A method for hoisting and installing a steel frame
Through the cooperation of the temporary support device and the rotatable center column, the difficulty and accuracy of the steel frame installation are solved, efficient hoisting and splicing are achieved, and the accuracy and stability of the installation are ensured.
Patent Information
- Application Number
- CN202310003047.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-01-03
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2043-01-03
AI Technical Summary
During the installation process, the steel frame is difficult to hoist at one time due to its large span and multi-arm joint characteristics, and the splicing accuracy is difficult to control after single-arm hoisting and splicing, resulting in difficulty in node alignment.
Temporary support devices are used to support the main body of the steel frame and the connecting sections, and the arm segment units are spliced in sequence, broken into parts, and the main body of the steel frame and the connecting sections are pre-spliced and installed on the ground, using rotatable center columns and counterweight bars. Adjust the center of gravity to ensure installation accuracy and stability.
It greatly reduces the difficulty of hoisting and improves the installation accuracy, ensuring the position accuracy and overall stability of the steel frame, reducing the hoisting movement range and other structural interference, and improving the accuracy of the splicing position.
Smart Images

Figure CN116084706B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of steel structure construction methods, and in particular to a method for hoisting and installing a steel frame. Background Art
[0002] Steel structure is a structure made of steel materials and is one of the main types of building structures. The structure is mainly composed of steel beams, steel columns, steel trusses and other components made of steel and steel plates. The components or parts are usually connected by welds, bolts or rivets. Because of its light weight and simple construction, it is widely used in large factories, venues, super high-rise buildings and other fields.
[0003] During the installation process of the steel frame, a crane is needed to lift the steel frame, move it to the specified height and position, and then weld or bolt it to install.
[0004] However, some special steel structures are difficult to install using conventional lifting methods, such as Fig. 9 The free ends of the multiple arms of the steel frame shown are used for splicing with the vertical columns 10. The entire steel frame has the characteristics of a large span and multiple arms connected to a common node. Its volume and weight are large and it is difficult to hoist it all at once. If the multiple arms are split and hoisted separately and spliced and fixed, although the volume and weight can be reduced for easy hoisting, the method of hoisting and splicing with a single arm, that is, the multiple arms are assembled separately, the span is too long and the splicing accuracy is difficult to control, which easily leads to difficulty in aligning the multiple arms when spliced at the middle node. Summary of the invention
[0005] In order to simplify the difficulty of hoisting and improve the installation accuracy, the present application provides a hoisting and installation method of a steel frame.
[0006] The present application provides a method for hoisting and installing a steel frame, which adopts the following technical solution:
[0007] A method for hoisting and installing a steel frame comprises the following steps:
[0008] S1. Configuring the steel frame: The steel frame includes a steel frame body and a plurality of sub-bracket arm segments. The surrounding side of the steel frame body has a plurality of connecting segments. One connecting segment corresponds to one sub-bracket arm segment. One sub-bracket arm segment includes a plurality of arm segment units. The steel frame body and the connecting segments are assembled, and the steel frame body is hoisted on a temporary support device.
[0009] S2, hoisting a single boom section unit to one of the connecting sections and splicing and connecting it, and completing the splicing and connection of the boom section units on each connecting section in turn;
[0010] S3, the hoisting boom section unit is spliced and connected with each installed boom section unit in turn until the splicing and connection of all boom section units is completed;
[0011] S4. Complete the installation and connection of the end arm segment unit and each column in sequence.
[0012] By adopting the above technical solution, temporary supporting devices are used to support the steel frame main body and connecting sections with higher connection requirements, and then starting from the connecting sections of the steel frame, the arm section units are spliced in sequence, that is, breaking the whole into parts, which greatly reduces the difficulty of lifting.
[0013] Secondly, the main body of the steel frame and the connecting sections have been pre-spliced and installed on the ground, that is, the steps with the highest installation accuracy requirements are completed on the ground, and then the temporary support device supports the main body of the steel frame to ensure the position accuracy of the main body of the steel frame, which facilitates the subsequent splicing accuracy.
