the removal method has a great impact on the social surroundings of the foundation pit, and it has failed to effectively prevent pipe tunnels. The problems of tunnel instability collapse and slurry in the mud and water pressure.
New pipe top work wells are established at both ends of the conflict section of the existing pipe top tunnel and the newly built shield tunnel, and local relocation and reinforcement are carried out. The conflict section is cleared by using underground continuous walls and hydraulic groove milling machines, drilling and filling with cement mortar, combining with Longitudinal tension steel and cement grouting reinforcement to ensure the stability of the top pipe tunnel.
Shortened the relocation scope and construction period, reduced investment costs, reduced the impact of foundation pit excavation depth on society, avoided the instability and collapse of the pipe header tunnel and the slurry pressure slurry, and met the safety during the shield excavation process. Require.
Smart Images

Figure CN115419419B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for processing position conflicts between shield tunneling and an existing jacking tunnel, belonging to the technical field of shield tunneling obstacle processing methods. Background Art
[0002] In recent years, due to the existence of a large number of infrastructure in shallow underground spaces, many engineering cases have occurred in which jacking tunnels were encountered during shield construction. The relocation of jacking tunnels usually needs to be implemented through jacking working shafts. Since jacking tunnels are generally buried at a large depth and the support piles directly below them are difficult to construct, the construction of new jacking working shafts in the jacking tunnel section has become a technical difficulty in the local relocation of jacking tunnels. The current approach is: to ensure that the jacking tunnel business is not interrupted for a long time, the existing jacking tunnel working shafts at both ends are used to relocate the entire section of the jacking tunnel, and then the open excavation method is used to remove the reinforced concrete structure of the jacking tunnel. However, the shortcomings of the above solution are:
[0003] 1) Using the working wells at both ends of the jacking tunnel to relocate the entire existing jacking tunnel, the relocation scope is far larger than the conflict scope, resulting in increased investment costs and a long construction period.
[0004] 2) The burial depth of pipe-jacking tunnels is generally large, and open excavation is required to remove the conflicting reinforced concrete structures. A deep foundation pit needs to be excavated. The cost of excavating a deep foundation pit is high, the construction period is long, and the impact on the society around the foundation pit is great, so it is not very practical.
[0005] The existing technology also uses a full-rotation obstacle removal machine to remove the residual pile foundation of the old building at a fixed point, and then construct the underground continuous wall for the maintenance of the foundation pit of the new building. However, this method has shortcomings in dealing with the conflict between shield excavation and existing top-pipe tunnels: first, this method is only suitable for removing abandoned residual pile foundations, and does not consider the top-pipe tunnel diversion plan in the obstacle removal area; second, the top-pipe tunnel in the clearance section is not pre-filled, and the direct use of the strong downward pressure of the full-rotation drilling rig will cause the top-pipe tunnel to instantly become unstable and collapse after damage, causing an accident; in addition, the full-rotation drilling rig obstacle removal hole uses soil backfilling and compaction, which cannot meet the requirements of preventing mud and water pressure from bubbling during shield excavation. Summary of the invention
[0006] The purpose of the present invention is to provide a method for handling position conflicts between shield tunneling and an existing jacking tunnel, so as to solve the problems raised in the above-mentioned background technology.
[0007] The technical solution of the present invention is as follows:
[0008] A method for handling position conflicts between shield tunneling and an existing pipe jacking tunnel comprises the following steps:
[0009] A new pipe jacking working pit is built at each end of the existing pipe jacking tunnel in the conflict section between the existing pipe jacking tunnel and the new shield tunnel to carry out partial relocation of the conflict area;
[0010] Clear the conflicting section of the existing pipe-jacking tunnel within the shield tunneling range;
[0011] Reinforce existing pipe-jacking tunnels within the area strongly affected by shield construction.
