A mirror stainless steel ceiling construction equipment and construction method thereof
By designing a mirror stainless steel ceiling construction equipment containing multiple mechanisms, the glue is evenly distributed using spiral transmission and spring devices, the problem of uneven distribution of glue during construction is solved, the adhesive firmness is improved and safety risks are reduced.
Patent Information
- Application Number
- CN202211241509.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-11
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2042-10-11
AI Technical Summary
During the construction of mirror stainless steel ceiling, it is difficult for workers to squeeze stainless steel plates on the scaffolding to evenly distribute the glue, which affects the firmness of the adhesive and poses safety risks.
A mirror stainless steel ceiling construction equipment including a compression mechanism, a support mechanism, a pulling mechanism, a driving mechanism, an extrusion mechanism and a limiting mechanism is designed. The compression rod is rolled on the surface of the stainless steel plate through spiral transmission and spring devices, and the glue is evenly distributed. The support rod is lifted and lowered through wire ropes and gears to achieve uniform extrusion of glue.
It effectively improves the uniform distribution of glue, enhances the adhesion firmness between the stainless steel plate and the base plate, and reduces construction safety risks.
Smart Images

Figure CN115749211B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of mirror stainless steel ceiling construction, and in particular to mirror stainless steel ceiling construction equipment and a construction method thereof. Background Art
[0002] With the development of the times, architectural shapes and interior designs are constantly seeking innovation and change. Many indoor ceilings often use mirrored glass to increase the size of indoor space and improve the novelty of indoor shapes. However, since mirrored glass is made of flat glass through processes such as cleaning, silver plating, and coating with surface protective paint, it is easy to fall off during use as a ceiling material, posing a safety hazard. In order to solve the safety hazards brought by mirrored glass ceilings and not lower the design requirements, through practical application, the construction method of using mirrored stainless steel ceilings instead of glass ceilings has not only solved the safety hazards, but also achieved the same effect as using glass ceilings.
[0003] During the construction of the mirror stainless steel ceiling, the stainless steel plate needs to be pasted on the surface of the base plate. In order to facilitate the alignment of the installation position of the stainless steel plate and the surface of the base plate, the amount of glue at the edge of the stainless steel plate is less than the amount of glue at the center of the stainless steel plate. After the stainless steel plate is pasted on the surface of the base plate, workers need to stand on the scaffolding and continuously squeeze the stainless steel plate upward to make the glue evenly distributed between the stainless steel plate and the base plate. However, workers standing on the scaffolding and exerting force upward is not conducive to their safety, and artificial squeezing makes it difficult to evenly distribute the glue between the stainless steel plate and the base plate, which reduces the firmness of the stainless steel plate.
[0004] Therefore, it is necessary to provide a new mirror stainless steel ceiling construction equipment and a construction method thereof to solve the above-mentioned technical problems. Summary of the invention
[0005] The invention provides mirror stainless steel ceiling construction equipment and a construction method thereof, which are convenient for providing support for a stainless steel plate and make glue evenly distributed between the stainless steel plate and a base plate.
[0006] In order to solve the above technical problems, the mirror stainless steel ceiling construction equipment provided by the present invention includes: a floor; a ceiling, the ceiling is installed on the surface of the floor; a compression mechanism, the compression mechanism includes a bracket, a compression rod and a first spring, the surface of the ceiling is slidably connected to the compression rod, one end of the bracket is rotatably connected to the compression rod, and the side wall of the compression rod is installed with the first spring; a support mechanism, the top end of the support mechanism is rotatably connected to the bracket; a pulling mechanism, the pulling mechanism includes a steel wire rope, a rotating rod, a fixed column, a fixed pulley, and a third support rod, the side wall of the support mechanism is symmetrically rotatably connected to the rotating rod, the side wall of the rotating rod is fixedly connected to the fixed column, the inside of the fixed column is slidably connected to the third support rod, and the side wall of the third support rod is fixedly connected to the steel wire rope; the fixed pulley is symmetrically installed on the side wall of the support mechanism, and the side wall of the fixed pulley is slidably connected to the steel wire rope; a driving mechanism, the driving mechanism is connected to the The cam is connected to the third support rod by a spring, and the cam is connected to the third support rod by a spring.
[0007] Preferably, the suspended ceiling includes a hanger rod, a keel frame, a base plate and mirror stainless steel, a plurality of the hangers are installed on the side walls of the floor slab, and the keel frame is installed on the bottom end of the hanger rod; the bottom end of the keel frame is fixedly connected to the base plate, the side wall of the base plate is pasted with the mirror stainless steel, and the surface of the mirror stainless steel is slidably connected to the compression rod.
[0008] Preferably, the supporting mechanism comprises a first supporting rod, a screw, a base, a second supporting rod, a sliding groove and a blocking block, the side wall of the second supporting rod is symmetrically rotationally connected to the rotating rod, and the top end of the screw is fixedly connected to the second supporting rod; the interior of the first supporting rod is slidingly connected to the screw, and the bottom end of the first supporting rod is fixedly connected to the base; the side wall of the screw is symmetrically fixedly connected to the blocking block, the interior of the first supporting rod is symmetrically provided with the sliding groove, and the interior of the sliding groove is slidingly connected to the blocking block.
[0009] Preferably, the side walls of the second support rod and the third support rod are respectively connected to the bracket in a symmetrical rotation manner, and the fixed pulley is symmetrically mounted on the side wall of the second support rod.