[0014] Furthermore, the arm segment units in each direction are spliced in sequence, rather than splicing the arm segment units in the same direction at one time. In this way, the temporary support device is less affected by the eccentric gravity, which can ensure the position accuracy of the steel frame body, thereby further improving the connection accuracy of subsequent arm segment units.
[0015] Optionally, the temporary support device includes a base, a first center column, a stabilizing sleeve, and a second center column. The first center column and the stabilizing sleeve are both vertically arranged at the center of the base. The second center column is vertically slidably connected to the stabilizing sleeve. The upper end of the second center column is fixed to the steel frame body. A lifting hydraulic cylinder is provided between the first center column and the second center column, and the lifting hydraulic cylinder is used to drive the second center column to move vertically.
[0016] By adopting the above technical solution and setting a lifting hydraulic cylinder, the height of the second center column can be fine-tuned, so as to fine-adjust the height of the steel frame body to adapt to the actual installation position requirements.
[0017] Optionally, a plug rod is vertically and eccentrically fixed to the upper end of the first center column, and a socket for sliding the plug rod into the lower end of the second center column; the first center column is rotatably connected to the base around its own axis, and the base is provided with a first driving assembly for driving the first center column to rotate; in step S2, when the previous arm segment unit is installed, the first driving assembly drives the first center column to rotate, so as to drive the second center column, the steel frame body, the connecting segment, and the installed arm segment unit to rotate in turn, so that the uninstalled connecting segment moves to the position to be hoisted, waiting for the new arm segment unit to be hoisted into place and assembled and connected.
[0018] By adopting the above technical solution, each time the arm segment unit is installed, the second central column drives the frame body, the connecting segment, and the installed arm segment unit to rotate, so that the uninstalled connecting segment moves to the position to be hoisted. In this way, the hoisting position remains in place, and there is no need to hoist the new arm segment unit to another connecting segment for assembly, thereby reducing the excessive hoisting movement range to reduce interference with other building structures. In addition, hoisting in place can ensure the accuracy of the splicing position to improve installation accuracy.
[0019] Optionally, the base is a disc, and two counterweight bars are provided on the upper surface of the base along its radial direction, one end of the counterweight bar is connected to the stabilizing sleeve for rotation around the axis of the base, and the base is provided with a second driving component for driving the counterweight bar to rotate.
[0020] By adopting the above technical solution, the shape and center of gravity of the steel frame supported and to be installed on the temporary support device are constantly changing as they are spliced one by one. Therefore, by providing a rotatable counterweight bar, the center of gravity of the temporary support device can be adjusted according to the change of the center of gravity of the steel frame, thereby ensuring the overall stability of the steel frame and improving the installation accuracy.
[0021] In addition, the setting of double counterweight bars makes the adjustment of the center of gravity more accurate.
[0022] Optionally, a limiting sleeve is welded to the outer side of the stabilizing sleeve, and an arc-shaped force-bearing plate is fixed to one end of the counterweight bar close to the stabilizing sleeve. The force-bearing plate is located in the gap between the limiting sleeve and the stabilizing sleeve, and the concave arc surface of the force-bearing plate fits the outer circumferential surface of the stabilizing sleeve.
[0023] By adopting the above technical solution, the gravity of the counterweight bar will be applied to the limit sleeve through the force plate, and then applied to the stabilizing sleeve and the second center column. The force transmission is more direct, thereby making the center of gravity adjustment effect of the overall structure better.
[0024] In addition, the force-bearing plate fits the stabilizing sleeve to achieve a rotatable connection effect between the counterweight bar and the stabilizing sleeve.
[0025] Optionally, a counterweight block and a third driving assembly are provided on the counterweight bar, and the third driving assembly is used to drive the counterweight block to slide along the length direction of the counterweight bar.