[0012] Preferably, the local relocation of the conflict range includes the following steps:
[0013] To ensure the normal operation of the existing pipe jacking tunnel, the foundation trenches of the underground continuous wall on both sides and directly below are excavated;
[0014] The underground continuous wall reinforcement cage is distributed with the center line of the existing top pipe tunnel as the symmetry axis, and the underground continuous wall reinforcement cage corresponds to the position of the existing top pipe tunnel and reserves a circular opening matching the outer diameter of the existing top pipe tunnel;
[0015] After the underground continuous wall steel cage is lowered to the predetermined depth, the left and right steel cages are moved horizontally together and poured with concrete to ensure that the underground continuous wall is poured under the normal operation of the existing top pipe tunnel;
[0016] The four sides of the underground continuous wall form a closed structure as the side wall of the existing top pipe tunnel working shaft in the conflict section, and the excavation is carried out to the designed elevation for the bottom plate pouring;
[0017] The gap between the existing top pipe tunnel surface and the underground continuous wall is sealed by hydraulic grouting with cement slurry and water glass mixed slurry;
[0018] The newly built jacking working pit is used to relocate the pipelines in the existing jacking tunnel in the conflict section to the newly built relocation tunnel.
[0019] Preferably, a trenching machine is used in conjunction with a hydraulic grab to remove soil on both sides of the existing pipe jacking tunnel to form a deep trench;
[0020] A vertical guide rail for installing a hydraulic slot milling machine is vertically placed in the deep groove, and the hydraulic slot milling machine is horizontally installed on the vertical guide rail and moves under the guidance of the vertical guide rail;
[0021] The horizontally arranged hydraulic slot milling machine mills the soil directly below the existing pipe jacking tunnel from bottom to top.
[0022] Preferably, the conflict segment clearing comprises the following steps:
[0023] For the existing top pipe tunnels that need to be removed within the shield tunneling range, holes are drilled at intervals on the top and cement mortar is injected to fill the existing top pipe tunnels that need to be removed;
[0024] The drilling adopts a bite arrangement, and the drilling length is from the ground surface to the bottom of the existing top pipe tunnel to be cleared, and the existing top pipe tunnel reinforced concrete structure is cleared with a grab bucket;
[0025] The obstacle clearance holes formed by drilling are backfilled with clay soil within the shield excavation range, and cement mortar is backfilled from the top plate of the shield tunneling machine to the ground surface.
[0026] Preferably, the centers of the interlocking boreholes are arranged in an equilateral triangle, the spacing between the borehole centers is 0.7-0.9 times the borehole diameter, and the interval skipping method is used to complete the cleaning and backfilling of all boreholes.
[0027] Preferably, reinforcing the existing pipe jacking tunnel comprises the following steps:
[0028] At least three longitudinal tension steel sections are used to reinforce the inner side of the existing pipe-jacking tunnel along the circumference to improve its deformation resistance;
[0029] Cement grouting is used on the outside of the existing top pipe tunnel to form a cement grouting reinforcement body to reduce the lateral deformation of the adjacent existing top pipe tunnel caused by shield excavation.
[0030] Preferably, at least three longitudinal tension steels are evenly distributed along the circumferential direction on the inner side of the existing jacking pipe tunnel, and the longitudinal tension steels are fixedly spaced axially along the existing jacking pipe tunnel and are arranged throughout the entire length.
[0031] Preferably, the longitudinal tensioning steel is fixed by chemical anchor bolts or embedded parts welding.
[0032] Preferably, a plurality of grouting holes are arranged at equal intervals in the lower part of the existing jacking tunnel;
[0033] The cement grouting reinforcement body is formed by injecting cement slurry from the inside of the existing jacking tunnel to the outside through the grouting holes.
[0034] Preferably, the cement grouting reinforcement body forms a 180° circular ring below the horizontal plane where the center of the existing jacking tunnel is located.
[0035] The present invention has the following beneficial effects:
[0036] By building two new pipe jacking working pits at both ends of the conflicting section of the existing pipe jacking tunnel, the relocation scope is greatly shortened, the investment cost is reduced, and the construction period is shortened;
[0037] Underground continuous wall foundation trenches are excavated on both sides and directly below the conflict section of the existing pipe jacking tunnel. Steel cages are placed in the underground continuous wall foundation trenches and concrete is poured. This solution has a shallower foundation pit than a deeper one and will not cause much impact on the surrounding area of the foundation pit, which is highly practical.