[0010] Preferably, the driving mechanism includes a crank, a first box, a first gear, a second gear, a third gear, a fourth gear, a drum, a second box, a connecting shaft and a hexagonal prism, the side wall of the first support rod is fixedly connected to the first box, and the first box is internally rotatably connected to the first gear and the second gear; the first gear meshes with the second gear, and the first gear is threadedly connected to the screw rod; the second box is symmetrically installed on the side wall of the first box, and the second box is internally rotatably connected to the third gear, the fourth gear, the drum and the connecting shaft; the steel wire rope is wrapped around the side wall of the drum, and the side wall of the drum is fixedly connected to the third gear, and the third gear meshes with the fourth gear; the side wall of the connecting shaft is fixedly connected to the fourth gear, the hexagonal prism engages with the inside of the connecting shaft and the second gear, and one end of the crank is fixedly connected to the hexagonal prism.
[0011] Preferably, the diameter of the first gear is greater than the diameter of the second gear, and the diameter of the third gear is greater than the diameter of the fourth gear.
[0012] Preferably, the limiting mechanism includes a slot, a fixing ring, a protrusion, a connecting block and a through hole, the side wall of the connecting shaft is symmetrically provided with the slot, and the inside of the slot is slidably connected to the protrusion; the protrusion is installed inside the fixing ring, and the side wall of the fixing ring is symmetrically fixedly connected to the connecting block; the side wall of the second box body is provided with the through hole, and the connecting block is engaged with the through hole.
[0013] Preferably, the top end of the sliding rod abuts against the side wall of the mirror stainless steel, and the side wall of the sliding rod is sleeved with the second spring; the top end of the compression block is a hemispherical structure, and the compression block is slidably connected to the fixed block and the interior of the fixed column, the diameter of the compression block is equal to the inner diameter of the fixed block, and the diameter of the compression block is larger than the inner diameter of the third support rod, and the top end of the compression block abuts against the bottom end of the third support rod.
[0014] Preferably, the connecting mechanism includes a connecting plate, screws, connecting rods and rubber pads, a plurality of the connecting plates are fixed to the side walls of the base plate by the screws, the rubber pads are installed at the bottom ends of the connecting plates with arc-shaped side walls, the connecting plates and the rubber pads are in contact with the side walls of the mirror stainless steel; a plurality of the connecting rods are symmetrically installed on the side walls of the connecting plates, and the connecting rods are in contact with the side walls of the mirror stainless steel.
[0015] Preferably, a mirror stainless steel ceiling construction method comprises the following steps:
[0016] Step 1: Use a level to copy out a 500mm elevation control point near each wall corner or column corner in the room, and pop up a horizontal line; measure upward from the popped-up horizontal line to the design elevation of the ceiling surface plus 10-20mm, and use a chalk line to pop up a level line along the wall or column, which is the lower skin line of the secondary keel of the ceiling; at the same time, according to the ceiling plan, pop up the installation position line of the main keel on the wall perpendicular to the main keel; the main keel should be divided from the center of the ceiling to both sides, with a maximum spacing of no more than 1500mm, and no pre-buried hanging rod The fasteners should also mark the position of the hanger fixing point on the bottom surface of the concrete slab; use expansion bolts to fix the hanger to the floor slab, and the installed hanger should be rust-proofed; then fix the keel to the bottom end of the hanger in sequence to form the keel frame. After the keel frame is installed and accepted, the block line is popped out according to the specifications of the base plate and the gap of the joints, and then the base plate is fixed to the keel frame; fix multiple rows of the connecting plates to the side wall of the base plate in sequence through the screws;
[0017] Step 2: Apply glue to the side wall of the mirror stainless steel, move the mirror stainless steel to align it with the installation position on the surface of the substrate, insert one end of the mirror stainless steel into the interior of the connecting mechanism, and then squeeze the other end of the mirror stainless steel with force, and use the elasticity of the mirror stainless steel itself to make it snap into another connecting mechanism, and preliminarily install the mirror stainless steel on the surface of the substrate;
[0018] Step three: Install the mirror stainless steel along a direction perpendicular to the connecting mechanism. When a row of the mirror stainless steel is installed, move the supporting mechanism to the bottom of a piece of the mirror stainless steel, rotate the driving mechanism, and the driving mechanism drives the second supporting rod to move upward. The second supporting rod pushes the compression rod to move upward and contact the side wall of the mirror stainless steel. As the second supporting rod moves upward, the mirror stainless steel continuously squeezes the compression rod, so that the bracket rotates and stretches the first spring on the side wall of the second supporting rod, so that the compression rod rolls on the surface of the mirror stainless steel toward the direction of the connecting mechanism, so that the compression rod squeezes the glue in the center of the mirror stainless steel toward the edge of the mirror stainless steel. When the third supporting rod descends, the first spring contracts to reset the bracket. As the third supporting rod continues to rise and fall, the compression rod is driven to continuously roll on the surface of the mirror stainless steel, so that the glue is evenly distributed on the mirror stainless steel and the substrate. The second spring is pressed downwardly and the ...
[0019] Step 4: Install the compression mechanism in sequence below the mirror stainless steel according to the method of step 3. During the glue drying process, the compression mechanism and the support mechanism provide support for the mirror stainless steel. When the glue is dry, remove the compression mechanism from below the mirror stainless steel.