[0026] By adopting the above technical solution, according to the needs of center of gravity adjustment, the third drive assembly can also be used to drive the counterweight block to move in the radial direction of the base to adjust the position of the counterweight block, thereby performing a secondary center of gravity adjustment (rotation of the counterweight bar is a primary center of gravity adjustment) with higher accuracy.
[0027] Optionally, it also includes a circular leveling plate located directly below the base, the lower end of the first center column is connected to the ball head at the center of the leveling plate, the contact surface between the leveling plate and the base is densely covered with multiple pressure sensors, and the pressure sensors are electrically connected to the second drive assembly through a controller.
[0028] By adopting the above technical solution, when the temporary support device is tilted due to the gravity of the irregular steel frame, the first center column and the second center column drive the base to shift. At this time, the local pressure sensor located between the base and the leveling plate is under pressure, and the other part of the pressure sensors is not under pressure. At this time, the pressure sensor transmits the pressure signal to the controller, and then the controller controls the operation of the second drive assembly, thereby driving the counterweight bar to rotate to adjust the center of gravity of the base until the pressure information on each pressure sensor is consistent. At this time, the base and the steel frame are both in a balanced state, thereby improving the subsequent splicing accuracy.
[0029] Optionally, it also includes steel strands arranged in one-to-one correspondence with the connecting sections, the upper ends of the steel strands are connected to the end of the connecting section away from the steel frame body, and the lower ends of the steel strands pass through the through holes of the second center column and enter the gap between the second center column and the first center column; the lower ends of the steel strands are commonly connected to a limiting ring, the inner wall of the stabilizing sleeve is provided with a plurality of pre-tightening hydraulic cylinders, the piston rod of the pre-tightening hydraulic cylinder is provided with an abutment ball head, the abutment ball head abuts downwardly against the upper surface of the limiting ring, and the upper surface of the limiting ring is a smooth surface.
[0030] By adopting the above technical solution, when the steel frame main body and the connecting section are installed on the top of the second center column, the pre-tightening hydraulic cylinder is started, the abutment ball head moves downward, forcing the limit ring and the lower end of the steel strand to move downward, thereby tightening the steel strand to apply a downward force to the steel frame main body and the connecting section, so as to greatly improve the installation stability of the steel frame main body and the second center column, thereby improving the position stability of the steel frame main body after the second center column drives the steel frame main body to rotate each time, and reducing the occurrence of shaking of the steel frame main body due to instability.
[0031] The cooperation between the abutting ball head and the limiting ring can provide the limiting ring with a degree of freedom to rotate along with the second center column.
[0032] Optionally, the surface of the abutting ball head is set to a rough surface, and the upper surface of the limit ring is divided into an annular rotation area and a braking area from the outside to the inside, and the braking area is covered with a rubber ring; the tangential direction of the rotation of the limit ring is opposite to the extension direction of the preload hydraulic cylinder.
[0033] When the temporary support device drives the steel frame thereon to rotate, since the steel frame has a large mass and a large moving inertia, when the temporary support device stops rotating, the reaction force of the rotational torque of the steel frame will be transmitted to the temporary support device, causing structural damage. By adopting the above technical solution, when the temporary support device is about to stop rotating, the pre-tightening hydraulic cylinder drives the abutment ball head to move downward a short distance, and the abutment ball head moves from the rotating area to the braking area. At this time, the friction resistance is used to brake the steel frame to offset the rotational inertia of the steel frame.
[0034] Furthermore, the tangential direction of the rotation of the limit ring is opposite to the extension direction of the pre-tightening hydraulic cylinder, so the strength of the friction force will increase, and the friction force will be more directly transmitted to the steel strands and the steel frame, thereby improving the braking effect.