[0038] Before clearing the existing top pipe tunnel in the conflict section, holes are drilled at intervals in the existing top pipe tunnel in the conflict section and filled with cement mortar to pre-fill the existing top pipe tunnel in the conflict section. Afterwards, the strong downward pressure of the full-rotation drilling rig can be used to avoid accidents caused by the instability and collapse of the existing top pipe tunnel.
[0039] The obstacle clearance holes created by drilling are compacted by backfilling with clay and cement mortar to meet the requirements of preventing mud and water pressure from bubbling during shield excavation. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 It is a plan view of the method for dealing with the conflict between shield tunneling and the existing jacking tunnel;
[0041] Figure 2 Conventional trenching machine for underground continuous wall cooperates with hydraulic grab bucket for trench excavation;
[0042] Figure 3 Excavation of foundation trench for underground continuous wall transverse hydraulic slot milling machine;
[0043] Figure 4 Partially relocate the pipelines for the newly built jacking well;
[0044] Figure 5 This is a cross-sectional view of the full-rotation drill bit drilling;
[0045] Figure 6 This is the reinforcement diagram of the existing jacking tunnel within the area strongly affected by shield tunneling.
[0046] The reference numerals in the figure represent:
[0047] 1. Existing jacking working shaft; 2. Existing jacking tunnel; 3. Obstacle clearance hole; 4. New jacking working shaft; 5. New shield tunnel; 6. New relocation tunnel; 7. Underground continuous wall; 8. Slotting machine; 9. Vertical guide rail; 10. Hydraulic slot milling machine; 11. Grouting of the contact surface between jacking pipe and underground continuous wall; 12. Backfill of clay soil; 13. Backfill of cement mortar; 14. Filling of cement mortar in jacking pipe; 15. Longitudinal tension steel; 16. Grouting hole; 17. Cement grouting reinforcement. DETAILED DESCRIPTION
[0048] The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
[0049] like Figure 1 As shown, the newly built shield tunnel 5 to be constructed partially overlaps with the existing top pipe tunnel 2, causing a conflict;
[0050] If the existing top pipe working shaft 1 is far away from the conflict section between the newly built shield tunnel 5 and the existing top pipe tunnel 2, a new top pipe working shaft 4 is built with the minimum distance close to the conflict section between the newly built shield tunnel 5 and the existing top pipe tunnel 2; if the existing top pipe working shaft 1 is very close to the conflict section between the newly built shield tunnel 5 and the existing top pipe tunnel 2, it can be used directly (equivalent to a new top pipe working shaft 4);
[0051] A newly built relocation tunnel 6 is added between two groups of newly built jacking working shafts 4 to replace the demolished existing jacking tunnel 2 to achieve partial relocation.
[0052] like Figure 2-3 As shown, to ensure the normal operation of the existing pipe jacking tunnel 2, underground continuous wall foundation trenches are dug on both sides and directly below the existing pipe jacking tunnel 2; the excavation process of the underground continuous wall foundation trench is as follows: Figure 2 As shown, a trenching machine 8 is used in conjunction with a hydraulic grab to grab the soil on both sides of the existing top pipe tunnel 2 to form a deep trench; Figure 3 As shown, a vertical guide rail 9 is vertically placed on the side wall of the deep trench, and a hydraulic slot milling machine 10 is horizontally installed on the vertical guide rail 9 and can move vertically on the vertical guide rail 9; the hydraulic slot milling machine 10 mills the soil directly below the existing jacking tunnel 2 from bottom to top;
[0053] Lower two sets of underground continuous wall steel cages into the underground continuous wall foundation trench, the two sets of underground continuous wall steel cages are symmetrically distributed with respect to the center line of the existing top pipe tunnel 2, and after the underground continuous wall steel cages are lowered to a predetermined depth, the two symmetrical sets of underground continuous wall steel cages are translated and closed and concrete is poured, so as to ensure that the underground continuous wall 7 is poured under the normal operation of the existing top pipe tunnel 2;
[0054] Two symmetrical sets of underground continuous wall steel cages are translated and closed to form a closed loop structure, and a circular opening matching the outer diameter of the existing top pipe tunnel 2 is reserved on the side wall after the two sets of underground continuous wall steel cages are translated and closed, so that the existing top pipe tunnel 2 relatively passes through the two symmetrical sets of underground continuous wall steel cages from the circular opening;
[0055] The four sides of the underground continuous wall 7 form a closed structure as the side wall of the existing top pipe tunnel 2 working pit. The excavation is carried out to the designed elevation to place the bottom plate steel bars and pour concrete to form a reinforced concrete bottom plate under the existing top pipe tunnel 2 located in the conflict section (such as Figure 4 shown);
[0056] The gap between the surface of the existing top pipe tunnel 2 and the underground continuous wall 7 is sealed by hydraulic grouting with a mixture of cement slurry and water glass. Figure 4 Grouting of the contact surface between the top pipe and the underground continuous wall 11;
[0057] like Figure 4 As shown, two groups of newly built pipe jacking working shafts 4 are used to relocate the pipelines in the existing pipe jacking tunnel 2 in the conflicting section to the newly built relocation tunnel 6.