[0020] Compared with the related art, the mirror stainless steel ceiling construction equipment and construction method provided by the present invention have the following beneficial effects:
[0021] The present invention provides a mirror stainless steel ceiling construction equipment and a construction method thereof, when the mirror stainless steel is installed, the support mechanism is moved to a position directly below a piece of the mirror stainless steel, the driving mechanism is rotated, and the driving mechanism drives the second support rod to move upward, and the second support rod pushes the compression rod to move upward and contact the side wall of the mirror stainless steel. As the second support rod moves upward, the mirror stainless steel continuously squeezes the compression rod, so that the bracket rotates and stretches the first spring at the side wall of the second support rod, so that the compression rod rolls on the surface of the mirror stainless steel toward the direction of the connecting mechanism, so that the compression rod squeezes the glue at the center of the mirror stainless steel toward the edge of the mirror stainless steel. When the third support rod descends, the first spring contracts to reset the bracket; as the third support rod is continuously raised and lowered, the compression rod is driven to continuously roll on the surface of the mirror stainless steel, so that the glue is evenly distributed between the mirror stainless steel and the substrate; the driving mechanism is rotated The third support rod and the third support rod are pushed by the third spring to push the third support rod and the third support rod to push the surface of the mirror stainless steel. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A schematic diagram of the structure of the mirror stainless steel ceiling construction equipment and the construction method thereof provided by the present invention;
[0023] Figure 2 for Figure 1 The schematic diagram of the compression mechanism structure shown;
[0024] Figure 3 for Figure 1 The schematic diagram of the internal structure of the driving mechanism shown;
[0025] Figure 4 for Figure 2 An enlarged view of the structure at A shown;
[0026] Figure 5 for Figure 2 An enlarged view of the structure at B is shown;
[0027] Figure 6 for Figure 3 An enlarged view of the structure at position C is shown;
[0028] Figure 7 for Figure 2 Bottom view of the mirrored stainless steel structure shown;
[0029] Figure 8 for Figure 2 A top view of the compression rod structure is shown.
[0030] Numbers in the figure: 1, floor, 2, ceiling, 21, suspension rod, 22, keel frame, 23, base plate, 24, mirror stainless steel, 3, support mechanism, 31, first support rod, 32, screw rod, 33, base, 34, second support rod, 35, slide groove, 36, block, 4, pulling mechanism, 41, wire rope, 42, rotating rod, 43, fixed column, 44, fixed pulley, 45, third support rod, 5, driving mechanism, 51, crank, 52, first box, 53, first gear, 54, second gear, 55, third gear, 56, fourth gear, 57 , roller, 58, second box body, 59, connecting shaft, 510, hexagonal prism, 6, compression mechanism, 61, bracket, 62, compression rod, 63, first spring, 7, extrusion mechanism, 71, second spring, 72, slide rod, 73, fixed block, 74, groove, 75, compression block, 76, limiting ring, 77, limiting rod, 78, third spring, 8, connecting mechanism, 81, connecting plate, 82, screw, 83, connecting rod, 84, rubber pad, 9, limiting mechanism, 91, slot, 92, fixing ring, 93, protrusion, 94, connecting block, 95, through hole. DETAILED DESCRIPTION
[0031] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.
[0032] Please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 , Figure 7 and Figure 8A mirror stainless steel ceiling construction equipment and a construction method thereof include: a floor 1; a ceiling 2, the ceiling 2 is installed on the surface of the floor 1; a compression mechanism 6, the compression mechanism 6 includes a bracket 61, a compression rod 62 and a first spring 63, the surface of the ceiling 2 is slidably connected to the compression rod 62, one end of the bracket 61 is rotatably connected to the compression rod 62, and the side wall of the compression rod 62 is installed with the first spring 63; a supporting mechanism 3, the top end of the supporting mechanism 3 is rotatably connected to the bracket 61; a pulling mechanism 4, the pulling mechanism 4 includes a steel wire rope 41 , a rotating rod 42, a fixed column 43, a fixed pulley 44, and a third support rod 45. The side wall of the support mechanism 3 is symmetrically connected to the rotating rod 42 by rotation. The side wall of the rotating rod 42 is fixedly connected to the fixed column 43. The inside of the fixed column 43 is slidably connected to the third support rod 45. The side wall of the third support rod 45 is fixedly connected to the wire rope 41. The fixed pulley 44 is symmetrically installed on the side wall of the support mechanism 3, and the side wall of the fixed pulley 44 is slidably connected to the wire rope 41. A driving mechanism 5 is provided, and the driving mechanism 5 connects the support mechanism 3 and the wire rope 41; extrusion mechanism 7, the extrusion mechanism 7 includes a second spring 71, a slide bar 72, a fixed block 73, a groove 74, a compression block 75, a limiting ring 76, a limiting rod 77 and a third spring 78, the interior of the fixed column 43 is slidably connected to the fixed block 73, and the fixed block 73 is fixedly connected to the third support rod 45; the side walls of the fixed block 73 and the fixed column 43 are respectively provided with the groove 74, the interior of the groove 74 is slidably connected to the limiting rod 77 and the limiting ring 76, and the side wall of the limiting rod 77 is sleeved with the third spring 78, One end of the third spring 78 is fixedly connected to the limiting ring 76; the fixed column 43 and the internal sliding connection of the third support rod 45 are connected to the sliding rod 72, and the two ends of the second spring 71 are respectively connected to the sliding rod 72 and the side wall of the third support rod 45; the bottom end of the sliding rod 72 is fixedly connected to the compression block 75, and the limiting rod 77 is connected to the compression block 75 and the side wall of the sliding rod 72; the limiting mechanism 9 is connected to the driving mechanism 5; the connecting mechanism 8 is installed on the side wall of the ceiling 2.