[0035] In summary, the present application includes at least one of the following beneficial technical effects:
[0036] 1. Use temporary support devices to support the main body of the steel frame and the connecting section, and then splice the arm section units in turn, breaking the whole into parts, greatly reducing the difficulty of lifting, and the main body of the steel frame and the connecting section have been pre-spliced and installed on the ground, that is, the steps with the highest installation accuracy are completed on the ground, and then the temporary support device supports the main body of the steel frame to ensure the position accuracy of the main body of the steel frame, which is convenient for the subsequent splicing accuracy;
[0037] 2. By setting a rotatable second center column, the splicing and hoisting position can be kept in the original position as much as possible, thereby reducing the excessive range of hoisting movement to reduce the interference of other building structures. In addition, hoisting in the original position can also ensure the accuracy of the splicing position to improve the installation accuracy;
[0038] 3. Therefore, by setting a rotatable counterweight bar, the center of gravity of the temporary support device can be adjusted according to the change of the center of gravity of the steel frame, thereby ensuring the overall stability of the steel frame and improving the installation accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] Figure 1 It is a schematic diagram of the overall structure of the steel frame of Example 1.
[0040] Figure 2 It is a schematic structural diagram of the temporary support device of Example 1.
[0041] Figure 3 It is a top view of the base of Example 1 with two counterweight bars in a position adjustment state.
[0042] Figure 4 It is a schematic structural diagram of the temporary support device of Example 2.
[0043] Figure 5It is a top view of the leveling plate of Example 2.
[0044] Figure 6 It is a schematic structural diagram of the temporary support device of Example 3.
[0045] Figure 7 yes Figure 6 A partial enlarged view of point A in the middle.
[0046] Figure 8 It is a top view of Example 3, which is used to reflect the relationship between the extension and contraction direction of the preload hydraulic cylinder and the rotation direction of the limit ring.
[0047] Fig. 9 It is a schematic diagram of a steel frame of the prior art.
[0048] Description of the reference numerals: 2, base; 4, leveling plate; 5, steel strand; 6, warning hydraulic cylinder; 7, limiting ring; 10, column; 11, steel frame body; 12, connecting section; 13, arm section unit; 21, first center column; 211, plug rod; 212, ball head surface; 22, second center column; 221, plug hole; 222, through hole; 23, anchor rod; 24, first drive assembly; 25, lifting hydraulic cylinder; 26, stabilizing sleeve; 261, limiting sleeve; 27, steel structure unit element; 271, vertical pole; 272, steel wire; 31, counterweight bar; 311, slide groove; 32, counterweight block; 33, second drive assembly; 331, second motor; 332, second gear; 333, second gear ring; 34, force plate; 35, third drive assembly; 351, third motor; 352, screw; 41, pressure sensor; 42, groove; 51, rope clamp; 61, abutment ball head; 71, rotation area; 72, braking area; 73, rubber ring; 74, through hole. DETAILED DESCRIPTION
[0049] The following is combined with Figure 1-8 This application is described in further detail.
[0050] Embodiment 1 of the present application discloses a temporary support device suitable for erecting a steel structure. It mainly supports the steel frame, such as Figure 1 As shown, the steel frame includes a steel frame body 11, five connecting segments 12, and multiple groups of arm segment units 13 arranged one by one corresponding to the connecting segments 12, wherein the steel frame body 11 and the connecting segments 12 are pre-welded on the ground, and in the initial stage, a temporary supporting device supports the steel frame body 11 and the connecting segments 12.
[0051] like Figure 2As shown, the temporary support device suitable for erecting a steel structure includes a base 2, a first central column 21, a stabilizing sleeve 26, a second central column 22 and a counterweight mechanism, wherein the base 2 is a horizontal disc, and the base 2 can be directly placed on the ground, or the base 2 can be fixed to the ground through an anchor rod 23. The stabilizing sleeve 26 is vertically fixed at the center of the base 2.
[0052] The first center column 21 is located in the stabilizing sleeve 26, and the first center column 21 is rotatably connected to the stabilizing sleeve 26. The base 2 is provided with a first driving assembly 24, and the first driving assembly 24 is used to drive the first center column 21 to rotate. In this embodiment, the first driving assembly 24 can be a hydraulic motor, and the hydraulic motor drives the first center column 21 to rotate through the cooperation of the gear ring.