[0058] like Figure 5 As shown, a geological drill is used to drill holes at a certain interval on the top of the existing top pipe tunnel 2 of the conflict section, and cement mortar is injected into the inside of the existing top pipe tunnel 2 of the conflict section through the drilled holes;
[0059] The drilling holes of the full-rotation drilling rig are arranged in an interlocking pattern, with the centers of the holes arranged in an equilateral triangle. The center spacing of the holes is 0.8 times the hole diameter. The interval jump method is used to complete the cleaning and backfilling of all the holes drilled by the full-rotation drilling rig. The length of the holes is from the surface to the bottom of the existing top pipe tunnel 2 in the conflict section, and the hydraulic grab is used to clear the reinforced concrete structure of the existing top pipe tunnel 2 in the conflict section.
[0060] The obstacle clearance hole 3 formed by drilling the full-rotation drill rig is backfilled with clay soil 12 within the shield tunneling range, and is backfilled with cement mortar 13 from the top plate of the shield tunneling machine to the ground surface.
[0061] like Figure 6 As shown, the inner side of the existing top pipe tunnel 2 near the shield tunneling is reinforced by four longitudinal tension steels 15 evenly distributed along the circumference of the existing top pipe tunnel 2. The longitudinal tension steels 15 are arranged throughout the length and are reliably fixed along the axial intervals of the existing top pipe tunnel 2 to improve the deformation resistance. The longitudinal tension steels 15 are fixed by chemical anchor bolts or embedded parts welding;
[0062] like Figure 6 As shown, a plurality of grouting holes 16 are arranged at equal intervals in the circumferential and axial directions at the lower part of the existing top pipe tunnel 2, and cement slurry is injected from the inside of the existing top pipe tunnel 2 to the outside to form a cement grouting reinforcement body 17 to reinforce the soil outside the top pipe; the cement grouting reinforcement body 17 is a 180° semicircular ring structure and is located at the lower part of the existing top pipe tunnel 2, so as to reduce the lateral deformation of the adjacent existing top pipe tunnel 2 caused by shield excavation.
[0063] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A method for handling conflicts between shield tunneling and existing jacking tunnel positions. Features: The following steps are involved: A new pipe jacking working well (4) is built at each end of the existing pipe jacking tunnel (2) in the conflict section between the existing pipe jacking tunnel (2) and the new shield tunnel (5) to carry out local relocation of the conflict area; Clearing the conflicting section of the existing pipe-jacking tunnel (2) within the shield tunneling range; Reinforce the existing pipe-jacking tunnel (2) within the area strongly affected by the shield construction; The local relocation of the conflict area includes the following steps: 1) To ensure the normal operation of the existing pipe jacking tunnel (2), the foundation trenches on both sides of the tunnel and the underground continuous wall (7) directly below the tunnel are excavated; 2) The underground continuous wall steel cage is distributed with the center line of the existing top pipe tunnel (2) as the symmetry axis, and a circular opening matching the outer diameter of the existing top pipe tunnel (2) is reserved at the position of the underground continuous wall steel cage corresponding to the existing top pipe tunnel (2); 3) After the steel cage of the underground continuous wall (7) is lowered to a predetermined depth, the left and right steel cages are moved horizontally together and poured with concrete, so as to ensure that the pouring of the underground continuous wall (7) is completed under the normal operation of the existing top pipe tunnel (2); 4) The four sides of the underground continuous wall (7) form a closed structure as the side wall of the working shaft of the existing top pipe tunnel (2) in the conflict section, and the excavation is carried out to the designed elevation for pouring the bottom plate; 5) The gap between the surface of the existing top pipe tunnel (2) and the underground continuous wall (7) is sealed by hydraulic grouting with a mixture of cement slurry and water glass; 6) Using the newly built pipe jacking working pit (4), the pipelines in the existing pipe jacking tunnel (2) in the conflict section are relocated to the newly built relocation tunnel (6).