[0033] The suspended ceiling 2 includes a hanger 21, a keel frame 22, a base plate 23 and a mirror stainless steel 24. A plurality of the hangers 21 are installed on the side walls of the floor 1, and the keel frame 22 is installed on the bottom end of the hanger 21; the bottom end of the keel frame 22 is fixedly connected to the base plate 23, the side wall of the base plate 23 is pasted with the mirror stainless steel 24, and the surface of the mirror stainless steel 24 is slidably connected to the compression rod 62, in order to facilitate the hanger 21 and the keel frame 22 to provide support to the base plate 23, it is convenient to paste the mirror stainless steel 24 on the surface of the base plate 23.
[0034] The side walls of the second support rod 34 and the third support rod 45 are symmetrically rotated and connected to the bracket 61 , so that the second support rod 34 and the third support rod 45 can drive the compression mechanism 6 to move upward and contact the mirror stainless steel 24 .
[0035] The driving mechanism 5 includes a crank 51, a first box 52, a first gear 53, a second gear 54, a third gear 55, a fourth gear 56, a roller 57, a second box 58, a connecting shaft 59 and a hexagonal prism 510. The side wall of the first support rod 31 is fixedly connected to the first box 52, and the first box 52 is internally rotatably connected to the first gear 53 and the second gear 54; the first gear 53 meshes with the second gear 54, and the first gear 53 is threadedly connected to the screw rod 32; the supporting mechanism 3 includes a first support rod 31, a screw rod 32, a base 33, a second support rod 34, a slide groove 35 and a block 36; the side wall of the second support rod 34 is symmetrically rotatably connected to the rotating rod 42, the top of the screw 32 is fixedly connected to the second support rod 34, and the side wall of the second support rod 34 is symmetrically installed with the fixed pulley 44; the first support The screw rod 32 is slidably connected to the inside of the support rod 31, and the bottom end of the first support rod 31 is fixedly connected to the base 33; the side wall of the screw rod 32 is symmetrically fixedly connected to the block 36, the inside of the first support rod 31 is symmetrically provided with the sliding groove 35, and the inside of the sliding groove 35 is slidably connected to the block 36. In order to facilitate the crank 51 to drive the second gear 54 to rotate, and the second gear 54 drives the first gear 53 to rotate, the first gear 53 and the screw rod 32 are threadedly connected, and the principle of spiral transmission is used to make the first gear 53 drive the screw rod 32 to move up and down inside the first support rod 31, and the screw 32 drives the block 36 to slide inside the sliding groove 35, so as to prevent the screw 32 from rotating inside the first support rod 31 and facilitate the movement of the screw 32 inside the first support rod 31.
[0036] The second box body 58 is symmetrically installed on the side wall of the first box body 52, and the interior of the second box body 58 is rotatably connected to the third gear 55, the fourth gear 56, the drum 57 and the connecting shaft 59; the side wall of the drum 57 is wrapped around the wire rope 41, and the side wall of the drum 57 is fixedly connected to the third gear 55, and the third gear 55 meshes with the fourth gear 56; the side wall of the connecting shaft 59 is fixedly connected to the fourth gear 56, the hexagonal prism 510 is engaged with the interior of the connecting shaft 59 and the second gear 54, and one end of the crank 51 is fixedly connected to the hexagonal prism 510; the limiting mechanism 9 includes a slot 91, a fixing ring 92, a protrusion 93, a connecting block 94 and a through hole 95, the side wall of the connecting shaft 59 is symmetrically provided with the slot 91, and the interior of the slot 91 is slidably connected to the protrusion 93; the protrusion 93 is installed inside the fixing ring 92 The side wall of the fixing ring 92 is symmetrically fixedly connected to the connecting block 94; the side wall of the second box body 58 is provided with the through hole 95, and the connecting block 94 engages with the through hole 95. In order to facilitate the movement of the crank 51, the hexagonal prism 510 is made to enter the interior of the connecting shaft 59. The rotation of the crank 51 drives the hexagonal prism 510, the connecting shaft 59 and the fourth gear 56 to rotate, and the fourth gear 56 drives the third gear 55 and the drum 57 to rotate, so that the wire rope 41 is wound around the side wall of the drum 57. When the wire rope 41 needs to be fixed, the fixing ring 92 is slid, and the fixing ring 92 drives the protrusion 93 to move inside the slot 91. At the same time, the fixing ring 92 drives the connecting block 94 to enter the interior of the through hole 95, thereby fixing the connecting shaft 59 to the side wall of the second box body 58 to prevent the connecting shaft 59 from rotating.
[0037] The diameter of the first gear 53 is greater than that of the second gear 54. In order to facilitate the second gear 54 to drive the first gear 53 to rotate more labor-savingly, the diameter of the third gear 55 is greater than that of the fourth gear 56. In order to enable the fourth gear 56 to push the third gear 55 to rotate more labor-savingly.