[0053] The second center column 22 is located in the stabilizing sleeve 26, and the second center column 22 is located directly above the first center column 21. A plurality of vertically arranged plug rods 211 are fixed to the upper end of the first center column 21, and a plug hole 221 is provided at the lower end of the second center column 22. The plug rod 211 slides upward and is inserted into the plug hole 221, so that the torque of the first center column 21 can be transmitted to the second center column 22. A lifting hydraulic cylinder 25 is fixed to the upper end of the first center column 21, and the piston rod of the lifting hydraulic cylinder 25 abuts upward against the lower end of the second center column 22 to drive the second center column 22 to perform fine adjustment of the height position.
[0054] The upper end of the second central column 22 is provided with a plurality of vertically spliced and fixed steel structure units 27. Different numbers of steel structure units 27 are spliced according to different support heights. The top of the steel structure unit 27 is provided with a plurality of vertical poles 271. The vertical poles 271 are inserted into the gaps of the steel frame body 11, and are tied with steel wires 272 to fix the steel frame body 11 and the uppermost steel structure unit 27.
[0055] like Figure 2 , Figure 3As shown, the counterweight mechanism includes two counterweight bars 31, counterweight blocks 32 arranged in one-to-one correspondence with the counterweight bars 31, a second drive assembly 33 and a third drive assembly 35; the counterweight bars 31 are placed on the upper surface of the base 2, and the counterweight bars 31 are arranged along the radial direction of the base 2. A vertically arranged force plate 34 is fixed to one end of the counterweight bar 31 close to the stabilizing sleeve 26. The force plate 34 is arc-shaped, and the inner arc surface of the force plate 34 fits the outer circumferential surface of the stabilizing sleeve 26. In addition, the stabilizing sleeve 26 is fixed with a limiting sleeve 261, which is arranged around the stabilizing sleeve 26. There is a gap between the limiting sleeve 261 and the stabilizing sleeve 26, and the force plate 34 is located in the gap, that is, the force plate 34 cooperates with the limiting sleeve 261 and the stabilizing sleeve 26 respectively to achieve the effect that the counterweight bar 31 can rotate around the stabilizing sleeve 26. Of course, in other embodiments, a connecting ring may be provided at the end of the counterweight bar 31 , which is directly sleeved on the stabilizing sleeve 26 to achieve a rotational connection.
[0056] The second driving assembly 33 is used to drive the counterweight bar 31 to rotate. Specifically, the second driving assembly 33 includes a second motor 331, and the second motor 331 is fixed to the end of the counterweight bar 31 away from the stabilizing sleeve 26. The output shaft of the second motor 331 is fixed with a second gear 332, and the outer diameter of the base 2 is provided with a second gear ring 333, and the second gear 332 cooperates with the second gear ring 333.
[0057] like Figure 3 As shown, a slide groove 311 is provided on the upper surface of the counterweight bar 31, and the slide groove 311 is arranged along the length direction of the counterweight bar 31. The counterweight block 32 is slidably connected to the slide groove 311. The third driving assembly 35 includes a third motor 351 and a screw rod 352. The third motor 351 is installed in the slide groove 311. One end of the screw rod 352 is fixedly connected to the output shaft of the third motor 351. The screw rod 352 passes through the counterweight block 32, and the screw rod 352 is threadedly matched with the counterweight block 32.
[0058] Example 1 of the present application also discloses a method for hoisting and installing a steel frame.
[0059] A method for hoisting and installing a steel frame comprises the following steps:
[0060] S1. Configuring the steel frame: When on the ground, five connecting sections 12 are respectively installed at five positions of the steel frame body 11. At the same time, according to the arrangement position of the columns 10, the pre-installation position of the steel frame body 11 is determined, and then a temporary support device is placed at the position. Then, a crane is used to hoist the steel frame body 11 and the connecting sections 12 onto the temporary support device and fix them.