2. A method for handling conflicts between shield tunneling and existing jacking tunnel positions as claimed in claim 1, Features: A trenching machine (8) is used in conjunction with a hydraulic grab to remove soil on both sides of the existing jacking tunnel (2) to form a deep trench; A vertical guide rail (9) for installing a hydraulic slot milling machine (10) is vertically placed in the deep groove, and the hydraulic slot milling machine (10) is horizontally installed on the vertical guide rail (9) and moves under the guidance of the vertical guide rail (9); A horizontally arranged hydraulic slot milling machine (10) mills the soil directly below the existing pipe jacking tunnel (2) from bottom to top.
3. A method for handling conflicts between shield tunneling and existing pipe jacking tunnel positions as claimed in claim 1, Features: Conflicting segment clearing includes the following steps: 1) drilling holes at intervals on the top of the existing top pipe tunnel (2) to be removed within the shield tunneling range and injecting cement mortar to fill the existing top pipe tunnel (2) to be removed; 2) The drilling holes are arranged in a bite pattern, and the length of the drilling holes is from the ground surface to the bottom of the existing top pipe tunnel (2) to be removed, and the existing top pipe tunnel (2) reinforced concrete structure is removed in cooperation with a grab bucket; 3) The obstacle clearance holes formed by drilling are backfilled with clay soil within the shield tunneling range (12), and cement mortar is backfilled from the top plate of the shield tunneling machine to the ground surface (13).
4. A method for handling conflicts between shield tunneling and existing jacking tunnel positions as claimed in claim 3, Features: The centers of the interlocking drill holes are arranged in an equilateral triangle, with the center spacing of the drill holes being 0.7-0.9 times the drill hole diameter. The interval skipping method is used to complete the cleaning and backfilling of all drill holes.
5. A method for handling conflicts between shield tunneling and existing jacking tunnel positions as claimed in claim 1, Features: Reinforcing the existing pipe jacking tunnel (2) comprises the following steps: 1) The inner side of the existing pipe-jacking tunnel (2) is reinforced by at least three longitudinal tension steel sections (15) along the circumferential direction to improve the deformation resistance; 2) Cement grouting is used on the outer side of the existing top pipe tunnel (2) to form a cement grouting reinforcement body (17) to reduce the lateral deformation of the adjacent existing top pipe tunnel (2) caused by shield tunneling.
6. A method for handling conflicts between shield tunneling and existing jacking tunnel positions as claimed in claim 5, Features: At least three longitudinal tension steels (15) are evenly distributed along the circumferential direction on the inner side of the existing top pipe tunnel (2); the longitudinal tension steels (15) are fixedly spaced axially along the existing top pipe tunnel (2) and are arranged throughout the entire length.
7. A method for handling position conflicts between shield tunneling and existing jacking tunnel as claimed in claim 6, Features: The longitudinal tension steel (15) is fixed by chemical anchor bolts or embedded parts welding.
8. A method for handling conflicts between shield tunneling and existing pipe jacking tunnel positions as claimed in claim 5, Features: A plurality of grouting holes (16) are arranged at equal intervals in the lower part of the existing jacking tunnel (2); Cement slurry is injected from the inside of the existing jacking tunnel (2) to the outside through the grouting hole (16) to form a cement grouting reinforcement body (17).
9. A method for handling conflicts between shield tunneling and existing pipe jacking tunnel positions as claimed in claim 8, Features: The cement grouting reinforcement body (17) forms a 180° circular ring below the horizontal plane where the center of the existing top pipe tunnel (2) is located.