[0038] The top end of the sliding rod 72 abuts against the side wall of the mirror stainless steel 24, and the side wall of the sliding rod 72 is fitted with the second spring 71; the top end of the compression block 75 is a hemispherical structure, and the compression block 75 is slidably connected to the fixed block 73 and the interior of the fixed column 43. The diameter of the compression block 75 is equal to the inner diameter of the fixed block 73, and the diameter of the compression block 75 is larger than the inner diameter of the third support rod 45. The top end of the compression block 75 abuts against the bottom end of the third support rod 45. In order to facilitate the compression block 75 to enter the interior of the fixed block 73, the limiting rod 77 is squeezed into the interior of the fixed column 43, and the compression block 75 is prevented from entering the interior of the third support rod 45.
[0039] The connecting mechanism 8 includes a connecting plate 81, a screw 82, a connecting rod 83 and a rubber pad 84. A plurality of the connecting plates 81 are fixed to the side wall of the base plate 23 by the screws 82. The rubber pad 84 is installed at the bottom end of the connecting plate 81 with an arc-shaped side wall. The connecting plate 81 and the rubber pad 84 abut against the side wall of the mirror stainless steel 24. A plurality of the connecting rods 83 are symmetrically installed on the side wall of the connecting plate 81, and the connecting rods 83 abut against the side wall of the mirror stainless steel 24. In order to facilitate the two ends of the mirror stainless steel 24 to enter the interior of the connecting plate 81, and the rubber pad 84 and the mirror stainless steel 24 The mirror stainless steel 24 is in contact with the connecting plate 81 to prevent damage to the mirror stainless steel 24, and the rubber pad 84 presses the mirror stainless steel 24 upward to make the mirror stainless steel 24 close to the substrate 23; and the glue discharged from the inside of the mirror stainless steel 24 enters the inside of the connecting plate 81, and the side wall of the connecting plate 81 is arc-shaped to increase the contact area between the glue and the connecting plate 81, and a plurality of connecting rods 83 are installed inside the connecting plate 81, and the connecting rods 83 are in contact with the glue to increase the strength of the glue inside the connecting plate 81 after drying, thereby increasing the stability and firmness of the mirror stainless steel 24 inside the connecting plate 81.
[0040] A mirror stainless steel ceiling construction method comprises the following steps:
[0041] Step 1: Use a level to copy out a 500mm elevation control point near each wall corner or column corner in the room, and pop out a horizontal line; measure upward from the popped-up horizontal line to the design elevation of the ceiling surface plus 10-20mm, and use a chalk line to pop out a level line along the wall or column, which is the lower skin line of the secondary keel of the ceiling; at the same time, according to the ceiling plan, pop out the installation position line of the main keel on the wall perpendicular to the main keel; the main keel should be divided from the center of the ceiling to both sides, with a maximum spacing of no more than 1500mm, and if the hanger fasteners are not embedded in advance, they should also be on the concrete slab The bottom surface indicates the position of the hanger fixing point; the hanger 21 is fixed to the floor 1 with expansion bolts, and the installed hanger 21 should be rust-proofed; the keels are then fixed to the bottom ends of the hangers 21 in sequence to form the keel frame 22. After the keel frame 22 is installed and accepted, the block line is popped out according to the specifications of the base plate 23 and the gap of the joints, and then the base plate 23 is fixed to the keel frame 22; multiple rows of the connecting plates 81 are fixed to the side walls of the base plate 23 in sequence with the screws 82;
[0042] Step 2: Apply glue to the side wall of the mirror stainless steel 24, move the mirror stainless steel 24 to align it with the installation position on the surface of the substrate 23, and then insert one end of the mirror stainless steel 24 into the interior of the connecting plate 81, so that the connecting rod 83 contacts the side wall of the mirror stainless steel 24; the mirror stainless steel 24 enters the interior of the connecting plate 81 to squeeze the rubber pad 84, the rubber pad 84 prevents the mirror stainless steel 24 from being damaged, and the rubber pad 84 squeezes the mirror stainless steel 24 upward, so that the mirror stainless steel 24 is close to the substrate 23; then squeeze the other end of the mirror stainless steel 24 hard, use the elasticity of the mirror stainless steel 24 itself to make it snap into another connecting mechanism 8, and preliminarily install the mirror stainless steel 24 on the surface of the substrate 23;
[0043] Step 3: Install the mirror stainless steel 24 (see the attached Figure 7The mirror stainless steel 24 is installed in rows horizontally). When a row of the mirror stainless steel 24 is installed, the support mechanism 3 is moved to the position directly below a piece of the mirror stainless steel 24, the hexagonal prism 510 is inserted into the second gear 54, and the crank 51 is rotated. The crank 51 drives the second gear 54 to rotate, and the second gear 54 drives the first gear 53 to rotate. The first gear 53 is threadedly connected to the screw rod 32. The principle of spiral transmission is used to make the first gear 53 drive the screw rod 32 to move up and down inside the first support rod 31, and the screw rod 32 drives the block 36 to slide inside the slide groove 35, so as to prevent the screw rod 32 from rotating inside the first support rod 31 and facilitate the screw rod 32 to move inside the first support rod 31, so that the screw 32 drives the second support rod 34 upward The second support rod 34 pushes the compression rod 62 to move upward and contact the side wall of the mirror stainless steel 24. As the second support rod 34 moves upward, the mirror stainless steel 24 continuously squeezes the compression rod 62, so that the bracket 61 rotates and stretches on the side wall of the second support rod 34 and stretches the first spring 63, so that the compression rod 62 rolls on the surface of the mirror stainless steel 24 toward the direction of the connecting mechanism 8, so that the compression rod 62 squeezes the glue in the center of the mirror stainless steel 24 toward the edge of the mirror stainless steel 24. When the third support rod 45 descends, the first spring 63 contracts to reset the bracket 61. As the third support rod 45 continues to rise and fall, the compression rod 62 is driven to continuously roll on the surface of the mirror stainless steel 24, so that the glue is evenly distributed between the mirror stainless steel 24 and the substrate 23.