[0061] S2. A single boom section unit 13 is hoisted to one of the connecting sections 12 and spliced and installed. Then, the first driving assembly 24 drives the first center column 21 to rotate, thereby simultaneously driving the second center column 22, the steel frame body 11, and the connecting section 12 to rotate, so that the new connecting section 12 moves to the hoisting position of the previous boom section unit 13. Then, the crane hoists the new boom section unit 13 to that position and splices and installs it. Then, the above operation is repeated until the five connecting sections 12 complete the splicing and installation of the first boom section unit 13.
[0062] S3, in the order of installing step S2, the hoisting boom section unit 13 is sequentially spliced and connected with each installed boom section unit 13 until the splicing and connection of all the boom section units 13 is completed.
[0063] Moreover, when the volume and weight of the steel frame are large, the shape and center of gravity of the entire steel frame are always changing as they are spliced one by one. Therefore, a center of gravity adjustment step can be added in step S2 and step S3. Specifically, according to the change of the center of gravity of the steel frame, the second drive assembly 33 and the third drive assembly 35 are started to drive the counterweight bar 31 to rotate and the counterweight block 32 to move linearly to adjust the center of gravity of the temporary support device, thereby ensuring the overall stability of the steel frame and improving the subsequent splicing and installation accuracy.
[0064] S4, completing the installation and connection of the arm segment unit 13 at the end and the columns 10 in sequence.
[0065] The implementation principle of Example 1 is as follows: first, the steel frame body 11 and the connecting section 12 have been pre-spliced and installed on the ground, that is, the step with the highest installation accuracy requirement is completed on the ground, and then a temporary support device supports the steel frame body 11 to ensure the position accuracy of the steel frame body 11, so as to facilitate the subsequent splicing accuracy.
[0066] In addition, the steel frame is divided into multiple steel components, breaking the whole into parts, which greatly reduces the difficulty of lifting, and the auxiliary support of temporary support devices can further reduce the difficulty of lifting.
[0067] Secondly, by using a progressive installation method from the center to the outside instead of splicing the arm segment units 13 in the same direction at one time, the temporary support device is less affected by the eccentric gravity, that is, the position offset of the steel frame body 11 is reduced, the position accuracy of the steel frame body 11 is ensured, and the connection accuracy of the subsequent arm segment units 13 is further improved.
[0068] In summary, the effects of simplifying the lifting difficulty and improving the installation accuracy are taken into account.
[0069] Example 2
[0070] The difference between Example 2 and Example 1 is that Figure 4 , Figure 5 As shown, the temporary support device also includes a circular leveling plate 4, which is placed on the ground. The base 2 is located directly above the leveling plate 4, and the lower end of the first center column 21 is set as a ball head surface 212. A groove 42 is provided at the center of the leveling plate 4, and the ball head surface 212 cooperates with the groove 42.
[0071] The contact surface between the leveling plate 4 and the base 2 is densely covered with a plurality of pressure sensors 41 , and the pressure sensors 41 are electrically connected to the second motor 331 and the third motor 351 through a controller.
[0072] When the center of gravity of the steel frame shifts during the splicing process, the first center column 21 and the second center column 22 will be shifted, thereby driving the base 2 to shift, causing some pressure sensors 41 located between the base 2 and the leveling plate 4 to be compressed, while other pressure sensors 41 are not compressed. At this time, each pressure sensor 41 transmits a pressure signal to the controller, and then the controller controls the second motor 331 and the third motor 351 to operate, thereby driving the counterweight bar 31 to rotate and the counterweight block 32 to move, so as to adjust the center of gravity of the base 2 until the pressure information on each pressure sensor 41 is consistent. At this time, the base 2 and the entire steel frame remain in a balanced state, thereby improving the subsequent splicing accuracy.
[0073] Example 3
[0074] The difference between Example 3 and Example 1 is that Figure 6 , Figure 7 As shown, the temporary support device also includes a pre-tightening hydraulic cylinder and a steel strand 5. The steel strand 5 is arranged in a one-to-one correspondence with the connecting section 12. The upper end of the steel strand 5 is connected to the end of the connecting section 12 away from the steel frame body 11, and the lower end of the steel strand 5 extends obliquely downward through the through hole 222 of the second center column 22 and enters the gap between the second center column 22 and the first center column 21.
[0075] like Figure 7 , Figure 8 As shown, a limit ring 7 is arranged in the gap between the second center column 22 and the first center column 21. The limit ring 7 is coaxially arranged with the stabilizing sleeve 26. A through hole 74 is opened on the limit ring 7 for the lower end of the steel strand 5 to pass through. A rope clamp 51 is fixed to the passing end of the steel strand 5. The size of the rope clamp 51 is larger than the size of the through hole 74.
[0076] The upper surface of the limiting ring 7 is divided into an annular rotating area 71 and a braking area 72 from outside to inside. The rotating surface is a smooth surface, and the surface of the braking area 72 is covered with a rubber ring 73.
[0077] There are multiple pre-tightening hydraulic cylinders, and each pre-tightening hydraulic cylinder is evenly arranged around the axis of the stabilizing sleeve 26. The cylinder body of the pre-tightening hydraulic cylinder is fixedly connected to the inner wall of the stabilizing sleeve 26. The piston rod of the pre-tightening hydraulic cylinder is tilted downward, and, in the projection in the vertical plane, the tangential direction of the rotation of the limit ring 7 (the rotation direction of the second center column 22) is opposite to the extension direction of the pre-tightening hydraulic cylinder; the piston rod of the pre-tightening hydraulic cylinder is fixed with a butt ball head 61, and the surface of the butt ball head 61 is set to a rough surface.
[0078] The implementation principle of Example 3 is as follows: when the steel frame body 11 and the connecting section 12 are installed on the top of the second center column 22, the pre-tightening hydraulic cylinder is started, and the abutment ball head 61 moves downward. At this time, the abutment ball head 61 abuts against the rotation area 71 on the limit ring 7, forcing the limit ring 7 and the lower end of the steel strand 5 to move downward, thereby tightening the steel strand 5 to apply a downward force to the steel frame body 11 and the connecting section 12, so as to greatly improve the installation stability of the steel frame body 11 and the second center column 22. In addition, the rotation area 71 is a smooth surface, which can reduce the friction when the second center column 22 and the steel strand 5 rotate.
[0079] When the temporary support device drives the steel frame to rotate until it is about to stop at the hoisting installation position, the pre-tightening hydraulic cylinder drives the abutment ball head 61 to move downward a short distance, and the abutment ball head 61 moves from the rotation area 71 to the braking area 72. At this time, the friction resistance between the abutment ball head 61 and the rubber ring 73 is used to brake the rotation of the limit ring 7 and the steel strand 5, thereby braking the steel frame to offset the rotational inertia of the steel frame, thereby reducing the damage to the connection structure between the temporary support device and the steel frame caused by the excessive rotational inertia of the overall steel frame.