[0044] Move the crank 51 to make the hexagonal prism 510 enter the interior of the connecting shaft 59. The crank 51 rotates to drive the hexagonal prism 510, the connecting shaft 59 and the fourth gear 56 to rotate. The fourth gear 56 drives the third gear 55 and the drum 57 to rotate, so that the wire rope 41 is wound around the side wall of the drum 57. The wire rope 41 enters the interior of the second box 58 to drive the rotating rod 42, the fixed column 43, the third support rod 45 and the slide bar 72 to rotate upward, so that the slide bar 72 contacts the side wall of the mirror stainless steel 24 (as shown in the attached figure). Figure 2 As the rotating rod 42 continues to rotate upward, the sliding rod 72 is squeezed and moves downward to compress the second spring 71. After the sliding rod 72 drives the compression block 75 to move and separate from the interior of the fixed block 73, the limiting rod 77 is pushed by the third spring 78 to slide out from the interior of the fixed column 43 and enter the interior of the fixed block 73 (as shown in the attached figure). Figure 4As shown), the fixing block 73 is freed from the restraint, and as the steel wire rope 41 continues to move, the third support rod 45 and the fixing block 73 are pushed to move vertically upward, so that the compression mechanism 6 at the top of the third support rod 45 moves to squeeze the surface of the mirror stainless steel 24; when the steel wire rope 41 slides out from the interior of the second box body 58, under the action of the second spring 71, the third support rod 34 and the fixing block 73 move and reset into the interior of the fixing column 43, and at the same time, the second spring 71 drives the sliding rod 72 to move and reset, so that the compression block 75 enters the interior of the fixing block 73, so that the compression block 75 squeezes the limiting rod 77, so that the limiting rod 77 slides out from the interior of the fixing block 73 into the interior of the fixing column 43, and fixes the fixing block 73 in the interior of the fixing column 43.
[0045] Similarly, as the crank 51 is rotated back and forth, the third support rod 45 is continuously raised and lowered, so that the compression mechanism 6 continuously squeezes the mirror stainless steel 24, so that the glue is evenly distributed, and the glue on the surface of the mirror stainless steel 24 is squeezed to the connection between the two mirror stainless steels 24 and the inside of the connecting mechanism 8, further improving the firmness of the mirror stainless steel 24. When the compression of the mirror stainless steel 24 is completed, the compression mechanism 6 is in an open state (as shown in the attached Figure 1 As shown), the fixing ring 92 is slid at this time, and the fixing ring 92 drives the protrusion 93 to move inside the slot 91, and at the same time, the fixing ring 92 drives the connecting block 94 to enter the through hole 95, thereby fixing the connecting shaft 59 to the side wall of the second box body 58 to prevent the connecting shaft 59 from rotating, so that the compression mechanism 6 is in an open state to improve the support of the mirror stainless steel 24;
[0046] Step 4: Install the compression mechanism 6 below the mirror stainless steel 24 in sequence according to the method of step 3. During the glue drying process, the compression mechanism 6 and the support mechanism 3 provide support for the mirror stainless steel 24. When the glue is dry, the compression mechanism 6 can be removed from below the mirror stainless steel 24.
[0047] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A mirror stainless steel ceiling construction equipment, characterized in that: include: Floor (1); A suspended ceiling (2), the suspended ceiling (2) being installed on the surface of the floor slab (1); A compression mechanism (6), the compression mechanism (6) comprising a bracket (61), a compression rod (62) and a first spring (63), the surface of the suspended ceiling (2) being slidably connected to the compression rod (62), one end of the bracket (61) being rotatably connected to the compression rod (62), and the first spring (63) being installed on a side wall of the compression rod (62); A supporting mechanism (3), the top end of the supporting mechanism (3) being rotatably connected to the bracket (61); A pulling mechanism (4), the pulling mechanism (4) comprising a steel wire rope (41), a rotating rod (42), a fixed column (43), a fixed pulley (44), and a third support rod (45); the side wall of the support mechanism (3) is symmetrically connected to the rotating rod (42), the side wall of the rotating rod (42) is fixedly connected to the fixed column (43), the interior of the fixed column (43) is slidably connected to the third support rod (45), and the side wall of the third support rod (45) is fixedly connected to the steel wire rope (41); the fixed pulley (44) is symmetrically mounted on the side wall of the support mechanism (3), and the side wall of the fixed pulley (44) is slidably connected to the steel wire rope (41); A driving mechanism (5), the driving mechanism (5) connecting the supporting mechanism (3) and the steel wire rope (41); The extrusion mechanism (7) comprises a second spring (71), a sliding rod (72), a fixed block (73), a groove (74), a compression block (75), a limiting ring (76), a limiting rod (77) and a third spring (78); the interior of the fixed column (43) is slidably connected to the fixed block (73); the fixed block (73) and the third support rod (45) are fixedly connected; the side walls of the fixed block (73) and the fixed column (43) are respectively provided with the groove (74); the interior of the groove (74) is slidably connected to the limiting rod (77) and the limiting rod (45); The third spring (78) is sleeved on the side wall of the limiting rod (77), and one end of the third spring (78) is fixedly connected to the limiting ring (76); the interior of the fixing column (43) and the third support rod (45) is slidably connected to the sliding rod (72), and the two ends of the second spring (71) are respectively fixedly connected to the side wall of the sliding rod (72) and the third support rod (45); the bottom end of the sliding rod (72) is fixedly connected to the compression block (75), and the limiting rod (77) is slidably connected to the compression block (75) and the side wall of the sliding rod (72); A limiting mechanism (9), the limiting mechanism (9) being connected to the driving mechanism (5); A connecting mechanism (8), wherein the connecting mechanism (8) is installed on a side wall of the suspended ceiling (2).
2. The mirror stainless steel ceiling construction equipment according to claim 1 is characterized in that: The suspended ceiling (2) comprises a suspension rod (21), a keel frame (22), a base plate (23) and mirror stainless steel (24); a plurality of the suspension rods (21) are installed on the side wall of the floor slab (1), and the keel frame (22) is installed on the bottom end of the suspension rod (21); the bottom end of the keel frame (22) is fixedly connected to the base plate (23), the side wall of the base plate (23) is adhered to the mirror stainless steel (24), and the surface of the mirror stainless steel (24) is slidably connected to the compression rod (62).
3. The mirror stainless steel ceiling construction equipment according to claim 2 is characterized in that: The support mechanism (3) comprises a first support rod (31), a screw rod (32), a base (33), a second support rod (34), a slide groove (35) and a block (36); the side wall of the second support rod (34) is symmetrically rotationally connected to the rotating rod (42), and the top end of the screw rod (32) is fixedly connected to the second support rod (34); the interior of the first support rod (31) is slidably connected to the screw rod (32), and the bottom end of the first support rod (31) is fixedly connected to the base (33); the side wall of the screw rod (32) is symmetrically fixedly connected to the block (36), the interior of the first support rod (31) is symmetrically provided with the slide groove (35), and the interior of the slide groove (35) is slidably connected to the block (36).
4. The mirror stainless steel ceiling construction equipment according to claim 3 is characterized in that: The side walls of the second support rod (34) and the third support rod (45) are respectively symmetrically rotatably connected to the bracket (61), and the fixed pulley (44) is symmetrically mounted on the side wall of the second support rod (34).
5. The mirror stainless steel ceiling construction equipment according to claim 4 is characterized in that: The driving mechanism (5) comprises a crank (51), a first housing (52), a first gear (53), a second gear (54), a third gear (55), a fourth gear (56), a roller (57), a second housing (58), a connecting shaft (59) and a hexagonal prism (510); the side wall of the first support rod (31) is fixedly connected to the first housing (52); the first housing (52) is internally rotatably connected to the first gear (53) and the second gear (54); the first gear (53) meshes with the second gear (54); the first gear (53) is threadedly connected to the screw rod (32); the side wall of the first housing (52) is symmetrically mounted with the second gear (54); The second housing (58) is rotatably connected to the third gear (55), the fourth gear (56), the drum (57) and the connecting shaft (59); the side wall of the drum (57) is wound around the steel wire rope (41); the side wall of the drum (57) is fixedly connected to the third gear (55), and the third gear (55) is meshed with the fourth gear (56); the side wall of the connecting shaft (59) is fixedly connected to the fourth gear (56); the hexagonal prism (510) is engaged with the connecting shaft (59) and the inside of the second gear (54), and one end of the crank (51) is fixedly connected to the hexagonal prism (510).
6. The mirror stainless steel ceiling construction equipment according to claim 5 is characterized in that: The diameter of the first gear (53) is greater than the diameter of the second gear (54), and the diameter of the third gear (55) is greater than the diameter of the fourth gear (56).
7. The mirror stainless steel ceiling construction equipment according to claim 6, characterized in that: The limiting mechanism (9) comprises a slot (91), a fixing ring (92), a protrusion (93), a connecting block (94) and a through hole (95); the side wall of the connecting shaft (59) is symmetrically provided with the slot (91); the inside of the slot (91) is slidably connected to the protrusion (93); the inside of the fixing ring (92) is provided with the protrusion (93); the side wall of the fixing ring (92) is symmetrically fixedly connected to the connecting block (94); the side wall of the second box body (58) is provided with the through hole (95), and the connecting block (94) is engaged with the through hole (95).
8. The mirror stainless steel ceiling construction equipment according to claim 7, characterized in that: The top end of the slide bar (72) abuts against the side wall of the mirror stainless steel (24), and the side wall of the slide bar (72) is sleeved with the second spring (71); the top end of the compression block (75) is a hemispherical structure, and the compression block (75) is slidably connected to the inside of the fixed block (73) and the fixed column (43); the diameter of the compression block (75) is equal to the inner diameter of the fixed block (73), and the diameter of the compression block (75) is greater than the inner diameter of the third support rod (45); the top end of the compression block (75) abuts against the bottom end of the third support rod (45).