[0080] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A method for hoisting and installing a steel frame, characterized in that: The following steps are involved: S1. Configuring a steel frame: The steel frame includes a steel frame body (11) and a plurality of sub-bracket arm segments. The steel frame body (11) has a plurality of connecting segments (12) on its periphery. One connecting segment (12) corresponds to one sub-bracket arm segment. One sub-bracket arm segment includes a plurality of arm segment units (13). The steel frame body (11) and the connecting segments (12) are assembled, and the steel frame body (11) is hoisted onto a temporary support device. S2, hoisting a single boom segment unit (13) to one of the connecting segments (12) and performing splicing connection, and completing the splicing connection of the boom segment units (13) on each connecting segment (12) in sequence; S3, the hoisting boom section unit (13) is sequentially spliced and connected with each installed boom section unit (13) until the splicing and connection of all boom section units (13) is completed; S4, sequentially completing the installation and connection of the arm segment unit (13) at the end and the columns (10); The temporary support device comprises a base (2), a first central column (21), a stabilizing sleeve (26), and a second central column (22); the first central column (21) and the stabilizing sleeve (26) are both vertically arranged at the center of the base (2); the second central column (22) is vertically slidably connected to the stabilizing sleeve (26); the upper end of the second central column (22) is fixed to the steel frame body (11); a lifting hydraulic cylinder (25) is arranged between the first central column (21) and the second central column (22); the lifting hydraulic cylinder (25) is used to drive the second central column (22) to move vertically; The upper end of the first central column (21) is vertically and eccentrically fixed with an insertion rod (211), and the lower end of the second central column (22) is provided with a socket (221) for the insertion rod (211) to be slidably inserted; the first central column (21) is rotatably connected to the base (2) around its own axis, and the base (2) is provided with a first driving component (24) for driving the first central column (21) to rotate; in step S2, when the previous arm segment unit (13) is installed, the first driving component (24) drives the first central column (21) to rotate, so as to drive the second central column (22), the steel frame body (11), the connecting section (12), and the installed arm segment unit (13) to rotate in sequence, so that the uninstalled connecting section (12) moves to a waiting position for hoisting, waiting for the new arm segment unit (13) to be hoisted into place and assembled and connected; The base (2) is a disc, and two counterweight bars (31) are provided on the upper surface of the base (2) along its radial direction, one end of the counterweight bar (31) is connected to the stabilizing sleeve (26) so as to rotate around the axis of the base (2), and the base (2) is provided with a second driving component (33) for driving the counterweight bar (31) to rotate.
2. The method for hoisting and installing a steel frame according to claim 1, characterized in that: A limiting sleeve (261) is welded to the outer side of the stabilizing sleeve (26); an arc-shaped force-bearing plate (34) is fixed to one end of the counterweight bar (31) close to the stabilizing sleeve (26); the force-bearing plate (34) is located in the gap between the limiting sleeve (261) and the stabilizing sleeve (26), and the inner concave arc surface of the force-bearing plate (34) fits the outer peripheral surface of the stabilizing sleeve (26).
3. The method for hoisting and installing a steel frame according to claim 1, characterized in that: The counterweight bar (31) is provided with a counterweight block (32) and a third driving assembly (35), and the third driving assembly (35) is used to drive the counterweight block (32) to slide along the length direction of the counterweight bar (31).
4. The method for hoisting and installing a steel frame according to claim 1, characterized in that: It also includes a circular leveling plate (4) located directly below the base (2), the lower end of the first center column (21) is connected to the ball head at the center of the leveling plate (4), and the contact surface between the leveling plate (4) and the base (2) is densely covered with a plurality of pressure sensors (41), and the pressure sensors (41) are electrically connected to the second drive assembly (33) through a controller.
5. The method for hoisting and installing a steel frame according to claim 1, characterized in that: It also includes steel strands (5) arranged one by one in correspondence with the connecting sections (12), the upper ends of the steel strands (5) being connected to an end of the connecting section (12) away from the steel frame body (11), and the lower ends of the steel strands (5) passing through the through holes (222) of the second center column (22) and entering the gap between the second center column (22) and the first center column (21); the lower ends of the steel strands (5) are commonly connected to a limit ring (7), the inner wall of the stabilizing sleeve (26) is provided with a plurality of pre-tightening hydraulic cylinders, the piston rods of the pre-tightening hydraulic cylinders are provided with abutment ball heads (61), the abutment ball heads (61) abut downwardly against the upper surface of the limit ring (7), and the upper surface of the limit ring (7) is a smooth surface.
6. The method for hoisting and installing a steel frame according to claim 5, characterized in that: The surface of the abutting ball head (61) is set as a rough surface, and the upper surface of the limiting ring (7) is divided into an annular rotation area (71) and a braking area (72) from the outside to the inside, and the braking area (72) is covered with a rubber ring (73); the tangential direction of the rotation of the limiting ring (7) is opposite to the extension direction of the preload hydraulic cylinder.