9. The mirror stainless steel ceiling construction equipment according to claim 8, characterized in that: The connecting mechanism (8) comprises a connecting plate (81), a screw (82), a connecting rod (83) and a rubber pad (84); a plurality of the connecting plates (81) are fixed to the side wall of the base plate (23) by means of the screws (82); the rubber pad (84) is installed at the bottom end of the connecting plate (81) whose side wall is arc-shaped; the connecting plate (81) and the rubber pad (84) abut against the side wall of the mirror-finished stainless steel (24); a plurality of the connecting rods (83) are symmetrically installed on the side wall of the connecting plate (81), and the connecting rods (83) abut against the side wall of the mirror-finished stainless steel (24).
10. A mirror stainless steel ceiling construction method, used for the mirror stainless steel ceiling construction equipment described in claim 9, characterized in that: The following steps are involved: Step 1: Use a level to copy out a 500mm elevation control point near each wall corner or column corner in the room, and pop out a horizontal line; measure upward from the popped-up horizontal line to the design elevation of the ceiling surface plus 10-20mm, and use a chalk line to pop out a level line along the wall or column, which is the lower skin line of the secondary keel of the ceiling; at the same time, according to the ceiling plan, pop out the installation position line of the main keel on the wall perpendicular to the main keel; the main keel should be divided from the center of the ceiling to both sides, with a maximum spacing of no more than 1500mm. If the hanger fasteners are not embedded in advance, the position of the hanger fixing point should also be marked on the bottom of the concrete slab. ; Use expansion bolts to fix the suspension rod (21) on the floor slab (1); the installed suspension rod (21) should be subjected to rust prevention treatment; then fix the keels on the bottom ends of the suspension rods (21) in sequence to form the keel frame (22); after the keel frame (22) is installed and accepted, pop up the block line according to the specifications of the base plate (23) and the gap between the joints, and then fix the base plate (23) on the keel frame (22); fix multiple rows of the connecting plates (81) on the side walls of the base plate (23) in sequence by means of the screws (82); Step 2: Apply glue to the side wall of the mirror stainless steel (24), move the mirror stainless steel (24) to align it with the installation position on the surface of the substrate (23), insert one end of the mirror stainless steel (24) into the interior of the connecting mechanism (8), and then squeeze the other end of the mirror stainless steel (24) with force, and use the elasticity of the mirror stainless steel (24) to make it snap into another connecting mechanism (8), and preliminarily install the mirror stainless steel (24) on the surface of the substrate (23); Step 3: Install the mirror stainless steel (24) along a direction perpendicular to the connecting mechanism (8). When a row of the mirror stainless steel (24) is installed, move the supporting mechanism (3) to the position directly below a piece of the mirror stainless steel (24), rotate the driving mechanism (5), and the driving mechanism (5) drives the second supporting rod (34) to move upward. The second supporting rod (34) pushes the compression rod (62) to move upward and contact the side wall of the mirror stainless steel (24). As the second supporting rod (34) moves upward, the mirror stainless steel (24) continuously squeezes the compression rod (62), so that the bracket (61) is on the side of the second supporting rod (34). The wall rotates to open and stretch the first spring (63), so that the compression rod (62) rolls on the surface of the mirror stainless steel (24) toward the direction of the connecting mechanism (8), so that the compression rod (62) squeezes the glue in the center of the mirror stainless steel (24) toward the edge of the mirror stainless steel (24); when the third support rod (45) descends, the first spring (63) contracts to reset the bracket (61); as the third support rod (45) continues to rise and fall, the compression rod (62) is driven to continuously roll on the surface of the mirror stainless steel (24), so that the glue is evenly distributed between the mirror stainless steel (24) and the substrate (23); the rotation of the The driving mechanism (5) drives the steel wire rope (41) to move, and the steel wire rope (41) drives the rotating rod (42), the fixed column (43), the third support rod (45) and the sliding rod (72) to rotate, so that the sliding rod (72) contacts the side wall of the mirror stainless steel (24). As the rotating rod (42) continues to rotate upward, the sliding rod (72) is squeezed and moves downward to compress the second spring (71). After the sliding rod (72) drives the compression block (75) to move and separate from the inside of the fixed block (73), the limiting rod (77) is pushed by the third spring (78) so that the limiting rod (77) is separated from the fixed column (43). The inside of the third support rod (43) slides out and enters the inside of the fixed block (73). As the steel wire rope (41) continues to move, the third support rod (45) and the fixed block (73) are pushed upward, so that the compression mechanism (6) at the top of the third support rod (45) squeezes the surface of the mirror stainless steel (24). Similarly, as the third support rod (45) rises and falls, the compression mechanism (6) continuously squeezes the mirror stainless steel (24), so that the glue is evenly distributed, and the glue on the surface of the mirror stainless steel (24) is squeezed to the connection between the two pieces of mirror stainless steel (24) and the inside of the connecting mechanism (8), so as to further improve the firmness of the mirror stainless steel (24) adhesion; Step 4: Install the compression mechanism (6) below the mirror stainless steel (24) in sequence according to the method of step 3. During the glue drying process, the compression mechanism (6) and the support mechanism (3) provide support for the mirror stainless steel (24). When the glue is dry, the compression mechanism (6) can be removed from below the mirror stainless steel (24).
Citation Information
Patent Citations
Ceiling mounting structure and construction method
CN115030389A
Architectural ornament suspended ceiling based on BIM technology
CN211058124U
Light steel keel quick-assembly ceiling system
CN213477350U
Suspended ceiling fixing mechanism for building decoration
CN214144340U
Ceiling stuff adhere exclusive use driver machine
KR200319308Y1